CN112983479A - Roadway surrounding rock sealing protection method - Google Patents

Roadway surrounding rock sealing protection method Download PDF

Info

Publication number
CN112983479A
CN112983479A CN202110202398.7A CN202110202398A CN112983479A CN 112983479 A CN112983479 A CN 112983479A CN 202110202398 A CN202110202398 A CN 202110202398A CN 112983479 A CN112983479 A CN 112983479A
Authority
CN
China
Prior art keywords
surrounding rock
thin
spraying
layer
roadway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110202398.7A
Other languages
Chinese (zh)
Other versions
CN112983479B (en
Inventor
梁海刚
黄克军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Coal and Chemical Technology Institute Co Ltd
Original Assignee
Shaanxi Coal and Chemical Technology Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Coal and Chemical Technology Institute Co Ltd filed Critical Shaanxi Coal and Chemical Technology Institute Co Ltd
Priority to CN202110202398.7A priority Critical patent/CN112983479B/en
Publication of CN112983479A publication Critical patent/CN112983479A/en
Application granted granted Critical
Publication of CN112983479B publication Critical patent/CN112983479B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/34Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing cold phosphate binders
    • C04B28/344Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing cold phosphate binders the phosphate binder being present in the starting composition solely as one or more phosphates
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/006Lining anchored in the rock
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/91Use of waste materials as fillers for mortars or concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Architecture (AREA)
  • Ceramic Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Inorganic Chemistry (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

本发明公开了一种巷道围岩封闭防护方法,在巷道围岩整体性未破坏之前,对巷道裸露围岩喷涂薄层喷涂浆料,薄层喷涂浆料在巷道裸露围岩表面形成连续致密的封闭层;其中,封闭层的厚度为15‑20mm,薄层喷涂浆料采用环保无筋高性能薄层喷涂材料与水混合配制得到;本发明薄层喷涂浆料采用湿式喷涂,薄层喷涂浆料能够渗透至围岩体表面的缝隙中,并有效粘接围岩表面缝隙,较强的粘结力能够恢复围岩的整体自稳性,避免了在围岩动压变化导致的逐步收敛变形时,影响深部围岩继续风化或失稳;薄层喷涂浆料具有较好的触变性,在喷涂工艺作用下能很容易渗透到巷道围岩表面的缝隙或裂隙中,进而较快速地固结;恢复围岩表面的整体连续性,有效地控制围岩的初始变形。

Figure 202110202398

The invention discloses a method for sealing and protecting the surrounding rock of a roadway. Before the integrity of the surrounding rock of the roadway is not damaged, a thin-layer spraying slurry is sprayed on the exposed surrounding rock of the roadway. The sealing layer; wherein, the thickness of the sealing layer is 15-20mm, and the thin-layer spraying slurry is prepared by mixing an environmentally friendly non-reinforced high-performance thin-layer spraying material with water; the thin-layer spraying slurry of the present invention adopts wet spraying, and the thin-layer spraying slurry The material can penetrate into the gaps on the surface of the surrounding rock mass, and effectively bond the gaps on the surface of the surrounding rock. The strong bonding force can restore the overall self-stability of the surrounding rock and avoid the gradual convergence deformation caused by changes in the dynamic pressure of the surrounding rock. When the spraying process occurs, it will affect the continued weathering or instability of the deep surrounding rock; the thin-layer spraying slurry has good thixotropy, and can easily penetrate into the gaps or fissures on the surface of the surrounding rock of the roadway under the action of the spraying process, and then consolidate more quickly. ; Restore the overall continuity of the surrounding rock surface and effectively control the initial deformation of the surrounding rock.

Figure 202110202398

Description

Roadway surrounding rock sealing protection method
Technical Field
The invention belongs to the technical field of roadway support, and particularly relates to a roadway surrounding rock closed protection method.
Background
The tunnel or the coal mine underground tunnel exposed surrounding rock sealing protection is usually protected by sprayed concrete, so that the coal bed is prevented from cracking, the internal coal is prevented from being oxidized, toxic and harmful gas in the coal bed is prevented from leaking into the tunnel, the sealing property and the durability of the coal bed and the integral integrity of the surrounding rock are improved, and the supporting body is prevented from being corroded and destabilized under the action of underground water gas and corrosive gas, so that the supporting failure and the safety accidents caused by the oxidation and weathering of the surrounding rock are prevented.
At present, the traditional concrete guniting material has the defects of poor compactness, poor bonding effect, high brittleness, easy cracking and peeling, high dust pollution, high spray resilience, high labor intensity and the like; and the method consumes great manpower and materials, has higher cost and poorer sealing protection effect, is difficult to adapt to the safety production requirement and the high-yield and high-efficiency development of modern coal mines, seriously restricts the rapid tunneling of the tunnel or tunnel and increases the production cost.
Disclosure of Invention
Aiming at the technical problems in the prior art, the invention provides a roadway surrounding rock sealing protection method, which aims to solve the technical problems of poor compactness, poor bonding effect, high brittleness, easy cracking and peeling and high injection resilience of the existing surrounding rock sealing protection.
In order to achieve the purpose, the invention adopts the technical scheme that:
the invention discloses a roadway surrounding rock sealing protection method, which comprises the steps of spraying thin-layer spraying slurry on exposed roadway surrounding rocks before the integrity of the roadway surrounding rocks is not damaged, wherein the thin-layer spraying slurry forms a continuous compact sealing layer on the surfaces of the exposed roadway surrounding rocks;
wherein, the thickness of the sealing layer is 15-20mm, and the thin layer spraying slurry is prepared by mixing an environment-friendly non-rib high-performance thin layer spraying material and water; the environment-friendly non-rib high-performance thin-layer spraying material is prepared from phosphorus-magnesium cement, sand, fibers, rubber powder, nano-grade micro-powder and an additive.
And further, after 3-4 cycles of tunneling and top plate supporting are completed, spraying thin-layer spraying slurry on the exposed surrounding rock of the roadway.
Further, when the environment-friendly non-rib high-performance thin-layer spraying material is mixed with water, the mass ratio of the environment-friendly non-rib high-performance thin-layer spraying material to the water is (0.2-0.23): 1; the initial setting time of the thin-layer spraying slurry is 40-60min, the final compressive strength is 60-80MPa, and the final flexural strength is 20-25 MPa;
wherein the sand adopts medium sand; the fiber adopts polypropylene fiber, the rubber powder adopts tire rubber powder, the nano-scale micro-powder adopts nano-scale slag micro-powder, and the additive adopts a high-efficiency polycarboxylic acid water reducing agent.
Further, wet spraying the thin-layer spraying slurry by using a pneumatic wet spraying machine; the pneumatic wet spraying machine comprises a stirring barrel, a water tank, a material conveying mechanism, a hopper bin, a high-pressure material conveying pipe, a spray gun and a high-pressure air pipe;
one side of the stirring barrel is provided with a water inlet which is connected with the water tank; the opposite side of agitator sets up the drain hole, and the hopper storehouse sets up in the below of drain hole, and defeated material mechanism sets up in the below of hopper storehouse, and the feed inlet of defeated material mechanism is connected with the discharge gate of hopper storehouse, and the discharge gate of defeated material mechanism passes through high-pressure conveying pipeline to be connected with the feed end of spray gun, and the one end and the high-pressure air supply of high-pressure blast pipe are connected, and the other end is connected with the air inlet end of spray gun.
Further, a stirring motor is arranged at the bottom of the stirring barrel, the output end of the stirring motor extends into the stirring barrel, and a stirring blade is arranged at the output end of the stirring motor; the material conveying mechanism comprises a material conveying motor and a screw pump, the output end of the material conveying motor is connected with the input end of the screw pump, and the feed inlet of the screw pump is connected with the discharge outlet of the hopper bin;
the pneumatic wet spraying machine further comprises a power control box, the input end of the power control box is connected with a high-pressure air source through a high-pressure air interface, the first output end of the power control box is connected with the stirring motor, and the second output end of the power control box is connected with the material conveying motor.
Further, the pneumatic wet spraying machine also comprises a frame, wherein the stirring barrel, the water tank, the material conveying mechanism and the hopper bin are all arranged on the frame; the bottom of the frame is provided with rollers.
Further, when the pneumatic wet spraying machine is used for spraying, the specific process is as follows:
step 1, adding a dry powder environment-friendly non-rib high-performance thin-layer spraying material into a stirring barrel, and adding water into a water tank; according to a preset water-cement ratio, introducing water in a water tank into a stirring barrel, and stirring and mixing the environment-friendly non-rib high-performance thin-layer spraying material and the water to obtain thin-layer spraying slurry;
step 2, conveying the prepared thin-layer spraying slurry to a spray gun through a high-pressure air pipe by a material conveying mechanism;
step 3, conveying high-pressure air into a spray gun through a high-pressure air pipe, atomizing the thin-layer spraying slurry by using the high-pressure air, and spraying the atomized thin-layer spraying slurry on a sprayed surface through the spray gun; and forming a continuous compact closed layer on the exposed surrounding rock surface of the roadway by thin-layer spraying slurry.
Further, in the step 1, when the environment-friendly non-rib high-performance thin-layer spraying material is stirred and mixed with water, the mixing and stirring time is 2-3min, and the mixture is stirred until slurry of the thin-layer spraying slurry is uniformly mixed, the color is consistent, and the sagging prevention height is 2-3 cm; in the step 3, the distance between the spray gun and the sprayed surface is 1-2cm, and the spray gun is vertical to the sprayed surface.
Further, the spraying process adopts linear spraying or spiral spraying; the spraying process adopts repeated spraying in different times, the thickness of each spraying is not more than 5mm, after the sprayed surface is dried last time, the next repeated spraying is carried out until the spraying thickness meets the preset requirement.
Further, after the thin-layer spraying slurry is sprayed for 1-2 hours, anchor cable construction is carried out on the closed layer.
Compared with the prior art, the invention has the beneficial effects that:
the invention provides a roadway surrounding rock sealing protection method, which is characterized in that before the integrity of the roadway surrounding rock is not damaged, a thin layer of spraying slurry is sprayed on the exposed roadway surrounding rock, and the thin layer of spraying slurry is prepared by mixing an environment-friendly non-rib high-performance thin layer spraying material and water; the thin-layer spraying slurry is sprayed in a wet mode, the thin-layer spraying slurry can penetrate into gaps on the surface of the surrounding rock and can be effectively bonded with the gaps on the surface of the surrounding rock, the overall stability of the surrounding rock can be recovered through strong bonding force, and the influence on continuous weathering or instability of deep surrounding rock due to cracking when the surrounding rock gradually converges and deforms due to dynamic pressure change of the surrounding rock is avoided; the thin-layer spraying slurry has better thixotropy, can easily permeate into gaps or cracks on the surface of the roadway surrounding rock under the action of a spraying process, further quickly concretes, recovers the integral continuity of the surface of the surrounding rock, has the compression strength and the rupture strength of a spraying layer more than 3-4 times of those of the traditional concrete material, and can effectively control the initial deformation of the surrounding rock; meanwhile, the sealing layer and the drawing effect of the anchor rod have good supporting synergistic effect, and a supporting and protecting ring effect can be effectively formed on the surface layer of the roadway, so that the anti-cracking, anti-weathering and integral supporting effects of the roadway are effectively improved.
Further, the mass ratio of the environment-friendly non-rib high-performance thin-layer spraying material to water is (0.2-0.23): 1, the water-cement ratio of the thin-layer spraying slurry is within the section proportion, and various mechanical properties such as compressive strength, flexural strength and the like of the material reach the optimal performance; setting the initial setting time of the thin-layer spraying slurry to be 40-60min, setting the compressive strength of the initial material of the material to be 60-80MPa, and setting the flexural strength to be 20-25 MPa; the compressive strength and the breaking strength of the material are improved, the cracking resistance, the brittleness and the stress concentration are improved, and the problem of compactness is solved.
Furthermore, a pneumatic wet spraying machine is adopted for wet spraying, so that the problems of large dust, roadway environment pollution, incapability of using electric equipment for the return air flow roadway and the like in construction operation are solved, and the adaptability is good; the water-cement ratio is proportioned by a quantitative water tank of the wet spraying machine, the wet spraying slurry is formed by mixing through a stirring motor, and then the wet spraying slurry is sprayed on a sprayed surface through a conveying screw to a spray gun.
Furthermore, the controller is arranged to intensively distribute high-pressure air to the stirring motor and the material conveying motor, so that the high-pressure air is distributed, and the high-pressure air distribution device has good effects on high-pressure pipeline disorder of equipment, equipment safety and pneumatic air flow control.
Further, the stirring barrel, the water tank, the material conveying mechanism and the hopper bin are all installed on the rack, and the rollers are arranged on the rack, so that the pneumatic wet spraying machine is convenient to move, and the working efficiency of the equipment is improved.
Furthermore, a wet spraying machine is adopted for spraying, the quantitative and proportional water-cement ratio can be realized, the integration of stirring, conveying and atomization is realized, the labor intensity of construction is reduced, the dust pollution is reduced, the thin layer spraying is realized, and the rebound rate and the sagging problem are reduced.
Furthermore, anchor cable construction is carried out on the closed protective slurry coating, so that metal anchor net construction is replaced, and the tunneling efficiency is improved; according to incomplete statistics, the tunneling coal cutting time accounts for 17% -34%, the anchoring and protecting time accounts for 50% -67%, a large amount of time is spent on anchoring and protecting the upper part, the transportation and the stretching of an anchor net, the guniting process cannot be operated in parallel with the tunneling, supporting and other processes, and the traditional guniting process has the defects of large transportation amount, high labor intensity, large dust and no environmental protection of polluted roadways, so that the method becomes a main factor for restricting rapid tunneling; in the invention, the parallel operation of the processes of guniting, tunneling, supporting and the like is realized by adopting the construction of the anchor rod cable on the closed layer, so that the construction time is greatly saved, the construction efficiency is higher, the transportation amount of the guniting process is small, the labor intensity is low, the wet-type spraying dust is less, and the pollution to the roadway is less.
In summary, the roadway surrounding rock sealing protection method adopts the mode that the thin-layer spraying slurry is sprayed on the exposed surrounding rock of the roadway to replace a metal anchor net, so that the surrounding rock can be sealed and can also be anchored; thin layer spraying is carried out, the thickness of the coating is 15-20mm, and the problem of thick spraying cracking of the traditional material is solved; the environment-friendly non-rib high-performance thin-layer spraying material is directly mixed with water, so that the proportioning is accurate and simple, and the field operation is convenient; the construction is quick and simple, the working procedures are simple and convenient, and each shift is at least 30-50 meters; the construction equipment is pneumatic, so that the safety, reliability and flexibility are high; the method has the advantages of real wet spraying, no dust pollution, no resilience and environmental friendliness; the labor intensity is low, and about 3 persons are needed for one class; the material transport volume is 1/30 for traditional materials; meanwhile, the invention saves 20% of the time of roadway excavation consumed by the transportation and the stretching of the anchor net and 30% of the time of roadway excavation occupied by the concrete sealing protection of the surface of the surrounding rock, realizes the development of the rapid roadway excavation technology and reduces the production cost; the invention can be used in the technical fields of safety and support of coal mines, tunnels and the like, meets the rapid sealing protection effect on exposed surrounding rocks, supporting bodies and the like of a coal mine tunnel, and realizes the replacement of anchor nets by rapid tunneling of the tunnel.
Drawings
FIG. 1 is a schematic view of a wet shotcrete machine according to the present invention;
fig. 2 is a schematic diagram of a supporting mechanism of the thin layer spraying slurry of the present invention.
The device comprises a stirring barrel 1, a water tank 2, a material conveying mechanism 3, a hopper bin 4, a high-pressure material conveying pipe 5, a spray gun 6, a high-pressure air pipe 7, a spraying surface 8, a power control box 9, a high-pressure air interface 10, a stirring motor 11, a discharge hole 12, a material conveying motor 13, a screw pump 14 and a rack 15.
Detailed Description
In order to make the technical problems, technical solutions and advantageous effects of the present invention more apparent, the following embodiments further describe the present invention in detail. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
The invention provides a roadway surrounding rock sealing protection method, which is characterized in that before the integrity of the roadway surrounding rock is not damaged, namely after the roadway is tunneled and a top plate is supported for 3-4 cycles, thin-layer spraying slurry is adopted for spraying the exposed roadway surrounding rock; thin-layer spraying slurry on the surface of the exposed surrounding rock of the roadway to form a continuous and compact closed layer; and after the thin-layer spraying slurry is sprayed for 1-2h, carrying out anchor cable construction on the closed protective slurry coating.
Wherein, the thickness of the sealing layer is 15-20mm, and the thin layer spraying slurry is prepared by mixing an environment-friendly non-rib high-performance thin layer spraying material and water; when the environment-friendly non-rib high-performance thin-layer spraying material is mixed with water, the mass ratio of the environment-friendly non-rib high-performance thin-layer spraying material to the water is (0.2-0.23): 1; the initial setting time of the thin-layer spraying slurry is 40-60min, the final compressive strength is 60-80MPa, and the final flexural strength is 20-25 MPa; the thin layer spraying slurry is subjected to wet spraying by a pneumatic wet spraying machine.
In the invention, the environment-friendly non-rib high-performance thin-layer spraying material is prepared from phosphorus-magnesium cement, sand, fiber, rubber powder, nano-grade micro-powder and an additive; wherein the sand is medium sand with fineness modulus of 2.6 and mud content<0.5 percent; the fiber is polypropylene fiber, the tensile strength of the polypropylene fiber is more than or equal to 450MPa, the elastic modulus is more than or equal to 3000, the elongation at break is less than or equal to 30 percent, and the length is 6-8 mm; the rubber powder is tire rubber powder, preferably 40-mesh waste tire rubber powder; the nanometer micro powder is slag micro powder with fineness of 400-450m2Per kg; the additive adopts a high-efficiency polycarboxylic acid water reducing agent.
As shown in the attached figure 1, the pneumatic wet spraying machine comprises a stirring barrel 1, a water tank 2, a material conveying mechanism 3, a hopper bin 4, a high-pressure material conveying pipe 5, a spray gun 6, a high-pressure air pipe 7, a power control box 9 and a frame 15; the stirring barrel 1, the water tank 2, the material conveying mechanism 3, the hopper bin 4, the high-pressure conveying pipe 5, the spray gun 6, the high-pressure air pipe 7 and the power control box 9 are all installed on a rack 15, and rollers are arranged on the rack 15.
One side of the stirring barrel 1 is provided with a water inlet which is connected with the water tank 2; the opposite side of agitator 1 sets up drain hole 12, and hopper storehouse 4 sets up the below at drain hole 12, and defeated material mechanism 3 sets up the below at hopper storehouse 4, and the feed inlet of defeated material mechanism 3 is connected with the discharge gate of hopper storehouse 4, and the discharge gate of defeated material mechanism 3 passes through high-pressure delivery pipe 5 to be connected with the feed end of spray gun 6, and the one end and the high-pressure wind source of high-pressure plenum duct 7 are connected, and the other end is connected with the air inlet end of spray gun 6.
The bottom of the stirring barrel 1 is provided with a stirring motor 11, the output end of the stirring motor 11 extends into the stirring barrel 1, and the output end of the stirring motor 11 is provided with a stirring blade; the material conveying mechanism 3 comprises a material conveying motor 13 and a screw pump 14, the output end of the material conveying motor 13 is connected with the input end of the screw pump 14, and the feed inlet of the screw pump 14 is connected with the discharge outlet of the hopper bin 4;
the input end of the power control box 9 is connected with a high-pressure air source through a high-pressure air interface 10, the first output end of the power control box 9 is connected with a stirring motor 11, and the second output end of the power control box is connected with a material conveying motor 13; in the invention, the power control box 9 is of a three-way structure and is used for shunting high-pressure air, and a protective cover is arranged on the outer side of the three-way structure.
When the pneumatic wet spraying machine is used for spraying, the specific process is as follows:
step 1, adding a dry powder environment-friendly non-rib high-performance thin-layer spraying material into a stirring barrel 1, and adding water into a water tank 2; according to a preset water-cement ratio, introducing water in a water tank 2 into a stirring barrel 1, and stirring and mixing the dry powder environment-friendly non-rib high-performance thin-layer spraying material and the water to obtain thin-layer spraying slurry; when the environment-friendly non-rib high-performance thin-layer spraying material is stirred and mixed with water, the mixing and stirring time is not more than 5min, preferably 2-3 min; the stirring speed is based on the condition that the slurry is not thrown out; stirring until the slurry of the thin-layer spraying slurry is uniformly mixed, the color is consistent, the consistency is proper, the slurry has fluidity, and the sagging prevention height is 2-3 cm.
Step 2, conveying the prepared thin-layer spraying slurry to a spray gun 6 through a high-pressure conveying pipe by a conveying mechanism 3;
3, conveying high-pressure air into a spray gun 6 through a high-pressure air pipe 7, atomizing the thin-layer spraying slurry by using the high-pressure air, and finally spraying the atomized thin-layer spraying slurry on a sprayed surface 8 through the spray gun 6; forming a continuous compact sealing layer on the exposed surrounding rock surface of the roadway by thin-layer spraying slurry; wherein, the distance between the spray gun 6 and the sprayed surface 8 is 1-2cm, and the spray gun 6 is vertical to the sprayed surface 8; the spraying process adopts in-line spraying or spiral spraying; wherein, the horizontal or longitudinal spraying mode is adopted in the linear spraying mode, and the material is sprayed in the spiral mode by a spray gun 6 in the spiral spraying mode; the spraying process adopts repeated spraying in different times, the thickness of each spraying is not more than 5mm, after the sprayed surface is dried last time, the next repeated spraying is carried out until the spraying thickness meets the preset requirement; the sagging phenomenon is prevented, and the rebound rate is reduced; for cracks or pipe holes and the like with larger surface of the surrounding rock, plugging is firstly carried out by plugging articles, and then uniform spraying is carried out.
The invention relates to a roadway surrounding rock sealing protection method, in particular to a roadway surrounding rock thin-layer spraying material and a process method which are safe, environment-friendly, high in compression resistance and fracture resistance, flame-retardant, antistatic, low in cost, quick in construction and capable of replacing an anchor net; the thin-layer spraying material is stirred and mixed with water in a fixed ratio by adopting a pneumatic wet spraying machine, and is directly sprayed to the surface of the surrounding rock of the roadway after atomization to form a thin-layer, continuous, compact, high-pressure-resistant, fracture-resistant and crack-resistant sealing layer.
The roadway surrounding rock sealing protection method can improve the tightness and durability of the coal bed and the overall integrity of the surrounding rock, and prevent the support body from being corroded and destabilized under the action of underground moisture and corrosive gas, so that the support fails and the surrounding rock is subjected to safety accidents such as spontaneous combustion, oxidation, weathering and the like; meanwhile, the novel environment-friendly guniting method can replace an anchor net and shotcrete in a roadway support body, reduce supporting cost, labor cost and transportation cost and reduce roadway air dust pollution caused by traditional concrete dry guniting, and improve the rapid tunneling efficiency.
In the invention, the use method of the pneumatic wet spraying machine comprises the following steps:
when the pneumatic wet spraying machine is used for spraying the thin-layer spraying slurry, a quantitative environment-friendly rib-free high-performance thin-layer spraying material and quantitative water of a water tank are stirred and mixed in a stirring barrel according to a certain water-cement ratio, the mixture is conveyed to a spray gun through a screw pump and a high-pressure conveying pipe, the mixed wet material is atomized with high-pressure air at the spray gun and is sprayed to a sprayed surface of roadway surrounding rock, and a continuous and compact sealing layer with the thickness of 15-20mm is formed; and finishing the spraying of one sprayed surface, and transferring to the next sprayed surface for circulation.
In the using process of the pneumatic wet spraying machine, the high-pressure air is connected to the wet spraying machine through the high-pressure air pressing interface; pouring a certain amount of the environment-friendly non-rib high-performance thin-layer spraying material into a stirring barrel, and putting a certain amount of water in a water tank into the stirring barrel; the high-pressure air distributed in the power control box drives the stirring motor to fully stir the water in the stirring barrel and the environment-friendly rib-free high-performance thin-layer spraying material; the stirred thin-layer spraying slurry is put into a hopper bin through a discharge hole at the bottom of the stirring barrel and then enters a screw pump; the high-pressure air distributed by the power control box drives a motor of the screw pump to convey the stirred thin-layer spraying slurry to a spray gun through a high-pressure conveying pipe; at the spray gun, the spray paint is atomized by high-pressure air in a high-pressure air pipe and sprayed to the sprayed surface of the surrounding rock of the roadway to form a continuous compact closed layer.
As shown in the attached figure 2, the roadway surrounding rock closed protection method disclosed by the invention has the advantages that the thin-layer spraying slurry is sprayed on the exposed surrounding rock surface of the roadway in a wet mode, the thin-layer spraying slurry permeates into gaps on the surface of the surrounding rock body, the surface gaps are effectively bonded, and the overall self-stability of the surrounding rock can be recovered through the strong bonding force of the surface gaps; the thin-layer spraying slurry forms a continuous and compact closed layer on the exposed surrounding rock surface of the roadway, and the functions of the thin-layer spraying slurry are mainly shown in the following aspects:
the bearing shell acts as follows:
the sealing layer bears external load through self compression strength and bending strength, the function of the sealing layer is represented as 'bearing (arching)' for bearing transverse or longitudinal pressure in a stress control mode, and the section of the sealing layer bears normal stress, shearing force and bending moment and is represented as 'bearing basket' function on a loose block body when the sealing layer and the anchor rod act together in a structure control mode; meanwhile, the sealing layer is thin and has strong tensile and ductility, so that the function of the bearing basket is larger.
Cementing action:
the bonding between the sealing layer and the rock surface and the cementing effect of the sealing layer penetrating into the cracks of the surrounding rock cover the tensile strength and the breaking strength; the bonding effect between the sealing layer and the rock surface is embodied in the adhesive strength between the spray layer and the rock surface, so that the synchronism of the displacement of the surrounding rock and the sealing layer under the action of stress is ensured; the cementation action infiltrated into the cracks of the surrounding rock cementation the cracks through the adhesive strength of the material and the rock mass and the tensile strength and the shear strength of the material and the rock mass under the action of the tensile stress and the shear stress, the joint cohesion is improved, a local composite bearing arch structure is formed, and the modern supporting concept of the combined action of the sealing layer and the surrounding rock is embodied.
Wedge action
Two conditions are required for collapse of surrounding rocks of the roadway: firstly, the applied active force is larger than the resistance between the blocks, and secondly, the rock blocks have enough shearing and expanding space in the sliding process; when the thin-layer spraying slurry permeates into the cracks, the crack space is filled as if a wedge is filled, the rock mass can be kept stable in the falling process because of insufficient shear expansion space, and meanwhile, the whole compressive strength of the rock mass is increased because joints are filled like grouting.
The above-described embodiment is only one of the embodiments that can implement the technical solution of the present invention, and the scope of the present invention is not limited by the embodiment, but includes any variations, substitutions and other embodiments that can be easily conceived by those skilled in the art within the technical scope of the present invention disclosed.

Claims (10)

1.一种巷道围岩封闭防护方法,其特征在于,在巷道围岩整体性未破坏之前,对巷道裸露围岩喷涂薄层喷涂浆料,薄层喷涂浆料在巷道裸露围岩表面形成连续致密的封闭层;1. a roadway surrounding rock sealing protection method, it is characterized in that, before roadway surrounding rock integrity is not destroyed, to roadway exposed surrounding rock spraying thin layer spraying slurry, thin layer spraying slurry forms continuous on the roadway exposed surrounding rock surface. dense sealing layer; 其中,封闭层的厚度为15-20mm,薄层喷涂浆料采用环保无筋高性能薄层喷涂材料与水混合配制得到;其中,环保无筋高性能薄层喷涂材料采用磷镁水泥、砂、纤维、胶粉、纳米级微粉及外加剂配制得到。Among them, the thickness of the sealing layer is 15-20mm, and the thin-layer spraying slurry is prepared by mixing environmentally friendly non-reinforced high-performance thin-layer spraying materials with water; among them, the environmentally-friendly non-reinforced high-performance thin-layer spraying materials are made of phosphorus-magnesium cement, sand, Fiber, rubber powder, nano-scale micro-powder and additives are prepared. 2.根据权利要求1所述的一种巷道围岩封闭防护方法,其特征在于,在巷道掘进并完成顶板支护3-4个循环后,对巷道裸露围岩喷涂薄层喷涂浆料。2 . The method for sealing and protecting the surrounding rock of a roadway according to claim 1 , wherein after the roadway is excavated and the roof support is completed for 3-4 cycles, the exposed surrounding rock of the roadway is sprayed with a thin layer of spraying slurry. 3 . 3.根据权利要求1所述的一种巷道围岩封闭防护方法,其特征在于,环保无筋高性能薄层喷涂材料与水混合时,环保无筋高性能薄层喷涂材料与水的质量比为(0.2-0.23):1;薄层喷涂浆料的初凝时间为40-60min,最终抗压强度为60-80MPa,最终抗折强度为20-25Mpa;3. a kind of roadway surrounding rock sealing protection method according to claim 1 is characterized in that, when environmental protection non-reinforced high-performance thin-layer spraying material is mixed with water, the mass ratio of environmental-friendly non-reinforced high-performance thin-layer spraying material to water is (0.2-0.23): 1; the initial setting time of the thin-layer spraying slurry is 40-60min, the final compressive strength is 60-80MPa, and the final flexural strength is 20-25Mpa; 其中,砂采用中砂;纤维采用聚丙烯纤维,胶粉采用轮胎橡胶粉,纳米级微粉采用纳米级矿渣微粉,外加剂采用高效聚羧酸减水剂。Among them, the sand is medium sand; the fiber is polypropylene fiber, the rubber powder is tire rubber powder, the nano-scale powder is nano-scale slag powder, and the admixture is high-efficiency polycarboxylate water reducer. 4.根据权利要求1所述的一种巷道围岩封闭防护方法,其特征在于,薄层喷涂浆料采用气动湿喷机进行湿式喷涂;气动湿喷机包括搅拌桶(1)、水箱(2)、输料机构(3)、料斗仓(4)、高压输料管(5)、喷枪(6)及高压风管(7);4. A kind of roadway surrounding rock sealing protection method according to claim 1, is characterized in that, thin-layer spraying slurry adopts pneumatic wet spraying machine to carry out wet spraying; the pneumatic wet spraying machine comprises mixing barrel (1), water tank (2) ), conveying mechanism (3), hopper bin (4), high-pressure conveying pipe (5), spray gun (6) and high-pressure air pipe (7); 搅拌桶(1)的一侧设置进水口,进水口与水箱(2)连接;搅拌桶(1)的另一侧设置放料口(12),料斗仓(4)设置在放料口(12)的下方,输料机构(3)设置在料斗仓(4)的下方,输料机构(3)的进料口与料斗仓(4)的出料口连接,输料机构(3)的出料口通过高压输料管(5)与喷枪(6)的进料端连接,高压风管(7)的一端与高压风源连接,另一端与喷枪(6)的进风端连接。One side of the mixing barrel (1) is provided with a water inlet, which is connected to the water tank (2); the other side of the mixing barrel (1) is provided with a discharging port (12), and the hopper bin (4) is provided at the discharging port (12). ), the feeding mechanism (3) is arranged below the hopper bin (4), the feeding port of the feeding mechanism (3) is connected with the discharging port of the hopper bin (4), and the output port of the feeding mechanism (3) is connected. The material port is connected with the feed end of the spray gun (6) through the high pressure material conveying pipe (5), one end of the high pressure air pipe (7) is connected with the high pressure air source, and the other end is connected with the air inlet end of the spray gun (6). 5.根据权利要求4所述的一种巷道围岩封闭防护方法,其特征在于,搅拌桶(1)的底部设置有搅拌马达(11),搅拌马达(11)的输出端伸入到搅拌桶(1)的内部,搅拌马达(11)的输出端上设置有搅拌叶片;输料机构(3)包括输料马达(13)及螺杆泵(14),输料马达(13)的输出端与螺杆泵(14)的输入端连接,螺杆泵(14)的进料口与料斗仓(4)的出料口连接;5. A method for protecting roadway surrounding rock according to claim 4, characterized in that a stirring motor (11) is provided at the bottom of the stirring barrel (1), and the output end of the stirring motor (11) extends into the stirring barrel Inside (1), a stirring blade is arranged on the output end of the stirring motor (11); the feeding mechanism (3) includes a feeding motor (13) and a screw pump (14), and the output end of the feeding motor (13) is connected to the feeding motor (13) and the screw pump (14). The input end of the screw pump (14) is connected, and the feed port of the screw pump (14) is connected with the discharge port of the hopper bin (4); 气动湿喷机还包括动力控制箱(9),动力控制箱(9)的输入端通过高压风接口(10)与高压风源连接,动力控制箱(9)的第一输出端与搅拌马达(11)连接,第二输出端与输料马达(13)连接。The pneumatic wet spraying machine further comprises a power control box (9), the input end of the power control box (9) is connected to the high pressure air source through the high pressure air interface (10), and the first output end of the power control box (9) is connected to the stirring motor ( 11) is connected, and the second output end is connected with the feeding motor (13). 6.根据权利要求4所述的一种巷道围岩封闭防护方法,其特征在于,气动湿喷机还包括机架(15),搅拌桶(1)、水箱(2)、输料机构(3)及料斗仓(4)均安装在机架(15)上;机架(15)的底部设置有滚轮。6. A method for sealing and protecting roadway surrounding rock according to claim 4, wherein the pneumatic wet spraying machine further comprises a frame (15), a mixing barrel (1), a water tank (2), a material conveying mechanism (3) ) and the hopper bin (4) are installed on the frame (15); the bottom of the frame (15) is provided with rollers. 7.根据权利要求5所述的一种巷道围岩封闭防护方法,其特征在于,利用气动湿喷机进行喷涂时,具体过程如下:7. a kind of roadway surrounding rock sealing protection method according to claim 5, is characterized in that, when utilizing pneumatic wet spraying machine to spray, concrete process is as follows: 步骤1、在搅拌桶(1)中加入干粉状环保无筋高性能薄层喷涂材料,在水箱(2)中加入水;按照预设水灰比,将水箱(2)中的水通入搅拌桶(1)中,对环保无筋高性能薄层喷涂材料与水进行搅拌混合,得到薄层喷涂浆料;Step 1. Add dry powder environmentally friendly, gluten-free, high-performance thin-layer spraying material into the mixing bucket (1), add water to the water tank (2), and pass the water in the water tank (2) into the water tank (2) according to the preset water-cement ratio. In the mixing bucket (1), the environmentally friendly non-reinforced high-performance thin-layer spraying material is stirred and mixed with water to obtain a thin-layer spraying slurry; 步骤2、将制备的薄层喷涂浆料通过输料机构(3)经高压风管输送至喷枪(6);Step 2, conveying the prepared thin-layer spraying slurry to the spray gun (6) through the high-pressure air pipe through the conveying mechanism (3); 步骤3、通过高压风管(7)将高压风输送至喷枪(6)中,利用高压风将薄层喷涂浆料进行雾化,并通过喷枪(6)将雾化后的薄层喷涂浆料喷涂在受喷面(8)上;使薄层喷涂浆料在巷道裸露围岩表面形成连续致密的封闭层。Step 3. The high-pressure air is transported to the spray gun (6) through the high-pressure air duct (7), the thin-layer spraying slurry is atomized by the high-pressure air, and the atomized thin-layer spraying slurry is sprayed through the spray gun (6). Spray on the sprayed surface (8); make the thin-layer sprayed slurry form a continuous and dense closed layer on the surface of the exposed surrounding rock of the roadway. 8.根据权利要求7所述的一种巷道围岩封闭防护方法,其特征在于,步骤1中,对环保无筋高性能薄层喷涂材料与水进行搅拌混合时,混合搅拌时间为2-3min,搅拌至薄层喷涂浆料的浆体混合均匀,颜色一致,不流挂高度为2-3cm;步骤3中,喷枪(6)与受喷面(8)之间的距离为1-2cm,喷枪(6)与受喷面(8)垂直。8. A method for protecting roadway surrounding rock according to claim 7, characterized in that, in step 1, when the environmentally friendly non-reinforced high-performance thin-layer spraying material is stirred and mixed with water, the mixing time is 2-3min , stir until the slurry of the thin-layer spraying slurry is evenly mixed, the color is consistent, and the non-sagging height is 2-3cm; in step 3, the distance between the spray gun (6) and the sprayed surface (8) is 1-2cm, The spray gun (6) is perpendicular to the spray surface (8). 9.根据权利要求1所述的一种巷道围岩封闭防护方法,其特征在于,喷涂过程采用一字喷涂或螺旋喷涂;喷涂过程采用分次往复喷涂,每次喷涂的厚度不超过5mm,待上次喷涂表面干燥后,进行下次复喷,至喷涂厚度满足预设要求。9. a kind of roadway surrounding rock sealing protection method according to claim 1, is characterized in that, spraying process adopts in-line spraying or spiral spraying; After the last sprayed surface is dry, carry out the next respray until the spray thickness meets the preset requirements. 10.根据权利要求1所述的一种巷道围岩封闭防护方法,其特征在于,薄层喷涂浆料喷涂完成1-2h后,在封闭层上进行锚杆索施工。10 . The method for sealing and protecting the surrounding rock of a roadway according to claim 1 , characterized in that 1-2 hours after the completion of spraying of the thin-layer spraying slurry, the anchor rod and cable construction is carried out on the sealing layer. 11 .
CN202110202398.7A 2021-02-23 2021-02-23 Roadway surrounding rock sealing protection method Active CN112983479B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110202398.7A CN112983479B (en) 2021-02-23 2021-02-23 Roadway surrounding rock sealing protection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110202398.7A CN112983479B (en) 2021-02-23 2021-02-23 Roadway surrounding rock sealing protection method

Publications (2)

Publication Number Publication Date
CN112983479A true CN112983479A (en) 2021-06-18
CN112983479B CN112983479B (en) 2023-06-02

Family

ID=76349777

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110202398.7A Active CN112983479B (en) 2021-02-23 2021-02-23 Roadway surrounding rock sealing protection method

Country Status (1)

Country Link
CN (1) CN112983479B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113771223A (en) * 2021-09-14 2021-12-10 铜陵化工集团新桥矿业有限公司 Underground dry self-propelled shotcrete machine

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070017418A1 (en) * 2005-07-25 2007-01-25 Dennis Andrew C Magnesium cementitious composition
CN103159439A (en) * 2011-12-16 2013-06-19 山东固安特工程材料有限公司 Spray-coating sealing material for coal rock mass
CN103912285A (en) * 2014-03-27 2014-07-09 神华集团有限责任公司 Coal mine roadway blocking method
CN104844103A (en) * 2015-04-01 2015-08-19 山东大学 Novel flexible composite shotcrete layer support material
CN108358564A (en) * 2018-05-11 2018-08-03 江南大学 A kind of high ductility cement-base composite material and preparation method thereof
CN109694231A (en) * 2019-02-22 2019-04-30 山东创能机械科技有限公司 A kind of phosphorus magnesia-based cements gunite material and its preparation method and application

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070017418A1 (en) * 2005-07-25 2007-01-25 Dennis Andrew C Magnesium cementitious composition
CN103159439A (en) * 2011-12-16 2013-06-19 山东固安特工程材料有限公司 Spray-coating sealing material for coal rock mass
CN103912285A (en) * 2014-03-27 2014-07-09 神华集团有限责任公司 Coal mine roadway blocking method
CN104844103A (en) * 2015-04-01 2015-08-19 山东大学 Novel flexible composite shotcrete layer support material
CN108358564A (en) * 2018-05-11 2018-08-03 江南大学 A kind of high ductility cement-base composite material and preparation method thereof
CN109694231A (en) * 2019-02-22 2019-04-30 山东创能机械科技有限公司 A kind of phosphorus magnesia-based cements gunite material and its preparation method and application

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113771223A (en) * 2021-09-14 2021-12-10 铜陵化工集团新桥矿业有限公司 Underground dry self-propelled shotcrete machine

Also Published As

Publication number Publication date
CN112983479B (en) 2023-06-02

Similar Documents

Publication Publication Date Title
CN111533519B (en) Flexible spraying material for tunnel roadway support and preparation method and application thereof
CN101915109B (en) Concrete spraying method for reducing dust and decreasing resilience
CN111533518B (en) Flexible spraying material for mine roadway support and preparation method and application thereof
CN104844103B (en) A kind of flexible compound concrete spray coating support protection material
CN109694231B (en) Phosphorus-magnesium-based cement guniting material and preparation method and application thereof
CN102155259A (en) Filling retaining wall constructed by using tunneling waste stones, and construction method of retaining wall
CN101439950B (en) Flexible coal powder foam concrete and preparation thereof
CN103693922A (en) Mining spraying material formula and application method
CN102352225A (en) Powder for plugging air leaking crack
CN106014476A (en) Overlying strata abscission layer grouting technology and device
CN113800870A (en) High-toughness thin-spraying material for rapid sealing and reinforcing underground coal mine and using method thereof
CN110788997B (en) Foam concrete filling device and application thereof and foam concrete filling method
CN108825301B (en) Quick wall building method for underground coal mine through pile-spraying concrete
CN112983479A (en) Roadway surrounding rock sealing protection method
CN105626097B (en) Thin-spraying sealing material, thin-spraying sealing method and open type powder spraying equipment
CN117588232A (en) Small coal pillar gob-side entry driving, roof cutting, roadway protecting and thin grouting reinforcement method
CN206635762U (en) A kind of wind spraying aid type concrete sprayer
KR20080034103A (en) Deteriorated Concrete Repair Method Using Uniform Dispersion System of Cement Mortar Reinforcing Fiber
CN103496901B (en) Country rock wet shot concrete method inferior
CN112300611B (en) Mining wet type thin spraying material and application thereof
CN112780336A (en) Pressure leaching type filling mining process
CN108439910A (en) A kind of early power dilatancy filler and its fill method
CN113880508A (en) Material for quickly sealing easily weathered surrounding rock of coal mine bottom suction roadway and using method thereof
CN108033747B (en) Antirust tensile cement slurry and spraying method
CN106747124A (en) A kind of very-high performance mortar for building puzzle joint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant