CN108825301B - Quick wall building method for underground coal mine through pile-spraying concrete - Google Patents
Quick wall building method for underground coal mine through pile-spraying concrete Download PDFInfo
- Publication number
- CN108825301B CN108825301B CN201810566315.0A CN201810566315A CN108825301B CN 108825301 B CN108825301 B CN 108825301B CN 201810566315 A CN201810566315 A CN 201810566315A CN 108825301 B CN108825301 B CN 108825301B
- Authority
- CN
- China
- Prior art keywords
- wall
- shotcrete
- concrete
- spraying
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 52
- 238000000034 method Methods 0.000 title claims abstract description 44
- 239000003245 coal Substances 0.000 title claims abstract description 35
- 238000005507 spraying Methods 0.000 title claims description 49
- 239000011378 shotcrete Substances 0.000 claims abstract description 58
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 32
- 238000010276 construction Methods 0.000 claims abstract description 27
- 239000000203 mixture Substances 0.000 claims abstract description 18
- 239000004576 sand Substances 0.000 claims abstract description 18
- 239000004568 cement Substances 0.000 claims abstract description 16
- 239000007921 spray Substances 0.000 claims description 33
- 239000004575 stone Substances 0.000 claims description 27
- 229910000831 Steel Inorganic materials 0.000 claims description 22
- 239000010959 steel Substances 0.000 claims description 22
- 239000000463 material Substances 0.000 claims description 14
- 239000007788 liquid Substances 0.000 claims description 10
- 238000012423 maintenance Methods 0.000 claims description 7
- 239000002245 particle Substances 0.000 claims description 7
- 238000002156 mixing Methods 0.000 claims description 5
- 239000011398 Portland cement Substances 0.000 claims description 3
- 239000002994 raw material Substances 0.000 claims description 3
- 238000003756 stirring Methods 0.000 claims description 3
- 238000009718 spray deposition Methods 0.000 abstract 1
- 238000009415 formwork Methods 0.000 description 9
- 238000010586 diagram Methods 0.000 description 5
- 239000010410 layer Substances 0.000 description 5
- 230000002787 reinforcement Effects 0.000 description 5
- 238000004519 manufacturing process Methods 0.000 description 3
- 206010067482 No adverse event Diseases 0.000 description 2
- 210000000988 bone and bone Anatomy 0.000 description 2
- 239000003795 chemical substances by application Substances 0.000 description 2
- 230000007547 defect Effects 0.000 description 2
- 238000000227 grinding Methods 0.000 description 2
- 238000005065 mining Methods 0.000 description 2
- 239000002086 nanomaterial Substances 0.000 description 2
- 231100000252 nontoxic Toxicity 0.000 description 2
- 230000003000 nontoxic effect Effects 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 239000002002 slurry Substances 0.000 description 2
- 230000009967 tasteless effect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 239000004566 building material Substances 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 239000002356 single layer Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/103—Dams, e.g. for ventilation
-
- C—CHEMISTRY; METALLURGY
- C04—CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
- C04B—LIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
- C04B28/00—Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
- C04B28/02—Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
- C04B28/04—Portland cements
-
- C—CHEMISTRY; METALLURGY
- C04—CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
- C04B—LIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
- C04B2111/00—Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
- C04B2111/00034—Physico-chemical characteristics of the mixtures
- C04B2111/00146—Sprayable or pumpable mixtures
- C04B2111/00155—Sprayable, i.e. concrete-like, materials able to be shaped by spraying instead of by casting, e.g. gunite
Landscapes
- Chemical & Material Sciences (AREA)
- Engineering & Computer Science (AREA)
- Ceramic Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Materials Engineering (AREA)
- Inorganic Chemistry (AREA)
- Organic Chemistry (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
一种用于煤矿井下的堆喷混凝土快速筑墙方法,属于煤矿井下构筑混凝土墙体和喷射混凝土技术领域,可解决现有煤矿井下构筑混凝土墙的方法速度慢、最终强度达不到设计要求、形不成对顶板的有效支撑以及适用范围小的问题,将砂石料、水泥、JCT‑1喷射混凝土外加剂和速凝剂在潮湿状态下按一定比例拌和均匀后装入喷射机,用压缩空气将潮湿混合料沿管路输送至喷头处与水混合并高速喷射构筑墙体的一种新型的用于煤矿井下的快速构筑混凝土墙方法。本发明的方法墙体易成形,初凝时间短,堆喷成形即具有较高的初期强度,不会滑移和坠落变形,墙体厚度不受限制。
The invention relates to a method for rapidly building a wall with shotcrete in a coal mine, belonging to the technical field of concrete wall construction and shotcrete in a coal mine, and can solve the problem that the existing method for building a concrete wall in a coal mine is slow, the final strength fails to meet the design requirements, and the There is no effective support for the roof and the problem of small application range. The sand and gravel, cement, JCT‑1 shotcrete admixture and accelerator are mixed evenly in a certain proportion in a wet state and then loaded into the jet machine. The wet mixture is transported along the pipeline to the nozzle, mixed with water and sprayed at high speed to build the wall, a new method for rapid construction of concrete walls in coal mines. According to the method of the invention, the wall body is easy to form, the initial setting time is short, and the pile spray forming has high initial strength, no slippage and falling deformation, and the thickness of the wall body is not limited.
Description
技术领域technical field
本发明属于煤矿井下构筑混凝土墙体和喷射混凝土技术领域,具体涉及一种用于煤矿井下的堆喷混凝土快速筑墙方法。The invention belongs to the technical field of concrete walls and shotcrete in underground coal mines, and particularly relates to a method for rapidly building walls with shotcrete in coal mines.
背景技术Background technique
混凝土因具有强度高、整体性及耐久性好等优点而成为最主要的土木工程材料之一,混凝土墙一般由支模浇筑而成,具体工艺是用水泥作胶凝材料、砂石作骨料与水按一定比例混合(可含外加剂和掺合料),经搅拌而成的混凝土被浇筑在支设好的定型模板内,密实成形,养护硬化后拆卸模板。定型模板对混凝土墙的结构尺寸和成形质量至关重要,定型模板支设不合格可引发漏浆、混凝土墙体垂直度和平整度差、蜂窝麻面等质量缺陷。此外,支设和拆卸模板工序占构筑混凝土墙工作的一半以上,严重制约混凝土墙体的构筑速度。Concrete has become one of the most important civil engineering materials due to its advantages of high strength, integrity and durability. It is mixed with water in a certain proportion (it may contain admixtures and admixtures), and the agitated concrete is poured into the set formwork, compacted and formed, and the formwork is removed after curing and hardening. The stereotyped formwork is very important to the structural size and forming quality of the concrete wall. The unqualified setting of the stereotyped formwork can cause quality defects such as slurry leakage, poor verticality and flatness of the concrete wall, and honeycomb pitted surface. In addition, the process of setting up and dismantling the formwork accounts for more than half of the work of constructing the concrete wall, which seriously restricts the construction speed of the concrete wall.
煤矿井下经常需要构筑密闭墙、硐室等工作空间墙体,受作业空间和施工环境限制,构筑混凝土墙体只能采用现场人工搅拌或小功率设备搅拌,支模拆模工序多,劳动强度大,材料配比不易控制,筑墙效率低,养护时间长且养护易受井下环境影响而使得墙体最终强度达不到设计要求,制约混凝土在煤矿井下的推广使用。Confined walls, chambers and other working space walls often need to be constructed underground in coal mines. Due to the limitation of working space and construction environment, the construction of concrete walls can only be done by manual mixing on site or by low-power equipment. , the material ratio is not easy to control, the wall building efficiency is low, the maintenance time is long, and the maintenance is easily affected by the underground environment, so that the final strength of the wall does not meet the design requirements, which restricts the popularization and use of concrete in coal mines.
煤矿井下目前多采用料石砌筑墙体,但砌筑料石墙工艺中的料石搬运、砌筑等环节都需要投入大量笨重的体力劳动,用工多,成本高,筑墙速度慢,且因井下作业环境差而在搬运和砌筑料石过程中容易发生砸伤等意外伤害事故。此外,砌筑料石墙体的另外一个缺陷是受料石尺寸限制,砌筑的料石墙体与顶板之间的最后缝隙填充困难,只能采用碎石或砂浆填满,料石墙体接顶部位强度明显不足,形不成对顶板的有效支撑,不能发挥墙体对顶板的支撑作用,使顶板存在一定范围的下沉变形空间,不利于通过砌筑墙体支撑顶板。At present, materials and stones are mostly used to build walls in coal mines. However, in the process of building materials and stone walls, a lot of heavy manual labor is required for material and stone transportation and masonry. Due to the poor underground working environment, accidents such as smashing and other accidents are prone to occur in the process of handling and masonry. In addition, another defect of the masonry stone wall is that due to the size of the stone, it is difficult to fill the final gap between the masonry stone wall and the roof, and can only be filled with crushed stone or mortar. The strength of the joint is obviously insufficient, and it cannot form an effective support for the roof, and cannot play the supporting role of the wall on the roof, so that the roof has a certain range of sinking deformation space, which is not conducive to supporting the roof through the masonry wall.
目前喷射混凝土主要用于隧道及巷道的初期或永久支护、基坑边坡支护、结构加固维修等领域。为了保证长距离输送及输送过程不发生结块堵管等问题,喷射的混凝土必须有良好的和易性,但成形厚度不能太大,否则就会滑移坠落。喷射混凝土在煤矿井下应用较多的是巷道等地下空间结构的表面单层衬砌支护,但喷层厚度多小于100mm,喷层太厚就会发生开裂、脱落等质量问题,因此喷射工艺只能形成厚度较小的喷层。At present, shotcrete is mainly used in the initial or permanent support of tunnels and roadways, foundation pit slope support, structural reinforcement and maintenance and other fields. In order to ensure long-distance transportation and no problems such as caking and blocking of pipes during transportation, the sprayed concrete must have good workability, but the forming thickness should not be too large, otherwise it will slip and fall. Shotcrete is mostly used in coal mines for single-layer lining support on the surface of underground space structures such as roadways, but the thickness of shotcrete is usually less than 100mm. If the shotcrete is too thick, quality problems such as cracking and falling off will occur. Therefore, the spraying process can only be used. Form a spray layer with a smaller thickness.
为了提高喷射混凝土的早期强度,喷射过程中都会添加一定比例的速凝剂。普通速凝剂虽然缩短了喷射混凝土的初凝时间,但会使混凝土的中期强度降低较多,标准养护28天后强度降低超过30%。以添加普通速凝剂的C35混凝土为例,标准养护28天后的混凝土强度只有18~19MPa,降压比达48.6%。In order to improve the early strength of shotcrete, a certain proportion of accelerator will be added during the spraying process. Although the ordinary quick-setting agent shortens the initial setting time of shotcrete, it will greatly reduce the medium-term strength of the concrete, and the strength will be reduced by more than 30% after 28 days of standard curing. Taking the C35 concrete added with ordinary accelerators as an example, the concrete strength after standard curing for 28 days is only 18~19MPa, and the pressure reduction ratio is 48.6%.
在公开文献中可以获得公开号为“CN 107522442 A”的“一种矿用喷射混凝土及其制备方法”专利,其主要提出了一种煤矿井下用喷浆材料商品化配制方法,该方法只是通过提供的材料配比使喷射浆料硬化后在强度上满足煤矿井下的施工要求,一定程度上减小了回弹率,但并没有具体说明煤矿井下的应用场所及可达到的最大喷层厚度,依然局限于形成厚度较小的混凝土喷层。The patent of "a shotcrete for mining and its preparation method" with the publication number of "CN 107522442 A" can be obtained in the published literature, which mainly proposes a commercial preparation method of shotcrete material for underground coal mines, which is only by The provided material ratio enables the jetting slurry to meet the construction requirements of underground coal mines in terms of strength after hardening, and reduces the rebound rate to a certain extent, but it does not specify the application site of coal mines and the maximum spray layer thickness that can be achieved. It is still limited to forming a concrete sprayed layer with a small thickness.
在煤矿井下构筑混凝土墙,可以发挥其墙体强度高和整体性好等优点,对促进煤矿井下安全生产具有重要意义。在已公开的文献及目前使用的浇筑或喷射混凝土方法中,并没有一种堆喷构筑混凝土墙体的方法。为了推广混凝土在煤矿井下筑墙等使用场所的的应用,迫切需要寻求一种在满足使用要求的前提下,简化传统浇筑混凝土工艺、不需要支模拆模等环节,养护简单,提高筑墙效率和速度,节省人工成本的可替代砌筑料石墙和传统支模浇筑混凝土墙的一种用于煤矿井下的新型堆喷快速构筑混凝土墙的方法。Constructing concrete walls in coal mines can give full play to the advantages of high strength and integrity of the walls, and is of great significance to promoting safe production in coal mines. In the published literature and the currently used pouring or spraying concrete methods, there is no method for constructing concrete walls by pile spraying. In order to popularize the application of concrete in building walls and other places of use in coal mines, it is urgent to seek a method that simplifies the traditional pouring concrete process, does not require formwork and dismantling, and improves the efficiency of building walls under the premise of meeting the requirements of use. A new method for rapid construction of concrete walls by spraying in coal mines, which can replace masonry stone walls and traditional formwork pouring concrete walls and save labor costs.
发明内容SUMMARY OF THE INVENTION
本发明针对现有煤矿井下构筑混凝土墙的方法速度慢、最终强度达不到设计要求、形不成对顶板的有效支撑以及适用范围小的问题,提供一种用于煤矿井下的堆喷混凝土快速筑墙方法,本发明将砂石料、水泥、JCT-1喷射混凝土外加剂和速凝剂在潮湿状态下按一定比例拌和均匀后装入喷射机,用压缩空气将潮湿混合料沿管路输送至喷头处与水混合并高速喷射构筑墙体。Aiming at the problems of the existing method of constructing concrete walls underground in coal mines, the speed is slow, the final strength cannot meet the design requirements, the effective support for the roof cannot be formed, and the scope of application is small, and the invention provides a rapid construction of shotcrete for underground coal mines. In the present invention, the sand and gravel, cement, JCT-1 shotcrete admixture and quick-setting agent are mixed uniformly in a certain proportion in a wet state and then loaded into the sprayer, and the wet mixture is transported along the pipeline to the sprayer with compressed air It is mixed with water and sprayed at high speed to build the wall.
本发明采用如下技术方案:The present invention adopts following technical scheme:
一种用于煤矿井下的堆喷混凝土快速筑墙方法,包括如下步骤:A method for rapidly building a wall with shotcrete in a coal mine, comprising the following steps:
第一步,敲帮问顶去除煤矿井下设计构筑墙体顶板范围的活矸,清除设计墙体范围底板的浮渣并找到硬底;The first step is to knock on the top to remove the live gangue in the range of the top plate of the wall designed and constructed in the coal mine, remove the scum on the bottom plate of the design wall and find the hard bottom;
第二步,在筑墙范围内放置预制好的钢筋笼,钢筋笼之间用16#绑丝绑扎连接;钢筋笼宽度与墙体宽度一致,以控制墙体成形尺寸;钢筋笼的高度和长度与设计构筑墙体的高度和长度相等;The second step is to place prefabricated steel cages within the wall construction range, and use 16# binding wires to bind and connect the steel cages; the width of the steel cages is consistent with the width of the wall to control the size of the wall; the height and length of the steel cages It is equal to the height and length of the designed construction wall;
第三步,根据井下堆喷构筑混凝土墙体的体积,在地面按照水泥:砂子:石子:JCT-1堆喷混凝土外加剂的质量比为1 : 2 : 2 : 0.06的比例准备堆喷混凝土原材料,堆喷混凝土工艺构筑1m3混凝土墙体需要589.04Kg水泥,1178.08Kg砂子,1178.08Kg石子,JCT-1堆喷混凝土外加剂35.34Kg;In the third step, according to the volume of the concrete wall constructed by the underground shotcrete, prepare the shotcrete raw materials on the ground according to the mass ratio of cement: sand: stone: JCT-1 shotcrete admixture of 1 : 2 : 2 : 0.06 , the construction of 1m 3 concrete wall by the shotcrete process requires 589.04Kg of cement, 1178.08Kg of sand, 1178.08Kg of stones, and 35.34Kg of JCT-1 shotcrete admixture;
第四步,将石子洒水充分浸湿并放入搅拌机内,向搅拌机内加入JCT-1堆喷混凝土外加剂,启动搅拌机开始搅拌,使石子和JCT-1堆喷混凝土外加剂混合均匀;The fourth step is to fully wet the stones with water and put them into the mixer, add the JCT-1 shotcrete admixture to the mixer, start the mixer and start mixing, so that the stones and the JCT-1 shotcrete admixture are evenly mixed;
第五步,当搅拌机内的石子和JCT-1堆喷混凝土外加剂混合均匀后,向搅拌机内加入砂子和水泥,继续搅拌至混合均匀,得到混凝土混合料;The fifth step, when the stones in the mixer and the JCT-1 shotcrete admixture are evenly mixed, add sand and cement into the mixer, and continue to mix until the mixture is uniform to obtain a concrete mixture;
第六步,将拌和形成均匀的混凝土混合料装车运输至井下堆喷筑墙地点,连续向喷射机料斗内加入拌和好的混凝土混合料并开启搅拌,打开喷枪处的水管阀门和自动添加液体速凝剂管路阀门,调节水管阀门流量,控制喷枪出口处混凝土的水灰比为0.4~0.5,接通喷射机的压风管路,启动风动震动器和喂料系统,开始堆喷筑墙作业,堆喷筑墙过程中,喷枪做连续不断的螺旋状圆周运动,螺旋直径为20~30 cm,后一圈覆盖前一圈1/3,先堆喷墙中间,再堆喷墙两侧以找平墙面,墙表面的不平整度小于10mm,堆喷路线在设计筑墙的墙体长度和高度范围内自下而上呈“S”形运行;The sixth step is to load the mixed concrete mixture into a truck and transport it to the underground spraying wall site, continuously add the mixed concrete mixture into the hopper of the jet machine and start the stirring, open the water pipe valve at the spray gun and automatically add liquid. Accelerator pipeline valve, adjust the flow rate of the water pipe valve, control the water-cement ratio of the concrete at the outlet of the spray gun to 0.4~0.5, connect the pressure air pipeline of the sprayer, start the pneumatic vibrator and the feeding system, and start the pile spraying. Wall work, in the process of stacking and spraying the wall, the spray gun makes a continuous spiral circular motion, the diameter of the spiral is 20~30 cm, and the latter circle covers 1/3 of the previous circle. The side is leveled with the wall, the unevenness of the wall surface is less than 10mm, and the spraying route runs in an "S" shape from bottom to top within the range of the length and height of the designed wall;
第七步,当堆喷形成的墙体达到设计高度时,停止向喷射机料斗内加料,确认喷射机料斗没有余料、喷枪处不再有料喷出时,关闭自动添加液体速凝剂管路阀门,再关闭风动震动器;向喷射机料斗内加入水,将喂料系统和输送管路清洗干净,最后关闭压风、压水和电源,清洗自动添加液体速凝剂管路和清理喷射机周围杂物;The seventh step, when the wall formed by the stacking spray reaches the design height, stop feeding into the ejector hopper, and confirm that there is no remaining material in the ejector hopper and when there is no more material ejected from the spray gun, close the automatic adding liquid accelerator pipeline. valve, and then turn off the pneumatic vibrator; add water to the hopper of the ejector, clean the feeding system and conveying pipeline, and finally turn off the air pressure, water pressure and power supply, clean the pipeline for adding liquid accelerator automatically and clean the spray debris around the machine;
第八步,堆喷混凝土墙体2小时后开始洒水养护,每隔8小时洒水养护一次,共养护7天,养护用水与堆喷用水相同,每次养护洒水量以充分湿润墙面为宜。The eighth step, spraying and curing the concrete wall after 2 hours. Sprinkling and curing every 8 hours for a total of 7 days. The maintenance water is the same as the heap spraying water.
堆喷筑墙的标准是墙体拱部圆滑、两帮平顺、整体无明显凹凸处(以堆喷形成墙体表面的凹凸度不超过10 mm为准),墙体接顶、接帮严密,不留任何空隙。The standard of pile spray construction is that the arch of the wall is smooth, the two sides are smooth, and there is no obvious unevenness as a whole (subject to the unevenness of the wall surface formed by pile spraying not exceeding 10 mm), the wall is connected to the top and the joints are tight. Leave no gaps.
优选地,所述水泥为硅酸盐水泥,强度等级不低于32.5Mpa。Preferably, the cement is Portland cement, and the strength grade is not lower than 32.5Mpa.
所述石子为碎石或卵石或两者混合物,粒径为5-15mm。The stones are crushed stones or pebbles or a mixture of the two, and the particle size is 5-15 mm.
所述砂子为中砂或粗砂,细度模数大于2.5,含水率为5-7%,含泥量小于等于3%。The sand is medium sand or coarse sand, the fineness modulus is greater than 2.5, the moisture content is 5-7%, and the mud content is less than or equal to 3%.
所述喷射机为转子式—Ⅱ型喷浆机,喷枪为双水环锥形喷头;喷枪设置双水环,环上按间排距10mm钻有直径为1mm的微孔,经水压射出细的水流,水流呈交叉网状,充分润湿物料。The spraying machine is a rotor type-II type spraying machine, and the spraying gun is a double-water ring conical spraying head; The water flow is in the form of a cross network, which fully wets the material.
所述喷射机喷射过程中的风压为0.12-0.17MPa,水压为0.18-0.21MPa。The wind pressure in the spraying process of the jet machine is 0.12-0.17MPa, and the water pressure is 0.18-0.21MPa.
JCT-1堆喷混凝土外加剂是采用机械研磨法进行细化的无机纳米级材料,是一种集促凝、早强、减水为一体的多效多功能型外加剂,呈灰白色粉末状,无毒无味,不燃,容重为200~300Kg/m3,密度为2.1~2.3g/cm3,粒径为0.3~0.5μm,在使用过程中对人体无不良影响。试验使用JCT-1堆喷混凝土外加剂时,标准养护28天后的C35混凝土强度可达35~36MPa,没有降压损失。JCT-1堆喷混凝土外加剂是由山西吉昌泰矿山工程技术有限公司开发研制的一种喷射混凝土外加剂,使用JCT-1喷射混凝土外加剂可实现使喷射层粘结力增加且不收缩,提高混凝土早期强度和最终强度,减少喷溅回弹,成型快,增加喷层厚度,接顶密实等效果。JCT-1 shotcrete admixture is an inorganic nano-scale material refined by mechanical grinding method. It is non-toxic, tasteless, non-flammable, with a bulk density of 200~300Kg/m 3 , a density of 2.1~2.3g/cm 3 , a particle size of 0.3~0.5μm, and no adverse effects on the human body during use. When JCT-1 shotcrete admixture is used in the test, the strength of C35 concrete after standard curing for 28 days can reach 35~36MPa, and there is no depressurization loss. JCT-1 shotcrete admixture is a shotcrete admixture developed by Shanxi Jichangtai Mining Engineering Technology Co., Ltd. The use of JCT-1 shotcrete admixture can increase the cohesion of the shotcrete layer without shrinking, improving the Early strength and final strength of concrete, reducing splashing and rebounding, forming fast, increasing the thickness of spray layer, and compacting the top.
堆喷墙内放置的钢筋笼由8#钢筋焊接的网孔尺寸为100mm的钢筋网片和连接钢筋构成,钢筋网片的宽度为堆喷墙的设计宽度,钢筋网片的高度为堆喷墙的设计高度,相邻钢筋网片之间连接钢筋的间排距为0.5m,连接钢筋的长度1.0m。The reinforcement cage placed in the spray wall is composed of steel mesh with a mesh size of 100mm welded by 8# steel bars and connecting steel bars. The width of the steel mesh is the design width of the spray wall, and the height of the steel mesh is the height of the spray wall. The design height is 0.5m and the length of the connecting bars is 1.0m.
堆喷筑墙作业至少配备两名施工人员,一人负责手持喷头进行堆喷,另一人辅助照明并负责联络,观察工作场所围岩安全和堆喷墙体质量。There should be at least two construction workers for the construction of walls by spraying and spraying, one of whom is responsible for spraying with a hand-held sprinkler, the other is responsible for auxiliary lighting and liaison, and observes the safety of surrounding rocks in the workplace and the quality of the sprayed wall.
本发明的有益效果如下:The beneficial effects of the present invention are as follows:
本发明的方法不需要支设模板,使用普通混凝土喷射机即可实现堆喷构筑混凝土墙,墙体易成形,初凝时间短,堆喷成形即具有较高的初期强度,不会滑移和坠落变形,墙体厚度不受限制。The method of the invention does not need to set up formwork, and can realize the construction of concrete wall by pile spraying by using ordinary concrete spraying machine. Falling deformation, the wall thickness is not limited.
与现有技术相比,本发明堆喷工艺施工方法填补了煤矿井下堆喷构筑混凝土墙的空白。通过在配制混合料时加入一种具有高粘结性的JCT-1堆喷混凝土外加剂,使喷头处喷射出的混凝土粘结性提高,不支设模板即可自行压实成形,简化了煤矿井下构筑混凝土墙体的工序,解放了劳动强度,提高了效率,节约了筑墙成本。喷射出的混凝土速度高,任何狭小的缝隙都可填满,使得墙体和顶板、帮部之间接触充填严密。Compared with the prior art, the construction method of the spraying process of the present invention fills the blank of the construction of concrete walls by spraying under the coal mine. By adding a JCT-1 shotcrete admixture with high cohesiveness when preparing the mixture, the cohesiveness of the concrete sprayed at the nozzle is improved, and it can be compacted and formed by itself without setting up a formwork, which simplifies the underground coal mine. The process of building a concrete wall liberates labor intensity, improves efficiency, and saves the cost of building walls. The speed of the sprayed concrete is high, and any narrow gap can be filled, so that the contact between the wall and the top plate and the help is tight.
本发明堆喷工艺构筑混凝土墙体施工速度快、操作方便、不损失混凝土强度、成本低,符合煤矿安全生产要求。堆喷工艺筑墙的速度主要和喷射机的喷射能力有关,在喷射机喷射能力满足要求的情况下,堆喷工艺的速度可达7~10m3/h,对提高筑墙速度,减少工人劳动强度,缩短工期,促进煤矿安全生产具有重要意义。The pile spraying process of the invention has the advantages of fast construction speed, convenient operation, no loss of concrete strength and low cost, and meets the safety production requirements of coal mines. The speed of building a wall by the stack spraying process is mainly related to the jetting capacity of the jet. When the jetting capacity of the jetting machine meets the requirements, the speed of the stacking jetting process can reach 7~10m 3 /h, which can improve the wall building speed and reduce the labor of workers It is of great significance to improve the strength, shorten the construction period, and promote the safe production of coal mines.
附图说明Description of drawings
图1为本发明工艺流程图;Fig. 1 is the process flow diagram of the present invention;
图2为本发明的喷射机结构示意图;Fig. 2 is a schematic diagram of the structure of the jet of the present invention;
图3为本发明堆喷筑墙内放置的钢筋笼结构示意图;Fig. 3 is the structure schematic diagram of the reinforcement cage placed in the pile spray construction wall of the present invention;
图4为本发明堆喷筑墙过程示意图,图中曲线的箭头方向为堆喷方向;Fig. 4 is a schematic diagram of the process of stacking spraying and building a wall according to the present invention, and the arrow direction of the curve in the figure is the stacking spraying direction;
图5为本发明堆喷筑墙最终墙体示意图;Fig. 5 is a schematic diagram of the final wall body of the present invention;
其中:1-压风源;2-系统风压表;3-工作风压表;4-料斗;5-混合环;6-喷嘴;7-喂料系统;8-主风阀;9-管路;10-辅助风阀;11-雾化器;12-液体速凝剂槽;13-计量泵;14-清水槽;15-钢筋网片;16-连接钢筋;17-顶板;18-堆喷混凝土墙;19-底板;20-侧帮。Among them: 1-pressure air source; 2-system air pressure gauge; 3-working air pressure gauge; 4-hopper; 5-mixing ring; 6-nozzle; 7-feeding system; 8-main air valve; 9-pipe Road; 10- Auxiliary Air Valve; 11- Atomizer; 12- Liquid Accelerator Tank; 13- Metering Pump; 14- Clear Water Tank; 15- Reinforcement Mesh; Shotcrete wall; 19-base plate; 20-side help.
具体实施方式Detailed ways
一种用于煤矿井下的堆喷混凝土快速筑墙方法,包括如下步骤:A method for rapidly building a wall with shotcrete in a coal mine, comprising the following steps:
第一步,敲帮问顶去除煤矿井下设计构筑墙体顶板范围的活矸,清除设计墙体范围底板的浮渣并找到硬底;The first step is to knock on the top to remove the live gangue in the range of the top plate of the wall designed and constructed in the coal mine, remove the scum on the bottom plate of the design wall and find the hard bottom;
第二步,在筑墙范围内放置预制好的钢筋笼,钢筋笼之间用16#绑丝绑扎连接;钢筋笼宽度与墙体宽度一致,以控制墙体成形尺寸;钢筋笼的高度和长度与设计构筑墙体的高度和长度相等;The second step is to place prefabricated steel cages within the wall construction range, and use 16# binding wires to bind and connect the steel cages; the width of the steel cages is consistent with the width of the wall to control the size of the wall; the height and length of the steel cages It is equal to the height and length of the designed construction wall;
第三步,根据井下堆喷构筑混凝土墙体的体积,在地面按照水泥:砂子:石子:JCT-1堆喷混凝土外加剂的质量比为1 : 2 : 2 : 0.06的比例准备堆喷混凝土原材料,堆喷混凝土工艺构筑1m3混凝土墙体需要589.04Kg水泥,1178.08Kg砂子,1178.08Kg石子,JCT-1堆喷混凝土外加剂35.34Kg;In the third step, according to the volume of the concrete wall constructed by the underground shotcrete, prepare the shotcrete raw materials on the ground according to the mass ratio of cement: sand: stone: JCT-1 shotcrete admixture of 1 : 2 : 2 : 0.06 , the construction of 1m 3 concrete wall by the shotcrete process requires 589.04Kg of cement, 1178.08Kg of sand, 1178.08Kg of stones, and 35.34Kg of JCT-1 shotcrete admixture;
第四步,将石子洒水充分浸湿并放入搅拌机内,向搅拌机内加入JCT-1堆喷混凝土外加剂,启动搅拌机开始搅拌,使石子和JCT-1堆喷混凝土外加剂混合均匀;The fourth step is to fully wet the stones with water and put them into the mixer, add the JCT-1 shotcrete admixture to the mixer, start the mixer and start mixing, so that the stones and the JCT-1 shotcrete admixture are evenly mixed;
第五步,当搅拌机内的石子和JCT-1堆喷混凝土外加剂混合均匀后,向搅拌机内加入砂子和水泥,继续搅拌至混合均匀,得到混凝土混合料;The fifth step, when the stones in the mixer and the JCT-1 shotcrete admixture are evenly mixed, add sand and cement into the mixer, and continue to mix until the mixture is uniform to obtain a concrete mixture;
第六步,将拌和形成均匀的混凝土混合料装车运输至井下堆喷筑墙地点,连续向喷射机料斗内加入拌和好的混凝土混合料并开启搅拌,打开喷枪处的水管阀门和自动添加液体速凝剂管路阀门,调节水管阀门流量,控制喷枪出口处混凝土的水灰比为0.4~0.5,接通喷射机的压风管路,启动风动震动器和喂料系统,开始堆喷筑墙作业,堆喷筑墙过程中,喷枪做连续不断的螺旋状圆周运动,螺旋直径为20~30 cm,后一圈覆盖前一圈1/3,先堆喷墙中间,再堆喷墙两侧以找平墙面,墙表面的不平整度小于10mm,堆喷路线在设计筑墙的墙体长度和高度范围内自下而上呈“S”形运行;The sixth step is to load the mixed concrete mixture into a truck and transport it to the underground spraying wall site, continuously add the mixed concrete mixture into the hopper of the jet machine and start the stirring, open the water pipe valve at the spray gun and automatically add liquid. Accelerator pipeline valve, adjust the flow rate of the water pipe valve, control the water-cement ratio of the concrete at the outlet of the spray gun to 0.4~0.5, connect the pressure air pipeline of the sprayer, start the pneumatic vibrator and the feeding system, and start the pile spraying. Wall work, in the process of stacking and spraying the wall, the spray gun makes a continuous spiral circular motion, the diameter of the spiral is 20~30 cm, and the latter circle covers 1/3 of the previous circle. The side is leveled with the wall, the unevenness of the wall surface is less than 10mm, and the spraying route runs in an "S" shape from bottom to top within the range of the length and height of the designed wall;
第七步,当堆喷形成的墙体达到设计高度时,停止向喷射机料斗内加料,确认喷射机料斗没有余料、喷枪处不再有料喷出时,关闭自动添加液体速凝剂管路阀门,再关闭风动震动器;向喷射机料斗内加入水,将喂料系统和输送管路清洗干净,最后关闭压风、压水和电源,清洗自动添加液体速凝剂管路和清理喷射机周围杂物;The seventh step, when the wall formed by the stacking spray reaches the design height, stop feeding into the ejector hopper, and confirm that there is no remaining material in the ejector hopper and when there is no more material ejected from the spray gun, close the automatic adding liquid accelerator pipeline. valve, and then turn off the pneumatic vibrator; add water to the hopper of the ejector, clean the feeding system and conveying pipeline, and finally turn off the air pressure, water pressure and power supply, clean the pipeline for adding liquid accelerator automatically and clean the spray debris around the machine;
第八步,堆喷混凝土墙体2小时后开始洒水养护,每隔8小时洒水养护一次,共养护7天,养护用水与堆喷用水相同,每次养护洒水量以充分湿润墙面为宜。The eighth step, spraying and curing the concrete wall after 2 hours. Sprinkling and curing every 8 hours for a total of 7 days. The maintenance water is the same as the heap spraying water.
堆喷筑墙的标准是墙体拱部圆滑、两帮平顺、整体无明显凹凸处(以堆喷形成墙体表面的凹凸度不超过10 mm为准),墙体接顶、接帮严密,不留任何空隙。The standard of pile spray construction is that the arch of the wall is smooth, the two sides are smooth, and there is no obvious unevenness as a whole (subject to the unevenness of the wall surface formed by pile spraying not exceeding 10 mm), the wall is connected to the top and the joints are tight. Leave no gaps.
优选地,所述水泥为硅酸盐水泥,强度等级不低于32.5Mpa。Preferably, the cement is Portland cement, and the strength grade is not lower than 32.5Mpa.
所述粗骨粒为碎石或卵石或两者混合物,粒径为5-15mm。The coarse bone particles are crushed stones or pebbles or a mixture of the two, and the particle size is 5-15 mm.
所述细骨粒为中砂或粗砂,细度模数大于2.5,含水率为5-7%,含泥量小于等于3%。The fine bone particles are medium sand or coarse sand, the fineness modulus is greater than 2.5, the moisture content is 5-7%, and the mud content is less than or equal to 3%.
所述喷射机为转子式—Ⅱ型喷浆机,喷枪为双水环锥形喷头;喷枪设置双水环,环上钻有微孔,经水压射出细的水流,水流呈交叉网状,充分润湿物料。The spraying machine is a rotor type-II type spraying machine, and the spraying gun is a double water ring conical spraying head; Wet the material well.
所述喷射机喷射过程中的风压为0.12-0.17MPa,水压为0.18-0.21MPa。The wind pressure in the spraying process of the jet machine is 0.12-0.17MPa, and the water pressure is 0.18-0.21MPa.
JCT-1堆喷混凝土外加剂是采用机械研磨法进行细化的无机纳米级材料,是一种集促凝、早强、减水为一体的多效多功能型外加剂,呈灰白色粉末状,无毒无味,不燃,容重为200~300Kg/m3,密度为2.1~2.3g/cm3,粒径为0.3~0.5μm,在使用过程中对人体无不良影响。试验使用JCT-1堆喷混凝土外加剂时,标准养护28天后的C35混凝土强度可达35~36MPa,没有降压损失。JCT-1 shotcrete admixture is an inorganic nano-scale material refined by mechanical grinding method. It is non-toxic, tasteless, non-flammable, with a bulk density of 200~300Kg/m 3 , a density of 2.1~2.3g/cm 3 , a particle size of 0.3~0.5μm, and no adverse effects on the human body during use. When JCT-1 shotcrete admixture is used in the test, the strength of C35 concrete after standard curing for 28 days can reach 35~36MPa, and there is no depressurization loss.
堆喷墙内放置的钢筋笼由8#钢筋焊接的网孔尺寸为100mm的钢筋网片和连接钢筋构成,钢筋网片的宽度为堆喷墙的设计宽度,钢筋网片的高度为堆喷墙的设计高度,相邻钢筋网片之间连接钢筋的间排距为0.5m,连接钢筋的长度1.0m。The reinforcement cage placed in the spray wall is composed of steel mesh with a mesh size of 100mm welded by 8# steel bars and connecting steel bars. The width of the steel mesh is the design width of the spray wall, and the height of the steel mesh is the height of the spray wall. The design height is 0.5m and the length of the connecting bars is 1.0m.
堆喷筑墙作业至少配备两名施工人员,一人负责手持喷头进行堆喷,另一人辅助照明并负责联络,观察工作场所围岩安全和堆喷墙体质量。There should be at least two construction workers for the construction of walls by spraying and spraying, one of whom is responsible for spraying with a hand-held sprinkler, the other is responsible for auxiliary lighting and liaison, and observes the safety of surrounding rocks in the workplace and the quality of the sprayed wall.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810566315.0A CN108825301B (en) | 2018-06-05 | 2018-06-05 | Quick wall building method for underground coal mine through pile-spraying concrete |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810566315.0A CN108825301B (en) | 2018-06-05 | 2018-06-05 | Quick wall building method for underground coal mine through pile-spraying concrete |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108825301A CN108825301A (en) | 2018-11-16 |
CN108825301B true CN108825301B (en) | 2020-07-03 |
Family
ID=64143696
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810566315.0A Active CN108825301B (en) | 2018-06-05 | 2018-06-05 | Quick wall building method for underground coal mine through pile-spraying concrete |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108825301B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111140280B (en) * | 2019-12-23 | 2021-04-13 | 太原理工大学 | A method for reinforcing and blocking water of gob-side roadway coal pillar-assisted shotcrete wall |
CN111018445B (en) * | 2019-12-27 | 2022-03-01 | 陕西煤业化工技术研究院有限责任公司 | A kind of material for permanent sealing wall in underground coal mine and method for establishing the sealing wall |
CN113931692B (en) * | 2021-11-01 | 2024-05-14 | 太原理工大学 | Quick sealing wall construction method for coal mine emergency rescue |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000247715A (en) * | 1999-02-24 | 2000-09-12 | Chugoku Electric Power Co Inc:The | Concrete for wet spraying |
DE10310599A1 (en) * | 2003-03-11 | 2004-09-23 | Linde Ag | Spraying concrete spray onto an object via nozzles with addition of carbon dioxide to the concrete useful as a safety measure in tunnel and side wall construction and for construction of mine walls |
CN101915109A (en) * | 2010-08-06 | 2010-12-15 | 中国矿业大学 | A Concrete Spraying Method for Dust Reduction and Bomb Reduction |
CN102777208A (en) * | 2012-08-02 | 2012-11-14 | 兖州煤业股份有限公司 | Method for constructing mining impact-resisting sealed wall |
CN107382214A (en) * | 2017-08-29 | 2017-11-24 | 北京铁建永泰新型建材有限公司昌平分公司 | A kind of concrete mix for the mass concrete construction of phase in autumn and its construction method for pouring wall |
CN108005685A (en) * | 2017-12-12 | 2018-05-08 | 中铁十八局集团有限公司 | A kind of anchor spraying concrete wall for grouting construction method |
-
2018
- 2018-06-05 CN CN201810566315.0A patent/CN108825301B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000247715A (en) * | 1999-02-24 | 2000-09-12 | Chugoku Electric Power Co Inc:The | Concrete for wet spraying |
DE10310599A1 (en) * | 2003-03-11 | 2004-09-23 | Linde Ag | Spraying concrete spray onto an object via nozzles with addition of carbon dioxide to the concrete useful as a safety measure in tunnel and side wall construction and for construction of mine walls |
CN101915109A (en) * | 2010-08-06 | 2010-12-15 | 中国矿业大学 | A Concrete Spraying Method for Dust Reduction and Bomb Reduction |
CN102777208A (en) * | 2012-08-02 | 2012-11-14 | 兖州煤业股份有限公司 | Method for constructing mining impact-resisting sealed wall |
CN107382214A (en) * | 2017-08-29 | 2017-11-24 | 北京铁建永泰新型建材有限公司昌平分公司 | A kind of concrete mix for the mass concrete construction of phase in autumn and its construction method for pouring wall |
CN108005685A (en) * | 2017-12-12 | 2018-05-08 | 中铁十八局集团有限公司 | A kind of anchor spraying concrete wall for grouting construction method |
Also Published As
Publication number | Publication date |
---|---|
CN108825301A (en) | 2018-11-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105041336B (en) | A kind of very-high performance hybrid fiber concrete shield duct piece and preparation method thereof | |
CN103216239B (en) | Backfill handling method for activity subsidence area of mine | |
CN109956712A (en) | System and technology of continuous building recycled aggregate filling coal mine goaf | |
CN108825301B (en) | Quick wall building method for underground coal mine through pile-spraying concrete | |
CN108316346B (en) | A green treatment method for abandoned underground shelters | |
CN105464006B (en) | A kind of masonry arch bridge ruggedized construction and its construction method | |
CN106082901B (en) | A kind of the green concrete prefabricated pile and construction method of strengthening soft foundation | |
CN106866085A (en) | Special grouting material and its grouting method are reinforced in a kind of high-speed railway subgrade repairing | |
CN104711976B (en) | A kind of construction refuse regenerated aggregate complex carrier stake and preparation method thereof | |
CN104278841A (en) | Method for pouring concrete in steel pipe column | |
CN104711974A (en) | Steel tube recycled concrete composite bearing base pile and manufacturing method thereof | |
CN103603676A (en) | Scraper roadway supporting method | |
CN107989049A (en) | A kind of construction method of frame bank protection | |
CN100361927C (en) | Subsequent backfilled pea gravel concrete for lining back of tunnels and backfilling method | |
CN116427396A (en) | Stirring pile construction method and composite pile construction method thereof | |
CN108439867A (en) | Using the rock-fill dams and its construction method of seamless panel | |
CN117105546B (en) | Metal-rich cement additive and application thereof in improving concrete performance by using reinforcing steel bars | |
CN108383470B (en) | Grouting material cooperatively prepared from red mud and steel slag and preparation method thereof | |
CN110984079A (en) | Construction method of self-compacting concrete rock-fill dam | |
CN117003537A (en) | Indoor floor settlement grouting material on soft soil foundation and its reinforcement method | |
Sun et al. | Develop a sustainable wet shotcrete for tunnel lining using industrial waste: a field experiment and simulation approach | |
CN114482409A (en) | Top-cast pouring construction method for self-compacting concrete of tubular column | |
CN111088804A (en) | Construction method of high-flow-state fine-aggregate concrete rock-fill dam in high-temperature area of equator | |
CN112983479A (en) | Roadway surrounding rock sealing protection method | |
CN107935626B (en) | Construction method of rapid-hardening early-strength road |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |