CN108732979A - A kind of construction safety managing and control system based on BIM technology - Google Patents
A kind of construction safety managing and control system based on BIM technology Download PDFInfo
- Publication number
- CN108732979A CN108732979A CN201810464264.0A CN201810464264A CN108732979A CN 108732979 A CN108732979 A CN 108732979A CN 201810464264 A CN201810464264 A CN 201810464264A CN 108732979 A CN108732979 A CN 108732979A
- Authority
- CN
- China
- Prior art keywords
- construction
- bim
- database
- personnel
- data
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05B—CONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
- G05B19/00—Programme-control systems
- G05B19/02—Programme-control systems electric
- G05B19/04—Programme control other than numerical control, i.e. in sequence controllers or logic controllers
- G05B19/048—Monitoring; Safety
Landscapes
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Engineering & Computer Science (AREA)
- Automation & Control Theory (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of construction safety managing and control system based on BIM technology, applied to the security management and control of construction project construction period, which includes background processing system, infrared inductor, warning device, sensor, electronic direction board, display terminal and transport services device;Electronic direction board is positioned over the danger zone of construction site, for showing current region risk situation;Infrared inductor is positioned over the danger zone that construction site forbids personnel to come in and go out, for detecting whether having personnel are violating the regulations to enter danger zone;Sensor arrangement is in construction site accident prone location and key structure position, the environmental data for monitoring the position and malformation data;Compared to traditional construction site security management and control, present system is based on BIM technology, it is transmitted in zone location and information more accurate and quick, while construction area is digitized supervision, real-time early warning is carried out to site operation personnel and monitoring personnel so that Safety Management is more concise effective.
Description
Technical field
The invention belongs to construction site management and control fields, and in particular to arrive a kind of construction safety management and control system based on BIM technology
System carries out more effective, more accurate safety management by BIM technology to scene.
Background technology
With scientific and technological progress and management standardization, large-scale construction engineering is constantly to function complexity, technological innovation, multi-party collaboration
The direction of work is developed, on the links of engineering construction also with greater need for it is efficient with it is accurate.Construction safety is always to build row
Important Problems in industry, the safety accident to take place frequently cause a large amount of unnecessary casualties and property loss.Traditional building peace
The problems such as there are still supervision absent-mindedness, dangerous warnings for full management aspect not in time, positioning is inaccurate.
Building Information Model BIM (Building Information Modeling) is the items with construction-engineering project
Basis of the relevant information data as model, carries out the foundation of buildings model, is had by digital information analogue simulation building
Some real informations.Have the characteristics that visualization, harmony, simulation, optimization property and can to go out figure five big.BIM technology is being constructed
Crucial application in safety management is field condition and manages the real-time connection of user, maximum by the quick transmission of information
It eliminates safe hidden trouble to degree, realizes " people-oriented " of construction link.
Invention content
In view of the above-mentioned deficiencies in the prior art, it is an object of the present invention to provide a kind of construction safety management and control based on BIM technology
System plays effective safety precaution by the accurate management and control to live key position and danger zone.
The technical solution adopted by the present invention is as follows:A kind of construction safety managing and control system based on BIM technology is applied to building
Security management and control during project construction, the system include background processing system, infrared inductor, warning device, sensor, electricity
Sub- direction board, display terminal and transport services device;
The electronic direction board is positioned over the danger zone of construction site, including electronic display and positioning device, electronics
Display screen is used to show the risk situation of current region, and positioning device is by depositing in the coordinate position and database of electronic direction board
The BIM models of storage link;
The infrared inductor is positioned over the danger zone that construction site forbids personnel to come in and go out, and is connected with alarm,
Coordinate position is linked with the BIM models stored in database, for detecting whether having personnel are violating the regulations to enter danger zone;When infrared
Sensing device detected personnel close to when, send out alarm signal to analysis processor, while triggering alarm and sending out alarm, it is alert
Show site operation personnel;
The sensor arrangement is connected in construction site accident prone location and key structure position with alarm, sits
Cursor position is linked with the BIM models stored in database, the environmental data for monitoring the position and malformation data;
The infrared inductor, sensor and electronic direction board connect background process system by transport services device
System;
The background processing system is for construction site situation and manages the information real-time delivery between user, including data
Library and analysis processor:
The database, the BIM models for storing construction project Life cycle can be carried out according to Practical Project progress
BIM models are transferred and are updated;
The analysis processor receives the monitoring data of the sensor of construction site, and format conversion is carried out to monitoring data
Processing in storage to database, and synchronizes update to the data of corresponding position on BIM models, by monitoring data and in advance
The threshold value of setting carries out comparison judgement, when a threshold is exceeded, is determined as the situation of causing danger, and background processing system is quickly fixed at this time
Position location of accident, is marked on display terminal by BIM models, while triggering alarm and sending out alarm, warning scene is applied
Worker person;Analysis processor receives the alarm signal that infrared inductor is sent out, and will be alarmed by BIM models on display terminal
Infrared inductor be marked;Analysis processor is drawn again according to the newest detection data of the sensor stored in database
Divide danger zone and grade, and change content is sent to the electronic direction board of corresponding position;
The display terminal, for showing BIM models, and when causing danger situation, on BIM models label handle affairs therefore
Position.
Further, the environmental data of the sensor acquisition includes temperature, humidity, and the malformation data of acquisition include
Settlement of foundation, the stress of component, the displacement of component and amount of deflection.
Further, the display content sources in the electronic display are in the database of background processing system:In correlation
After department completes danger source investigation, detailed Danger source inventory is obtained, and by the region division of each danger source, dangerous class
Not, risk rating, workaround data are stored in database in case calling;If the information in database has change, electronical display
Content on screen will synchronize change.
Further, the infrared inductor, sensor will send location information, backstage to background processing system simultaneously
Processing system links quick localized accident position according to BIM models, and by accident information be sent to management user mobile phone or its
His mobile device, accident situation is quickly grasped to help all affected members, takes counter-measure.
Further, the background processing system automatically generates the optimal processing path of dangerous situation, is sent to relevant people
Member marks optimal path by BIM models on display terminal, while carrying out data record and storage to whole process.
The beneficial effects of the invention are as follows:Compared to traditional construction safety management system, the present invention is based on the constructions of BIM technology
Security management and control system organically contacts construction site and back-stage management together, realizes the real-time delivery of information, on the one hand
More effective warning function can be played to Field Force, on the one hand can be made when change occurs for information data or accident occurs
Go out series reaction to solve the problems, such as.Meanwhile live electronic direction board and infrared inductor, database, background process system
Moment holding synchronizing information of uniting updates, and improves the accuracy and validity of security management and control, and the present invention has intelligent, number
The huge advantages such as change, systematization, real time implementation, can reduce the safe blind area of construction site, shorten and are arranged from discovery accident to taking
The reaction time applied, the efficiency of significant increase Safety Management.
Description of the drawings
Fig. 1 is the system framework schematic diagram of the present invention;
Fig. 2 is the infrared inductor and working sensor general flow chart of the present invention;
Fig. 3 is the electronic direction board workflow schematic diagram of the present invention.
Specific implementation mode
The invention will be further described in the following with reference to the drawings and specific embodiments.
As shown in Figs. 1-3, a kind of construction safety managing and control system based on BIM technology provided by the invention is applied to building
Security management and control during project construction, the system include background processing system, infrared inductor, warning device, sensor, electricity
Sub- direction board, display terminal and transport services device;The present invention passes through background processing system using BIM models as Information base
With transport services device, the information real-time delivery between field condition, construction personnel and management user three is realized;
The electronic direction board is positioned over the danger zone of construction site, including electronic display and positioning device, electronics
Display screen is used to show the risk situation of current region, and positioning device is by depositing in the coordinate position and database of electronic direction board
The BIM models of storage link;
The infrared inductor is positioned over the danger zone that construction site forbids personnel to come in and go out, and is connected with alarm,
Coordinate position is linked with the BIM models stored in database, for detecting whether having personnel are violating the regulations to enter danger zone;When infrared
Sensing device detected personnel close to when, send out alarm signal to analysis processor, while triggering alarm and sending out alarm, it is alert
Show site operation personnel;
The sensor arrangement is connected in construction site accident prone location and key structure position with alarm, sits
Cursor position is linked with the BIM models stored in database, the environmental data for monitoring the position and malformation data;
The infrared inductor, sensor and electronic direction board connect background process system by transport services device
System;
The background processing system is for construction site situation and manages the information real-time delivery between user, including data
Library and analysis processor:
The database, the BIM models for storing construction project Life cycle can be carried out according to Practical Project progress
BIM models are transferred and are updated;
The analysis processor receives the monitoring data of the sensor of construction site, and format conversion is carried out to monitoring data
Processing in storage to database, and synchronizes update to the data of corresponding position on BIM models, by monitoring data and in advance
The threshold value of setting carries out comparison judgement, when a threshold is exceeded, is determined as the situation of causing danger, and background processing system is quickly fixed at this time
Position location of accident, is marked on display terminal by BIM models, while triggering alarm and sending out alarm, warning scene is applied
Worker person;Analysis processor receives the alarm signal that infrared inductor is sent out, and will be alarmed by BIM models on display terminal
Infrared inductor be marked;Analysis processor is drawn again according to the newest detection data of the sensor stored in database
Divide danger zone and grade, and change content is sent to the electronic direction board of corresponding position;
The display terminal, for showing BIM models, and when causing danger situation, on BIM models label handle affairs therefore
Position.
Further, the environmental data of the sensor acquisition includes temperature, humidity, and the malformation data of acquisition include
Settlement of foundation, the stress of component, the displacement of component and amount of deflection.
Further, the display content sources in the electronic display are in the database of background processing system:In correlation
After department completes danger source investigation, detailed Danger source inventory is obtained, and by the region division of each danger source, dangerous class
Not, risk rating, workaround data are stored in database in case calling;If the information in database has change, electronical display
Content on screen will synchronize change, and personnel can be made to have sufficient preparation before entering danger zone.
Further, the infrared inductor, sensor will send location information, backstage to background processing system simultaneously
Processing system links quick localized accident position according to BIM models, and by accident information be sent to management user mobile phone or its
His mobile device, accident situation is quickly grasped to help all affected members, takes counter-measure.
Further, the background processing system automatically generates the optimal processing path of dangerous situation, is sent to relevant people
Member marks optimal path by BIM models on display terminal, while carrying out data record and storage to whole process.
Claims (5)
1. a kind of construction safety managing and control system based on BIM technology is applied to the security management and control of construction project construction period, special
Sign is that the system includes background processing system, infrared inductor, warning device, sensor, electronic direction board, shows eventually
End and transport services device;
The electronic direction board is positioned over the danger zone of construction site, including electronic display and positioning device, electronical display
Shield risk situation for showing current region, positioning device is by the storage in the coordinate position and database of electronic direction board
BIM models link;
The infrared inductor is positioned over the danger zone that construction site forbids personnel to come in and go out, and is connected with alarm, coordinate
Position is linked with the BIM models stored in database, for detecting whether having personnel are violating the regulations to enter danger zone;Work as infrared induction
Device detected personnel close to when, send out alarm signal to analysis processor, while triggering alarm and sending out alarm, warning is existing
Field construction personnel;
The sensor arrangement is connected in construction site accident prone location and key structure position with alarm, coordinate bit
It sets and is linked with the BIM models stored in database, the environmental data for monitoring the position and malformation data;
The infrared inductor, sensor and electronic direction board connect background processing system by transport services device;
The background processing system for construction site situation and manage user between information real-time delivery, including database with
Analysis processor:
The database, the BIM models for storing construction project Life cycle can carry out BIM according to Practical Project progress
Model is transferred and is updated;
The analysis processor receives the monitoring data of the sensor of construction site, and format conversion processing is carried out to monitoring data,
Store in database, and update synchronized to the data of corresponding position on BIM models, by monitoring data with it is preset
Threshold value carries out comparison judgement, when a threshold is exceeded, is determined as the situation of causing danger, at this time the quick localized accident of background processing system
Position is marked on display terminal by BIM models, while being triggered alarm and being sent out alarm, and site operation personnel are warned;
Analysis processor receives the alarm signal that sends out of infrared inductor, by BIM models by the infrared of alarm on display terminal
Sensing device is marked;Analysis processor repartitions danger according to the newest detection data of the sensor stored in database
Region and grade, and it is sent to the electronic direction board of corresponding position by content is changed;
The display terminal, for showing BIM models, and when causing danger situation, on BIM models label handle affairs thus position
It sets.
2. a kind of construction safety managing and control system based on BIM technology according to claim 1, which is characterized in that the biography
The environmental data of sensor acquisition includes temperature, humidity, and the malformation data of acquisition include settlement of foundation, the stress of component, structure
The displacement of part and amount of deflection.
3. a kind of construction safety managing and control system based on BIM technology according to claim 1, which is characterized in that the electricity
Display content sources on sub- display screen are in the database of background processing system:After relevant departments complete danger source investigation, obtain
To detailed Danger source inventory, and by the region division of each danger source, the class of risk, risk rating, workaround data
It is stored in database in case calling;If the information in database has change, the content in electronic display will synchronize change.
4. a kind of construction safety managing and control system based on BIM technology according to claim 1, which is characterized in that described red
Outer sensing device, sensor will send location information to background processing system simultaneously, and background processing system is linked according to BIM models
Quick localized accident position, and accident information is sent to the mobile phone or other mobile devices for managing user, to help all phases
Pass personnel quickly grasp accident situation, take counter-measure.
5. a kind of construction safety managing and control system based on BIM technology according to claim 1, which is characterized in that after described
Platform processing system automatically generates the optimal processing path of dangerous situation, is sent to related personnel, passes through BIM moulds on display terminal
Phenotypic marker goes out optimal path, while carrying out data record and storage to whole process.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810464264.0A CN108732979A (en) | 2018-05-15 | 2018-05-15 | A kind of construction safety managing and control system based on BIM technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810464264.0A CN108732979A (en) | 2018-05-15 | 2018-05-15 | A kind of construction safety managing and control system based on BIM technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108732979A true CN108732979A (en) | 2018-11-02 |
Family
ID=63938245
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810464264.0A Pending CN108732979A (en) | 2018-05-15 | 2018-05-15 | A kind of construction safety managing and control system based on BIM technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108732979A (en) |
Cited By (25)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109409776A (en) * | 2018-11-15 | 2019-03-01 | 中铁第六勘察设计院集团有限公司 | A kind of security risk three dimensional constitution reports and submits method |
CN109583772A (en) * | 2018-12-04 | 2019-04-05 | 上海宝冶集团有限公司 | Method for managing and monitoring, device, system and the readable storage medium storing program for executing of construction site |
CN109767605A (en) * | 2019-02-26 | 2019-05-17 | 安徽虹桥交通建设监理有限公司 | A kind of engineering safety accident monitor system |
CN109858829A (en) * | 2019-02-22 | 2019-06-07 | 赛飞特工程技术集团有限公司 | Hidden danger accident early warning method based on block chain |
CN109914798A (en) * | 2019-03-11 | 2019-06-21 | 福建工程学院 | A kind of intelligent concrete, which pours, sets template method for managing security |
CN110021142A (en) * | 2019-04-22 | 2019-07-16 | 国网江苏省电力有限公司南通供电分公司 | A kind of protection of intelligent substation and control safety on line operating analysis system |
CN110264070A (en) * | 2019-06-19 | 2019-09-20 | 徐州工业职业技术学院 | A kind of quality detecting system based on BIM |
CN110335173A (en) * | 2019-07-06 | 2019-10-15 | 中铁二十五局集团第五工程有限公司 | Based on BIM construction management platform and comprehensive monitoring system |
CN110472858A (en) * | 2019-08-10 | 2019-11-19 | 浙江同洲项目管理有限公司 | A kind of Project Supervision approaches to IM |
WO2020023869A1 (en) * | 2018-07-27 | 2020-01-30 | The Joan and Irwin Jacobs Technion-Cornell Institute | Techniques for identifying hazardous site conditions in geo-localized enhanced floor plans |
CN110750885A (en) * | 2019-10-08 | 2020-02-04 | 上海建工五建集团有限公司 | On-site fire safety monitoring method and system |
CN110813977A (en) * | 2019-09-25 | 2020-02-21 | 浙江天之元物流科技有限公司 | On-site recycling and retreatment process for bottom materials |
CN110991282A (en) * | 2019-11-21 | 2020-04-10 | 深圳市赛为智能股份有限公司 | Construction safety management method and device based on unmanned aerial vehicle and computer equipment |
CN111144776A (en) * | 2019-12-30 | 2020-05-12 | 广州途威慧信息科技有限公司 | Construction safety supervisory systems based on BIM model |
CN111274635A (en) * | 2020-01-19 | 2020-06-12 | 深圳云联万企科技有限公司 | Construction safety management system and method based on building information model |
CN111650863A (en) * | 2020-06-09 | 2020-09-11 | 湖南城市学院 | Engineering safety monitoring instrument and monitoring method |
CN112053272A (en) * | 2020-08-19 | 2020-12-08 | 中国一冶集团有限公司 | Civil air defense basement wartime system based on BIM and use method thereof |
CN112257138A (en) * | 2020-09-05 | 2021-01-22 | 赛飞特工程技术集团有限公司 | Remote safety inquiry method, system, intelligent terminal and storage medium |
CN112685812A (en) * | 2020-12-16 | 2021-04-20 | 中冶建筑研究总院有限公司 | Dynamic supervision method, device, equipment and storage medium |
US11010966B2 (en) | 2017-12-14 | 2021-05-18 | The Joan and Irwin Jacobs Technion-Cornell Institute | System and method for creating geo-localized enhanced floor plans |
CN112863119A (en) * | 2020-12-31 | 2021-05-28 | 中铁建设集团基础设施建设有限公司 | Engineering construction safety risk early warning system and method |
US11127129B2 (en) | 2017-12-14 | 2021-09-21 | The Joan and Irwin Jacobs Technion-Cornell Institute | Techniques for identifying hazardous site conditions in geo-localized enhanced floor plans |
CN113777658A (en) * | 2021-08-06 | 2021-12-10 | 上海建工一建集团有限公司 | BIM technology-based construction site temporary opening monitoring method |
CN114266678A (en) * | 2021-11-30 | 2022-04-01 | 国网上海市电力公司 | Control platform for defining space area of construction site |
CN118114956A (en) * | 2024-04-30 | 2024-05-31 | 江铃汽车集团江西工程建设有限公司 | Building construction management method and system based on BIM |
Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203325362U (en) * | 2013-07-17 | 2013-12-04 | 曹志云 | Electronic type safety sign convenient to manage |
CN105631979A (en) * | 2014-10-27 | 2016-06-01 | 哈尔滨隆艺科技开发有限公司 | Method for safety management of mine construction by using electronic information |
CN205564242U (en) * | 2016-04-15 | 2016-09-07 | 深圳市建安(集团)股份有限公司 | Building site electron publicity board |
CN106228474A (en) * | 2016-09-09 | 2016-12-14 | 华中科技大学 | A kind of construction safety managing and control system based on three-dimensional localization and BIM and method |
CN106372854A (en) * | 2016-08-30 | 2017-02-01 | 中建三局第建设工程有限责任公司 | Project safety management system based on BIM |
CN106383463A (en) * | 2016-09-06 | 2017-02-08 | 华中科技大学 | Construction environmental monitoring system and method based on safety helmet |
CN106595565A (en) * | 2017-01-17 | 2017-04-26 | 中山大学 | BIM-based intelligent monitoring system |
CN106980705A (en) * | 2017-02-22 | 2017-07-25 | 中国建筑第八工程局有限公司 | Safety protection standard construction method based on BIM technology |
CN107255981A (en) * | 2017-06-14 | 2017-10-17 | 成都智建新业建筑设计咨询有限公司 | A kind of super high rise building transport of materials management system based on BIM |
CN107879260A (en) * | 2017-10-11 | 2018-04-06 | 武汉科技大学 | Tower crane collision avoidance system and safety-protection system based on BIM |
CN107927979A (en) * | 2017-11-29 | 2018-04-20 | 湖南大学 | A kind of safety cap based on BIM model safety early warning systems |
CN107993389A (en) * | 2017-11-29 | 2018-05-04 | 湖南大学 | A kind of construction site safe early warning method and system based on BIM models |
CN108019093A (en) * | 2017-11-30 | 2018-05-11 | 国家电网公司 | A kind of safe fence with electronic display |
-
2018
- 2018-05-15 CN CN201810464264.0A patent/CN108732979A/en active Pending
Patent Citations (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203325362U (en) * | 2013-07-17 | 2013-12-04 | 曹志云 | Electronic type safety sign convenient to manage |
CN105631979A (en) * | 2014-10-27 | 2016-06-01 | 哈尔滨隆艺科技开发有限公司 | Method for safety management of mine construction by using electronic information |
CN205564242U (en) * | 2016-04-15 | 2016-09-07 | 深圳市建安(集团)股份有限公司 | Building site electron publicity board |
CN106372854A (en) * | 2016-08-30 | 2017-02-01 | 中建三局第建设工程有限责任公司 | Project safety management system based on BIM |
CN106383463A (en) * | 2016-09-06 | 2017-02-08 | 华中科技大学 | Construction environmental monitoring system and method based on safety helmet |
CN106228474A (en) * | 2016-09-09 | 2016-12-14 | 华中科技大学 | A kind of construction safety managing and control system based on three-dimensional localization and BIM and method |
CN106595565A (en) * | 2017-01-17 | 2017-04-26 | 中山大学 | BIM-based intelligent monitoring system |
CN106980705A (en) * | 2017-02-22 | 2017-07-25 | 中国建筑第八工程局有限公司 | Safety protection standard construction method based on BIM technology |
CN107255981A (en) * | 2017-06-14 | 2017-10-17 | 成都智建新业建筑设计咨询有限公司 | A kind of super high rise building transport of materials management system based on BIM |
CN107879260A (en) * | 2017-10-11 | 2018-04-06 | 武汉科技大学 | Tower crane collision avoidance system and safety-protection system based on BIM |
CN107927979A (en) * | 2017-11-29 | 2018-04-20 | 湖南大学 | A kind of safety cap based on BIM model safety early warning systems |
CN107993389A (en) * | 2017-11-29 | 2018-05-04 | 湖南大学 | A kind of construction site safe early warning method and system based on BIM models |
CN108019093A (en) * | 2017-11-30 | 2018-05-11 | 国家电网公司 | A kind of safe fence with electronic display |
Cited By (29)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11010966B2 (en) | 2017-12-14 | 2021-05-18 | The Joan and Irwin Jacobs Technion-Cornell Institute | System and method for creating geo-localized enhanced floor plans |
US11127129B2 (en) | 2017-12-14 | 2021-09-21 | The Joan and Irwin Jacobs Technion-Cornell Institute | Techniques for identifying hazardous site conditions in geo-localized enhanced floor plans |
WO2020023869A1 (en) * | 2018-07-27 | 2020-01-30 | The Joan and Irwin Jacobs Technion-Cornell Institute | Techniques for identifying hazardous site conditions in geo-localized enhanced floor plans |
CN109409776A (en) * | 2018-11-15 | 2019-03-01 | 中铁第六勘察设计院集团有限公司 | A kind of security risk three dimensional constitution reports and submits method |
CN109583772A (en) * | 2018-12-04 | 2019-04-05 | 上海宝冶集团有限公司 | Method for managing and monitoring, device, system and the readable storage medium storing program for executing of construction site |
CN109858829A (en) * | 2019-02-22 | 2019-06-07 | 赛飞特工程技术集团有限公司 | Hidden danger accident early warning method based on block chain |
CN109767605A (en) * | 2019-02-26 | 2019-05-17 | 安徽虹桥交通建设监理有限公司 | A kind of engineering safety accident monitor system |
CN109914798A (en) * | 2019-03-11 | 2019-06-21 | 福建工程学院 | A kind of intelligent concrete, which pours, sets template method for managing security |
CN110021142A (en) * | 2019-04-22 | 2019-07-16 | 国网江苏省电力有限公司南通供电分公司 | A kind of protection of intelligent substation and control safety on line operating analysis system |
CN110264070A (en) * | 2019-06-19 | 2019-09-20 | 徐州工业职业技术学院 | A kind of quality detecting system based on BIM |
CN110335173A (en) * | 2019-07-06 | 2019-10-15 | 中铁二十五局集团第五工程有限公司 | Based on BIM construction management platform and comprehensive monitoring system |
CN110472858A (en) * | 2019-08-10 | 2019-11-19 | 浙江同洲项目管理有限公司 | A kind of Project Supervision approaches to IM |
CN110813977A (en) * | 2019-09-25 | 2020-02-21 | 浙江天之元物流科技有限公司 | On-site recycling and retreatment process for bottom materials |
CN110813977B (en) * | 2019-09-25 | 2021-10-08 | 浙江天之元物流科技有限公司 | On-site recycling and retreatment process for bottom materials |
CN110750885A (en) * | 2019-10-08 | 2020-02-04 | 上海建工五建集团有限公司 | On-site fire safety monitoring method and system |
CN110991282A (en) * | 2019-11-21 | 2020-04-10 | 深圳市赛为智能股份有限公司 | Construction safety management method and device based on unmanned aerial vehicle and computer equipment |
CN111144776A (en) * | 2019-12-30 | 2020-05-12 | 广州途威慧信息科技有限公司 | Construction safety supervisory systems based on BIM model |
CN111274635A (en) * | 2020-01-19 | 2020-06-12 | 深圳云联万企科技有限公司 | Construction safety management system and method based on building information model |
CN111650863A (en) * | 2020-06-09 | 2020-09-11 | 湖南城市学院 | Engineering safety monitoring instrument and monitoring method |
CN111650863B (en) * | 2020-06-09 | 2022-07-08 | 湖南城市学院 | Engineering safety monitoring instrument and monitoring method |
CN112053272A (en) * | 2020-08-19 | 2020-12-08 | 中国一冶集团有限公司 | Civil air defense basement wartime system based on BIM and use method thereof |
CN112257138A (en) * | 2020-09-05 | 2021-01-22 | 赛飞特工程技术集团有限公司 | Remote safety inquiry method, system, intelligent terminal and storage medium |
CN112257138B (en) * | 2020-09-05 | 2023-03-21 | 赛飞特工程技术集团有限公司 | Remote safety inquiry method, system, intelligent terminal and storage medium |
CN112685812A (en) * | 2020-12-16 | 2021-04-20 | 中冶建筑研究总院有限公司 | Dynamic supervision method, device, equipment and storage medium |
CN112863119A (en) * | 2020-12-31 | 2021-05-28 | 中铁建设集团基础设施建设有限公司 | Engineering construction safety risk early warning system and method |
CN113777658A (en) * | 2021-08-06 | 2021-12-10 | 上海建工一建集团有限公司 | BIM technology-based construction site temporary opening monitoring method |
CN113777658B (en) * | 2021-08-06 | 2023-11-28 | 上海建工一建集团有限公司 | BIM technology-based method for monitoring temporary tunnel portal in construction site |
CN114266678A (en) * | 2021-11-30 | 2022-04-01 | 国网上海市电力公司 | Control platform for defining space area of construction site |
CN118114956A (en) * | 2024-04-30 | 2024-05-31 | 江铃汽车集团江西工程建设有限公司 | Building construction management method and system based on BIM |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108732979A (en) | A kind of construction safety managing and control system based on BIM technology | |
CN108830462A (en) | A kind of pipe gallery wisdom operation management platform and method | |
CN107369006B (en) | Community fire fighting dynamic management and control system and management and control method | |
CN109375594A (en) | Urban safety wisdom control platform and managing and control system | |
CN110135682A (en) | Danger large construction project monitoring management method based on BIM technology | |
CN105913600A (en) | High-rise intelligent fire alarm system | |
CN107240164A (en) | The data processing of security cruising inspection system and device | |
CN104637260A (en) | Method and device for realizing regional monitoring alarm and server | |
CN107239868A (en) | End message processing method and processing device for security cruising inspection system | |
CN108182738A (en) | A kind of Urban Underground pipe gallery method for inspecting based on WI-FI positioning | |
CN108154663A (en) | A kind of safety detection early warning system | |
CN102982654A (en) | Portable intelligent elder care instrument | |
US20140210671A1 (en) | Computerized Device for Object Locating System and Method Thereof | |
CN109005386A (en) | Community Watch method, device and equipment based on image analysis | |
CN107657390A (en) | A kind of special safety equipment hidden danger management and control big data monitoring system and monitoring method | |
CN105424711A (en) | Automatic test equipment and method for screw looseness of locomotive | |
JP2006059185A (en) | Data management system and method | |
CN111126751A (en) | Intelligent inspection and safety monitoring early warning system and method based on mobile interconnection | |
CN204374643U (en) | Zigbee wireless sensor Intelligent home monitoring system and Zigbee wireless speech Acoustic control remote controller | |
CN116976832A (en) | Intelligent fire-fighting centralized unified supervision platform based on AI, big data and Internet of things | |
CN108986881A (en) | A kind of medication alert system based on robot | |
CN112666911A (en) | Cooperative control system | |
CN112367620A (en) | Outgoing escort edge early warning visualization system, method and medium | |
KR20100074445A (en) | System reponding to emergency | |
CN111050119A (en) | Information fact transmission system for hospital department patients |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181102 |