CN106088436A - BRT Lightweight core mould construction technology - Google Patents

BRT Lightweight core mould construction technology Download PDF

Info

Publication number
CN106088436A
CN106088436A CN201610405622.1A CN201610405622A CN106088436A CN 106088436 A CN106088436 A CN 106088436A CN 201610405622 A CN201610405622 A CN 201610405622A CN 106088436 A CN106088436 A CN 106088436A
Authority
CN
China
Prior art keywords
floor
mould
ferrum
concrete
girt strip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610405622.1A
Other languages
Chinese (zh)
Inventor
李绪春
张庆涛
张伟
其他发明人请求不公开姓名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Haichuan Construction Group Co Ltd
Original Assignee
Qingdao Haichuan Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Haichuan Construction Group Co Ltd filed Critical Qingdao Haichuan Construction Group Co Ltd
Priority to CN201610405622.1A priority Critical patent/CN106088436A/en
Publication of CN106088436A publication Critical patent/CN106088436A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Ceramic Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Physics & Mathematics (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of BRT Lightweight core mould construction technology, comprise the following steps: (one) preparation of construction;(2) colligation floor floor iron and girt strip;(3) preheating embedding line and reserved sleeve pipe are laid;(4) anti-floating fixing point is set;(5) anti-floating of inspecting for acceptance point is arranged;(6) hollow box mould bottom cushion block is installed;(7) hollow box mould is installed;(8) ferrum on colligation floor;(9) ferrum cushion block is set;(10) erection construction sidewalk, erection concrete conveying pipe;(11) concealment acceptance;(12) concrete placings;(13) maintenance, form removal;(14) later stage processes.The construction technology of the present invention reduces the deadweight of plate face, it is ensured that the safety coefficient of support system;It is applicable to various span and the building of various load, is particularly well-suited to large span and big load, the multilamellar of large space and skyscraper.

Description

BRT Lightweight core mould construction technology
Technical field
The present invention relates to a kind of BRT Lightweight core mould construction technology.
Background technology
BRT Lightweight core mould close rib composite floor plate system, forms through casting concrete after mould in placing by certain rule Cavity building roof.By the interior mould in the internal embedding lightweight of floor, reach, in the case of the computed altitude increasing floor, not increase The deadweight of floor construction, thus it is finally reached minimizing number of steel bars, reduce concrete amount, reduce the purpose of construction costs.From From the point of view of Flexural Strength, placing hollow box body and form cavity in cast-in-situ floor, the normal section of the plate in the horizontal, vertical direction of interior mould becomes The bearing capacity in I-shaped cross section and the solid slab of equivalent are identical.
Summary of the invention
The technical problem to be solved is: provide a kind of BRT Lightweight core mould construction technology.
For solving above-mentioned technical problem, the technical solution used in the present invention is:
The BRT Lightweight core mould construction technology that the present invention provides, comprises the following steps:
(1) preparation of construction
(1) slab form has been propped up and has been checked and accepted by preliminary examination, and the Vierendeel girder reinforcing bar colligation of frame structure completes;
(2) reinforcing bar and case mould riding position line are played
According to designing and arranging case figure requirement, unwrapping wire on slab form, it is ensured that the position that follow-up girt strip reinforcing bar binding and case mould are installed Accurately;According to axis, release vertically and horizontally girt strip control line, be i.e. to lay case mould position between girt strip;Unwrapping wire is at inner membrance for the second time After casing installs, in hollow box body, unwrapping wire uses whiting to replace prepared Chinese ink, and to ensure, unwrapping wire is clear firm;
(2) colligation floor floor iron and girt strip
According to the position of snap the line in template, colligation floor floor iron and case mould limit girt strip successively;First according to tying up the method for beam along floor Xia Tie lower floor muscle direction colligation floor girt strip, and lay same direction floor floor iron;Then, muscle direction, underfloor ferrum upper strata is laid Girt strip on ferrum, be inserted in rib beam hoop reinforcement one by one, after stirrup has overlapped, wear the lower ferrum of girt strip and underfloor ferrum and colligation is firm;
(3) preheating embedding line and reserved sleeve pipe are laid
Each specialty preheating embedding line in floor along girt strip and is arranged in girt strip cross section, avoids case mould position;External diameter 15mm with Under small pipe line be laid on case mould bottom, but less than one layer, must not intersect under case mould, in order to avoid padded case mould;
(4) anti-floating fixing point is set
After floor floor iron and girt strip reinforcing bar binding, anti-floating point can be started setting up;The anti-floating force path that anti-floating point is arranged It is as follows: case mould buoyancy that------rib beam hoop reinforcement or iron wire connect---floor floor iron---anti-floating point iron wire---mould to ferrum on floor Plate body system;Anti-floating point uses No. 14 iron wires, punches at floor floor iron upper strata muscle two side template with power drill (using Φ 4 drill bit), Iron wire is tightened through template in formwork keel side, by floor floor iron upper strata muscle and template fixation;Fixing point is from floor week While start to arrange to centre, spacing 1 meter in length and breadth, edge, post-cast strip also to be arranged;Rib beam hoop reinforcement to be made or drag hook hook on floor Ferrum upper strata muscle, to ensure the effective force of anti-floating point;Otherwise, should again with No. 14 iron wires by ferrum upper strata muscle on floor and lower ferrum colligation Tighten, be correspondingly arranged with lower ferrum anti-floating point, it is ensured that anti-floating effect;
(5) anti-floating of inspecting for acceptance point is arranged
After anti-floating point has set, carrying out anti-floating point special project middle inspection and check and accept, to ensure that anti-floating point arranges uniformly, position is accurate, Fixation is reliable, meets anti-floating requirement;
(6) hollow box mould bottom cushion block is installed
Cushion block is set under hollow box mould, it is ensured that the concrete thickness of case mould bottom;Pad thickness case to be met mould bottom coagulation The design thickness requirement of soil;Quantity is set, for the case mould of 700*700, only respectively arranges one piece, for 700* in case mould corner The case mould of 400, places 2 pieces, and can guarantee that case mould bottom concrete thickness is as the criterion;Because casing is subject to mixed when casting concrete The buoyancy of solidifying soil, thus the cushion block of lower box can also save need not;
(7) hollow box mould is installed
The handling of hollow box mould uses the uncovered steel reinforcement cage welded, and inside steel reinforcement cage, four limits and bottom surface multi-layer sheet are closed;Press According to cloth case figure, put successively in each girt strip space, place smooth, all around align, align;Intensive to local pipeline, The position that caliber is big, it is impossible to when placing thick case mould, the case mould of other specification can be used instead;After case mould is laid, it should be noted that finished product is protected Protect, it is to avoid personnel frequently trample, destroy;Damaged case mould, should change during ferrum in colligation in time;
(8) ferrum on colligation floor
After hollow box mould has been laid, start ferrum on colligation floor;Now, on girt strip, ferrum colligation completes, in the most remaining girt strip Between floor on ferrum;On floor, ferrum should be positioned at same layer with ferrum on girt strip, and firm with girt strip reinforcing bar binding;For ensureing anti-floating point Effective, on floor on ferrum girt strip to be pressed under ferrum, otherwise should be separately provided ferrum anti-floating point corresponding with lower ferrum anti-floating point connect;
On floor after ferrum colligation, each hollow box mould top and floor add cushion block between ferrum, pushes down case mould, and ensure Case mould top concrete thickness;
(9) ferrum cushion block is set
Upper ferrum method to set up and quantity are with bottom cushion block;
(10) erection construction sidewalk, erection concrete conveying pipe
Case calligraphy or painting model body has certain intensity, but frequently tramples and also easily cause damage, after especially adding top cushion block, and stress collection In, fragile;In construction, application scaffold board sets up built on stilts builder's road, and convenient construction operator operate, pass through, and protect Case mould and floor bar finished product;Concrete delivery pump pipe directly on floor bar, should can not set up short tube shelf or chock by frame The riding positions such as side etc. are high by pump line frame, boom answer schedule ahead good, and boom application scaffold board and shelf frame are high, must not be straight Connect and be pressed on case mould;Construction equipments etc. must not be placed on hollow box mould, and constructing operation personnel must not trample hollow box mould;
(11) concealment acceptance
After the operations such as reinforcing bar binding, case mould installation complete, tissue related personnel carry out three inspections and hidden inspect for acceptance, and emphasis is strengthened The inspection that antagonism floating-point is arranged, after acceptance(check), enters concreting operation;
(12) concrete placings
Cast-in-place concrete hollow building roof structure pours with concrete, and its slump should be more slightly larger than solid plain superstructure, desirable 18 ~ 20cm, and be the slump to cast in situs;Coarse aggregate size preferably selects less than 25mm;Case calligraphy or painting model body belongs to cement products, Should first sprinkle water before concreting moistening (winter should not sprinkle water);Concreting preferably uses pumping;Pour along floor span side To from the beginning of side, order is carried out successively, and cloth is the most uniformly, it is to avoid concrete piles up too high damage case mould at same position;Vibrate Rod vibrates along girt strip position successively along casting direction, should suitably strengthen vibrating time and a quantity of vibrating than solid superstructure, vibrate Observing hollow box mould surrounding simultaneously, until no longer there being bubble to emerge, representing that case mould lower concrete is the most closely knit;Vibrating spear should be avoided Directly touching hollow box mould;In casting process as bad in hollow box wear, it is necessary to process in time;The lightweights such as available nylon braided bag It is tight that article fill in breakage closure, fills in article and exposes case mould surface, cause concrete slag inclusion after being careful not to make;
Using special strong concrete to pour, concrete includes the composition of following parts by weight: cement 100 parts, water 100-150 part, flyash 20-30 part, nemalite 22-31 part, basalt fibre 15-24 part, silicon bath soil 9-17 part, chlorination Sodium 8-14 part, melamine cyanurate 5-13 part, water reducer 12-17 part.
Water reducer includes the component of following parts by weight: tert-butyl acrylate 25-30 part, melamine cyanurate salt 20- 30 parts, sodium hexameta phosphate 15-25 part, sulfamic acid sodium 10-17 part.
The preparation method of described strong concrete, comprises the following steps:
(1), first cement, water, flyash, nemalite stirring are made its mix homogeneously;
(2), the water reducer stirring of basalt fibre, silicon bath soil, sodium chloride and half parts by weight is made its mix homogeneously, then Being added in the blending ingredients that step (1) obtains, stirring makes its mix homogeneously;
(3), the water reducer of melamine cyanurate and half parts by weight is added in the blending ingredients that step (2) obtains, stir Mix and make its mix homogeneously, obtain strong concrete.
(13) maintenance, form removal
The maintenance of concrete is identical with solid superstructure with form removal, uses water seasoning summer, and winter can be (thick with Polypropylence Sheet and straw screen or mat Degree is determined by thermodynamic metering) carry out covering and heat insulating maintenance;
(14) later stage processes
BRT Lightweight core mould form removal is complete, for preventing floor slab bottoms steel bar corrosion, need to be cut by 14# iron wire used by fixing core Cut, antirust treatment;Construction method is: dig iron wire root to the 1cm degree of depth in plate, is then cut by iron wire, then brush antirust paint, Floating with waterproof mortar again;
Processed by this operation, it is ensured that in floor, reinforcing bar is not because tie wire causes getting rusty, and affects project durability, from all On solve the internal steel bar corrosion problem of floor.
Winter construction: winter construction hollow box mould is deposited and preferably hidden, when laying, should there be ice and snow foreign material surface and inside, no Then must remove clean;Should not water on winter construction cast-in-situ hollow building roof case mould;Concreting covers guarantor after completing in time Replenishing vital QI with drugs of warm nature protects;Floor is hung: hangs weight on floor and should meet design requirement;Sling point selects girt strip or floor solid section as far as possible Position.
Beneficial effects of the present invention
1 economic aspect: to cast-in-place concrete hollow building roof structure and soap-free emulsion polymeization under the conditions of identical load (mobile load is 3.5KN/m2) The economy of prestressed concrete slab structure two schemes is contrasted,
Situation is contrasted as follows after analyzing:
Hollow building cover cost: construction area * analysis unit price=4828.15 * 300.99 yuan /=1453224.87 yuan
Prestressed concrete slab cost: construction area * analysis unit price=4828.15 * 332.12 yuan /=1603525.18 Unit, saves the amount of money=1603525.18-1453224.87=150300.31 unit obvious economic.
2 secure contexts: BRT Lightweight core mould close rib composite floor plate system, reduce the deadweight of plate face, it is ensured that the peace of support system Overall coefficient.
3 technical elements: reduce floor deadweight, improve the effect such as heat-insulating property, it is adaptable to various spans and various load Building, is particularly well-suited to large span and big load, the multilamellar of large space and skyscraper.
4 mass aspects: this construction system uses closes cavity hole creating technology, it is suppressed that the transmission of floor noise up and down, gram Take the interference of upper and lower floor noise, improve heat-proof quality simultaneously.
Detailed description of the invention
Embodiment 1
The BRT Lightweight core mould construction technology that the present embodiment provides, comprises the following steps:
(1) preparation of construction
(1) slab form has been propped up and has been checked and accepted by preliminary examination, and the Vierendeel girder reinforcing bar colligation of frame structure completes;
(2) reinforcing bar and case mould riding position line are played
According to designing and arranging case figure requirement, unwrapping wire on slab form, it is ensured that the position that follow-up girt strip reinforcing bar binding and case mould are installed Accurately;According to axis, release vertically and horizontally girt strip control line, be i.e. to lay case mould position between girt strip;Unwrapping wire is at inner membrance for the second time After casing installs, in hollow box body, unwrapping wire uses whiting to replace prepared Chinese ink, and to ensure, unwrapping wire is clear firm;
(2) colligation floor floor iron and girt strip
According to the position of snap the line in template, colligation floor floor iron and case mould limit girt strip successively;First according to tying up the method for beam along floor Xia Tie lower floor muscle direction colligation floor girt strip, and lay same direction floor floor iron;Then, muscle direction, underfloor ferrum upper strata is laid Girt strip on ferrum, be inserted in rib beam hoop reinforcement one by one, after stirrup has overlapped, wear the lower ferrum of girt strip and underfloor ferrum and colligation is firm;
(3) preheating embedding line and reserved sleeve pipe are laid
Each specialty preheating embedding line in floor along girt strip and is arranged in girt strip cross section, avoids case mould position;External diameter 15mm with Under small pipe line be laid on case mould bottom, but less than one layer, must not intersect under case mould, in order to avoid padded case mould;
(4) anti-floating fixing point is set
After floor floor iron and girt strip reinforcing bar binding, anti-floating point can be started setting up;The anti-floating force path that anti-floating point is arranged It is as follows: case mould buoyancy that------rib beam hoop reinforcement or iron wire connect---floor floor iron---anti-floating point iron wire---mould to ferrum on floor Plate body system;Anti-floating point uses No. 14 iron wires, punches at floor floor iron upper strata muscle two side template with power drill (using Φ 4 drill bit), Iron wire is tightened through template in formwork keel side, by floor floor iron upper strata muscle and template fixation;Fixing point is from floor week While start to arrange to centre, spacing 1 meter in length and breadth, edge, post-cast strip also to be arranged;Rib beam hoop reinforcement to be made or drag hook hook on floor Ferrum upper strata muscle, to ensure the effective force of anti-floating point;Otherwise, should again with No. 14 iron wires by ferrum upper strata muscle on floor and lower ferrum colligation Tighten, be correspondingly arranged with lower ferrum anti-floating point, it is ensured that anti-floating effect;
(5) anti-floating of inspecting for acceptance point is arranged
After anti-floating point has set, carrying out anti-floating point special project middle inspection and check and accept, to ensure that anti-floating point arranges uniformly, position is accurate, Fixation is reliable, meets anti-floating requirement;
(6) hollow box mould bottom cushion block is installed
Cushion block is set under hollow box mould, it is ensured that the concrete thickness of case mould bottom;Pad thickness case to be met mould bottom coagulation The design thickness requirement of soil;Quantity is set, for the case mould of 700*700, only respectively arranges one piece, for 700* in case mould corner The case mould of 400, places 2 pieces, and can guarantee that case mould bottom concrete thickness is as the criterion;Because casing is subject to mixed when casting concrete The buoyancy of solidifying soil, thus the cushion block of lower box can also save need not;
(7) hollow box mould is installed
The handling of hollow box mould uses the uncovered steel reinforcement cage welded, and inside steel reinforcement cage, four limits and bottom surface multi-layer sheet are closed;Press According to cloth case figure, put successively in each girt strip space, place smooth, all around align, align;Intensive to local pipeline, The position that caliber is big, it is impossible to when placing thick case mould, the case mould of other specification can be used instead;After case mould is laid, it should be noted that finished product is protected Protect, it is to avoid personnel frequently trample, destroy;Damaged case mould, should change during ferrum in colligation in time;
(8) ferrum on colligation floor
After hollow box mould has been laid, start ferrum on colligation floor;Now, on girt strip, ferrum colligation completes, in the most remaining girt strip Between floor on ferrum;On floor, ferrum should be positioned at same layer with ferrum on girt strip, and firm with girt strip reinforcing bar binding;For ensureing anti-floating point Effective, on floor on ferrum girt strip to be pressed under ferrum, otherwise should be separately provided ferrum anti-floating point corresponding with lower ferrum anti-floating point connect;
On floor after ferrum colligation, each hollow box mould top and floor add cushion block between ferrum, pushes down case mould, and ensure Case mould top concrete thickness;
(9) ferrum cushion block is set
Upper ferrum method to set up and quantity are with bottom cushion block;
(10) erection construction sidewalk, erection concrete conveying pipe
Case calligraphy or painting model body has certain intensity, but frequently tramples and also easily cause damage, after especially adding top cushion block, and stress collection In, fragile;In construction, application scaffold board sets up built on stilts builder's road, and convenient construction operator operate, pass through, and protect Case mould and floor bar finished product;Concrete delivery pump pipe directly on floor bar, should can not set up short tube shelf or chock by frame The riding positions such as side etc. are high by pump line frame, boom answer schedule ahead good, and boom application scaffold board and shelf frame are high, must not be straight Connect and be pressed on case mould;Construction equipments etc. must not be placed on hollow box mould, and constructing operation personnel must not trample hollow box mould;
(11) concealment acceptance
After the operations such as reinforcing bar binding, case mould installation complete, tissue related personnel carry out three inspections and hidden inspect for acceptance, and emphasis is strengthened The inspection that antagonism floating-point is arranged, after acceptance(check), enters concreting operation;
(12) concrete placings
Cast-in-place concrete hollow building roof structure pours with concrete, and its slump should be more slightly larger than solid plain superstructure, desirable 18 ~ 20cm, and be the slump to cast in situs;Coarse aggregate size preferably selects less than 25mm;Case calligraphy or painting model body belongs to cement products, Should first sprinkle water before concreting moistening (winter should not sprinkle water);Concreting preferably uses pumping;Pour along floor span side To from the beginning of side, order is carried out successively, and cloth is the most uniformly, it is to avoid concrete piles up too high damage case mould at same position;Vibrate Rod vibrates along girt strip position successively along casting direction, should suitably strengthen vibrating time and a quantity of vibrating than solid superstructure, vibrate Observing hollow box mould surrounding simultaneously, until no longer there being bubble to emerge, representing that case mould lower concrete is the most closely knit;Vibrating spear should be avoided Directly touching hollow box mould;In casting process as bad in hollow box wear, it is necessary to process in time;The lightweights such as available nylon braided bag It is tight that article fill in breakage closure, fills in article and exposes case mould surface, cause concrete slag inclusion after being careful not to make;
Using special strong concrete to pour, concrete includes the composition of following parts by weight: cement 100 parts, water 150 parts, 30 parts of flyash, nemalite 31 parts, basalt fibre 24 parts, 17 parts of silicon bath soil, 14 parts of sodium chloride, cyanuric acid three Poly cyanamid 13 parts, water reducer 17 parts.
Water reducer includes the component of following parts by weight: tert-butyl acrylate 30 parts, melamine cyanurate salt 30 parts, six Polymeric sodium metaphosphate. 25 parts, 17 parts of sulfamic acid sodium.
The preparation method of described strong concrete, comprises the following steps:
(1), first cement, water, flyash, nemalite stirring are made its mix homogeneously;
(2), the water reducer stirring of basalt fibre, silicon bath soil, sodium chloride and half parts by weight is made its mix homogeneously, then Being added in the blending ingredients that step (1) obtains, stirring makes its mix homogeneously;
(3), the water reducer of melamine cyanurate and half parts by weight is added in the blending ingredients that step (2) obtains, stir Mix and make its mix homogeneously, obtain strong concrete;
(13) maintenance, form removal
The maintenance of concrete is identical with solid superstructure with form removal, uses water seasoning summer, and winter can be (thick with Polypropylence Sheet and straw screen or mat Degree is determined by thermodynamic metering) carry out covering and heat insulating maintenance;
(14) later stage processes
BRT Lightweight core mould form removal is complete, for preventing floor slab bottoms steel bar corrosion, need to be cut by 14# iron wire used by fixing core Cut, antirust treatment;Construction method is: dig iron wire root to the 1cm degree of depth in plate, is then cut by iron wire, then brush antirust paint, Floating with waterproof mortar again;
Processed by this operation, it is ensured that in floor, reinforcing bar is not because tie wire causes getting rusty, and affects project durability, from all On solve the internal steel bar corrosion problem of floor.
Winter construction: winter construction hollow box mould is deposited and preferably hidden, when laying, should there be ice and snow foreign material surface and inside, no Then must remove clean;Should not water on winter construction cast-in-situ hollow building roof case mould;Concreting covers guarantor after completing in time Replenishing vital QI with drugs of warm nature protects;Floor is hung: hangs weight on floor and should meet design requirement;Sling point selects girt strip or floor solid section as far as possible Position.

Claims (1)

1.BRT Lightweight core mould construction technology, it is characterised in that comprise the following steps:
(1) preparation of construction
(1) slab form has been propped up and has been checked and accepted by preliminary examination, and the Vierendeel girder reinforcing bar colligation of frame structure completes;
(2) reinforcing bar and case mould riding position line are played
According to designing and arranging case figure requirement, unwrapping wire on slab form, it is ensured that the position that follow-up girt strip reinforcing bar binding and case mould are installed Accurately;According to axis, release vertically and horizontally girt strip control line, be i.e. to lay case mould position between girt strip;Unwrapping wire is at inner membrance for the second time After casing installs, in hollow box body, unwrapping wire uses whiting to replace prepared Chinese ink, and to ensure, unwrapping wire is clear firm;
(2) colligation floor floor iron and girt strip
According to the position of snap the line in template, colligation floor floor iron and case mould limit girt strip successively;First according to tying up the method for beam along floor Xia Tie lower floor muscle direction colligation floor girt strip, and lay same direction floor floor iron;Then, muscle direction, underfloor ferrum upper strata is laid Girt strip on ferrum, be inserted in rib beam hoop reinforcement one by one, after stirrup has overlapped, wear the lower ferrum of girt strip and underfloor ferrum and colligation is firm;
(3) preheating embedding line and reserved sleeve pipe are laid
Each specialty preheating embedding line in floor along girt strip and is arranged in girt strip cross section, avoids case mould position;External diameter 15mm with Under small pipe line be laid on case mould bottom, but less than one layer, must not intersect under case mould, in order to avoid padded case mould;
(4) anti-floating fixing point is set
After floor floor iron and girt strip reinforcing bar binding, anti-floating point can be started setting up;The anti-floating force path that anti-floating point is arranged It is as follows: case mould buoyancy that------rib beam hoop reinforcement or iron wire connect---floor floor iron---anti-floating point iron wire---mould to ferrum on floor Plate body system;Anti-floating point uses No. 14 iron wires, punches at floor floor iron upper strata muscle two side template with power drill (using Φ 4 drill bit), Iron wire is tightened through template in formwork keel side, by floor floor iron upper strata muscle and template fixation;Fixing point is from floor week While start to arrange to centre, spacing 1 meter in length and breadth, edge, post-cast strip also to be arranged;Rib beam hoop reinforcement to be made or drag hook hook on floor Ferrum upper strata muscle, to ensure the effective force of anti-floating point;Otherwise, should again with No. 14 iron wires by ferrum upper strata muscle on floor and lower ferrum colligation Tighten, be correspondingly arranged with lower ferrum anti-floating point, it is ensured that anti-floating effect;
(5) anti-floating of inspecting for acceptance point is arranged
After anti-floating point has set, carrying out anti-floating point special project middle inspection and check and accept, to ensure that anti-floating point arranges uniformly, position is accurate, Fixation is reliable, meets anti-floating requirement;
(6) hollow box mould bottom cushion block is installed
Cushion block is set under hollow box mould, it is ensured that the concrete thickness of case mould bottom;Pad thickness case to be met mould bottom coagulation The design thickness requirement of soil;Quantity is set, for the case mould of 700*700, only respectively arranges one piece, for 700* in case mould corner The case mould of 400, places 2 pieces, and can guarantee that case mould bottom concrete thickness is as the criterion;Because casing is subject to mixed when casting concrete The buoyancy of solidifying soil, thus the cushion block of lower box can also save need not;
(7) hollow box mould is installed
The handling of hollow box mould uses the uncovered steel reinforcement cage welded, and inside steel reinforcement cage, four limits and bottom surface multi-layer sheet are closed;Press According to cloth case figure, put successively in each girt strip space, place smooth, all around align, align;Intensive to local pipeline, The position that caliber is big, it is impossible to when placing thick case mould, the case mould of other specification can be used instead;After case mould is laid, it should be noted that finished product is protected Protect, it is to avoid personnel frequently trample, destroy;Damaged case mould, should change during ferrum in colligation in time;
(8) ferrum on colligation floor
After hollow box mould has been laid, start ferrum on colligation floor;Now, on girt strip, ferrum colligation completes, in the most remaining girt strip Between floor on ferrum;On floor, ferrum should be positioned at same layer with ferrum on girt strip, and firm with girt strip reinforcing bar binding;For ensureing anti-floating point Effective, on floor on ferrum girt strip to be pressed under ferrum, otherwise should be separately provided ferrum anti-floating point corresponding with lower ferrum anti-floating point connect;
On floor after ferrum colligation, each hollow box mould top and floor add cushion block between ferrum, pushes down case mould, and ensure Case mould top concrete thickness;
(9) ferrum cushion block is set
Upper ferrum method to set up and quantity are with bottom cushion block;
(10) erection construction sidewalk, erection concrete conveying pipe
In construction, setting up built on stilts builder's road with scaffold board, convenient construction operator operate, pass through, and guard box Mo He building Slab muscle finished product;The not direct frame of concrete delivery pump pipe, on floor bar, sets up short tube shelf or chock side by pump line frame Height, boom riding position answers schedule ahead good, and boom application scaffold board and shelf frame are high, must not directly bear against on case mould; Construction equipment must not be placed on hollow box mould, and constructing operation personnel must not trample hollow box mould;
(11) concealment acceptance
After reinforcing bar binding, case mould installation procedure complete, tissue related personnel carry out three inspections and hidden inspect for acceptance, acceptance(check) After, enter concreting operation;
(12) concrete placings
Cast-in-place concrete hollow building roof structure pours uses concrete, and its slump takes 18-20cm, and is the slump to cast in situs Degree;Coarse aggregate size is less than 25mm;Case mould is first sprinkled water moistening before concreting;Concreting uses pumping;Pour Along floor span direction from the beginning of side, order is carried out successively, and cloth is uniform, it is to avoid concrete piles up too high damage case at same position Mould;Vibrating spear vibrates along girt strip position successively along casting direction, should suitably strengthen vibrating time than solid superstructure and count with vibrating Amount, vibrates and observes hollow box mould surrounding simultaneously, until no longer there being bubble to emerge, represents that case mould lower concrete is the most closely knit;Vibrate Rod should be avoided directly touching hollow box mould;In casting process as bad in hollow box wear, process in time;Fill in nylon braided bag Breakage closure is tight, fills in article and exposes case mould surface, cause concrete slag inclusion after being careful not to make;
Using special strong concrete to pour, concrete includes the composition of following parts by weight: cement 100 parts, water 100-150 part, flyash 20-30 part, nemalite 22-31 part, basalt fibre 15-24 part, silicon bath soil 9-17 part, chlorination Sodium 8-14 part, melamine cyanurate 5-13 part, water reducer 12-17 part;
Water reducer includes the component of following parts by weight: tert-butyl acrylate 25-30 part, melamine cyanurate salt 20-30 part, Sodium hexameta phosphate 15-25 part, sulfamic acid sodium 10-17 part;
(13) maintenance, form removal
The maintenance of concrete uses water seasoning summer, winter Polypropylence Sheet and straw screen or mat carry out covering and heat insulating maintenance;
(14) later stage processes
BRT Lightweight core mould form removal is complete, for preventing floor slab bottoms steel bar corrosion, need to be cut by 14# iron wire used by fixing core Cut, antirust treatment;Construction method is: dig iron wire root to the 1cm degree of depth in plate, is then cut by iron wire, then brush antirust paint, Floating with waterproof mortar again.
CN201610405622.1A 2016-06-12 2016-06-12 BRT Lightweight core mould construction technology Pending CN106088436A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610405622.1A CN106088436A (en) 2016-06-12 2016-06-12 BRT Lightweight core mould construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610405622.1A CN106088436A (en) 2016-06-12 2016-06-12 BRT Lightweight core mould construction technology

Publications (1)

Publication Number Publication Date
CN106088436A true CN106088436A (en) 2016-11-09

Family

ID=57227752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610405622.1A Pending CN106088436A (en) 2016-06-12 2016-06-12 BRT Lightweight core mould construction technology

Country Status (1)

Country Link
CN (1) CN106088436A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222350A (en) * 2017-12-28 2018-06-29 上海二十冶建设有限公司 A kind of basement cast-in-situ hollow building roof steel mesh babinet construction technology
CN108756037A (en) * 2018-06-01 2018-11-06 平煤神马建工集团有限公司 A kind of mounting structure of the whole anti-floating of GBF square chests cassette ceiling
CN110080454A (en) * 2019-05-31 2019-08-02 中联世纪建设集团有限公司 LPM light filling body Construction of Cast-in-situ Concrete Hollow
CN110258883A (en) * 2019-06-24 2019-09-20 南通大学 A kind of construction method of hollow floor BDF steel mesh film filling cabinet
CN111622407A (en) * 2020-05-28 2020-09-04 中国二十冶集团有限公司 Construction method of large-cavity hollow floor slab

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1167095A (en) * 1997-03-13 1997-12-10 湖南韶峰水泥集团有限公司 Technology for making high-quality concrete slag composite blended material
JPH10196108A (en) * 1997-01-13 1998-07-28 Kankyo Keikaku Sekkei Jimusho:Kk Concrete forming method and air mat
CN2711306Y (en) * 2004-05-21 2005-07-20 李海深 High strength and thin-wall inner pipe used for on-site depositing steel-bar reinforced concrete
CN201202197Y (en) * 2008-04-22 2009-03-04 刘国友 Filling pipe
CN104030642A (en) * 2014-06-30 2014-09-10 湖南省建筑工程集团总公司 Fiber concrete

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10196108A (en) * 1997-01-13 1998-07-28 Kankyo Keikaku Sekkei Jimusho:Kk Concrete forming method and air mat
CN1167095A (en) * 1997-03-13 1997-12-10 湖南韶峰水泥集团有限公司 Technology for making high-quality concrete slag composite blended material
CN2711306Y (en) * 2004-05-21 2005-07-20 李海深 High strength and thin-wall inner pipe used for on-site depositing steel-bar reinforced concrete
CN201202197Y (en) * 2008-04-22 2009-03-04 刘国友 Filling pipe
CN104030642A (en) * 2014-06-30 2014-09-10 湖南省建筑工程集团总公司 Fiber concrete

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李春锦: "现浇钢筋混凝土空心楼板施工与应用", 《中国期刊在线》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222350A (en) * 2017-12-28 2018-06-29 上海二十冶建设有限公司 A kind of basement cast-in-situ hollow building roof steel mesh babinet construction technology
CN108756037A (en) * 2018-06-01 2018-11-06 平煤神马建工集团有限公司 A kind of mounting structure of the whole anti-floating of GBF square chests cassette ceiling
CN110080454A (en) * 2019-05-31 2019-08-02 中联世纪建设集团有限公司 LPM light filling body Construction of Cast-in-situ Concrete Hollow
CN110258883A (en) * 2019-06-24 2019-09-20 南通大学 A kind of construction method of hollow floor BDF steel mesh film filling cabinet
CN111622407A (en) * 2020-05-28 2020-09-04 中国二十冶集团有限公司 Construction method of large-cavity hollow floor slab

Similar Documents

Publication Publication Date Title
CN106088436A (en) BRT Lightweight core mould construction technology
CN101852031B (en) Construction method of soil covering tank
CN101319525A (en) Externally reinforced concrete irrigated and heat preservation wall structure embedded energy-saving system and its construction method
CN108412125A (en) A kind of strengthening concrete composite structure frame beam column construction
CN109811878A (en) The shell integrated structure of the cast-in-place coinsiding die of assembled architecture and construction method
CN110258848A (en) A kind of construction method of building energy conservation CL composite shear wall
CN105780976B (en) Compound concrete shear wall structure and its concreting method
CN109706846B (en) High and narrow bridge capping beam through steel bar construction method for slope foundation
CN104863063B (en) Cofferdam method for rapidly reinforcing is exempted from based on the bridge submerged structure of PVC composite shuttering
CN106088147A (en) Wallboard mixes prefabricated assembled pipe gallery and construction method thereof on an empty stomach
CN108330835A (en) The construction method of setting bracket
CN103615053A (en) Construction method for post-cast belt of cast-in-place reinforced concrete structure
CN107574762A (en) A kind of construction method for strengthening Cast-in-situ Beam 0# block construction qualities
CN205444887U (en) Slope roofing template system
CN103806659B (en) Super thick prestressing force change-over panel individual layer comprehensively supports and splits temperature control construction technology with control
CN109537895A (en) A kind of cast-in-place core wall structure slab column installation method of prefabricated integral frame
CN109235891A (en) A kind of Large Span Prestressed Beam concrete pitched roof jump storehouse method construction method
CN205576955U (en) Raft foundation's reinforced structure is displaced into to strip footing
CN106760050A (en) The attachment structure and through processing method of shear wall and after-pouring concrete frame beam
CN106088459B (en) A kind of prefabricated assembled composite heat preserving external wall wall and preparation method thereof, design method and the steel building comprising the wall
CN107143141A (en) External wall of high-rise building warming plate construction
CN107299773B (en) Load bearing wall reinforcing construction method
CN110080454A (en) LPM light filling body Construction of Cast-in-situ Concrete Hollow
CN107905609A (en) Underground people's air defense construction method
CN105089182B (en) A kind of concrete partition system and its construction method for steel construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161109

RJ01 Rejection of invention patent application after publication