CN207392189U - Unilateral template structure is consolidated to assembled stagnant water screw rod - Google Patents
Unilateral template structure is consolidated to assembled stagnant water screw rod Download PDFInfo
- Publication number
- CN207392189U CN207392189U CN201721145206.9U CN201721145206U CN207392189U CN 207392189 U CN207392189 U CN 207392189U CN 201721145206 U CN201721145206 U CN 201721145206U CN 207392189 U CN207392189 U CN 207392189U
- Authority
- CN
- China
- Prior art keywords
- supporting construction
- screw
- foundation pit
- sealing
- template
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims abstract description 13
- 238000010276 construction Methods 0.000 claims abstract description 83
- 239000000463 material Substances 0.000 claims abstract description 22
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 19
- 238000007789 sealing Methods 0.000 claims description 55
- 230000002787 reinforcement Effects 0.000 claims description 30
- 229910000831 Steel Inorganic materials 0.000 claims description 28
- 239000010959 steel Substances 0.000 claims description 28
- 238000009415 formwork Methods 0.000 claims description 23
- 229910001220 stainless steel Inorganic materials 0.000 claims description 9
- 239000010935 stainless steel Substances 0.000 claims description 9
- 230000008595 infiltration Effects 0.000 claims description 3
- 238000001764 infiltration Methods 0.000 claims description 3
- 210000003205 muscle Anatomy 0.000 claims description 2
- 239000012528 membrane Substances 0.000 claims 1
- 229910001294 Reinforcing steel Inorganic materials 0.000 abstract 2
- 239000012779 reinforcing material Substances 0.000 abstract 1
- 239000010410 layer Substances 0.000 description 12
- 239000002689 soil Substances 0.000 description 5
- 238000003466 welding Methods 0.000 description 5
- 238000002372 labelling Methods 0.000 description 4
- 239000007921 spray Substances 0.000 description 4
- 239000011083 cement mortar Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- POIUWJQBRNEFGX-XAMSXPGMSA-N cathelicidin Chemical compound C([C@@H](C(=O)N[C@@H](CCCNC(N)=N)C(=O)N[C@@H](CCCCN)C(=O)N[C@@H](CO)C(=O)N[C@@H](CCCCN)C(=O)N[C@@H](CCC(O)=O)C(=O)N[C@@H](CCCCN)C(=O)N[C@@H]([C@@H](C)CC)C(=O)NCC(=O)N[C@@H](CCCCN)C(=O)N[C@@H](CCC(O)=O)C(=O)N[C@@H](CC=1C=CC=CC=1)C(=O)N[C@@H](CCCCN)C(=O)N[C@@H](CCCNC(N)=N)C(=O)N[C@@H]([C@@H](C)CC)C(=O)N[C@@H](C(C)C)C(=O)N[C@@H](CCC(N)=O)C(=O)N[C@@H](CCCNC(N)=N)C(=O)N[C@@H]([C@@H](C)CC)C(=O)N[C@@H](CCCCN)C(=O)N[C@@H](CC(O)=O)C(=O)N[C@@H](CC=1C=CC=CC=1)C(=O)N[C@@H](CC(C)C)C(=O)N[C@@H](CCCNC(N)=N)C(=O)N[C@@H](CC(N)=O)C(=O)N[C@@H](CC(C)C)C(=O)N[C@@H](C(C)C)C(=O)N1[C@@H](CCC1)C(=O)N[C@@H](CCCNC(N)=N)C(=O)N[C@@H]([C@@H](C)O)C(=O)N[C@@H](CCC(O)=O)C(=O)N[C@@H](CO)C(O)=O)NC(=O)[C@H](CC=1C=CC=CC=1)NC(=O)[C@H](CC(O)=O)NC(=O)CNC(=O)[C@H](CC(C)C)NC(=O)[C@@H](N)CC(C)C)C1=CC=CC=C1 POIUWJQBRNEFGX-XAMSXPGMSA-N 0.000 description 2
- 230000007797 corrosion Effects 0.000 description 2
- 238000005260 corrosion Methods 0.000 description 2
- 238000005553 drilling Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000011241 protective layer Substances 0.000 description 2
- 238000005507 spraying Methods 0.000 description 2
- 238000003892 spreading Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 238000013459 approach Methods 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000015271 coagulation Effects 0.000 description 1
- 238000005345 coagulation Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- JEIPFZHSYJVQDO-UHFFFAOYSA-N iron(III) oxide Inorganic materials O=[Fe]O[Fe]=O JEIPFZHSYJVQDO-UHFFFAOYSA-N 0.000 description 1
- 238000002955 isolation Methods 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 238000004080 punching Methods 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 238000003900 soil pollution Methods 0.000 description 1
- 238000005728 strengthening Methods 0.000 description 1
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
An assembled water stop screw reinforced unilateral template structure comprises a foundation pit supporting structure and a template, wherein the foundation pit supporting structure is formed by pouring supporting structure concrete in a supporting structure reinforcing cage, the supporting structure reinforcing cage is formed by connecting vertical stressed reinforcing steel bars through annular stirrups and reinforcing stirrups, a plurality of pre-buried pull rods are uniformly arranged on the vertical stressed reinforcing steel bars on one side of the supporting structure reinforcing cage along the axial direction, the parts of the pre-buried pull rods extending out of the foundation pit supporting structure are perpendicular to the foundation pit supporting structure, the foundation pit supporting structures are arranged side by side, so that the surface where the pre-buried pull rods are arranged faces the template, water stop screws are fixed on the template and are connected with the pre-buried pull rods through connecting sleeves, the structure is quicker in construction speed and reasonable in stress, the reinforcing materials are conventional materials, and large-scale equipment is not needed for hoisting, the construction cost is low.
Description
Technical field
The utility model is related to a kind of assembled sealing up screw to reinforce one side formwork structure.
Background technology
Under the feelings being limited in place are wished, the form work engineering of underground engineering shear wall is generally added using unilateral die body system
Gu being so just well positioned to meet the needs of engineering, without slope, the mould material of one side can be saved.One side formwork reinforcing is applied
Oneself uses work technology in numerous engineering projects at present.
In the single side formwork engineering of part, employ sealing up screw and carry out single formwork reinforcement.Sealing up screw method carries out single
Collateral mould has the advantages that following several respects:(1) stress system is identical with common two-sided formwork, uses and draws bolt pattern, by
Power form is comparatively safe;(2) formwork and form removal are convenient and efficient, skilled operation, and manpower consumption amount is close with common two-sided formwork;
(3) exterior wall can with floor girder and board primary concreting, it is suitable with conventional two-sided formwork construction speed.
In traditional sealing up screw carries out single mode plate reinforcement means, there are two types of connection sides with supporting construction for sealing up screw
Formula.The first is to pass through the steel planting on foundation pit supporting construction or ground-connecting-wall;It is for second, by supporting construction concrete
Protective layer is cut, and is then connected sealing up screw with supporting construction reinforcement welding.On the one hand both connection modes need to spend
A large amount of costs of labor and time cost, another aspect both approaches are required to the regular arrangement that sealing up screw is embarked on journey in column,
It can ensure to lead stupefied horizontal continuity or vertical continuous, reasonable stress.But it is difficult to realize in practical operation.
In traditional sealing up screw carries out single mode plate reinforcement means, the external labeling type waterproof roll preformed hole at sealing up screw
Hole is suspended on after supporting construction and cuts hole and pass through external labeling type waterproof roll convenient for sealing up screw.If first by sealing up screw
It is fixed in supporting construction, it is rear to hang paving external labeling type waterproof roll, it is necessary to one side paving coiled material, while drilling on coiled material.
To ensure that coiled material is smooth, it is necessary to ensure that sealing up screw perpendicular to branch mask, will so influence outer patch in boring procedure after paving
Formula coiled material installation effectiveness, while external labeling type coiled material is drilled with substantial amounts of hole, can not form complete water-proof system.Sealing up screw is broken
The globality of the outer waterproof of exterior wall is broken, a large amount of bolts hole are added on waterproof layer, repairing is time-consuming and laborious, and can not ensure own
The waterproof repairing of bolt hole can meet antiseep requirement.
In traditional sealing up screw carries out single mode plate reinforcement means, sealing up screw is repaiied after can not cutting on the outside of outer shear wall
It mends, although there is provided sealing steel discs, after the several years, bolt corrosion can form many penetrating passages, greatly increase outside underground
The possibility that wall seeps water in the future.
Utility model content
The utility model solve the deficiencies in the prior art and provide a kind of speed of application faster, reasonable stress, reinforce material
Material is conventional material, is lifted without large scale equipment, and the relatively low assembled sealing up screw of construction cost reinforces one side formwork
Structure and construction method.
To achieve these goals, the utility model provides following technical solution:A kind of sealing up screw reinforces unilateral mould
Harden structure, including foundation pit supporting construction and template, the foundation pit supporting construction in supporting construction steel reinforcement cage by pouring supporting knot
Structure concrete is formed, and the supporting construction steel reinforcement cage is connected and composed by vertical applied force reinforcing bar by ring-shaped stirrup and reinforcement stirrup,
Multiple pre-buried pull rods, the pre-buried drawing are evenly arranged on the vertical applied force reinforcing bar of the supporting construction steel reinforcement cage one side vertically
The part that bar stretches out the foundation pit supporting construction is vertical with foundation pit supporting construction, and multiple foundation pit supporting constructions are laid side by side,
So that towards template, sealing up screw is being fixed in the template equipped with the face where pre-buried pull rod for foundation pit supporting construction, it is described
Sealing up screw is connected by branch sleeve with pre-buried pull rod.
The template is stupefied including panel, secondary stupefied and master, and the sealing up screw passes through positioning screw cap, butterfly button and reinforces nut
Be located on panel, the front of the panel towards foundation pit supporting construction, the back side of the panel by secondary stupefied and main stupefied support,
The part of the same sealing up screw axially laid through panel be installed in two masters it is stupefied, and by being mounted on sealing up screw
Butterfly button and reinforce nut compressing it is secondary it is stupefied on, the panel front determined by the positioning screw cap being mounted on sealing up screw
Position ensures the spacing between panel and foundation pit supporting construction.
The foundation pit supporting construction is equipped with basal plane screed-coat towards template one side, and the basal plane screed-coat is parallel with template
It sets.
Adjacent Pit supporting construction junction is axially disposed the semicircle pvc pipe for preventing infiltration.By foundation pit supporting construction
The water that outside soil layer penetrates is along semicircle pvc pipe water conservancy diversion, and the waterproof material for preventing from being sprayed on supporting construction screed-coat is because of soil
The layer excessive breakage of seepage water pressure.
Waterproof layer is coated on the basal plane screed-coat and the opposite face of template, the waterproof layer is rapid hardening rubber
Glue flexible spray filmogen.
The branch sleeve is made of stainless steel, is non-through hole in the middle part of branch sleeve, has among non-through hole and pass through
Stainless steel separator is isolated.
This single side formwork bracing means has the advantages that:
(1) pull rod is reserved according to certain rule can ensure that sealing up screw transverse and longitudinal is embarked on journey into advance on supporting construction steel reinforcement cage
Row are reinforced convenient for sealing up screw, and foundation pit supporting construction protective layer welded reinforcement or bar planting, speed of application are cut compared with tradition
Faster;
(2) sealing up screw is connected on pre-buried pull rod, reasonable stress, be can effectively prevent concrete and is risen mould;
(3) waterproof material can effectively ensure construction in foundation pit branch using flexible sprays filmogens such as spraying rapid hardening rubber
Waterproof material on protection structure basal plane forms closing rounded system;
(4) branch sleeve is made of stainless steel, and to be non-through, there is stainless steel separator in centre, can effectively prevent sealing
Screw rod corrosion, rust are worn so as to cause exterior wall leakage;
(5) it is main it is stupefied for double steel pipe it is vertical, can to avoid on different foundation pit supporting constructions with arrange pre-buried pull rod absolute altitude occur compared with
Large deviation still can be reinforced effectively;
(6) this single side formwork reinforcing mode can be adapted for the shear wall one side formwork reinforcing of any height;
(7) English truss single side formwork reinforcing area was not applied in shear wall corner or other limited spaces should add
Gu mode.
(8) material that this reinforcement means uses is conventional material, is lifted without large scale equipment, construction cost compared with
It is low.
In conclusion using this structure construction speed faster, reasonable stress, reinforcement material be conventional material, without big
Type equipment is lifted, and construction cost is relatively low.
Description of the drawings
Fig. 1 is the schematic diagram of supporting construction steel reinforcement cage;
Fig. 2 is the sectional view of supporting construction steel reinforcement cage;
Fig. 3 is pre-buried pull rod and sealing up screw connection diagram;
Fig. 4 is the structure diagram of the present apparatus;
Specific embodiment
With reference to the accompanying drawings and examples, the specific embodiment of the utility model patent is described in further detail.
With embodiment for illustrating the utility model patent, but it is not intended to limit the scope of the present invention.
As shown in Figures 1 to 4, a kind of sealing up screw reinforces one side formwork structure, described including foundation pit supporting construction and template
Foundation pit supporting construction is formed by pouring supporting construction concrete in supporting construction steel reinforcement cage, and the supporting construction steel reinforcement cage is by erecting
It is connected and composed to steel bar stress 1 by ring-shaped stirrup 2 and reinforcement stirrup 3, the vertical applied force of the supporting construction steel reinforcement cage one side
Be evenly arranged with multiple pre-buried pull rods 7 on reinforcing bar vertically, the pre-buried pull rod 7 stretch out the part of the foundation pit supporting construction with
Foundation pit supporting construction is vertical, and multiple foundation pit supporting constructions are laid side by side so that foundation pit supporting construction is equipped with pre-buried pull rod 7
The face at place is fixed with sealing up screw 11 towards template in the template, the sealing up screw 11 by branch sleeve 10 with it is pre-
Pull rod 7 is buried to connect.Seal ring 12 is provided on sealing up screw 11, so as to play the role of waterproof when pouring shear wall in the later stage.
The template includes panel 13, secondary stupefied 14 and main stupefied 15, and panel 13 is equipped with 11 mounting hole of sealing up screw, described to stop
Water screw rod 11 is located in by positioning screw cap 18, butterfly button 16 and reinforcing nut 17 on panel 13, the positive face of the panel 13
To foundation pit supporting construction, the back side of the panel 13 passes through secondary stupefied 14 and main stupefied 15 support, the same sealing up screw axially laid
11 are installed in two masters stupefied 15 through the part of panel 13, and 16 He of butterfly button by being mounted on sealing up screw 11
It reinforces nut 17 to be pressed on secondary stupefied 14, the positive positioning screw cap 18 by being mounted on sealing up screw 11 of the panel 13
Positioning ensures the spacing between panel 13 and foundation pit supporting construction.
The foundation pit supporting construction is equipped with basal plane screed-coat 5 towards template one side, and the basal plane screed-coat 5 is put down with template
Row is set.
Adjacent Pit supporting construction junction is axially disposed the semicircle pvc pipe 8 for preventing infiltration.Semicircle PVC pipes 8 will
The water that soil layer penetrates on the outside of foundation pit supporting construction prevents from being sprayed on supporting construction screed-coat along semicircle pvc pipe water conservancy diversion
Waterproof material is because of the excessive breakage of soil layer seepage water pressure.
Waterproof layer 6 is coated on the basal plane screed-coat and the opposite face of template, the waterproof layer 6 is speed
Gel rubber flexible spray filmogen.
The branch sleeve 10 is made of stainless steel, is non-through hole in the middle part of branch sleeve, has among non-through hole logical
Cross stainless steel separator isolation.
A kind of assembled sealing up screw is reinforced one side formwork construction method and is included the following steps:
A, vertical applied force Steel Reinforcing Bar Material is carried out according to each stake drilling depth, using strengthening stirrup 3, vertical applied force reinforcing bar 1, ring
U stirrup 2 makes supporting construction steel reinforcement cage, and pre-buried drawing is marked on vertical applied force reinforcing bar according to the good spacing of template Force Calculation
The pre-buried pull rod of position welding of the position of bar, vertically steel bar stress mark, is being welded with the vertical applied force reinforcing bar of pre-buried pull rod
Upper tether rope mark;Pre-buried pull rod silk head is wrapped up using package covering material 9 and being covered, prevents silk head from being mixed by foundation pit supporting construction
Solidifying soil pollution;
B, supporting construction reinforcing bar cage hoisting is entered in stake holes, rotates supporting construction steel reinforcement cage by marking so that pre-buried drawing
For bar 7 towards template, concreting forms foundation pit supporting construction, and foundation pit supporting construction intensity carries out the earthwork point after reaching design load
Layer excavates and Guan Liang construction;
C, during earthwork stage excavation and pre-buried pull rod is found out, by stainless steel branch sleeve 10 by the sealing in template
Screw rod 11 and pre-buried pull rod 7 are correspondingly connected with;
Semicircle pvc pipe between Adjacent Pit supporting construction is installed, plain microlith coagulation is sprayed on foundation pit supporting construction d,
Soil after plain pea gravel concreten intensity is waited to reach 50%, does ash cake, and levelling formation basal plane screed-coat, basal plane are carried out with cement mortar
Screed-coat is parallel with template;Basal plane screed-coat reaches construction spraying waterproof layer after 50% intensity;Basal plane screed-coat 5 can smear water
Cement mortar can also be form concrete, when not extending out basal plane screed-coat 5 for pre-buried pull rod 7, using extension bar spreading, connect
There are sleeve in stock one end thread, one end, and exceeding basal plane screed-coat 5 after spreading is not less than 5cm.
E, installation form, successively on sealing up screw installation panel, it is secondary stupefied and master it is stupefied, by positioning screw cap, butterfly button and
Hold-doun nut adjusts panel, the secondary stupefied and main stupefied verticality that fixation is connected with sealing up screw, panel is checked with plumb line, bracing wire
Then flatness applies waterproof layer in template towards foundation pit supporting construction side spray;Positioning screw cap is installed at sealing up screw on-fixed end
18, it is ensured that all positioning screw caps 18 on the same line, while effectively ensure exterior wall thickness apart from base's distance with shearing wall thickness
Spend size.
F, shear wall concreting is carried out after template acceptance(check).
Pre-buried pull rod is L-shaped, after supporting construction steel reinforcement cage machines, by single welding or welding by both sides by pre-buried drawing
Bar welding parallel with foundation pit supporting construction same root vertical applied force muscle, it is ensured that all pre-buried pull rod directions are consistent, pre-buried pull rod edge
Vertical and horizontal direction spacing matches with sealing up screw design, and the pre-buried tie bar space supporting construction steel reinforcement cage bottom of same row
It is identical.
By supporting construction steel reinforcement cage into hoisting process in stake holes so that pre-buried pull rod direction is perpendicular to template so that
Each supporting construction steel reinforcement cage is identical away from vertical applied force reinforcing bar distance from bottom with pre-buried pull rod is arranged;The branch of supporting construction different depth
The most upper pre-buried pull rod of row of protection structure steel reinforcement cage is in same absolute altitude so that pre-buried pull rod is horizontal on each foundation pit supporting construction embarks on journey, and erects into
Row.
The panel is punching block or glued mould, and the described stupefied flitch or steel pipe being arranged horizontally, the master is stupefied to be
The double steel pipe being vertically arranged.
Inside shear wall pre-embedded anchoring bolts before template is sealed, need to implement measures to ensure that screw rod the relative position error compared with
It is small.If inside wall flatness is poor, it is necessary to using cement mortar that ground bolt near zone is levelling.
Claims (6)
1. a kind of assembled sealing up screw reinforces one side formwork structure, it is characterised in that:Including foundation pit supporting construction and template, institute
Foundation pit supporting construction is stated to be formed by pouring supporting construction concrete in supporting construction steel reinforcement cage, the supporting construction steel reinforcement cage by
Vertical applied force reinforcing bar is connected and composed by ring-shaped stirrup and reinforcement stirrup, the vertical applied force steel of the supporting construction steel reinforcement cage one side
Multiple pre-buried pull rods are evenly arranged on muscle vertically, the pre-buried pull rod stretches out part and the foundation pit of the foundation pit supporting construction
Supporting construction is vertical, and multiple foundation pit supporting constructions are laid side by side so that foundation pit supporting construction is where equipped with pre-buried pull rod
Face towards template, be fixed with sealing up screw in the template, the sealing up screw is connected by branch sleeve with pre-buried pull rod.
2. assembled sealing up screw according to claim 1 reinforces one side formwork structure, it is characterised in that:The template bag
Include panel, it is secondary stupefied and master it is stupefied, the sealing up screw by positioning screw cap, butterfly button and reinforce nut be located on panel, it is described
The front of panel towards foundation pit supporting construction, the back side of the panel by secondary stupefied and main stupefied support, it is same axially lay only
The part of water screw rod through panel be installed in two masters it is stupefied, and the butterfly button by being mounted on sealing up screw and reinforce spiral shell
Cap is pressed on time stupefied, and the front of the panel is positioned by the positioning screw cap being mounted on sealing up screw, ensures panel and base
Spacing between pit supporting construction.
3. assembled sealing up screw according to claim 1 or 2 reinforces one side formwork structure, it is characterised in that:The base
Pit supporting construction is equipped with basal plane screed-coat towards template one side, and the basal plane screed-coat is arranged in parallel with template.
4. assembled sealing up screw according to claim 3 reinforces one side formwork structure, it is characterised in that:Adjacent Pit branch
Protection structure junction is axially disposed the semicircle pvc pipe for preventing infiltration.
5. assembled sealing up screw according to claim 3 reinforces one side formwork structure, it is characterised in that:The basal plane is looked for
Waterproof layer is coated on flat bed and the opposite face of template, the waterproof layer is sprayed into membrane material for rapid hardening rubber flexible
Material.
6. assembled sealing up screw according to claim 5 reinforces one side formwork structure, it is characterised in that:The connector sleeve
Cylinder is made of stainless steel, is non-through hole in the middle part of branch sleeve, has among non-through hole and isolated by stainless steel separator.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721145206.9U CN207392189U (en) | 2017-09-07 | 2017-09-07 | Unilateral template structure is consolidated to assembled stagnant water screw rod |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721145206.9U CN207392189U (en) | 2017-09-07 | 2017-09-07 | Unilateral template structure is consolidated to assembled stagnant water screw rod |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207392189U true CN207392189U (en) | 2018-05-22 |
Family
ID=62415959
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721145206.9U Expired - Fee Related CN207392189U (en) | 2017-09-07 | 2017-09-07 | Unilateral template structure is consolidated to assembled stagnant water screw rod |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207392189U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107675699A (en) * | 2017-09-07 | 2018-02-09 | 中建五局第三建设有限公司 | Fabricated water-stop screw reinforced unilateral formwork structure and construction method |
-
2017
- 2017-09-07 CN CN201721145206.9U patent/CN207392189U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107675699A (en) * | 2017-09-07 | 2018-02-09 | 中建五局第三建设有限公司 | Fabricated water-stop screw reinforced unilateral formwork structure and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2021223573A1 (en) | Construction structure for communication and connection between newly added mined channel and existing station hall layer | |
CN106223360B (en) | Using the open cut cast in place and precast construction subway station construction method of stake supporting system | |
CN205742213U (en) | Foundation pit supporting construction | |
CN104389610B (en) | A kind of ultrashort step construction method of traversing operation freeway tunnel | |
CN106050266A (en) | Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel | |
CN111576431A (en) | Excavation method for foundation pit of four-layer subway station | |
CN112554885B (en) | Tunnel vertical shaft and transverse channel excavation method | |
CN104847365B (en) | A kind of small interval Four-Lane Road Shallow-buried Large-span Tunnel construction method | |
CN108612110A (en) | A kind of Deep Foundation Pit of Metro Stations combined type construction method for supporting | |
CN109610473A (en) | A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration | |
CN109537579A (en) | The construction method of cast-in-situ bored pile | |
CN103437779B (en) | The construction method of regulation tunnel lining pore gas flow | |
CN107489106A (en) | A kind of rocky bed subaqueous bearing platform construction method | |
CN207392189U (en) | Unilateral template structure is consolidated to assembled stagnant water screw rod | |
CN108331367A (en) | The Basement reconstruction structure of raft foundation | |
CN112012763B (en) | Construction method of double-layer primary support multi-arch tunnel structure | |
CN106088758B (en) | A kind of bilayer assembled underground granary | |
CN104032713B (en) | A kind of pressure diversion tunnel composite lining concrete anti-seepage structure and construction technology thereof | |
CN109930610A (en) | Constrained environment foundation pit adds the construction method of steel pipe mixing diagonal brace using concrete | |
CN112012762A (en) | Construction method of double-layer secondary lining multi-arch tunnel structure | |
CN112012761A (en) | Construction method of anti-disturbance double-arch tunnel structure | |
CN107675699A (en) | Fabricated water-stop screw reinforced unilateral formwork structure and construction method | |
CN203891047U (en) | Equipment equipped with steel platform for foundation construction of land bridge | |
CN209293068U (en) | A kind of open trench tunnel falsework system | |
CN106703015A (en) | Steel plate concrete prefabricated part, permanent-temporary combined underground enclosure system and construction methods |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180522 |