CN108150191A - A kind of tunnel bottom structure and its construction method - Google Patents

A kind of tunnel bottom structure and its construction method Download PDF

Info

Publication number
CN108150191A
CN108150191A CN201810041516.9A CN201810041516A CN108150191A CN 108150191 A CN108150191 A CN 108150191A CN 201810041516 A CN201810041516 A CN 201810041516A CN 108150191 A CN108150191 A CN 108150191A
Authority
CN
China
Prior art keywords
floral tube
steel floral
concrete
tunnel
inverted arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810041516.9A
Other languages
Chinese (zh)
Inventor
方钱宝
冯冀蒙
何昌国
张俊儒
赵万强
李洪涛
刘祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201810041516.9A priority Critical patent/CN108150191A/en
Publication of CN108150191A publication Critical patent/CN108150191A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/28Longitudinal struts, i.e. longitudinal connections between adjoining arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Abstract

A kind of tunnel bottom structure and its construction method the defects of to eliminate the easy disease in the region tunnel of underground water prosperity, improve the bearing capacity of tunnel structure bottom itself, while effectively reduce influence of the underground water to tunnel bottom structure.Tunnel bottom structure includes inverted arch and the lateral sulcus of both sides, armoured concrete slab is set between the both sides lateral sulcus, pervious concrete filling body is set between armoured concrete slab bottom surface and inverted arch surface, vertically and horizontally spaced steel floral tube is passed down through pervious concrete filling body and inverted arch is inserted into basement rock, and the upper end of each steel floral tube is fixedly connected with armoured concrete slab.The pervious concrete filling body bottom centre position sets gutter.

Description

A kind of tunnel bottom structure and its construction method
Technical field
The present invention relates to tunnel structures, and in particular to a kind of tunnel bottom structure and its construction method.
Background technology
It is shown according to related data, the existing railway tunnel in China passes through the operation of many decades, particularly in underground water prosperity In the case of, it is flourishing that situations such as cracking, percolating water, bottom disease, particularly underground water more generally occurs in supporting construction Limestone and can lava stratum.It is entirely local to share 1995 by taking the tunnel investigation in Chengdu Railway Bureau administration in 2010 as an example Seat tunnel, total kilometrage is up to 1397 kilometers, wherein there is 1418 tunnels disease occur, occur disease tunnel account for institute it is cunicular 71.08%.From the quantity of disease, 84.6% disease is Lining cracks and percolating water.Come from the quantity in disease tunnel It sees, 70.5% disease is percolating water, pumping equipment damage and bottom are risen soil inside and outside hole.Even create into reaching soon Into new line, 35% tunnel is also different degrees of to there is the situation of percolating water.The Guizhou Province particularly just built up and be open to traffic 1 year Osmanthus line sinks and rises soil wherein there is 9 tunnels more serious bottom occur, seriously affected traffic safety.
It is tunnel structure bottom disease traffic safety to be influenced in disease maximum, and principal mode is that substrate is emptied, bursts and become muddy when a thaw sets in Mud and track settlement etc. are emitted, the generation of these diseases is all related with underground water without exception.Simultaneously substrate scum silica frost do not clean up, The intensity of inverted arch or bottom plate is insufficient or missing is often to cause the human factor of bottom disease.
Processing currently for tunnel structure bottom disease is all often by the way of grouting and reinforcing or clump of piles anchoring. From the point of view of construction effect, slip casting effect is unsatisfactory, since underground water is flourishing and the problem of bottom structure itself, underground water is often It cannot be completely exhausted out outside hole, and structure can also undertake certain water pressure, push wave can be played to bottom structure disease Help the effect of billows.
Invention content
The technical problem to be solved in the present invention is to provide a kind of tunnel bottom structure, to eliminate the region tunnel of underground water prosperity The defects of easy disease in road, improves the bearing capacity of tunnel structure bottom itself, while effectively reduces underground water to tunnel bottom knot The influence of structure.
The present invention solves above-mentioned technical problem and uses the technical solution taken as follows:
A kind of tunnel bottom structure of the present invention, the lateral sulcus including inverted arch and both sides, it is characterized in that:The both sides lateral sulcus it Between armoured concrete slab is set, between armoured concrete slab bottom surface and inverted arch surface set pervious concrete filling body, vertically and horizontally Spaced steel floral tube is passed down through pervious concrete filling body and inverted arch is inserted into basement rock, the upper end of each steel floral tube and reinforcing bar Concrete slab is fixedly connected;The pervious concrete filling body bottom centre position sets gutter.
Concrete perfusion in the steel floral tube.
Another technical problem to be solved by this invention is to provide a kind of construction method of above-mentioned tunnel bottom structure, the party Method includes the following steps:
1. after the completion of tunnel excavation, construction inverted arch and both sides lateral sulcus, inverted arch are reserved for the through-hole that steel floral tube passes through;
2. it is laid with gutter waterway in inverted arch bottom centre position;
3. steel floral tube is passed through reserved through hole to be inserted into basement rock, concrete perfusion in each steel floral tube by steel floral tube of constructing;
4. after steel floral tube inner concrete reaches the 70% of design strength, pervious concrete filling body is poured;
5. by the top of steel floral tube and the reinforcement welding of armoured concrete slab, casting concrete is completed armoured concrete slab and is applied Work.
The invention has the advantages that the steel floral tube of armoured concrete slab and internal casting concrete is as main carrying Load can be efficiently transferred to the bearing bed of substrate by structure;Pervious concrete and gutter collective effect, by lateral sulcus cannot and When the water discharged or the water of injection be discharged to outside tunnel, reduce soaking time and inverted arch of the underground water to tunnel bottom structure The groundwater pressure that structure is subject to effectively reduces the probability that disease occurs;Present invention is mainly used for the tunnel bottoms of underground water prosperity The design and Disease Treatment in lesion section easily occur for portion's structure, and can effectively reduce track due to disease and caused by irregularity ask Topic.
Description of the drawings
Fig. 1 is a kind of cross-section diagram of tunnel bottom structure of the present invention.
Component name and corresponding label are shown in figure:Inverted arch 11, lateral sulcus 12, armoured concrete slab 20, permeable coagulation Native filling body 21, steel floral tube 22, gutter 23.
Specific embodiment
The invention will be further described with reference to the accompanying drawings and examples.
With reference to Fig. 1, present invention is mainly used for underground water prosperity tunnel bottom structure easily occur lesion section design and Disease Treatment, tunnel bottom structure include inverted arch 11 and the lateral sulcus 12 of both sides.Reinforced concrete is set between the both sides lateral sulcus 12 Native plate 20, setting pervious concrete filling body 21 between 11 surface of 20 bottom surface of armoured concrete slab and inverted arch, vertically and horizontally interval set The steel floral tube 22 put is passed down through pervious concrete filling body 21 and inverted arch 11 is inserted into basement rock, the upper end of each steel floral tube 22 and steel Reinforced concrete plate 20 is fixedly connected.21 bottom centre position of pervious concrete filling body sets gutter 23.The spray of molten steel Concrete perfusion in pipe 22.
With reference to Fig. 1, the steel floral tube 22 of armoured concrete slab 20 and internal casting concrete is used as main bearing structure energy Load is efficiently transferred to the bearing bed of substrate.Pervious concrete filling body 21 and 23 collective effect of gutter, by lateral sulcus 12 The water or the water of injection that cannot be discharged in time are discharged to outside tunnel, reduce soaking time of the underground water to tunnel bottom structure The groundwater pressure being subject to inverted arch structure effectively reduces the probability that disease occurs.
With reference to Fig. 1, the transmission path of train load that the present invention is mainly subject to is:Track → armoured concrete slab 20 → thoroughly Water coagulation soil filling body 21 → inverted arch, 11 → base carrier layer.When bottom generation disease or inverted arch and base carrier layer are hanging When, then the transmission path of train load is:Track → 21 → steel floral tube of pervious concrete filling body 22 (concrete steel floral tube column) → base carrier layer, effectively reduce track due to disease and caused by irregularity problem.
The steel floral tube 22 is vertically and horizontally spaced in quincuncial arrangement, and diameter is usually 10cm, also can be according to construction site Situation be adjusted.The depth for being inserted into basement rock is typically no less than 0.5m, and the label of interior concrete perfusion is not less than C35.Steel The top of floral tube 22 is connect with the reinforcement welding of armoured concrete slab 20.
A kind of construction method of tunnel bottom structure of the present invention, includes the following steps:
1. after the completion of tunnel excavation, construct inverted arch 11 and both sides lateral sulcus 12, inverted arch 11 be reserved for steel floral tube 22 pass through it is logical Hole;
2. it is laid with gutter waterway 23 in 11 bottom centre position of inverted arch;
3. steel floral tube 22 is passed through reserved through hole to be inserted into basement rock by steel floral tube 22 of constructing, perfusion coagulation in each steel floral tube 22 Soil;
4. after 22 inner concrete of steel floral tube reaches the 70% of design strength, pervious concrete filling body 21 is poured;
5. by the top of steel floral tube 22 and the reinforcement welding of armoured concrete slab 20, casting concrete completes armored concrete Plate 20 is constructed.
It constructs in strict accordance with construction method, will can ensure that the construction quality of tunnel bottom structure.
Some principles of only explain through diagrams a kind of tunnel bottom structure of the present invention and its construction method described above, and It is non-be by the present invention be confined to shown in and the concrete structure and the scope of application in, it is therefore every it is possible that the phase being utilized It should change and equivalent, belong to the apllied the scope of the claims of the present invention.

Claims (5)

1. a kind of tunnel bottom structure, the lateral sulcus (12) including inverted arch (11) and both sides, it is characterized in that:The both sides lateral sulcus (12) Between setting armoured concrete slab (20), pervious concrete is set between armoured concrete slab (20) bottom surface and inverted arch (11) surface Filling body (21), vertically and horizontally spaced steel floral tube (22) is passed down through pervious concrete filling body (21) and inverted arch (11) is inserted Enter in basement rock, the upper end of each steel floral tube (22) is fixedly connected with armoured concrete slab (20);The pervious concrete filling body (21) bottom centre position setting gutter (23).
2. a kind of tunnel bottom structure as described in claim 1, it is characterized in that:The interior concrete perfusion of the steel floral tube (22).
3. a kind of tunnel bottom structure as claimed in claim 2, it is characterized in that:A diameter of 10cm of the steel floral tube (22), The depth of basement rock is inserted into not less than 0.5m, the label of interior concrete perfusion is not less than C35.
4. a kind of tunnel bottom structure as claimed in claim 3, it is characterized in that:It is mixed with reinforcing bar at the top of the steel floral tube (22) The reinforcement welding connection of concrete board (20).
5. a kind of construction method of tunnel bottom structure, includes the following steps as described in Claims 1-4 any one:
1. after the completion of tunnel excavation, construction inverted arch (11) and both sides lateral sulcus (12), inverted arch (11) are reserved for steel floral tube (22) and pass through Through-hole;
2. it is laid with gutter waterway (23) in inverted arch (11) bottom centre position;
3. steel floral tube (22) is inserted into across reserved through hole in basement rock by steel floral tube (22) of constructing, perfusion is mixed in each steel floral tube (22) Solidifying soil;
4. after steel floral tube (22) inner concrete reaches the 70% of design strength, pervious concrete filling body (21) is poured;
5. by the top of steel floral tube (22) and the reinforcement welding of armoured concrete slab (20), casting concrete completes armored concrete Plate (20) is constructed.
CN201810041516.9A 2018-01-16 2018-01-16 A kind of tunnel bottom structure and its construction method Pending CN108150191A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810041516.9A CN108150191A (en) 2018-01-16 2018-01-16 A kind of tunnel bottom structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810041516.9A CN108150191A (en) 2018-01-16 2018-01-16 A kind of tunnel bottom structure and its construction method

Publications (1)

Publication Number Publication Date
CN108150191A true CN108150191A (en) 2018-06-12

Family

ID=62461576

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810041516.9A Pending CN108150191A (en) 2018-01-16 2018-01-16 A kind of tunnel bottom structure and its construction method

Country Status (1)

Country Link
CN (1) CN108150191A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111810185A (en) * 2020-06-30 2020-10-23 中铁二院工程集团有限责任公司 Tunnel bottom pre-reinforcement construction method
CN114575197A (en) * 2022-03-14 2022-06-03 中铁二院工程集团有限责任公司 Treatment structure and treatment method for inverted arch disease of high-speed railway tunnel in mountainous area

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040027252A (en) * 2002-11-22 2004-04-01 (주)현이앤씨 Construction and design method about center wall of three arch tunnel excavation method
CN101493011A (en) * 2008-12-30 2009-07-29 中国科学院武汉岩土力学研究所 Soft expansion type wall rock tunnel support method
CN101768974A (en) * 2009-12-29 2010-07-07 中铁隧道集团有限公司 Method and device for grouting in hole and effectively stopping grout
CN203783590U (en) * 2013-11-12 2014-08-20 中铁二院工程集团有限责任公司 Tunnel bottom soft ground dynamic load and static load separating tunnel structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040027252A (en) * 2002-11-22 2004-04-01 (주)현이앤씨 Construction and design method about center wall of three arch tunnel excavation method
CN101493011A (en) * 2008-12-30 2009-07-29 中国科学院武汉岩土力学研究所 Soft expansion type wall rock tunnel support method
CN101768974A (en) * 2009-12-29 2010-07-07 中铁隧道集团有限公司 Method and device for grouting in hole and effectively stopping grout
CN203783590U (en) * 2013-11-12 2014-08-20 中铁二院工程集团有限责任公司 Tunnel bottom soft ground dynamic load and static load separating tunnel structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
田永铸: "重载铁路软弱基底黄土隧道仰拱开裂整治及隧底加固", 《铁道勘察》, no. 5, pages 59 - 63 *
范圣明等: "高压劈裂注浆技术在隧道软弱围岩加固中的运用研究", vol. 8, no. 8, pages 57 - 62 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111810185A (en) * 2020-06-30 2020-10-23 中铁二院工程集团有限责任公司 Tunnel bottom pre-reinforcement construction method
CN111810185B (en) * 2020-06-30 2022-04-05 中铁二院工程集团有限责任公司 Tunnel bottom pre-reinforcement construction method
CN114575197A (en) * 2022-03-14 2022-06-03 中铁二院工程集团有限责任公司 Treatment structure and treatment method for inverted arch disease of high-speed railway tunnel in mountainous area

Similar Documents

Publication Publication Date Title
CN104453913B (en) A kind of Shaft Stopes front pre-grouting method
CN105696427B (en) The construction method and its road structure of a kind of consolidation process newly built railway karst foundation
CN107642360A (en) Tunneling boring front pre-grouting construction method
CN104499479B (en) It is a kind of to pass through the dug pile construction method that sand gravel backfills layer
CN107237651A (en) A kind of multi-level grouting water-tight reinforcement means of coal mine underground reservoir and reservoir dam
CN202645592U (en) Full-face grouting holes and a grout-stop wall for a tunnel in sections of water-rich quicksand and fault
CN107201908A (en) A kind of construction method of the regional buried Central drain in tunnel of bitter cold
CN205206838U (en) Collapsible loess tunnel supporting construction
CN206337474U (en) The slip casting structure of covered karst embankment
CN106088094B (en) High mountain strid Method of Arch Dam Foundation is segmented stage grouting method
CN102979535B (en) Draining type section of jurisdiction is used in a kind of tunnel lining
CN205576940U (en) Compound retaining structure of friction pile that pile bolck is connected entirely
CN106437726A (en) Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation
CN104328782A (en) Expansive pouring device and method for governing railway roadbed sedimentation and deformation
CN103993594B (en) A kind of micro-nano bubble process can liquefied foundation device and working method
CN109083682A (en) A kind of construction method of mine working antiseepage high intensity fire dam
CN105735055B (en) Imbibition drainage
CN101525881A (en) Structure of karst strata pile holes protecting wall and method for constructing pile holes
CN108547641A (en) The bottom stab ilization system and its construction method in rich water soft stratum heavy haul railway tunnel
CN107513995A (en) A kind of bridge struction pile post grouting construction method
CN110130936A (en) It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack
CN106894428A (en) A kind of multi layer waterproof method for blocking of mass raft foundation dewatering well
CN106869151A (en) A kind of bridge construction method of deep foundation ditch
CN207377562U (en) Mine Shaft Lining and constructing device in a kind of poor strata
CN104532714B (en) Roadbed structure for treating deep soft soil karst foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination