CN108005685A - A kind of anchor spraying concrete wall for grouting construction method - Google Patents

A kind of anchor spraying concrete wall for grouting construction method Download PDF

Info

Publication number
CN108005685A
CN108005685A CN201711314379.3A CN201711314379A CN108005685A CN 108005685 A CN108005685 A CN 108005685A CN 201711314379 A CN201711314379 A CN 201711314379A CN 108005685 A CN108005685 A CN 108005685A
Authority
CN
China
Prior art keywords
layer
concrete
concrete layer
grouting
mesh sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711314379.3A
Other languages
Chinese (zh)
Other versions
CN108005685B (en
Inventor
张馨
王小丹
李永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN201711314379.3A priority Critical patent/CN108005685B/en
Publication of CN108005685A publication Critical patent/CN108005685A/en
Application granted granted Critical
Publication of CN108005685B publication Critical patent/CN108005685B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention relates to a kind of anchor spraying concrete wall for grouting construction method, step is:S1 is needing first just the first layer concrete of injection of the face for carrying out curtain-grouting paragraph;S2 applies total length binding type anchor pole on the first concrete layer, and anchor pole will add backing plate, and backing plate nut tightening is simultaneously closely connected with the outer surface of the first concrete layer;S3 hangs first layer mesh sheet in the outer surface of the first concrete layer, and the outer end spot welding of first layer mesh sheet and anchor pole connects;Outer jet second layer concretes of the S4 in the first concrete layer;Outer jet third layer concrete of the S5 in the second concrete layer;S6 applies second layer mesh sheet in the outer surface of the 3rd concrete layer;S7 the 3rd concrete layer the 4th layer concrete of outer jet, to wall for grouting require thickness, after intensity is met the requirements, you can carry out Curtain Grouting Construction.This wall for grouting construction method is not required that template, technique are simple, speed of application is fast, and the wall for grouting of formation is reliable effectively, good integrity.

Description

A kind of anchor spraying concrete wall for grouting construction method
Technical field
The present invention relates to technical field of tunnel construction, more particularly to a kind of anchor spraying concrete wall for grouting structure and its construction party Method.
Background technology
The scale of great Qian Shi ridges tunnel entrance talus is very big, and talus scope includes the almost whole massif of tunnel entrance, 26 °~38 ° of natural grade, talus thickness are 26.3m~48.4m, and body extends to korneforos near the mountain for Study on Rock lower part.Talus mainly by Block stone composition not of uniform size, rock matter are early Sinian system fishing platform group (Z1d) quartzy sandstone, and block stone diameter is more in 0.5m~1.5m Between, big 2~3m of person, block footpath is overall more homogeneous, in loose aerial construction, basic non-binding.Great Qian Shi ridges tunnel is from huge Talus middle and upper part passes through, and tunnel top talus maximum gauge 50m, tunnel bottom highly reaches more than 32m from talus base rock.In order to Ensure that project subject structure is safe, steel tube shed+curtain-grouting is the important working measure of one of which in hole.But carry out curtain note During slurry, concrete wall for grouting is mainly concrete soil structure, and thickness, it is necessary to first shuttering, then is reinforced generally in more than 40cm, most After-pouring concrete, complicated construction technique, time are long, of high cost, larger to site operation tissue effect.
The content of the invention
The present invention for solve known technology present in technical problem provide one kind be not required template, technique simply, apply Work speed is fast, reliable effective, the anchor spraying concrete wall for grouting construction method of good integrity of wall for grouting of formation.
The present invention is adopted the technical scheme that to solve technical problem present in known technology:
A kind of anchor spraying concrete wall for grouting construction method, it is characterised in that including following construction procedure:
S1 is needing the face for carrying out curtain-grouting paragraph first just to spray the first layer concrete, forms the first concrete Layer;
S2 applies total length binding type anchor pole on the first concrete layer, and anchor pole will add backing plate, backing plate with nut tightening simultaneously It is closely connected with the outer surface of the first layer concrete.
S3 hangs first layer mesh sheet in the outer surface of the first concrete layer, and the outer end spot welding of first layer mesh sheet and anchor pole connects Connect, easy to fixation;
S4 is in the second layer concrete of outer jet of the first concrete layer, the second concrete layer of formation;
S5 is in the outer jet third layer concrete of the second concrete layer, the 3rd concrete layer of formation;
S6 applies second layer mesh sheet in the outer surface of the 3rd concrete layer, and second layer mesh sheet is with being fixed on the 3rd concrete layer On useless steel bar end exposed junction spot welding connection;
S7 the 3rd concrete layer the 4th layer concrete of outer jet, to wall for grouting require thickness, formed the 4th coagulation Soil layer, after intensity is met the requirements, you can carry out Curtain Grouting Construction.
Further:The thickness of first concrete layer is 60mm, and the thickness of the second concrete layer is 120mm, the 3rd coagulation The thickness of the layer is 120mm, and the thickness of the 4th concrete layer is 100mm.
Further:Anchor pole is process with φ 20mm screw-thread steels, length 1.5m, plate thickness 10mm, and size is 100mm×100mm。
Further:First layer mesh sheet and second layer mesh sheet are process using No. 8 iron wires, the grid spacing of two mesh sheet It is 100mm × 100mm.
Further:The concrete grade of injection is C25, and the compacting agent with accelerator equivalent is mixed in concrete.
The present invention has the advantages and positive effects of:
1st, this wall for grouting construction method mainly forms wall for grouting by spraying multi-layer concrete, it is not necessary to template, technique Simply, speed of application is fast, so as to save investment and labour, shortens the duration.
2nd, concrete spray coating has high-adhesiveness, cementing loose sillar, and filling fracture simultaneously gos deep into rock interior, makes spray-up With the common bearing load in rock stratum, reach preferable globality.
3rd, the wall for grouting that this construction method is formed have high density or high intensity, it is reliable effectively, disclosure satisfy that grouting pressure> The construction requirement of 1MPa.
Brief description of the drawings
Fig. 1 is the sectional schematic diagram of wall for grouting of the present invention.
In figure:1st, the first concrete layer;2nd, anchor pole;3rd, backing plate;4th, nut;5th, first layer mesh sheet;6th, the second concrete layer; 7th, the 3rd concrete layer;8th, second layer mesh sheet;9th, the 4th concrete layer;1,, scar.
Embodiment
In order to further understand the content, features and effects of the present invention, the following examples are hereby given, and with reference to attached drawing Describe in detail as follows:
Fig. 1 is referred to, a kind of anchor spraying concrete wall for grouting construction method, its innovative point is, including following construction procedure:
S1 is needing the face (scar 1) for carrying out curtain-grouting paragraph first just to spray the first layer concrete, forms first Concrete layer 1.
S2 applies total length binding type anchor pole 2 on the first concrete layer, and anchor pole will add backing plate 3, and backing plate nut 4 tightens And it is closely connected with the outer surface of the first concrete layer, the purpose for setting anchor pole mainly ensures that whole wall for grouting is fixed on by anchor pole On scar, prevent grouting pressure from crossing the extruding of senior general's slip casting wall and collapsing.
S3 hangs first layer mesh sheet 5 in the outer surface of the first concrete layer, and the outer end spot welding of first layer mesh sheet and anchor pole connects Connect, easy to fixation, the purpose of setting first layer mesh sheet:Strengthen the globality and compression strength of whole wall for grouting.
S4 is in the second layer concrete of outer jet of the first concrete layer, the second concrete layer 6 of formation;
S5 is in the outer jet third layer concrete of the second concrete layer, the 3rd concrete layer 7 of formation;
S6 applies second layer mesh sheet 8 in the outer surface of the second concrete layer, and second layer mesh sheet is with being fixed on the 3rd concrete The exposed junction spot welding connection of useless steel bar end on layer.Mixed specifically, being ordered with the drilling of about 10cm long φ 20mm screw-thread steels into third layer On solidifying soil, expose about 2cm, second layer mesh sheet is connected with steel bar end exposed junction spot welding.The purpose of second layer mesh sheet is set:Equally it is To strengthen the globality and compression strength of whole wall for grouting.
S7 the 3rd concrete layer the 4th layer concrete of outer jet, to wall for grouting require thickness, formed the 3rd coagulation Soil layer 9, after intensity is met the requirements, you can carry out Curtain Grouting Construction.
In above-mentioned wall for grouting construction method:The thickness of each concrete layer is further preferably as follows:
The thickness of first concrete layer is 60mm, and the thickness of the second concrete layer is 120mm, the thickness of the 3rd concrete layer For 120mm, the thickness of the 4th concrete layer is 100mm.
In above-mentioned wall for grouting construction method:The size of anchor pole and cushion block is preferably as follows:
Anchor pole is process with φ 20mm screw-thread steels, length 1.5m;Plate thickness 10mm, size for 100mm × 100mm。
In above-mentioned wall for grouting construction method:The iron wire diameter dimension and grid spacing of two layers mesh sheet are as follows:
First layer mesh sheet and second layer mesh sheet are process using No. 8 iron wires, and the grid spacing of two mesh sheet is 100mm ×100mm。
In above-mentioned wall for grouting construction method:The concrete of injection preferably uses the concrete marked as C25, is mixed in concrete Enter that (compacting agent often there are siliceous compacting agents of JH etc. with model, and accelerator often has Red Star I with model with the compacting agent of accelerator equivalent Type, 7 II types, 782 types, 8604 types etc.), to ensure that slip casting rear slurry does not ooze out.
The better embodiment of the present invention is explained in detail above, but the present invention is not limited to above-mentioned embodiment party Formula, can also be on the premise of present inventive concept not be departed from the knowledge that one skilled in the relevant art possesses Various changes can be made, belongs to protection scope of the present invention.

Claims (5)

1. a kind of anchor spraying concrete wall for grouting construction method, it is characterised in that including following construction procedure:
S1 is needing the face for carrying out curtain-grouting paragraph first just to spray the first layer concrete, forms the first concrete layer;
S2 applies total length binding type anchor pole on the first concrete layer, and anchor pole will add backing plate, backing plate nut tightening and with The outer surface of one concrete layer is closely connected.
S3 hangs first layer mesh sheet in the outer surface of the first concrete layer, and the outer end spot welding of first layer mesh sheet and anchor pole connects, just In fixation;
S4 is in the second layer concrete of outer jet of the first concrete layer, the second concrete layer of formation;
S5 is in the outer jet third layer concrete of the second concrete layer, the 3rd concrete layer of formation;
S6 applies second layer mesh sheet in the outer surface of the 3rd concrete layer, and second layer mesh sheet is with being fixed on the 3rd concrete layer The exposed junction spot welding connection of useless steel bar end;
S7 the 3rd concrete layer the 4th layer concrete of outer jet, to wall for grouting require thickness, formed the 4th concrete layer, After intensity is met the requirements, you can carry out Curtain Grouting Construction.
2. anchor spraying concrete wall for grouting construction method according to claim 1, it is characterised in that:The thickness of first concrete layer Spend for 60mm, the thickness of the second concrete layer is 120mm, and the thickness of the 3rd concrete layer is 120mm, the thickness of the 4th concrete layer Spend for 100mm.
3. anchor spraying concrete wall for grouting construction method according to claim 2, it is characterised in that:Anchor pole φ 20mm screw threads Steel is process, length 1.5m;Plate thickness 10mm, size are 100mm × 100mm.
4. anchor spraying concrete wall for grouting construction method according to claim 1, it is characterised in that:First layer mesh sheet and second Floor mesh sheet is process using No. 8 iron wires, and the grid spacing of two mesh sheet is 100mm × 100mm.
5. anchor spraying concrete wall for grouting construction method according to claim 1, it is characterised in that:The concrete grade of injection For C25, incorporation and the compacting agent of accelerator equivalent in concrete.
CN201711314379.3A 2017-12-12 2017-12-12 A kind of anchor spraying concrete wall for grouting construction method Active CN108005685B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711314379.3A CN108005685B (en) 2017-12-12 2017-12-12 A kind of anchor spraying concrete wall for grouting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711314379.3A CN108005685B (en) 2017-12-12 2017-12-12 A kind of anchor spraying concrete wall for grouting construction method

Publications (2)

Publication Number Publication Date
CN108005685A true CN108005685A (en) 2018-05-08
CN108005685B CN108005685B (en) 2019-05-31

Family

ID=62058127

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711314379.3A Active CN108005685B (en) 2017-12-12 2017-12-12 A kind of anchor spraying concrete wall for grouting construction method

Country Status (1)

Country Link
CN (1) CN108005685B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108825301A (en) * 2018-06-05 2018-11-16 太原理工大学 A kind of quick walling method of heap pneumatically placed concrete for underground coal mine
CN109372555A (en) * 2018-12-26 2019-02-22 中国矿业大学 A kind of fault disruption zone area tunnel 3 D stereo grouting support method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0988077A (en) * 1995-07-13 1997-03-31 Sango:Kk Repair method of falling rock preventive concrete wall of slope
CN204212163U (en) * 2014-10-22 2015-03-18 贵州正业工程技术投资有限公司 Karst depression talus off-load reinforced structure
CN204371365U (en) * 2014-12-22 2015-06-03 中铁十九局集团轨道交通工程有限公司 Deep hole sealing filling system
CN206205915U (en) * 2016-11-10 2017-05-31 河南理工大学 A kind of flexible entirety concrete spray-up structure of deep tunnel bolt-spary supports
CN206636570U (en) * 2017-04-13 2017-11-14 中国电建集团成都勘测设计研究院有限公司 A kind of tunnel abutment wall collapses the supporting construction at place

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0988077A (en) * 1995-07-13 1997-03-31 Sango:Kk Repair method of falling rock preventive concrete wall of slope
CN204212163U (en) * 2014-10-22 2015-03-18 贵州正业工程技术投资有限公司 Karst depression talus off-load reinforced structure
CN204371365U (en) * 2014-12-22 2015-06-03 中铁十九局集团轨道交通工程有限公司 Deep hole sealing filling system
CN206205915U (en) * 2016-11-10 2017-05-31 河南理工大学 A kind of flexible entirety concrete spray-up structure of deep tunnel bolt-spary supports
CN206636570U (en) * 2017-04-13 2017-11-14 中国电建集团成都勘测设计研究院有限公司 A kind of tunnel abutment wall collapses the supporting construction at place

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108825301A (en) * 2018-06-05 2018-11-16 太原理工大学 A kind of quick walling method of heap pneumatically placed concrete for underground coal mine
CN108825301B (en) * 2018-06-05 2020-07-03 太原理工大学 Quick wall building method for underground coal mine through pile-spraying concrete
CN109372555A (en) * 2018-12-26 2019-02-22 中国矿业大学 A kind of fault disruption zone area tunnel 3 D stereo grouting support method

Also Published As

Publication number Publication date
CN108005685B (en) 2019-05-31

Similar Documents

Publication Publication Date Title
CN110486023A (en) Tunnel defect administering method
CN104895581B (en) Structure and its restorative procedure are quickly repaired in a kind of tunnel-liner based on Carbon Fibre Textile
CN104847130B (en) A kind of ruggedized construction and its construction method of existing structure beam
CN101333815B (en) Concrete anchor rod and its construction method
CN109083682A (en) A kind of construction method of mine working antiseepage high intensity fire dam
CN206957731U (en) A kind of supporting construction for section of being caved in hole
CN106801517A (en) A kind of schoolhouse surface consolidation of Prefabricated porous plate brick mixed structure strengthens method
US11840820B2 (en) Method for strengthening and lifting high-rise building having raft foundation
CN108005685B (en) A kind of anchor spraying concrete wall for grouting construction method
CN103046513A (en) Method for coating and sealing fracture of bed rock in uncovered heavy consolidation grouting
CN110080454A (en) LPM light filling body Construction of Cast-in-situ Concrete Hollow
CN106013078B (en) A kind of construction method of highly permeable stratum consolidation curtain structure
CN106836551A (en) Infill Wall with Aerated Concrete Block construction method
CN205243528U (en) Lining cutting fracture reinforced structure is subsided to tunnel bottom
CN201495651U (en) Composite wall construction tie node of antique bricks and insulation blocks
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN103790168A (en) Application method of soil nailing wall in deep foundation pit supporting
CN206246133U (en) A kind of anti-rock burst support system in tunnel and tunnel structure
CN207123231U (en) A kind of positioning rule of embedded sleeve barrel and reserving hole channel after being used for prefabricated part hanging
CN102535493B (en) Method for constructing inverted type foundation beam
CN105970997B (en) A kind of steel towers prefabricated compound assembling external member pile foundation of thing and preparation method thereof
CN105986574A (en) Hollow grouting anchor rod construction process
CN207392189U (en) A kind of assembled sealing up screw reinforces one side formwork structure
CN108150191A (en) A kind of tunnel bottom structure and its construction method
CN106988321A (en) A kind of miscellaneous fill foundation ditch bamboo reinforcement support system and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant