CN110080454A - LPM light filling body Construction of Cast-in-situ Concrete Hollow - Google Patents

LPM light filling body Construction of Cast-in-situ Concrete Hollow Download PDF

Info

Publication number
CN110080454A
CN110080454A CN201910468303.9A CN201910468303A CN110080454A CN 110080454 A CN110080454 A CN 110080454A CN 201910468303 A CN201910468303 A CN 201910468303A CN 110080454 A CN110080454 A CN 110080454A
Authority
CN
China
Prior art keywords
concrete
floating
construction
reinforcing bar
light filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910468303.9A
Other languages
Chinese (zh)
Inventor
汤鑫
闫立
黄磊
花继华
李春辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA UNION CENTURY BUILDING GROUP Co Ltd
Original Assignee
CHINA UNION CENTURY BUILDING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHINA UNION CENTURY BUILDING GROUP Co Ltd filed Critical CHINA UNION CENTURY BUILDING GROUP Co Ltd
Priority to CN201910468303.9A priority Critical patent/CN110080454A/en
Publication of CN110080454A publication Critical patent/CN110080454A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/48Special adaptations of floors for incorporating ducts, e.g. for heating or ventilating
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C1/00Building elements of block or other shape for the construction of parts of buildings
    • E04C1/24Elements for building-up floors, ceilings, roofs, arches, or beams
    • E04C1/34Elements for building-up floors, ceilings, roofs, arches, or beams designed for use as filling elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C1/00Building elements of block or other shape for the construction of parts of buildings
    • E04C1/40Building elements of block or other shape for the construction of parts of buildings built-up from parts of different materials, e.g. composed of layers of different materials or stones with filling material or with insulating inserts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs

Abstract

The invention discloses a kind of LPM light filling body Construction of Cast-in-situ Concrete Hollow, after the completion of installing board bottom template, board bottom and the installation of dark rib beam steel bar colligation cushion block, anti-floating drilling, board bottom and rib beam steel bar colligation, send special messenger to punch in bottom plate according to anti-floating cloth point diagram, water is installed, electric line, handling LPM light filling part, placement filling member, the binding of plate face reinforcing bar, the reinforcing of filling member anti-floating iron wire, casting concrete, maintenance and demoulding.Present invention process is simple, easy for construction, easily operated;This technology is used in suitable structure, while guaranteeing construction quality, is also had the characteristics that concrete amount is few, space is big, dead load is light, geological process power is small, the heat-insulated of structure, sound insulation property is good, is shortened the construction period.

Description

LPM light filling body Construction of Cast-in-situ Concrete Hollow
Technical field
The present invention relates to a kind of LPM light filling body Construction of Cast-in-situ Concrete Hollow.
Background technique
In modern architecture, wideling popularize green construction is the grand strategy for solving china natural resources energy problem.But it is existing Construction of Cast-in-situ Concrete Hollow is not able to satisfy the requirement of green construction, needs further to be improved.
Summary of the invention
The purpose of the present invention is to provide a kind of simple process, easy for construction, easily operated LPM light filling embodiment is poured Concrete hollow building roof construction method.
The technical solution of the invention is as follows:
A kind of LPM light filling body Construction of Cast-in-situ Concrete Hollow, it is characterized in that: the LPM light filling Body is with self-extinguishment flame-retarded light porous material-polyphenyl foam for filling main material, in addition reinforcement and separation layer;Isolation is wrapped up in outside main material The surface setting enhancement layer of layer protection and waterproof action, top or bottom is to resist construction and anti-floating load;
Construction method includes the following steps:
(1) board bottom template is installed
The end template of hollow floor use 15mm multi-layer board, secondary joist 40mm × 90mm flitch, main joist with 48mm × The double steel pipe of 3.2mm, support use fastener type steel pipe scaffold system, and full hall scaffold upright bar is equipped with adjustable jack; When span of slab >=4m, top plate palpus arch camber, springing height is the 2/1000-3/1000 (20mm) of full span length's degree;Formwork erection is completed It leads jug hustler that the position of concealed beam and filling member is released according to design drawing by builder afterwards, makes which construction personnel understands Position is obturator arrangement area, which position is solid main rib;Subsequent construction is carried out again;
(2) board bottom and the installation of dark rib beam steel bar colligation cushion block, anti-floating drilling
According to the position that setting-out determines, board bottom main reinforcement, distributing reinforcement spacing, by the straight of design drawing reinforcing bar are pulled in template Diameter and spacing, long short sequence, bind board bottom and dark girt strip reinforcing bar;Mounting plate bottom, dark girt strip bottom spacer after the completion of binding, Cushion block quantity must not be less than two in every square metre, and the distance between two neighboring cushion block is not preferably greater than 60cm;
(3) after the completion of board bottom and rib beam steel bar colligation, special messenger is sent to punch in bottom plate according to anti-floating cloth point diagram, aperture For 8-10mm;Each profession must carry out cooperation, accomplish to clear up sawdust in time after punching, when anti-floating control point drills, technical staff It should be checked and be instructed, it is ensured that it is accurate, it avoids doing over again;
(4) water, electric line are installed
The technology communication between profession is carried out before water, electric professional construction, consults work, is reduced to the greatest extent and is destroyed light filling part; Technical measures are as follows:
A, it is finished in plate formwork erection, examination, after the completion of board bottom and beam steel bar colligation, water, power technology personnel are according to profession Piping in-depth figure be accurately positioned, determine comb unwrapping wire and pipe away from;Brick or concrete duct person, professional surveyor carry out cooperating;
B, the pipeline in cored slab should be laid in as far as possible smooth vertical and horizontally in the real rib of packing material, can not such as be implemented and be managed When line and packing material position clash, can on packing material differential trench open, stay a channel to pipeline, then use plastics Adhesive tape is to carrying out repairing reinforcement at packing material fluting;
(5) handling LPM light filling part
LPM light filling part is put entirety on the horizontal blanket net of white as requested, blanket net surrounding is simultaneously tied up securely, Prevent high-altitude from falling object;The work surface of needs is hoisted to using the derrick crane of construction site;
(6) filling member, the binding of plate face reinforcing bar are placed
A, after board bottom, dark rib beam steel bar colligation and cushion block are installed, the position of beam uses double headed roller line, it is necessary to adjust one On bar line, it is ensured that the thickness of beam two sides protective layer carries out an acceptance inspection through quality person, management, after acceptance(check), then is filled body Placement is discharged into hollow zone position;
B, obturator placement is discharged into hollow zone position, and according to the requirement laying plate face reinforcing bar of design drawing, reinforcing bar is tied up It is certain it is noted that the finished product protection to light filling part should be repaired in time if destroyed accidentally in construction when pricking construction.
(7) filling member anti-floating iron wire is reinforced
After the completion of the binding of filling member top bars, in order to ensure filling member does not occur floating situation in concreting, Anti-floating reinforcement measure must be taken, requires reasonable Arrangement anti-floating control point according to technical solution, control point is generally located at girt strip, According to rectangle or quincuncial arrangement, when buoyancy is bigger, control point is also added in light filling area;In any case, all Guarantee to be no less than an anti-floating control point within the scope of each square metre;When fixed anti-floating control point, 16# iron wire is first passed through into mould Reinforcement and support for shuttering are fixed plate, fixed point vertically and horizontally spacing≤800mm;Iron wire one end is past from hole in template Under be pierced by, iron wire end is lived in wear back from hole after tying with the support system of template;By two ends of iron wire anti- It is tightened at floating control point, each anti-floating point is fixed using bifilar iron wire;The top and bottom of obturator is both needed to setting cushion block, It avoids upper and lower level reinforcing bar from directly contacting with obturator, leads to reduce concrete to the bond stress of reinforcing bar;
(8) casting concrete
Filling member installs, reinforcing bar binding is completed, and conscientiously checks in place each anti-floating fixed point, the hidden inspection of reinforcing bar After qualification, fill in that reinforcing bar is hidden and light filling body installation inspection lot inspection of quality record can pour after checking that confirmation is qualified Concrete;Slump >=150mm of concrete, maximum particle diameter≤25mm of coarse aggregate in concrete;Due to filling member self weight compared with Gently, buoyancy is larger, when concreting, takes the mode of placement layer by layer, assigns special messenger's nurse, timely processing of finding the problem, when When cored slab thickness h >=250mm, suitable casting concrete in two times, when h >=800mm, points 3 times;First by concreting to plate thickness Vibrating spear is inserted into girt strip and carefully vibrates, vibrating spear should be avoided and directly contact with tube filler by place, to prevent from destroying cylinder Core, must not leakage;After confirming that concrete vibrating is closely knit, i.e., concrete surface no longer declines or has seen from adjacent rib concrete Underflow vibrated, then pour layer concrete;Crack is generated very much fastly in order to avoid concrete surface moisture is shunk, and is used Wooden looking for flat or iron plate are covered with plastic film immediately after receiving light;
(9) maintenance and demoulding
A, concrete curing preferably uses plastic film to cover, and keeps concrete surface wet, and curing time is no less than 7 days, There is the curing time of seepage resistance demand concrete to be no less than 14 days;
B, demoulding foundation
Form removable must declare the same condition of concrete using test cube in the same condition pressure testing result as foundation to management before demoulding Curing test block Measurement Report strictly fulfils demoulding examination and approval procedures;Top plate, beam strength of mould stripping see the table below:
Concrete structure strength of mould stripping table
The present invention not only simple process, easy for construction, it is easily operated, this technology is used in suitable structure, is guaranteed While construction quality, also have concrete amount is few, space is big, dead load is light, geological process power is small, structure it is heat-insulated, Sound insulation property is good, the features such as shortening the construction period, thus can it is energy saving, reduce and build and use cost, to generate good warp Ji benefit, energy conservation and environmental protection benefit and social benefit.
It is a kind of environmentally protective construction technology that LPM light filling, which embodies pouring concrete hollow slab floor structure, suitable Structure in using after the technology, other than it can mitigate dead load and geological process, moreover it is possible to energy saving, reduce and build and make Cost generates good economic benefit and social benefit.Compared with other hollow floors, LPM hollow floor in addition to sound insulation, Except heat-proof quality is good, there are also following characteristics:
1, superstructure hollow rate is big, and hollow rate is about 65% or so, higher than conventional hollow superstructure by 10% or so;
2, facilitate the installation of pipeline, can slot on packing material or Durchgangshohle, pipeline installation are unrestricted;
3, packing material water absorption rate is small, and the separation layer outside light-weight body material is less than packing material water absorption rate 0.5%, so need not specially moisten cylinder, particularly convenient winter construction, smooth separation layer and concrete before casting concrete Coefficient of friction is small, convenient for concrete flowing and pour closely knit.
4, packing material is light-weight and not cracky, and every square metre of LPM cylinder weight is only 3~12 ㎏, horizontal and vertical Transport very convenient, and solid cylinder is elastic-plastic material, and not cracky is easy repairing.Its construction and installation is relatively easy.
5, speed of application is fast, and effect is good.
Especially suitable for tier building, skyscraper, underground garage and podium engineering.
Below with reference to embodiment, the invention will be further described.
Specific embodiment
A kind of LPM light filling body Construction of Cast-in-situ Concrete Hollow, the LPM light filling body is with self-extinguishment Flame-retarded light porous material-polyphenyl foam is filling main material, in addition reinforcement and separation layer;Wrap up in outside main material separation layer rise protection with The surface setting enhancement layer of waterproof action, top or bottom is to resist construction and anti-floating load;
Construction method includes the following steps:
(1) board bottom template is installed
The end template of hollow floor use 15mm multi-layer board, secondary joist 40mm × 90mm flitch, main joist with 48mm × The double steel pipe of 3.2mm, support use fastener type steel pipe scaffold system, and full hall scaffold upright bar is equipped with adjustable jack; When span of slab >=4m, top plate palpus arch camber, springing height is the 2/1000-3/1000 (20mm) of full span length's degree;Formwork erection is completed It leads jug hustler that the position of concealed beam and filling member is released according to design drawing by builder afterwards, makes which construction personnel understands Position is obturator arrangement area, which position is solid main rib;Subsequent construction is carried out again;
(2) board bottom and the installation of dark rib beam steel bar colligation cushion block, anti-floating drilling
According to the position that setting-out determines, board bottom main reinforcement, distributing reinforcement spacing, by the straight of design drawing reinforcing bar are pulled in template Diameter and spacing, long short sequence, bind board bottom and dark girt strip reinforcing bar;Mounting plate bottom, dark girt strip bottom spacer after the completion of binding, Cushion block quantity must not be less than two in every square metre, and the distance between two neighboring cushion block is not preferably greater than 60cm;
(3) after the completion of board bottom and rib beam steel bar colligation, special messenger is sent to punch in bottom plate according to anti-floating cloth point diagram, aperture For 8-10mm;Each profession must carry out cooperation, accomplish to clear up sawdust in time after punching, when anti-floating control point drills, technical staff It should be checked and be instructed, it is ensured that it is accurate, it avoids doing over again;
(4) water, electric line are installed
The technology communication between profession is carried out before water, electric professional construction, consults work, is reduced to the greatest extent and is destroyed light filling part; Technical measures are as follows:
A, it is finished in plate formwork erection, examination, after the completion of board bottom and beam steel bar colligation, water, power technology personnel are according to profession Piping in-depth figure be accurately positioned, determine comb unwrapping wire and pipe away from;Brick or concrete duct person, professional surveyor carry out cooperating;
B, the pipeline in cored slab should be laid in as far as possible smooth vertical and horizontally in the real rib of packing material, can not such as be implemented and be managed When line and packing material position clash, can on packing material differential trench open, stay a channel to pipeline, then use plastics Adhesive tape is to carrying out repairing reinforcement at packing material fluting;
(5) handling LPM light filling part
LPM light filling part is put entirety on the horizontal blanket net of white as requested, blanket net surrounding is simultaneously tied up securely, Prevent high-altitude from falling object;The work surface of needs is hoisted to using the derrick crane of construction site;
(6) filling member, the binding of plate face reinforcing bar are placed
A, after board bottom, dark rib beam steel bar colligation and cushion block are installed, the position of beam uses double headed roller line, it is necessary to adjust one On bar line, it is ensured that the thickness of beam two sides protective layer carries out an acceptance inspection through quality person, management, after acceptance(check), then is filled body Placement is discharged into hollow zone position;
B, obturator placement is discharged into hollow zone position, and according to the requirement laying plate face reinforcing bar of design drawing, reinforcing bar is tied up It is certain it is noted that the finished product protection to light filling part should be repaired in time if destroyed accidentally in construction when pricking construction.
(7) filling member anti-floating iron wire is reinforced
After the completion of the binding of filling member top bars, in order to ensure filling member does not occur floating situation in concreting, Anti-floating reinforcement measure must be taken, requires reasonable Arrangement anti-floating control point according to technical solution, control point is generally located at girt strip, According to rectangle or quincuncial arrangement, when buoyancy is bigger, control point is also added in light filling area;In any case, all Guarantee to be no less than an anti-floating control point within the scope of each square metre;When fixed anti-floating control point, 16# iron wire is first passed through into mould Reinforcement and support for shuttering are fixed plate, fixed point vertically and horizontally spacing≤800mm;Iron wire one end is past from hole in template Under be pierced by, iron wire end is lived in wear back from hole after tying with the support system of template;By two ends of iron wire anti- It is tightened at floating control point, each anti-floating point is fixed using bifilar iron wire;The top and bottom of obturator is both needed to setting cushion block, It avoids upper and lower level reinforcing bar from directly contacting with obturator, leads to reduce concrete to the bond stress of reinforcing bar;
(8) casting concrete
Filling member installs, reinforcing bar binding is completed, and conscientiously checks in place each anti-floating fixed point, the hidden inspection of reinforcing bar After qualification, fill in that reinforcing bar is hidden and light filling body installation inspection lot inspection of quality record can pour after checking that confirmation is qualified Concrete;Slump >=150mm of concrete, maximum particle diameter≤25mm of coarse aggregate in concrete;Due to filling member self weight compared with Gently, buoyancy is larger, when concreting, takes the mode of placement layer by layer, assigns special messenger's nurse, timely processing of finding the problem, when When cored slab thickness h >=250mm, suitable casting concrete in two times, when h >=800mm, points 3 times;First by concreting to plate thickness Vibrating spear is inserted into girt strip and carefully vibrates, vibrating spear should be avoided and directly contact with tube filler by place, to prevent from destroying cylinder Core, must not leakage;After confirming that concrete vibrating is closely knit, i.e., concrete surface no longer declines or has seen from adjacent rib concrete Underflow vibrated, then pour layer concrete;Crack is generated very much fastly in order to avoid concrete surface moisture is shunk, and is used Wooden looking for flat or iron plate are covered with plastic film immediately after receiving light;
(9) maintenance and demoulding
A, concrete curing preferably uses plastic film to cover, and keeps concrete surface wet, and curing time is no less than 7 days, There is the curing time of seepage resistance demand concrete to be no less than 14 days;
B, demoulding foundation
Form removable must declare the same condition of concrete using test cube in the same condition pressure testing result as foundation to management before demoulding Curing test block Measurement Report strictly fulfils demoulding examination and approval procedures;Top plate, beam strength of mould stripping see the table below:
Concrete structure strength of mould stripping table

Claims (1)

1. a kind of LPM light filling body Construction of Cast-in-situ Concrete Hollow, it is characterized in that: the LPM light filling body It is with self-extinguishment flame-retarded light porous material-polyphenyl foam for filling main material, tyre reinforces and separation layer;Separation layer is wrapped up in outside main material Protection and waterproof action are played, the surface setting enhancement layer of top or bottom is to resist construction and anti-floating load;
Construction method includes the following steps:
(1) board bottom template is installed
The end template of hollow floor uses 15mm multi-layer board, secondary joist 40mm × 90mm flitch, main joist 48mm × 3.2mm Double steel pipe, support use fastener type steel pipe scaffold system, full hall scaffold upright bar be equipped with adjustable jack;Span of slab When >=4m, top plate palpus arch camber, springing height is the 2/1000-3/1000 of full span length's degree;After the completion of formwork erection by builder with Neck jug hustler releases the position of concealed beam and filling member according to design drawing, and construction personnel is made to understand which position is obturator Arrange area, which position is solid main rib;Subsequent construction is carried out again;
(2) board bottom and the installation of dark rib beam steel bar colligation cushion block, anti-floating drilling
According to the position that setting-out determines, pull board bottom main reinforcement in template, distributing reinforcement spacing, by design drawing reinforcing bar diameter and Spacing, long short sequence, bind board bottom and dark girt strip reinforcing bar;Mounting plate bottom, dark girt strip bottom spacer, often put down after the completion of binding Cushion block quantity must not be less than two in square rice, and the distance between two neighboring cushion block is not preferably greater than 60cm;
(3) after the completion of board bottom and rib beam steel bar colligation, special messenger is sent to punch in bottom plate according to anti-floating cloth point diagram, aperture 8- 10mm;Each profession must carry out cooperation, accomplish to clear up sawdust in time after punching, and when anti-floating control point drills, technical staff should be into Row checks and guidance, it is ensured that and it is accurate, it avoids doing over again;
(4) water, electric line are installed
The technology communication between profession is carried out before water, electric professional construction, consults work, is reduced to the greatest extent and is destroyed light filling part;Mainly Technical measures are as follows:
A, it is finished in plate formwork erection, examination, after the completion of board bottom and beam steel bar colligation, water, power technology personnel are piped according to profession In-depth figure be accurately positioned, determine comb unwrapping wire and pipe away from;Brick or concrete duct person, professional surveyor carry out cooperating;
B, the pipeline in cored slab should be laid in as far as possible smooth vertical and horizontally in the real rib of packing material, can not such as implement and pipeline with When packing material position clashes, can on packing material differential trench open, stay a channel to pipeline, then use plastic adhesive tape To carrying out repairing reinforcement at packing material fluting;
(5) handling LPM light filling part
LPM light filling part is put entirety on the horizontal blanket net of white as requested, blanket net surrounding is simultaneously tied up securely, is prevented Fall object in high-altitude;The work surface of needs is hoisted to using the derrick crane of construction site;
(6) filling member, the binding of plate face reinforcing bar are placed
A, after board bottom, dark rib beam steel bar colligation and cushion block are installed, the position of beam uses double headed roller line, it is necessary to adjust in a line On, it is ensured that the thickness of beam two sides protective layer carries out an acceptance inspection through quality person, management, after acceptance(check), then is filled the placement of body It is discharged into hollow zone position;
B, obturator placement is discharged into hollow zone position, and according to the requirement laying plate face reinforcing bar of design drawing, reinforcing bar binding is applied Working hour is certain it is noted that the finished product protection to light filling part should be repaired in time if destroyed accidentally in construction.
(7) filling member anti-floating iron wire is reinforced
After the completion of the binding of filling member top bars, in order to ensure filling member does not occur floating situation in concreting, it is necessary to Anti-floating reinforcement measure to be taken, requires reasonable Arrangement anti-floating control point according to technical solution, control point is generally located at girt strip, according to Rectangle or quincuncial arrangement will also add control point in light filling area when buoyancy is bigger;In any case, Dou Yaobao It demonstrate,proves and is no less than an anti-floating control point within the scope of each square metre;It, first will across template by 16# iron wire when fixed anti-floating control point Reinforcement is fixed with support for shuttering, fixed point vertically and horizontally spacing≤800mm;It is worn down from hole in template iron wire one end Out, iron wire end is lived in wear back from hole after tying with the support system of template;By two ends of iron wire in anti-floating control It is tightened at system point, each anti-floating point is fixed using bifilar iron wire;The top and bottom of obturator is both needed to setting cushion block, avoids Upper and lower level reinforcing bar is directly contacted with obturator, leads to reduce concrete to the bond stress of reinforcing bar;
(8) casting concrete
Filling member installs, reinforcing bar binding is completed, and conscientiously checks in place each anti-floating fixed point, the hidden passed examination of reinforcing bar Afterwards, fill in that reinforcing bar is hidden and light filling body installation inspection lot inspection of quality record can pour coagulation after checking that confirmation is qualified Soil;Slump >=150mm of concrete, maximum particle diameter≤25mm of coarse aggregate in concrete;Since filling member self weight is lighter, floating Power is larger, when concreting, takes the mode of placement layer by layer, assigns special messenger's nurse, and cored slab is worked as in timely processing of finding the problem When thickness h >=250mm, suitable casting concrete in two times, when h >=800mm, points 3 times;First by concreting to plate thickness 1/3- At 1/2, vibrating spear is inserted into girt strip and is carefully vibrated, vibrating spear should be avoided and directly contacted with tube filler, to prevent from destroying tube filler, no Obtain leakage;After confirming that concrete vibrating is closely knit, i.e., concrete surface no longer declines or sees from adjacent rib the dense of concrete Slurry is vibrated, then pours layer concrete;Crack is generated very much fastly in order to avoid concrete surface moisture is shunk, and use is wooden Looking for flat or iron plate are covered with plastic film immediately after receiving light;
(9) maintenance and demoulding
A, concrete curing preferably uses plastic film to cover, and keeps concrete surface wet, curing time is no less than 7 days, is had anti- Infiltration requires the curing time of concrete to be no less than 14 days;
B, demoulding foundation
Form removable must declare concrete cured under same condition using test cube in the same condition pressure testing result as foundation to management before demoulding Intensity of test block report, strictly fulfils demoulding examination and approval procedures;Top plate, beam strength of mould stripping see the table below:
Concrete structure strength of mould stripping table
CN201910468303.9A 2019-05-31 2019-05-31 LPM light filling body Construction of Cast-in-situ Concrete Hollow Pending CN110080454A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910468303.9A CN110080454A (en) 2019-05-31 2019-05-31 LPM light filling body Construction of Cast-in-situ Concrete Hollow

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910468303.9A CN110080454A (en) 2019-05-31 2019-05-31 LPM light filling body Construction of Cast-in-situ Concrete Hollow

Publications (1)

Publication Number Publication Date
CN110080454A true CN110080454A (en) 2019-08-02

Family

ID=67422864

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910468303.9A Pending CN110080454A (en) 2019-05-31 2019-05-31 LPM light filling body Construction of Cast-in-situ Concrete Hollow

Country Status (1)

Country Link
CN (1) CN110080454A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113309282A (en) * 2021-06-11 2021-08-27 中电建十一局工程有限公司 Hollow floor slab construction process
CN113622572A (en) * 2021-08-19 2021-11-09 广东省第四建筑工程有限公司 Hollow floor slab filling box fixing construction method
CN114908914A (en) * 2022-05-20 2022-08-16 江苏国鹏建工集团有限公司 Method for improving construction quality of EPS foam light filling body hollow floor
CN117286978A (en) * 2023-11-24 2023-12-26 中铁二十二局集团轨道工程有限公司 Construction process of prestressed hollow slab

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105442736A (en) * 2015-12-03 2016-03-30 荣盛建设工程有限公司 Anti-floating construction method for cast-in-place concrete hollow floor sectional type combined device
CN106088436A (en) * 2016-06-12 2016-11-09 青岛海川建设集团有限公司 BRT Lightweight core mould construction technology
KR101928315B1 (en) * 2018-02-12 2018-12-12 우진에코텍 주식회사 Construction Method by Using Double Welded Steel Mesh

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105442736A (en) * 2015-12-03 2016-03-30 荣盛建设工程有限公司 Anti-floating construction method for cast-in-place concrete hollow floor sectional type combined device
CN106088436A (en) * 2016-06-12 2016-11-09 青岛海川建设集团有限公司 BRT Lightweight core mould construction technology
KR101928315B1 (en) * 2018-02-12 2018-12-12 우진에코텍 주식회사 Construction Method by Using Double Welded Steel Mesh

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
李华刚: "LPM填充件混凝土现浇空心楼板施工技术", 《城市建设理论研究》 *
狄超: "LPM填充体混凝土空心楼盖施工技术", 《建筑技术》 *
罗广: "新型预应力空心楼盖技术在广电中心工程中应用", 《施工机械化新技术交流会论文集(第九辑)》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113309282A (en) * 2021-06-11 2021-08-27 中电建十一局工程有限公司 Hollow floor slab construction process
CN113622572A (en) * 2021-08-19 2021-11-09 广东省第四建筑工程有限公司 Hollow floor slab filling box fixing construction method
CN113622572B (en) * 2021-08-19 2022-08-05 广东省第四建筑工程有限公司 Fixing construction method for hollow floor slab filling box
CN114908914A (en) * 2022-05-20 2022-08-16 江苏国鹏建工集团有限公司 Method for improving construction quality of EPS foam light filling body hollow floor
CN114908914B (en) * 2022-05-20 2023-11-21 江苏国鹏建工集团有限公司 Method for improving construction quality of EPS foam light filling body hollow floor system
CN117286978A (en) * 2023-11-24 2023-12-26 中铁二十二局集团轨道工程有限公司 Construction process of prestressed hollow slab

Similar Documents

Publication Publication Date Title
CN110080454A (en) LPM light filling body Construction of Cast-in-situ Concrete Hollow
CN101413251B (en) 0 type block anti-cracking construction method of high pier large across creeping formwork
CN107083817A (en) A kind of cast-in-place concrete bamboo core floor construction and its construction technology
CN103590602B (en) The construction method of cast-in-place concrete hollow building roof
CN106437142A (en) Construction method and double-layer formwork structure for cast-in-situ slope roof
CN109706846B (en) High and narrow bridge capping beam through steel bar construction method for slope foundation
CN108330835A (en) The construction method of setting bracket
CN103806656A (en) Construction method of cast-in-place concrete flat slab built-in thin-wall hollow box body
CN105178603A (en) EPS polyphenyl dismantling-exempt template concrete building cover plate construction technology method
CN109235891A (en) A kind of Large Span Prestressed Beam concrete pitched roof jump storehouse method construction method
CN104631332B (en) PC T beam precast erection construction method
CN103498425A (en) Full-dismounting combination type multifunctional bracket supporting structure and construction method thereof
CN105442629B (en) A kind of large scale equipment T stage vibration isolation mounts construction
CN103806659B (en) Super thick prestressing force change-over panel individual layer comprehensively supports and splits temperature control construction technology with control
CN103410269A (en) Unbonded prestress cast-in-place reinforced concrete hollow slab construction structure and method
CN104405068A (en) Construction method of post-tensioned unbonded prestressed hollow floor slab
CN104060760B (en) High Rise Building Transfer Floor Structure concrete super large beam construction in layer method
CN111997066A (en) Manufacturing and construction method of assembled prestressed anchor cable frame beam for slope reinforcement
CN106760050A (en) The attachment structure and through processing method of shear wall and after-pouring concrete frame beam
CN107476567A (en) It is a kind of to control the pitched roof gradient and the construction method and track-type facilities of thickness
CN104975614B (en) Shaped steel combination formula single side formwork strengthening construction engineering method
CN207363251U (en) A kind of track-type facilities for being used to control the pitched roof gradient and thickness
CN111042569B (en) Construction method for additionally building linear accelerator machine room in limited space of hospital basement
CN102797223A (en) Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method
CN104846745B (en) Urban high-pier support-free formwork turnover construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190802

RJ01 Rejection of invention patent application after publication