CN106372854A - Project safety management system based on BIM - Google Patents
Project safety management system based on BIM Download PDFInfo
- Publication number
- CN106372854A CN106372854A CN201610779336.1A CN201610779336A CN106372854A CN 106372854 A CN106372854 A CN 106372854A CN 201610779336 A CN201610779336 A CN 201610779336A CN 106372854 A CN106372854 A CN 106372854A
- Authority
- CN
- China
- Prior art keywords
- project
- management
- module
- personnel
- safety helmet
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 claims abstract description 14
- 238000012544 monitoring process Methods 0.000 claims abstract description 14
- 238000001514 detection method Methods 0.000 claims abstract description 10
- 238000000034 method Methods 0.000 claims abstract description 6
- 238000004891 communication Methods 0.000 claims abstract description 5
- 230000008569 process Effects 0.000 claims abstract description 5
- 230000036541 health Effects 0.000 claims abstract description 4
- 238000007689 inspection Methods 0.000 claims description 13
- 230000000007 visual effect Effects 0.000 claims description 6
- 238000009825 accumulation Methods 0.000 claims description 3
- 238000011010 flushing procedure Methods 0.000 claims description 3
- 230000003862 health status Effects 0.000 claims description 3
- 230000010354 integration Effects 0.000 claims description 3
- 238000011835 investigation Methods 0.000 claims description 3
- 230000033764 rhythmic process Effects 0.000 claims description 3
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- G—PHYSICS
- G08—SIGNALLING
- G08B—SIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
- G08B21/00—Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
- G08B21/02—Alarms for ensuring the safety of persons
-
- G—PHYSICS
- G08—SIGNALLING
- G08B—SIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
- G08B21/00—Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
- G08B21/02—Alarms for ensuring the safety of persons
- G08B21/04—Alarms for ensuring the safety of persons responsive to non-activity, e.g. of elderly persons
- G08B21/0438—Sensor means for detecting
- G08B21/0453—Sensor means for detecting worn on the body to detect health condition by physiological monitoring, e.g. electrocardiogram, temperature, breathing
Landscapes
- Business, Economics & Management (AREA)
- Strategic Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Tourism & Hospitality (AREA)
- Entrepreneurship & Innovation (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Emergency Management (AREA)
- Theoretical Computer Science (AREA)
- Economics (AREA)
- Life Sciences & Earth Sciences (AREA)
- Cardiology (AREA)
- Heart & Thoracic Surgery (AREA)
- Physical Education & Sports Medicine (AREA)
- Physiology (AREA)
- Pulmonology (AREA)
- Gerontology & Geriatric Medicine (AREA)
- Biophysics (AREA)
- Data Mining & Analysis (AREA)
- Primary Health Care (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Alarm Systems (AREA)
- Emergency Alarm Devices (AREA)
Abstract
The present invention discloses a project safety management system based on BIM. The system comprises: an orientation voice disclosure management module, a quality information collection and quality acceptance module, a safety early warning and construction recording module, a personnel health state detection module, a field staff trend monitoring module and a field mechanical equipment monitoring module. The project safety management system based on the BIM improves the project quality safety management efficiency, improves the communication efficiency, improves the safety management timeliness and ensures the overall process traceability of the quality management.
Description
Technical field
The present invention relates to project management techniques, more particularly, to a kind of project security management system based on bim.
Background technology
Currently, construction projects are numerous, and during project construction, personnel's machinery is complicated, and management difficulty is big, and project
Field Force's peopleware and safety consciousness are uneven, go wrong unavoidably in project management process, in project management
During, due to mainly being signed a bill by papery in project management, site inspection and various regular meeting carrying out project management, totally
For the efficiency of management low, information transmission exists and postpones and omit, and relevant information has the interference of a large amount of anthropic factors,
On project management impact greatly.
Content of the invention
The technical problem to be solved in the present invention is for defect of the prior art, provides a kind of project based on bim
Safety management system.
The technical solution adopted for the present invention to solve the technical problems is: a kind of project security management system based on bim,
Including safety helmet, button of taking pictures that described safety helmet includes being arranged on safety helmet, photographic head, rhythm of the heart chip, raise one's voice
Device, positioning chip and wifi module;
It is characterized in that, comprising:
Management system, for the meta-synthetic management of the information data of each module in project security management system;
Orientation voice is told somebody what one's real intentions are management module, for according to demand, select in management module in bim model a certain work post or certain
The Field Force in one region is oriented communication, carries out targetedly voice and tells somebody what one's real intentions are;
Quality information is collected and inspection of quality module, and for being shared by the visual angle based on bim and positioning, management personnel pass through
Management module is carried out long-range inspection during inspection of quality and site operation personnel and is linked up with the same visual angle of management personnel;It is additionally operable to
By the construction quality situation of each of photo record entry work progress link of taking pictures in the course of receiving, described photo is real-time
It is linked at the corresponding position of bim model in management module, as the overall process data accumulation of Project quality management;
Safe early warning and construction note module, for detecting the row of every Field Force using the gyroscope being arranged in safety helmet
Walk form, and by related real-time data synchronization in management module, when certain workmen has larger toppling in time to attached
Nearly workmen and office send and ask warning to rescue signal;Positioning chip in safety helmet and photographic head can record this work people
Member have an accident before track route and periphery environment, as the investigation foundation of accident;It is additionally operable to determining staff
Position information is mated with bim model, when workmen goes to and faces side openings position, automatically sends out pre- to related personnel's safety helmet
Alert signal, it is to avoid the generation of security incident;
Personnel health's state detection module, for by arranging whether heart rate detection sensing chip correctly joins for site personnel
Wear a safety helmet, and project management red line is set in management module, safety helmet is detected and enter project construction field management red line
When, if appearance is not correctly worn safety helmet and sent alarm immediately, can be supervised in real time by heart rate detection result in work progress
The health status of control Field Force, exceed safety value and send alarm in time;
Field Force's trend monitoring module, for uploading to personnel's track positioning information in management module in real time, by personnel
Track positioning can each work surface of real time inspection number of work, secondly by divide project work red line and work flushing
Line, can be with real-time statistics site operation personnel amount, and settling accounts for labour force provides foundation, can by the curve movement following the tracks of personal
To monitor the work state of workmen, the conventional track route of next integration project personnel in the project implementation, reasonable arrangement
The setting of project related roads;
Site machinery monitoring of tools module, is positioned by the associated machines live to project and site machinery equipment is transported
Row monitoring and capacity are managed;By location-based monitoring, plant room will appear from collision to management personnel at the scene
Send orientation early warning, it is to avoid collision.
The beneficial effect comprise that:
1 present invention reduces construction organization difficulty, and labor service information is automatically integrating, can check at any time project site administrator with
And labor service personnel's working condition.
2nd, the present invention improves the safety of project construction, danger early warning more automatization, much sooner, it is to avoid correlation
The generation of accident.
3, present invention achieves the trackability of quality information, facilitate the inquiry to information for the later stage.
4th, the present invention improves the efficiency of remote communication, is shared by vision, is conveniently remotely linked up.
Brief description
Below in conjunction with drawings and Examples, the invention will be further described, in accompanying drawing:
Fig. 1 is the structural representation of the embodiment of the present invention;
Specific embodiment
In order that the objects, technical solutions and advantages of the present invention become more apparent, with reference to embodiments, to the present invention
It is further elaborated.It should be appreciated that specific embodiment described herein, only in order to explain the present invention, is not used to limit
Determine the present invention.
As shown in figure 1, a kind of project security management system based on bim, comprising: safety helmet, described safety helmet includes setting
Put button of taking pictures on safety helmet, photographic head, rhythm of the heart chip, speaker, positioning chip and wifi module;
This system includes with lower module:
Management module, for the meta-synthetic management of the information data of each module in project security management system;
Orientation voice is told somebody what one's real intentions are management module, for according to demand, select in management module in bim model a certain work post or certain
The Field Force in one region is oriented communication, carries out targetedly voice and tells somebody what one's real intentions are;
Quality information is collected and inspection of quality module, and for being shared by the visual angle based on bim and positioning, management personnel pass through
Management module is carried out long-range inspection during inspection of quality and site operation personnel and is linked up with the same visual angle of management personnel;It is additionally operable to
By the construction quality situation of each of photo record entry work progress link of taking pictures in the course of receiving, described photo is real-time
It is linked at the corresponding position of bim model in management module, as the overall process data accumulation of Project quality management;
Safe early warning and construction note module, for detecting the row of every Field Force using the gyroscope being arranged in safety helmet
Walk form, and by related real-time data synchronization in management module, when certain workmen has larger toppling in time to attached
Nearly workmen and office send and ask warning to rescue signal;Positioning chip in safety helmet and photographic head can record this work people
Member have an accident before track route and periphery environment, as the investigation foundation of accident;It is additionally operable to determining staff
Position information is mated with bim model, when workmen goes to and faces side openings position, automatically sends out pre- to related personnel's safety helmet
Alert signal, it is to avoid the generation of security incident;
Personnel health's state detection module, for by arranging whether heart rate detection sensing chip correctly joins for site personnel
Wear a safety helmet, and project management red line is set in management module, safety helmet is detected and enter project construction field management red line
When, if appearance is not correctly worn safety helmet and sent alarm immediately, can be supervised in real time by heart rate detection result in work progress
The health status of control Field Force, exceed safety value and send alarm in time;
Field Force's trend monitoring module, for uploading to personnel's track positioning information in management module in real time, by personnel
Track positioning can each work surface of real time inspection number of work, secondly by divide project work red line and work flushing
Line, can be with real-time statistics site operation personnel amount, and settling accounts for labour force provides foundation, can by the curve movement following the tracks of personal
To monitor the work state of workmen, the conventional track route of next integration project personnel in the project implementation, reasonable arrangement
The setting of project related roads;
Site machinery monitoring of tools module, is positioned by the associated machines live to project and site machinery equipment is transported
Row monitoring and capacity are managed;By location-based monitoring, plant room will appear from collision to management personnel at the scene
Send orientation early warning, it is to avoid collision.
It should be appreciated that for those of ordinary skills, can be improved according to the above description or be converted,
And all these modifications and variations all should belong to the protection domain of claims of the present invention.
Claims (1)
1. a kind of project security management system based on bim, comprising: safety helmet, described safety helmet includes being arranged on safety helmet
Button of taking pictures, photographic head, rhythm of the heart chip, speaker, positioning chip and wifi module;
It is characterized in that, comprising:
Management module, for the meta-synthetic management of the information data of each module in project security management system;
Orientation voice is told somebody what one's real intentions are management module, for according to demand, select in management module in bim model a certain work post or certain
The Field Force in one region is oriented communication, carries out targetedly voice and tells somebody what one's real intentions are;
Quality information is collected and inspection of quality module, and for being shared by the visual angle based on bim and positioning, management personnel pass through
Management module is carried out long-range inspection during inspection of quality and site operation personnel and is linked up with the same visual angle of management personnel;It is additionally operable to
By the construction quality situation of each of photo record entry work progress link of taking pictures in the course of receiving, described photo is real-time
It is linked at the corresponding position of bim model in management module, as the overall process data accumulation of Project quality management;
Safe early warning and construction note module, for detecting the row of every Field Force using the gyroscope being arranged in safety helmet
Walk form, and by related real-time data synchronization in management module, when certain workmen has larger toppling in time to attached
Nearly workmen and office send and ask warning to rescue signal;Positioning chip in safety helmet and photographic head can record this work people
Member have an accident before track route and periphery environment, as the investigation foundation of accident;It is additionally operable to determining staff
Position information is mated with bim model, when workmen goes to and faces side openings position, automatically sends out pre- to related personnel's safety helmet
Alert signal, it is to avoid the generation of security incident;
Personnel health's state detection module, for by arranging whether heart rate detection sensing chip correctly joins for site personnel
Wear a safety helmet, and project management red line is set in management module, safety helmet is detected and enter project construction field management red line
When, if appearance is not correctly worn safety helmet and sent alarm immediately, can be supervised in real time by heart rate detection result in work progress
The health status of control Field Force, exceed safety value and send alarm in time;
Field Force's trend monitoring module, for uploading to personnel's track positioning information in management module in real time, by personnel
Track positioning can each work surface of real time inspection number of work, secondly by divide project work red line and work flushing
Line, can be with real-time statistics site operation personnel amount, and settling accounts for labour force provides foundation, can by the curve movement following the tracks of personal
To monitor the work state of workmen, the conventional track route of next integration project personnel in the project implementation, reasonable arrangement
The setting of project related roads;
Site machinery monitoring of tools module, is positioned by the associated machines live to project and site machinery equipment is transported
Row monitoring and capacity are managed;By location-based monitoring, plant room will appear from collision to management personnel at the scene
Send orientation early warning, it is to avoid collision.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610779336.1A CN106372854B (en) | 2016-08-30 | 2016-08-30 | A kind of project security management system based on BIM |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610779336.1A CN106372854B (en) | 2016-08-30 | 2016-08-30 | A kind of project security management system based on BIM |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106372854A true CN106372854A (en) | 2017-02-01 |
CN106372854B CN106372854B (en) | 2018-07-13 |
Family
ID=57898635
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610779336.1A Active CN106372854B (en) | 2016-08-30 | 2016-08-30 | A kind of project security management system based on BIM |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106372854B (en) |
Cited By (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106934729A (en) * | 2017-03-09 | 2017-07-07 | 河北省建筑科学研究院 | Building Testing and appraisal method and device |
CN106980705A (en) * | 2017-02-22 | 2017-07-25 | 中国建筑第八工程局有限公司 | Safety protection standard construction method based on BIM technology |
CN107748945A (en) * | 2017-09-01 | 2018-03-02 | 郭亚晋 | A kind of wisdom site staff management system |
CN108089510A (en) * | 2017-12-22 | 2018-05-29 | 深圳市前海公共安全科学研究院有限公司 | A kind of construction personnel's behavior intelligent monitoring system and method |
CN108268985A (en) * | 2016-12-30 | 2018-07-10 | 上海大学 | Cross-river tunnel engineering construction quality safety tracing system based on BIM |
CN108427815A (en) * | 2017-08-12 | 2018-08-21 | 中民筑友科技投资有限公司 | A kind of collision detection method and device in engineering project |
CN108446889A (en) * | 2018-02-11 | 2018-08-24 | 北京市轨道交通建设管理有限公司 | A kind of exchange method of construction site and construction speed platform |
CN108732979A (en) * | 2018-05-15 | 2018-11-02 | 浙江大学 | A kind of construction safety managing and control system based on BIM technology |
CN109410544A (en) * | 2018-10-16 | 2019-03-01 | 广州源贸易有限公司 | A kind of enterprise security early warning system that early warning effect is good |
CN109637078A (en) * | 2018-11-16 | 2019-04-16 | 万翼科技有限公司 | A kind of abnormality monitoring method of intelligent wearable device |
CN109658665A (en) * | 2017-10-10 | 2019-04-19 | 重庆大学 | Personal protection protection against electric shock method for early warning, device, system, storage equipment and terminal |
CN110557501A (en) * | 2019-08-07 | 2019-12-10 | 黄莹 | risk identification rescue method and system based on coordination of smart watch and smart phone |
CN111428299A (en) * | 2020-03-25 | 2020-07-17 | 河南华北水电工程监理有限公司 | Engineering whole-course monitoring system |
CN111784967A (en) * | 2020-07-23 | 2020-10-16 | 南通市达欣工程股份有限公司 | Building construction safety early warning protection system based on BIM |
CN111985736A (en) * | 2019-05-21 | 2020-11-24 | 中铁北京工程局集团有限公司 | Quality supervision system for expressway bridge construction |
CN112016884A (en) * | 2020-07-30 | 2020-12-01 | 河北新金轧材有限公司 | Safety management method and system for field production |
CN112884444A (en) * | 2021-03-10 | 2021-06-01 | 苏州思萃融合基建技术研究所有限公司 | Intelligent system for managing construction site personnel based on digital twin technology |
CN113570327A (en) * | 2021-07-06 | 2021-10-29 | 廖妹远 | Construction supervision intelligent management system and supervision method |
CN114360205A (en) * | 2022-03-21 | 2022-04-15 | 四川新迎顺信息技术股份有限公司 | BIM-based danger source early warning method, device, equipment and readable storage medium |
CN117114619A (en) * | 2023-09-07 | 2023-11-24 | 深圳叮当科技技术有限公司 | Project security management system based on big data analysis |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103544556A (en) * | 2013-09-06 | 2014-01-29 | 上海大学 | Life-cycle management system and method for tunnels |
CN103955174A (en) * | 2014-03-31 | 2014-07-30 | 湖南大学 | Building health monitoring system based on building information model technology |
-
2016
- 2016-08-30 CN CN201610779336.1A patent/CN106372854B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103544556A (en) * | 2013-09-06 | 2014-01-29 | 上海大学 | Life-cycle management system and method for tunnels |
CN103955174A (en) * | 2014-03-31 | 2014-07-30 | 湖南大学 | Building health monitoring system based on building information model technology |
Non-Patent Citations (2)
Title |
---|
江帆: "基于BIM和RFID技术的建设项目安全管理研究", 《中国优秀硕士学位论文全文数据库 工程科技II辑》 * |
郭红领 等: "BIM和RFID在施工安全管理中的集成应用研究", 《工程管理学报》 * |
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108268985A (en) * | 2016-12-30 | 2018-07-10 | 上海大学 | Cross-river tunnel engineering construction quality safety tracing system based on BIM |
CN106980705A (en) * | 2017-02-22 | 2017-07-25 | 中国建筑第八工程局有限公司 | Safety protection standard construction method based on BIM technology |
CN106934729A (en) * | 2017-03-09 | 2017-07-07 | 河北省建筑科学研究院 | Building Testing and appraisal method and device |
CN106934729B (en) * | 2017-03-09 | 2021-03-30 | 河北省建筑科学研究院有限公司 | Building detection and identification method and device |
CN108427815A (en) * | 2017-08-12 | 2018-08-21 | 中民筑友科技投资有限公司 | A kind of collision detection method and device in engineering project |
CN107748945A (en) * | 2017-09-01 | 2018-03-02 | 郭亚晋 | A kind of wisdom site staff management system |
CN109658665A (en) * | 2017-10-10 | 2019-04-19 | 重庆大学 | Personal protection protection against electric shock method for early warning, device, system, storage equipment and terminal |
CN108089510A (en) * | 2017-12-22 | 2018-05-29 | 深圳市前海公共安全科学研究院有限公司 | A kind of construction personnel's behavior intelligent monitoring system and method |
CN108446889A (en) * | 2018-02-11 | 2018-08-24 | 北京市轨道交通建设管理有限公司 | A kind of exchange method of construction site and construction speed platform |
CN108732979A (en) * | 2018-05-15 | 2018-11-02 | 浙江大学 | A kind of construction safety managing and control system based on BIM technology |
CN109410544A (en) * | 2018-10-16 | 2019-03-01 | 广州源贸易有限公司 | A kind of enterprise security early warning system that early warning effect is good |
CN109637078A (en) * | 2018-11-16 | 2019-04-16 | 万翼科技有限公司 | A kind of abnormality monitoring method of intelligent wearable device |
CN111985736A (en) * | 2019-05-21 | 2020-11-24 | 中铁北京工程局集团有限公司 | Quality supervision system for expressway bridge construction |
CN110557501A (en) * | 2019-08-07 | 2019-12-10 | 黄莹 | risk identification rescue method and system based on coordination of smart watch and smart phone |
CN111428299A (en) * | 2020-03-25 | 2020-07-17 | 河南华北水电工程监理有限公司 | Engineering whole-course monitoring system |
CN111784967A (en) * | 2020-07-23 | 2020-10-16 | 南通市达欣工程股份有限公司 | Building construction safety early warning protection system based on BIM |
CN112016884A (en) * | 2020-07-30 | 2020-12-01 | 河北新金轧材有限公司 | Safety management method and system for field production |
CN112884444A (en) * | 2021-03-10 | 2021-06-01 | 苏州思萃融合基建技术研究所有限公司 | Intelligent system for managing construction site personnel based on digital twin technology |
CN112884444B (en) * | 2021-03-10 | 2023-07-18 | 苏州思萃融合基建技术研究所有限公司 | Intelligent system for managing construction site personnel based on digital twin technology |
CN113570327A (en) * | 2021-07-06 | 2021-10-29 | 廖妹远 | Construction supervision intelligent management system and supervision method |
CN114360205A (en) * | 2022-03-21 | 2022-04-15 | 四川新迎顺信息技术股份有限公司 | BIM-based danger source early warning method, device, equipment and readable storage medium |
CN117114619A (en) * | 2023-09-07 | 2023-11-24 | 深圳叮当科技技术有限公司 | Project security management system based on big data analysis |
CN117114619B (en) * | 2023-09-07 | 2024-05-14 | 深圳叮当科技技术有限公司 | Project security management system based on big data analysis |
Also Published As
Publication number | Publication date |
---|---|
CN106372854B (en) | 2018-07-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106372854A (en) | Project safety management system based on BIM | |
CN109240311B (en) | Outdoor electric power field construction operation supervision method based on intelligent robot | |
CN105989682A (en) | Safety early warning and monitoring system and monitoring method for construction machinery under power transmission line | |
CN105563488A (en) | Night patrol robot | |
CN104392582B (en) | The Ship Welding long-range monitor and alarm system of personnel based on multi-sensor information fusion | |
CN109345056A (en) | A kind of construction personnel's behavior real time monitoring system | |
CN109388115A (en) | Mining intelligent individual soldier operation and safeguards system, method and intelligent polling method | |
CN112530144B (en) | Method and system for warning violation behaviors of thermal power plant based on neural network | |
CN103311829B (en) | Monitoring system of electric substation | |
CN113206978A (en) | Security intelligent monitoring early warning system and method for oil and gas pipeline station | |
CN103244186A (en) | Identification, tracking and early-warning system based on coal and gas outburst development process | |
CN113506416A (en) | Engineering abnormity early warning method and system based on intelligent visual analysis | |
CN205819229U (en) | A kind of guard system being applicable to Railway Site attendant | |
CN209199300U (en) | A kind of comprehensive monitor system based on intelligent safety helmet | |
CN115731670A (en) | Safety alarm method, device and monitoring system for construction site | |
CN108388873A (en) | A kind of supervisory systems of machine vision, method and client computer, storage medium | |
CN204515966U (en) | A kind of warning system based on Internet of Things and image recognition | |
CN207352670U (en) | A kind of construction personnel deploys to ensure effective monitoring and control of illegal activities safely system | |
CN106744221B (en) | A kind of well-bucket operational safety integrated protection system and its means of defence | |
CN206144242U (en) | Communication tower | |
CN109459966A (en) | A kind of construction safety intelligent management system | |
CN105988444A (en) | Iron tower remote control monitoring system | |
CN107545610A (en) | A kind of workmen deploys to ensure effective monitoring and control of illegal activities safely system | |
CN115240362A (en) | Monitoring alarm system and method of intelligent construction site management and control platform | |
CN204496658U (en) | Crag avalanche monitoring warning device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |