CN108661655B - Large-section U-shaped earth pressure balance shield tunnel construction method based on U-shaped shield machine - Google Patents
Large-section U-shaped earth pressure balance shield tunnel construction method based on U-shaped shield machine Download PDFInfo
- Publication number
- CN108661655B CN108661655B CN201810446543.4A CN201810446543A CN108661655B CN 108661655 B CN108661655 B CN 108661655B CN 201810446543 A CN201810446543 A CN 201810446543A CN 108661655 B CN108661655 B CN 108661655B
- Authority
- CN
- China
- Prior art keywords
- shield
- shield machine
- soil
- shaped
- horseshoe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 35
- 230000005641 tunneling Effects 0.000 claims abstract description 25
- 230000002787 reinforcement Effects 0.000 claims abstract description 12
- 238000003466 welding Methods 0.000 claims abstract description 10
- 239000002689 soil Substances 0.000 claims description 75
- 229910000831 Steel Inorganic materials 0.000 claims description 48
- 239000010959 steel Substances 0.000 claims description 48
- 239000000463 material Substances 0.000 claims description 33
- 238000000034 method Methods 0.000 claims description 33
- 238000009412 basement excavation Methods 0.000 claims description 25
- 230000001360 synchronised effect Effects 0.000 claims description 20
- 230000008569 process Effects 0.000 claims description 19
- 239000002002 slurry Substances 0.000 claims description 18
- 238000007789 sealing Methods 0.000 claims description 16
- 239000004568 cement Substances 0.000 claims description 15
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 12
- 238000005520 cutting process Methods 0.000 claims description 11
- 239000004570 mortar (masonry) Substances 0.000 claims description 11
- 238000002156 mixing Methods 0.000 claims description 10
- 239000002893 slag Substances 0.000 claims description 9
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 8
- 239000004567 concrete Substances 0.000 claims description 7
- 230000000694 effects Effects 0.000 claims description 7
- 239000007788 liquid Substances 0.000 claims description 7
- 238000002347 injection Methods 0.000 claims description 6
- 239000007924 injection Substances 0.000 claims description 6
- 238000003860 storage Methods 0.000 claims description 5
- 229910000278 bentonite Inorganic materials 0.000 claims description 4
- 239000000440 bentonite Substances 0.000 claims description 4
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 claims description 4
- 238000013461 design Methods 0.000 claims description 4
- 239000004088 foaming agent Substances 0.000 claims description 4
- 229910052742 iron Inorganic materials 0.000 claims description 4
- 239000000203 mixture Substances 0.000 claims description 4
- 230000004048 modification Effects 0.000 claims description 4
- 238000012986 modification Methods 0.000 claims description 4
- 238000007711 solidification Methods 0.000 claims description 4
- 230000008023 solidification Effects 0.000 claims description 4
- 230000008859 change Effects 0.000 claims description 3
- 239000006260 foam Substances 0.000 claims description 3
- 230000002706 hydrostatic effect Effects 0.000 claims description 3
- 230000002452 interceptive effect Effects 0.000 claims description 3
- 238000010298 pulverizing process Methods 0.000 claims description 3
- 239000000243 solution Substances 0.000 claims description 3
- 230000006641 stabilisation Effects 0.000 claims description 2
- 238000011105 stabilization Methods 0.000 claims description 2
- 238000005516 engineering process Methods 0.000 abstract description 21
- 230000006872 improvement Effects 0.000 abstract description 8
- 238000010586 diagram Methods 0.000 description 6
- 230000000903 blocking effect Effects 0.000 description 4
- 230000008901 benefit Effects 0.000 description 3
- 230000005484 gravity Effects 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 238000009825 accumulation Methods 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 2
- 230000006835 compression Effects 0.000 description 2
- 238000007906 compression Methods 0.000 description 2
- 239000004519 grease Substances 0.000 description 2
- 239000010410 layer Substances 0.000 description 2
- 238000005065 mining Methods 0.000 description 2
- WHXSMMKQMYFTQS-UHFFFAOYSA-N Lithium Chemical compound [Li] WHXSMMKQMYFTQS-UHFFFAOYSA-N 0.000 description 1
- 230000009471 action Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000005336 cracking Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 239000010881 fly ash Substances 0.000 description 1
- 230000000977 initiatory effect Effects 0.000 description 1
- 238000001746 injection moulding Methods 0.000 description 1
- 229910052744 lithium Inorganic materials 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 235000019353 potassium silicate Nutrition 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000009418 renovation Methods 0.000 description 1
- 238000012827 research and development Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000011378 shotcrete Substances 0.000 description 1
- 239000002356 single layer Substances 0.000 description 1
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/18—Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/06—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
- E21D9/0607—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/06—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
- E21D9/08—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield
- E21D9/0875—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a movable support arm carrying cutting tools for attacking the front face, e.g. a bucket
- E21D9/0879—Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining with additional boring or cutting means other than the conventional cutting edge of the shield with a movable support arm carrying cutting tools for attacking the front face, e.g. a bucket the shield being provided with devices for lining the tunnel, e.g. shuttering
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/12—Devices for removing or hauling away excavated material or spoil; Working or loading platforms
- E21D9/124—Helical conveying means therefor
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Environmental & Geological Engineering (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
一种基于马蹄形盾构机的大断面马蹄形土压平衡盾构隧道施工方法,采用以下步骤,步骤1:设置明洞反力结构盾构始发装置,端头向进洞方向采用大管棚加固。步骤2:在底板结构上设置始发基座,在始发基座上设置3根第一导轨作为盾构机导向轨道,在洞门导洞中铺设3根第二导轨,将第一导轨和第二导轨相连,位于盾构机盾尾与中盾的连接处,在始发基座上设置有盾尾焊接槽。步骤3:设置明洞加强段结构为盾构机提供反力。在大断面马蹄形盾构机基础上,形成了大断面马蹄形盾构施工的成套技术:明洞反力结构盾构始发技术;盾构掘进参数控制技术;大断面马蹄形盾构管片拼装技术;渣土改良技术。
A large-section horseshoe-shaped earth pressure balance shield tunnel construction method based on a horseshoe-shaped shield machine adopts the following steps, step 1: set up a shield starting device for a reaction force structure in the open hole, and use a large pipe shed to reinforce the end in the direction of entering the hole . Step 2: Set the starting base on the base plate structure, set 3 first guide rails on the starting base as the guide rails of the shield machine, lay 3 second guide rails in the guide hole of the cave door, connect the first guide rail and The second guide rail is connected and located at the connection between the shield tail of the shield machine and the middle shield, and a shield tail welding groove is arranged on the starting base. Step 3: Set the Myeongdong reinforcement section structure to provide reaction force for the shield machine. On the basis of the large-section horseshoe-shaped shield machine, a complete set of technologies for large-section horseshoe-shaped shield construction has been formed: the starting technology of the Myeongdong reaction force structure shield; the control technology of the shield tunneling parameters; the large-section horseshoe-shaped shield segment assembly technology; Muck improvement technology.
Description
技术领域technical field
本发明涉及隧道施工领域,具体涉及一种基于马蹄形盾构机的大断面马蹄形土压平衡盾构隧道施工方法。The invention relates to the field of tunnel construction, in particular to a large-section horseshoe-shaped earth pressure balance shield tunnel construction method based on a horseshoe-shaped shield machine.
背景技术Background technique
目前,在大规模的铁路隧道施工中,以矿山法为主,辅以少量的TBM和盾构法,其中盾构法主要用于下穿河流、海峡及城市软土地层中。当铁路山岭隧道穿越砂质和新黄土地层时,采用矿山法施工需要辅助工法和大刚度的支护,代价较大,而采用盾构法施工较为便利,结构主要为单层预制管片,无额外的施工支护成本,优点明显,但也需要增加初期机械研发和制造成本问题。在断面形式上,常规盾构以圆形为主,特别当面对双线大断面的形式下,大部分为大断面圆形盾构。国际上也有采用双圆甚至三圆土压平衡盾构的先例,但存在开挖断面加大、受力效果差和支护构件增加的劣势。由此,产生了开发大断面马蹄形盾构施工双线黄土地层铁路隧道的构想,本施工技术基于多刀盘马蹄形大断面盾构机专利技术而配套研发的相应的施工技术。由于多刀盘大断面马蹄形盾构施工是个前所未有的尝试,存在以下难点或未解决的问题:At present, in the construction of large-scale railway tunnels, the mining method is the main method, supplemented by a small amount of TBM and the shield method, of which the shield method is mainly used to penetrate rivers, straits and urban soft soil layers. When the railway mountain tunnel passes through the sandy and new loess strata, the mining method construction requires auxiliary construction methods and high stiffness support, which is costly, while the shield method is more convenient for construction, the structure is mainly single-layer prefabricated segment, no The additional construction support cost has obvious advantages, but it also needs to increase the initial mechanical research and development and manufacturing costs. In terms of section form, conventional shields are mainly circular, especially when facing the form of double-line large sections, most of them are large-section circular shields. There are also international precedents for the use of double-circle or even three-circle earth pressure balance shields, but there are disadvantages such as increased excavation section, poor stress effect and increased supporting members. As a result, the concept of developing a large-section horseshoe-shaped shield for the construction of a double-track loess-strata railway tunnel was born. Since the construction of a large-section horseshoe shield with multiple cutter heads is an unprecedented attempt, there are the following difficulties or unsolved problems:
(1)铁路山岭隧道工程不同于常规地铁盾构在车站内的始发,一般洞口为路堑,可以充分利用明洞结构代替常规地铁所使用的盾构始发专用反力架提供反力。(1) The railway mountain tunnel project is different from the departure of the conventional subway shield in the station. The general entrance is a road cutting, and the Myeongdong structure can be fully utilized to replace the special reaction frame for the initiation of the shield used in the conventional subway to provide reaction force.
(2)盾构施工关键是需要根据掘进的地质条件及时准确的确定盾构机的掘进参数,对马蹄形大断面盾构施工更是如此,盾构机掘进参数确定的得当与否直接关系到盾构施工的进度、安全和质量。(2) The key of shield tunnel construction is to determine the tunneling parameters of the shield tunneling machine in a timely and accurate manner according to the geological conditions of tunneling, especially for the construction of a large horseshoe-shaped shield tunnel. Whether the tunneling parameters of the shield tunneling machine are properly determined or not is directly related to the shield tunnel. progress, safety and quality of construction.
(3)马蹄形管片拼装是马蹄形盾构机的设计难点之一,也是盾构施工的难点。也由于马蹄形断面没有圆形的中心对称优势,导致每块管片内表面变曲率、重量大、惯性大、重心偏置等特点,从而使管片安装时微调工作量很大、管片错位搭接现象多,且楔形块在最后拼装时周向压紧力不易传导等诸多难题。(3) The assembly of the horseshoe-shaped segment is one of the design difficulties of the horseshoe-shaped shield machine, and it is also a difficulty in the construction of the shield. Also, because the horseshoe-shaped section does not have the advantage of circular center symmetry, the inner surface of each segment has the characteristics of variable curvature, large weight, large inertia, and offset center of gravity, etc., so that the fine-tuning work during the installation of the segment is heavy, and the segments are misaligned. There are many problems such as many connection phenomena, and the circumferential compression force of the wedge-shaped block is not easily transmitted during the final assembly.
(4)鉴于马蹄形断面面积大、九刀盘同时开挖、搅拌效果不均、同时存在搅拌盲区,渣土改良存在很大不均匀性,对盾体(姿态)方向控制影响大。因此保证渣土改良效果至关重要,通过渣土改良让渣土实现真正的注塑状。(4) In view of the large horseshoe-shaped cross-sectional area, the simultaneous excavation of the nine cutter heads, the uneven mixing effect, and the existence of a mixing blind area, there is a great unevenness in the improvement of the slag, which has a great influence on the direction control of the shield body (attitude). Therefore, it is very important to ensure the improvement of the muck. Through the improvement of the muck, the muck can achieve a real injection molding shape.
(5)超大断面马蹄形盾构,隧道主要穿越地层为全断面新黄土地层,隧道断面面积大、同步注浆量大,管片脱出盾尾后的稳定性直接影响成型隧道的质量。因传统的二次注浆采用水玻璃与水泥浆液的双液浆,每次施作最低配备4人方可进行,工序繁琐且费时费力,经常出现堵管和抱死盾壳的现象。此外,大断面马蹄形盾构断面大,管片结构自身重量和浆液浮力均大,同步注浆浆液性能和操作不当,极易引起管片开裂等隐患。(5) Horseshoe-shaped shield with super large cross-section, the tunnel mainly passes through the new loess stratum with full cross-section. The tunnel has a large cross-sectional area and a large amount of synchronous grouting. The stability of the segment after the segment comes out of the shield tail directly affects the quality of the formed tunnel. Because the traditional secondary grouting uses a double-liquid slurry of water glass and cement slurry, a minimum of 4 people can be required for each application. The process is cumbersome and time-consuming, and the phenomenon of pipe blocking and shielding often occurs. In addition, the large-section horseshoe-shaped shield has a large section, and the weight of the segment structure and the buoyancy of the slurry are large. The improper performance and operation of the synchronous grouting slurry can easily cause hidden dangers such as segment cracking.
(6)掘进中3#、5#、7#刀盘在前,与1#、4#、6#后刀盘之间形成盲区,盲区位置渣土积累,导致推力逐渐加大刀盘之间形成盲区,盲区位置渣土积累,导致推力逐渐加大砂质老黄土地层,导致掘进困难,刀盘与切口的阻力增大,盲区土柱难以破坏直接顶入土仓内隔板上,导致推力增大的同时无速度,且刀盘扭矩也随之增大。(6) During the excavation, the 3#, 5#, and 7# cutterheads are in front, and a blind zone is formed between the 1#, 4#, and 6# rear cutterheads. Blind area, the accumulation of muck in the blind area causes the thrust to gradually increase in the sandy old loess layer, which leads to the difficulty of excavation, the resistance between the cutter head and the incision increases, and the soil column in the blind area is difficult to destroy and directly pushes into the clapboard of the soil bin, resulting in the increase of thrust At the same time, there is no speed, and the torque of the cutter head also increases.
(6)铁路山岭隧道洞口一般为路堑,不同于常规地铁盾构在车站内的接收,因此需结合洞口边仰坡和明洞结构进行接收施工。路堑明洞接收技术采用挡墙支护仰坡代替常规的洞口段旋喷或桩加固,解决了边仰坡稳定问题;接收基座-挡墙段采用管片结构,解决了挡墙干扰盾构机接收与拆解的问题;接缝构造措施解决了管片结构与明洞段的衔接问题。(6) The entrance of the railway mountain tunnel is generally a cutting, which is different from the receiving of the conventional subway shield in the station. Therefore, the receiving construction needs to be combined with the slope of the tunnel entrance and the structure of the open hole. The road cutting open hole receiving technology adopts the retaining wall to support the inclined slope instead of the conventional rotary jetting or pile reinforcement at the entrance section, which solves the problem of the stability of the side slope; The problem of machine receiving and dismantling is solved; the joint construction measures solve the connection problem between the segment structure and the Myeongdong section.
因此,大断面马蹄形盾构的施工是个新兴事物,与常规的小断面异形盾构或大断面圆形盾构施工均存在很大差异。本工法专利在针对性解决上述施工难点和新问题基础上而综合形成。Therefore, the construction of large-section horseshoe-shaped shield is a new thing, which is very different from the conventional small-section special-shaped shield or large-section circular shield construction. This construction method patent is comprehensively formed on the basis of addressing the above-mentioned construction difficulties and new problems.
发明内容SUMMARY OF THE INVENTION
本发明针对现有技术的不足,提出一种基于马蹄形盾构机的大断面马蹄形土压平衡盾构隧道施工方法,具体技术方案如下:Aiming at the deficiencies of the prior art, the present invention proposes a large-section horseshoe-shaped earth pressure balance shield tunnel construction method based on a horseshoe-shaped shield machine. The specific technical scheme is as follows:
一种基于马蹄形盾构机的大断面马蹄形土压平衡盾构隧道施工方法,其特征在于:采用以下步骤,A large-section horseshoe-shaped earth pressure balance shield tunnel construction method based on a horseshoe-shaped shield machine is characterized in that: the following steps are adopted:
步骤1:设置盾构机始发装置,端头向进洞方向采用大管棚加固。Step 1: Set the starting device of the shield machine, and use a large pipe shed to reinforce the end toward the hole.
步骤2:在底板结构(10)上设置始发基座(11),在始发基座(11)上设置3根第一导轨作为盾构机导向轨道,在洞门导洞中铺设3根第二导轨(12),将第一导轨和第二导轨相连,位于盾构机盾尾与中盾的连接处,在始发基座上设置有盾尾焊接槽(13)。Step 2: A starting base (11) is set on the bottom plate structure (10), three first guide rails are set on the starting base (11) as guide rails for the shield machine, and three are laid in the guide hole of the tunnel door The second guide rail (12) connects the first guide rail and the second guide rail and is located at the connection between the shield tail of the shield machine and the middle shield, and a shield tail welding groove (13) is arranged on the starting base.
步骤3:设置明洞加强段结构(14)为盾构机提供反力。Step 3: Setting the Myeongdong reinforcement section structure (14) to provide reaction force for the shield machine.
步骤4:设置洞门密封装置,在套拱进洞口方向,施作始发导洞,始发导洞出洞端与套拱连接,进洞端焊接第一预埋钢环,在第一管片脱出盾尾后,通过第一管片与套拱之间的缝隙进行封闭,设置铁皮用于封闭始发导洞的拱架与管片之间缝隙,同时在拱架内安设支撑;Step 4: Set up the sealing device of the tunnel door, construct the starting guide hole in the direction of the entrance of the sleeve arch, connect the exit end of the starting guide hole with the sleeve arch, weld the first embedded steel ring at the entrance end, and install the first embedded steel ring on the first pipe. After the piece comes out of the shield tail, it is closed by the gap between the first segment and the sleeve arch, and the iron sheet is arranged to close the gap between the arch of the starting guide hole and the segment, and at the same time, a support is installed in the arch;
步骤5:盾构机(5)开始工作掘进,在整个盾构机(5)掘进过程中,采用A料和B料同步注浆;Step 5: The shield machine (5) starts to work and excavate, and during the entire excavation process of the shield machine (5), the A material and the B material are used for simultaneous grouting;
同时,盾构机(5)每在隧道中掘进一定距离,在盾构机(5)盾尾进行马蹄形盾构管片拼装;At the same time, every time the shield machine (5) excavates a certain distance in the tunnel, the horseshoe-shaped shield segment is assembled at the shield tail of the shield machine (5);
同时,在整个盾构机(5)掘进过程中,实时控制土仓内的压力稳定平衡。At the same time, during the whole excavation process of the shield machine (5), the pressure in the soil bin is controlled to be stable and balanced in real time.
步骤6:实施盾构机(5)接收。Step 6: Receive the shield machine (5).
为更好的实现本发明,可进一步为:For better realization of the present invention, it can be further:
所述步骤5中,在整个盾构掘进过程中,采用A料和B料同步注浆包括以下步骤:In the
步骤S1:通过注浆量与盾构机掘进时扰动地层范围的关系,确定充填系数为1.3~1.8;Step S1: According to the relationship between the grouting amount and the disturbed stratum range when the shield machine is excavating, the filling coefficient is determined to be 1.3-1.8;
步骤S2:将A料直接在搅拌站拌制时加入,同质量代替同步注浆砂浆中的水泥,B料在洞内溶解后导入储存罐中。Step S2: Add material A directly during mixing in the mixing station, replace the cement in the synchronous grouting mortar with the same quality, and introduce material B into the storage tank after dissolving in the hole.
步骤S3:对盾构机尾部的同步注浆管路进行改造,在盾构机尾部处使B溶液与含A料的砂浆充分混合,且通过计量泵使注入量及压力精确可控。Step S3: Renovate the synchronous grouting pipeline at the tail of the shield machine, fully mix the B solution with the mortar containing the A material at the tail of the shield machine, and accurately control the injection amount and pressure through the metering pump.
步骤S4:凝固一段时间后,其中AB料的比例根据砂浆配比中水泥的含量变化而随之改变,且初凝时间可通过调节AB料两者的比例来进行控制。Step S4: After solidifying for a period of time, the proportion of AB material changes according to the change of the cement content in the mortar ratio, and the initial setting time can be controlled by adjusting the proportion of the two materials.
进一步地:在盾构机掘进时,对刀盘改造,对五号刀盘(16)和六号刀盘(17)每个单边扩挖300mm,中间的一号刀盘(18)需要将刀梁进行割除,然后用封板将刀梁缺口封堵。Further: when the shield machine is excavating, the cutter head is modified, and the No. 5 cutter head (16) and the No. 6 cutter head (17) are excavated by 300mm on each side, and the No. 1 cutter head (18) in the middle needs to be replaced. The knife beam is cut off, and then the gap of the knife beam is sealed with a sealing plate.
五号刀盘(16)改造:将刀梁加长;在刀梁上焊接刀具;将中心五方的斜梁割除,并焊接新斜梁;Modification of No. 5 cutter head (16): lengthen the cutter beam; weld the cutter on the cutter beam; cut off the five-sided oblique beam in the center, and weld a new oblique beam;
一号刀盘(18)的改造:割除干涉的刀梁,将泡沫管封堵,将刀梁缺口封堵;Modification of the No. 1 cutter head (18): cut off the interfering cutter beam, plug the foam tube, and seal the gap of the cutter beam;
四号刀盘(19)和六号刀盘(20)改造,将刀梁加长,在刀梁上焊接刮刀,增加四号刀盘(19)、五号刀盘(16)和六号刀盘(20)的开挖直径。The No. 4 cutter head (19) and No. 6 cutter head (20) are modified, the cutter beam is lengthened, the scraper is welded on the cutter beam, and the No. 4 cutter head (19), No. 5 cutter head (16) and No. 6 cutter head are added. (20) excavation diameter.
在土仓底部增加圆锥形分碴器,破坏此处掌子面硬结土体,在刀盘盲区中设置高压水管。A conical ballast divider is added at the bottom of the soil bin to destroy the hardened soil body on the face here, and a high-pressure water pipe is installed in the blind area of the cutter head.
进一步地:所述步骤6包括如下步骤:Further: the
采用以下步骤,Take the following steps,
步骤61:在洞口环两侧施作八字挡墙支护边仰坡;Step 61: Apply the slope of the eight-character retaining wall to support the edge on both sides of the hole ring;
步骤62:根据盾构机掘进情况及接收工艺要求确定开始凿除洞门时间,准备凿除洞门;Step 62: Determine the time to start cutting the tunnel door according to the tunneling situation of the shield machine and the requirements of the receiving process, and prepare to cut the tunnel door;
步骤63:洞门凿除首先在接收基座(1)上的洞门钢环(2)范围内搭设钢制脚手架,在接收基座(1)内生根并与两侧接收挡墙(3)搭设为一个整体;Step 63: chisel the hole door First, set up steel scaffolding within the scope of the hole door steel ring (2) on the receiving base (1), take root in the receiving base (1), and connect with the receiving retaining walls (3) on both sides. set up as a whole;
将脚手架下部垫实,脚手架的两侧分别与挡墙连接紧固,在横撑上面均铺设木板并与横撑固定;Pad the lower part of the scaffolding, connect the two sides of the scaffolding to the retaining wall and fasten them respectively, and lay wooden boards on the horizontal braces and fix them with the horizontal braces;
在洞门上中下均匀分布五个观察孔,随时观察端墙背后土体状况,当刀盘距离端墙(4)50cm时,盾构操作手将土仓压力降至0后,立即采取粉碎性凿除的方式凿除洞门钢环(2)范围内的30cm厚素混凝土,凿除工序采取自上而下,随凿随清的方式;Five observation holes are evenly distributed on the top, middle and bottom of the tunnel door, and the soil condition behind the end wall can be observed at any time. When the cutter head is 50cm away from the end wall (4), the shield operator reduces the soil bin pressure to 0, and immediately takes pulverization measures. The 30cm-thick plain concrete within the range of the steel ring (2) of the tunnel door is chiseled by the method of natural chiseling.
步骤64:实施盾构机(5)一次接收,判断洞门处混凝土是否凿除,如果是,则进入下一步骤,否则,回到步骤63;Step 64: Execute the shield machine (5) to receive once, and judge whether the concrete at the tunnel door is chiseled, if so, go to the next step, otherwise, go back to step 63;
步骤65:对脚手架进行拆除,且在指定时间内顶推盾构机、停止同步浆液的压注,在刀盘(6)至基座延伸导轨前停止刀盘(6)旋转;Step 65: dismantle the scaffold, push the shield machine within a specified time, stop the injection of the synchronous slurry, and stop the rotation of the cutter head (6) before the cutter head (6) reaches the extension guide rail of the base;
步骤66:在延伸导轨上沿着盾构机(5)掘进方向切割出一个上坡的豁口,当盾尾至洞口(7)指定距离时,完成第一次出洞,盾构机停止推进,在洞门钢环(2)与盾构机(5)外壳之间空隙采用段焊方式焊接整圈弧形钢板对洞圈进行封堵,并把预留有注浆管的钢板焊在相应的位置,弧形钢板与盾壳和钢环间的缝隙用速凝水泥填充,在封堵完成后,对加固区内的盾构管片外建筑空隙进行注浆,离盾尾的三环处压注双液水泥浆或直接在盾尾采取同步注浆配合AB液的方式进行填充;Step 66: Cut an uphill gap on the extended guide rail along the tunneling direction of the shield machine (5). When the shield tail reaches the specified distance from the hole (7), the first exit is completed, and the shield machine stops advancing. In the gap between the steel ring (2) of the tunnel door and the outer casing of the shield machine (5), a whole circle of arc-shaped steel plates is welded by segment welding to seal the hole ring, and the steel plate reserved for the grouting pipe is welded to the corresponding Position, the gap between the arc-shaped steel plate and the shield shell and the steel ring is filled with quick-setting cement. After the sealing is completed, grouting is performed on the building gap outside the shield segment in the reinforcement area, and the third ring away from the shield tail is pressed. Inject two-liquid cement slurry or directly fill the shield tail by synchronous grouting with AB liquid;
步骤67:在补压浆工作结束后,开孔检查浆液凝固效果。待浆液基本凝固后,盾构机(5)开始进行第二次接收,盾构机(5)爬上基座导轨后继续推进;Step 67: After the grouting work is completed, open the hole to check the solidification effect of the slurry. After the slurry is basically solidified, the shield machine (5) starts to receive the second time, and the shield machine (5) climbs the base guide rail and continues to advance;
待盾尾完全露出端墙(4)后,立即用封堵钢板(8)封闭洞门钢环(2)与盾构管片(9)之间缝隙,封堵钢板(8)分块制作好,精确定位后焊接在洞门钢环(2)上,封堵钢板(8)在洞门钢环(2)处焊接均采取满焊,在焊接结束后,在指定时间内用浆液对盾构管片(9)与洞门钢环(2)处的建筑空隙进行填充;After the shield tail is completely exposed from the end wall (4), immediately seal the gap between the steel ring (2) of the tunnel door and the shield segment (9) with the sealing steel plate (8), and the sealing steel plate (8) is made in blocks. , welded on the steel ring (2) of the tunnel door after accurate positioning, and the sealing steel plate (8) is fully welded at the steel ring (2) of the tunnel door. The segment (9) is filled with the building gap at the steel ring (2) of the tunnel door;
步骤68:进一步利用管片注浆孔,对洞口注浆,以防止漏水,并为端墙(4)与盾构管片(9)的稳定连接创造条件;Step 68: further use the segment grouting hole to grouting the hole to prevent water leakage and create conditions for the stable connection between the end wall (4) and the shield segment (9);
步骤69:盾构机(5)顶推至预定位置后,整个接收工作完成。Step 69: After the shield machine (5) is pushed to the predetermined position, the entire receiving work is completed.
进一步地:在整个盾构掘进过程中,每环姿态调整量控制在6mm以内,盾构轴线偏离设计轴线不大于±50mm,地面隆陷控制在+10mm~-30mm,始发时在始发基座上推进速度控制在20-30mm/min,盾构机进入原状土的前12m推进速度控制在20-30mm/min以内,在盾构机盾尾完全进入原状土后逐步提高到30-40mm/min。Further: During the entire shield tunneling process, the attitude adjustment amount of each ring is controlled within 6mm, the shield axis deviation from the design axis is not more than ±50mm, the ground uplift is controlled within +10mm ~ -30mm, and the starting point is at the starting base. The propelling speed on the seat is controlled at 20-30mm/min, the first 12m of the shield machine entering the undisturbed soil is controlled within 20-30mm/min, and it is gradually increased to 30-40mm/min after the shield tail of the shield machine completely enters the undisturbed soil. min.
进一步地:所述步骤5中实时控制土仓内的压力稳定平衡包括以下步骤:Further: in the described
S51:设置土仓内土压力值为P,取得静水压力和地层土压力之和为P0,满足P=K*P0,土仓压力通过采取设定掘进速度、调整排土量或设定排土量、调整掘进速度两种方法建立,并应维持切削土量与排土量的平衡,以使土仓内的压力稳定平衡,以上K值介于1.0~3.0;S51: Set the soil pressure value in the soil bin as P, obtain the sum of the hydrostatic pressure and the stratum soil pressure as P0, and satisfy P=K*P 0 . Two methods of soil volume and adjustment of driving speed should be established, and the balance of cutting soil volume and soil discharge volume should be maintained, so that the pressure in the soil bin can be stably balanced. The above K value is between 1.0 and 3.0;
S52:采用至少一条螺旋输送机出渣,同时,控制土仓左右压力实现土压平衡,控制地表沉降。S52: Use at least one screw conveyor to discharge slag, and at the same time, control the pressure on the left and right sides of the soil bin to achieve earth pressure balance and control the surface settlement.
S53:在砂性土流动性差的地层添加泡沫剂、膨润土改善碴土的止水性,使土仓内的压力稳定平衡。S53: Add foaming agent and bentonite to the stratum with poor fluidity of sandy soil to improve the water-stopping properties of ballast soil, so as to stabilize and balance the pressure in the soil bin.
S54:根据地质条件、排出的碴土状态,以及盾构机的各项工作状态参数,动态调整盾构机掘进速度和出土量的平衡来控制土仓压力,通过调整螺旋输送机的转速来调节排土量。S54: According to the geological conditions, the state of the discharged ballast, and the various working state parameters of the shield machine, dynamically adjust the balance of the shield machine’s tunneling speed and the amount of excavation to control the pressure of the soil bin, and adjust the speed by adjusting the speed of the screw conveyor. soil discharge.
本发明的有益效果为:第一,在大断面马蹄形盾构机基础上,形成了大断面马蹄形盾构施工的成套技术:明洞反力结构盾构始发技术;盾构掘进参数控制技术;大断面马蹄形盾构管片拼装技术;渣土改良技术;A、B料同步注浆技术;长距离皮带出渣技术,开挖面盲区处理技术,路堑接收技术。The beneficial effects of the invention are as follows: first, on the basis of the large-section horseshoe-shaped shield machine, a complete set of technologies for the construction of the large-section horseshoe-shaped shield is formed: the starting technology of the shield with the reaction force structure in the open hole; the control technology of the shield tunneling parameters; Large-section horseshoe-shaped shield segment assembly technology; slag improvement technology; A and B material synchronous grouting technology; long-distance belt slag removal technology, excavation surface blind area treatment technology, cutting receiving technology.
第二,明洞反力结构盾构始发技术不但节省了反力架、竖井、始发端墙和负环施做及拆除的费用,大大节约了施工成本,同时规避了即使在使用反力架的情况下反力架本身不好有效固定的难题。Second, the Myeongdong reaction force structure shield starting technology not only saves the construction and dismantling costs of the reaction force frame, shaft, starting end wall and negative ring, but also greatly saves the construction cost. In the case of the frame, the reaction frame itself is not easy to fix effectively.
第三,盾构机的掘进参数确保了大断面马蹄形盾构的顺利正常掘进。Third, the tunneling parameters of the shield machine ensure the smooth and normal tunneling of the large-section horseshoe shield.
第四,大断面马蹄形盾构管片拼装技术解决了大断面马蹄形管片重心偏置、安装时微调工作量很大、管片错位搭接现象多,且楔形块在最后拼装时周向压紧力不易传导等诸多难题。Fourth, the large-section horseshoe-shaped shield segment assembly technology solves the problem of the offset of the center of gravity of the large-section horseshoe-shaped segment, the heavy workload of fine-tuning during installation, the dislocation and overlap of the segments, and the circumferential compression of the wedge-shaped blocks during final assembly. Difficulty in power transmission and many other problems.
第五,通过渣土改良技术解决了马蹄形断面面积大、九刀盘搅拌效果不均、同时存在搅拌盲区,渣土流塑性差的难题。Fifth, the problems of large horseshoe-shaped cross-sectional area, uneven mixing effect of nine cutters, blind mixing zones and poor flow plasticity of the slag are solved through the slag improvement technology.
六、A、B料同步注浆技术解决了出现堵管和抱死盾壳的现象,以及大断面管片在自身重力和同步注浆浮力作用下易开裂的难题。6. The synchronous grouting technology of materials A and B solves the phenomenon of blocking the pipe and locking the shield shell, as well as the problem that the large-section segment is easy to crack under the action of its own gravity and synchronous grouting buoyancy.
七、长距离连续皮带机出渣技术提高了运输效率,改善了洞内环境。7. The long-distance continuous belt conveyor slag removal technology improves the transportation efficiency and improves the environment in the cave.
八、开挖面盲区处理技术解决了掘进中多刀盘之间形成盲区,盲区位置渣土积累,导致推力逐渐加大,掘进困难的难题。特别当出现与地勘不符的硬土或岩石地层时,盲区土柱难以破坏直接顶入土仓内隔板上,导致推力和扭矩增大,难以掘进。8. The blind spot treatment technology of the excavation face solves the problem of the formation of blind spots between multiple cutter heads during the excavation, and the accumulation of dregs in the blind spots, which leads to the gradual increase of thrust and the difficulty of excavation. Especially when there is a hard soil or rock formation inconsistent with the geological survey, it is difficult for the soil column in the blind area to be destroyed and directly pushed into the inner clapboard of the soil bin, resulting in increased thrust and torque, making it difficult to excavate.
附图说明Description of drawings
图1为始发基座站的结构示意图;Fig. 1 is the structural representation of originating base station;
图2为明洞加强段与盾构主机位置图;Figure 2 is the location diagram of the reinforcement section of Myeongdong and the main machine of the shield;
图3为洞门和接收基座脚手架搭设布置图;Figure 3 is a layout diagram of the scaffolding erection of the cave door and the receiving base;
图4为密封装置示意图;4 is a schematic diagram of a sealing device;
图5为盾构接收后与接收端墙位置关系图;Figure 5 is a diagram showing the positional relationship between the shield and the receiving end wall after receiving;
图6为改装刀盘分布结构示意图。Figure 6 is a schematic diagram of the distribution structure of the modified cutter head.
具体实施方式Detailed ways
下面结合附图对本发明的较佳实施例进行详细阐述,以使本发明的优点和特征能更易于被本领域技术人员理解,从而对本发明的保护范围做出更为清楚明确的界定。The preferred embodiments of the present invention will be described in detail below with reference to the accompanying drawings, so that the advantages and features of the present invention can be more easily understood by those skilled in the art, and the protection scope of the present invention can be more clearly defined.
一种基于马蹄形盾构机的大断面马蹄形土压平衡盾构隧道施工方法,主要包括以下步骤:A large-section horseshoe-shaped earth pressure balance shield tunnel construction method based on a horseshoe-shaped shield machine mainly includes the following steps:
步骤1:设置盾构机始发装置,端头加固,端头向大里程方向采用大管棚加固,长40m。在始发掘进时,通过洞门密封装置及掘进过程中的保压措施,可保证洞顶地层稳定,无需再进行其他端头加固措施。针对施作的大管棚,需采取人工进行探测水平范围及深度,保证大管棚不侵入隧道净空。Step 1: Set up the shield machine starting device, strengthen the end, and use a large tube shed to strengthen the end in the direction of the large mileage, with a length of 40m. At the beginning of excavation, through the tunnel door sealing device and the pressure maintaining measures during the excavation process, the stability of the stratum at the top of the tunnel can be ensured, and other end reinforcement measures are not required. For the large pipe shed to be constructed, it is necessary to manually detect the horizontal range and depth to ensure that the large pipe shed does not intrude into the tunnel clearance.
步骤2:始发基座11安装位置按照测量放样的基线,井下定位施工,始发基座11上的轨道按实测洞门中心居中对称放置。始发基座11全长24m,宽16m,始发基座11两侧高3m。盾构始发基座11采用C30钢筋混凝土结构,底部连接在一起组成整体结构。在始发基座11上设置3根120kg/m第一导轨作为盾构机5导向轨道,底部导轨居中,上部两根导轨12距中心4.8m。始发基座11施工时,通过与底板结构10上植筋进行加固,保证始发基座11与底板结构10成为整体。在洞门导洞中铺设3根第二导轨,第二导轨与始发导洞内第一导轨相连,并要焊接牢固,防止盾构机5掘进时将其破坏,而影响盾构机5的正常掘进。导轨位置以始发基座11滑轨延伸对应的位置为准。在盾尾与中盾连接处,预留宽800mm,高700mm的盾尾焊接槽13,盾尾焊接槽13处不设置导向钢轨,且在盾尾焊接槽13前方的导轨打斜坡口处理。Step 2: The installation position of the starting
步骤3:设置明洞加强段结构14,盾构的反力由明洞提供,替代通常地铁盾构始发中的反力架结构。明洞加强段14提供盾构机推进时所需的反力,盾构始发时,推力主要集中在下半部。明洞加强段14与盾构机位置示意图1、图2。Step 3: Set the Myeongdong
步骤4:洞门密封装置安装,在套拱向进洞口方向,施作13.5m长始发导洞,拱架内径为开挖轮廓线外15.5cm。始发导洞洞外端与套拱连接,进洞端焊接预埋钢环,在管片脱出盾尾后,按照要求进行洞门的密封,即将管片与套拱之间的缝隙进行封闭。保证盾构在通过拱架区时呈密封状态。用1mm铁皮用于封闭盾构导洞拱架与管片之间缝隙,铁皮分块制作好,精确定位后焊接在导洞拱架上,同时在拱架内安设支撑,防止在喷浆或者同步注浆时,封闭块发生变形,铁皮必须牢固地嵌入喷浆料且单面紧靠拱架,灌注混凝土或砂浆填筑时不得松动而影响使用。在施作过程中:钢环位置的纵向偏差为3mm,低于标准偏差5mm。Step 4: Install the sealing device of the cave door. In the direction of the sleeve arch towards the entrance of the cave, a 13.5m-long starting guide hole is constructed, and the inner diameter of the arch frame is 15.5cm outside the excavation outline. The outer end of the starting guide hole is connected with the sleeve arch, and the entrance end is welded with a pre-embedded steel ring. After the segment comes out of the shield tail, the tunnel door is sealed as required, that is, the gap between the segment and the sleeve arch is closed. Ensure that the shield is in a sealed state when passing through the arch area. The 1mm iron sheet is used to close the gap between the arch frame and the segment of the shield tunnel. During simultaneous grouting, the closed block is deformed, the iron sheet must be firmly embedded in the shotcrete and one side is close to the arch frame, and the concrete or mortar filling must not be loose and affect the use. During the application process: the longitudinal deviation of the steel ring position is 3mm, which is 5mm lower than the standard deviation.
步骤5:盾构机5开始工作掘进,在整个盾构机5掘进过程中,每环姿态调整量控制在6mm以内,盾构轴线偏离设计轴线不大于±50mm,地面隆陷控制在+10mm~-30mm,始发时在始发基座11上推进速度控制在20-30mm/min,盾构机进入原状土的前12m推进速度控制在20-30mm/min以内,在盾构机5盾尾完全进入原状土后逐步提高到30-40mm/min;Step 5: The
在整个盾构机5掘进过程中,采用A料和B料同步注浆;During the entire excavation process of
同时,盾构机5每在隧道中掘进指定距离,在隧道的该距离进行马蹄形盾构管片拼装;At the same time, every time the
同时,在整个盾构掘进过程中,实时控制土仓内的压力稳定平衡。At the same time, during the entire shield tunneling process, the pressure in the soil bin is controlled in real time to stabilize and balance.
步骤6:实施盾构机5接收;Step 6: Receive
步骤6包括如下步骤:
步骤61:在洞口环两侧施作八字挡墙支护边仰坡。八字挡墙墙脚长5m,宽2m,墙顶长*宽为1*1m,墙高6m,底部与接收基座1刚性连接;Step 61: Apply a figure-eight retaining wall to support the slopes on both sides of the opening ring. The length of the foot of the eight-character retaining wall is 5m, the width is 2m, the length*width of the top of the wall is 1*1m, the height of the wall is 6m, and the bottom is rigidly connected to the receiving base 1;
步骤62:根据盾构机掘进情况及接收工艺要求确定开始凿除洞门时间,准备凿除洞门;Step 62: Determine the time to start cutting the tunnel door according to the tunneling situation of the shield machine and the requirements of the receiving process, and prepare to cut the tunnel door;
步骤63:洞门凿除首先在接收基座1上的洞门钢环2范围内搭设钢制脚手架,在接收基座1内生根并与两侧接收挡墙3搭设为一个整体;Step 63: chisel the hole door. First, set up a steel scaffold within the range of the
将脚手架下部垫实,脚手架的两侧与接收挡墙3连接紧固,在横撑上面均铺设木板并与横撑固定;Pad the lower part of the scaffolding, connect the two sides of the scaffolding with the receiving retaining wall 3 tightly, and lay wooden boards on the cross braces and fix them with the cross braces;
在洞门上中下均匀分布五个观察孔,随时观察端墙背后土体状况,当刀盘距离端墙4的距离50cm时,盾构操作手将土仓压力降至0后,立即采取粉碎性凿除的方式凿除洞门钢环2范围内30cm厚素混凝土,凿除工序采取自上而下,随凿随清的方式;Five observation holes are evenly distributed on the top, middle and bottom of the tunnel door, and the soil condition behind the end wall can be observed at any time. When the distance between the cutter head and the
步骤64:实施盾构机5一次接收,判断洞门处混凝土是否凿除,如果是,则进入下一步骤,否则,回到步骤63;Step 64: Execute the
步骤65:对脚手架进行拆除,且在指定时间内顶推盾构、停止同步浆液的压注,在刀盘至接收基座1延伸导轨前停止刀盘旋转;Step 65: dismantle the scaffold, push the shield within the specified time, stop the injection of the synchronous slurry, and stop the rotation of the cutter head before the cutter head reaches the extension guide rail of the receiving base 1;
步骤66:在延伸导轨上沿着盾构机5掘进方向切割出一个上坡的豁口,当盾尾至洞口指定距离时,完成第一次出洞,盾构机5停止推进,在洞门钢环2与盾构外壳之间空隙采用段焊方式焊接整圈弧形钢板对洞圈进行封堵,并把预留有注浆管的钢板焊在相应的位置,钢板与盾壳、洞门钢环2间的缝隙用速凝水泥填充,在封堵完成后,对加固区内的管片外建筑空隙进行注浆,离盾尾的三环处压注双液水泥浆或直接在盾尾采取同步注浆配合AB液的方式进行填充。Step 66: Cut an uphill gap on the extension guide along the tunneling direction of the
步骤67:在补压浆工作结束后,开孔检查浆液凝固效果。待浆液基本凝固后,盾构机5开始进行第二次接收,盾构机爬上接收基座导轨1后继续推进;Step 67: After the grouting work is completed, open the hole to check the solidification effect of the slurry. After the slurry is basically solidified, the
待盾尾完全露出接收端墙4后,立即用封堵钢板8封闭盾构洞钢环2与盾构管片9之间缝隙,封堵钢板8分块制作好,精确定位后焊接在洞门钢环2上,封堵钢板8在洞门钢环2处焊接均采取满焊,在焊接结束后,在指定时间内用浆液对盾构管片9与洞门钢环2处的建筑空隙进行填充;After the shield tail is completely exposed to the receiving
将盾构管片9直接拼出接收端墙4范围内,同时盾尾切割槽预留位置相应向前延伸指定距离,焊接槽在基座中间轨道地面以下80cm,宽80cm;The
步骤68:进一步利用管片注浆孔,对洞口注浆,以防止漏水,并为端墙与管片的稳定连接创造条件;Step 68: Further use the segment grouting hole to grouting the hole to prevent water leakage and create conditions for the stable connection between the end wall and the segment;
步骤69:盾构主机顶推至预定位置后,整个接收工作完成。Step 69: After the shield machine is pushed to the predetermined position, the entire receiving work is completed.
盾构的组装与调试包括如下:1、盾构机组装场地及组装设备2、组装场地的布置。The assembly and debugging of the shield includes the following: 1. The shield machine assembly site and
盾构组装场地分成三个区:后配套拖车存放区、主机及配件存放区、吊机放置区。The shield assembly site is divided into three areas: rear supporting trailer storage area, main engine and accessories storage area, and crane placement area.
盾构机组装设备盾构机组装设备:250T履带吊1台,230t门吊一台,及相应的吊具、机具、工具。Shield machine assembly equipment Shield machine assembly equipment: one 250t crawler crane, one 230t door crane, and corresponding spreaders, implements and tools.
大断面马蹄形土压盾构机掘进参数主要是指:盾构机刀盘转速及扭矩;推进油缸总推力、各组行程差及推进速度;土仓压力的设定;泡沫剂等参数的调整;盾尾油脂、锂基脂消耗量的控制等。The tunneling parameters of the large-section horseshoe-shaped earth pressure shield machine mainly refer to: the rotation speed and torque of the shield machine cutter head; the total thrust of the propulsion cylinder, the stroke difference of each group and the propulsion speed; the setting of the soil bin pressure; the adjustment of parameters such as foaming agent; Shield tail grease, lithium base grease consumption control, etc.
所述步骤5中实时控制土仓内的压力稳定平衡包括以下步骤:In the
S51:设置土仓内土压力值为P,取得静水压力和地层土压力之和为P0,满足P=K*P0,土仓压力通过采取设定掘进速度、调整排土量或设定排土量、调整掘进速度两种方法建立,并应维持切削土量与排土量的平衡,以使土仓内的压力稳定平衡,以上K值介于1.0~3.0;S51: Set the soil pressure value in the soil bin as P, obtain the sum of the hydrostatic pressure and the stratum soil pressure as P0, and satisfy P=K*P 0 . Two methods of soil volume and adjustment of driving speed should be established, and the balance of cutting soil volume and soil discharge volume should be maintained, so that the pressure in the soil bin can be stably balanced. The above K value is between 1.0 and 3.0;
S52:采用至少一条螺旋输送机出渣,同时,控制土仓左右压力实现土压平衡,控制地表沉降。S52: Use at least one screw conveyor to discharge slag, and at the same time, control the pressure on the left and right sides of the soil bin to achieve earth pressure balance and control the surface settlement.
步骤S6:在砂性土流动性差的地层添加泡沫剂、膨润土等改善碴土的止水性,使土仓内的压力稳定平衡。Step S6: adding foaming agent, bentonite, etc. to the stratum with poor fluidity of sandy soil to improve the water stoppage of the ballast soil, so as to stabilize the pressure in the soil bin.
S53:根据地质条件、排出的碴土状态,以及盾构机的各项工作状态参数,动态调整盾构机掘进速度和出土量的平衡来控制土仓压力,通过调整螺旋输送机的转速来调节排土量。S53: According to the geological conditions, the state of the discharged ballast, and various working state parameters of the shield machine, dynamically adjust the balance of the shield machine’s tunneling speed and the amount of excavation to control the pressure of the soil bin, and adjust the speed of the screw conveyor to adjust soil discharge.
在盾构机掘进时,进行马蹄形盾构管片拼装,包括以下流程和要点:When the shield machine is excavating, the horseshoe-shaped shield segment is assembled, including the following procedures and points:
管片拼装工艺流程:基于按比例控制的马蹄形管片拼装机的伸缩、旋转和移动等功能,实现对管片拼装的精确定位。Segment assembly process: Based on the proportional control of the telescoping, rotating and moving functions of the horseshoe-shaped segment assembly machine, the precise positioning of the segment assembly is realized.
拼装要点:管片安装时安装司机、螺栓安装人员要就位,首先安装最下方一块管片,先连接纵向螺栓;由下到上左右对称安装剩余管片,随每块管片的安装将纵向螺栓及环向螺栓连接好并进行紧固;封顶块安装时,先搭接1/3,再径向插入,边调整位置边缓慢纵向顶推;整环管片全部安装完后,用风动搬手紧固所有螺栓;盾构掘进时,在上一个循环管片脱出盾尾后,及时以风动扳手对所有管片环纵向螺栓进行复紧。Assembly points: When installing the segment, the driver and bolt installer should be in place. First install the bottom segment and connect the longitudinal bolts first; install the remaining segments symmetrically from bottom to top, and install the longitudinal Bolts and annular bolts are connected and tightened; when the capping block is installed, first overlap 1/3, then insert it radially, and slowly push it longitudinally while adjusting the position; Tighten all the bolts by hand; when the shield is excavating, after the last circulating segment is out of the shield tail, use the pneumatic wrench to re-tighten all the longitudinal bolts of the segment ring in time.
所述步骤5中,在整个盾构掘进过程中,采用A料和B料同步注浆包括以下步骤:In the
步骤S1:通过注浆量与盾构机掘进时扰动地层范围的关系,确定充填系数为1.3~1.8;Step S1: According to the relationship between the grouting amount and the disturbed stratum range when the shield machine is excavating, the filling coefficient is determined to be 1.3-1.8;
步骤S2:将A料直接在搅拌站拌制时加入,同质量代替同步注浆砂浆中的水泥,B料在洞内溶解后导入储存罐中。Step S2: Add material A directly during mixing in the mixing station, replace the cement in the synchronous grouting mortar with the same quality, and introduce material B into the storage tank after dissolving in the hole.
步骤S3:对盾构机尾部的同步注浆管路进行改造,在盾构机尾部处使B溶液与含A料的砂浆充分混合,且通过计量泵使注入量及压力精确可控。Step S3: Renovate the synchronous grouting pipeline at the tail of the shield machine, fully mix the B solution with the mortar containing the A material at the tail of the shield machine, and accurately control the injection amount and pressure through the metering pump.
步骤S4:凝固一段时间后,其中AB料的比例根据砂浆配比中水泥的含量变化而随之改变,且初凝时间可通过调节AB料两者的比例来进行控制。初凝时间为15分钟左右。其中AB料的比例根据砂浆配比中水泥的含量变化而随之改变,且初凝时间可调节AB料两者的比例来进行控制,故在使用前,需根据当地气候、砂浆特性等方面实地进行调整。Step S4: After solidifying for a period of time, the proportion of AB material changes according to the change of the cement content in the mortar ratio, and the initial setting time can be controlled by adjusting the proportion of the two materials. The initial setting time is about 15 minutes. Among them, the proportion of AB material changes according to the content of cement in the mortar ratio, and the initial setting time can be controlled by adjusting the proportion of AB materials. make adjustments.
根据多次试验,在本工程中选用浆液效果最佳配合比(kg):According to many tests, the best mix ratio (kg) of the slurry effect is selected in this project:
水泥:粉煤灰:膨润土:砂:水:A料:B料(与水1:1溶解)=185:350:50:800:460:15:30;Cement: fly ash: bentonite: sand: water: material A: material B (dissolved with water 1:1) = 185:350:50:800:460:15:30;
对土仓和出土口改造包括如下:The renovation of earth bins and excavation openings includes the following:
在土仓底部5、7点钟位置增加圆锥形分碴器,破坏此处掌子面硬结土体;Add a conical ballast divider at the 5 and 7 o'clock positions at the bottom of the soil bin to destroy the hardened soil on the face here;
为防止碴土在5号刀盘16中心旋转轴下部集结,取消10、11号搅拌器,并在原搅拌器中间位置增加大型分碴器,便于碴土直接溜到螺旋输送机口,保证出土顺畅。In order to prevent the ballast soil from accumulating at the lower part of the center rotating shaft of the No. 5
在盾构机掘进时,对刀盘改造,对五号刀盘16和六号刀盘17每个单边扩挖300mm,中间的一号刀盘18需要将刀梁进行割除,然后用封板将刀梁缺口封堵。When the shield machine is excavating, the cutter head is modified, and the No. 5
五号刀盘16改造:将刀梁加长;在刀梁上焊接刀具;将中心五方的斜梁割除,并焊接新斜梁;No. 5
一号刀盘18的改造:割除干涉的刀梁,将泡沫管封堵,将刀梁缺口封堵;Reconstruction of No. 1 cutter head 18: cut off the interfering cutter beam, plug the foam tube, and seal the gap of the cutter beam;
四号刀盘19和六号刀盘20改造,将刀梁加长,在刀梁上焊接刮刀,增加四号刀盘19、五号刀盘16和六号刀盘20的开挖直径。No. 4 cutter head 19 and No. 6 cutter head 20 were modified, the cutter beam was lengthened, scrapers were welded on the cutter beam, and the excavation diameter of No. 4 cutter head 19, No. 5
在土仓底部增加圆锥形分碴器,破坏此处掌子面硬结土体,在刀盘盲区中设置高压水管。A conical ballast divider is added at the bottom of the soil bin to destroy the hardened soil body on the face here, and a high-pressure water pipe is installed in the blind area of the cutter head.
利用刀盘盲区中设置高压水管,利用高压水冲刷盲区土体,使之分散塌落。同时辅以渣土改良措施,详见渣土改良部分。Use high-pressure water pipes in the blind area of the cutter head, and use high-pressure water to wash the soil in the blind area to disperse and collapse. At the same time, supplemented by muck improvement measures, see the muck improvement section for details.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810446543.4A CN108661655B (en) | 2018-05-11 | 2018-05-11 | Large-section U-shaped earth pressure balance shield tunnel construction method based on U-shaped shield machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810446543.4A CN108661655B (en) | 2018-05-11 | 2018-05-11 | Large-section U-shaped earth pressure balance shield tunnel construction method based on U-shaped shield machine |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108661655A CN108661655A (en) | 2018-10-16 |
CN108661655B true CN108661655B (en) | 2020-03-17 |
Family
ID=63779080
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810446543.4A Expired - Fee Related CN108661655B (en) | 2018-05-11 | 2018-05-11 | Large-section U-shaped earth pressure balance shield tunnel construction method based on U-shaped shield machine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108661655B (en) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109236305A (en) * | 2018-10-26 | 2019-01-18 | 中铁第勘察设计院集团有限公司 | Shield sky is pushed away through bored tunnel and the secondary construction method and its structure originated |
CN109707388B (en) * | 2019-01-07 | 2024-02-06 | 中铁十一局集团城市轨道工程有限公司 | Method for preventing ground collapse when shield tunneling machine starts to pass through existing shield tunnel |
CN110242331B (en) * | 2019-07-29 | 2024-03-26 | 西南交通大学 | Anti-floating device for shield tunnel and method for assisting segment lining ring anti-floating by adopting anti-floating device |
CN111058860A (en) * | 2019-12-10 | 2020-04-24 | 中铁十四局集团隧道工程有限公司 | Cave opening construction method |
CN111350509B (en) * | 2020-01-21 | 2025-03-07 | 中铁二十二局集团轨道工程有限公司 | A method for improving and grouting slag in shield construction of sandy gravel strata tunnel |
CN111794780A (en) * | 2020-03-31 | 2020-10-20 | 中铁十六局集团北京轨道交通工程建设有限公司 | Shield tunneling machine in-out hole safety guarantee method for water-rich round gravel stratum |
CN112049650B (en) * | 2020-09-16 | 2022-07-15 | 中国铁路设计集团有限公司 | Method for expanding and excavating existing small shield tunnel by using large shield |
CN112412481A (en) * | 2020-12-17 | 2021-02-26 | 中铁二十二局集团轨道工程有限公司 | Starting method of shield special-shaped extension steel ring |
CN114370286B (en) * | 2021-12-08 | 2024-06-04 | 上海市基础工程集团有限公司 | Safety hole entering method of shield machine for open caisson structure |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102767379A (en) * | 2012-08-10 | 2012-11-07 | 中国建筑第四工程局有限公司 | Shallow-buried unsymmetrical pressure section tunnel drilling construction method |
CN107575239A (en) * | 2017-10-16 | 2018-01-12 | 粤水电轨道交通建设有限公司 | A kind of portable shield launching device for small space |
CN107676097A (en) * | 2017-08-27 | 2018-02-09 | 中铁十二局集团有限公司 | A kind of high hydraulic pressure soft soil layer HFE composite shield originating methods |
CN107747488A (en) * | 2017-10-13 | 2018-03-02 | 中铁四局集团第四工程有限公司 | The construction method of big cross section shape of a hoof shield launching |
-
2018
- 2018-05-11 CN CN201810446543.4A patent/CN108661655B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102767379A (en) * | 2012-08-10 | 2012-11-07 | 中国建筑第四工程局有限公司 | Shallow-buried unsymmetrical pressure section tunnel drilling construction method |
CN107676097A (en) * | 2017-08-27 | 2018-02-09 | 中铁十二局集团有限公司 | A kind of high hydraulic pressure soft soil layer HFE composite shield originating methods |
CN107747488A (en) * | 2017-10-13 | 2018-03-02 | 中铁四局集团第四工程有限公司 | The construction method of big cross section shape of a hoof shield launching |
CN107575239A (en) * | 2017-10-16 | 2018-01-12 | 粤水电轨道交通建设有限公司 | A kind of portable shield launching device for small space |
Also Published As
Publication number | Publication date |
---|---|
CN108661655A (en) | 2018-10-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108661655B (en) | Large-section U-shaped earth pressure balance shield tunnel construction method based on U-shaped shield machine | |
CN100501124C (en) | The construction method of the connecting channel of the tunnel in the shield section of the subway | |
CN103306687B (en) | Soft rock tunnel long cantilever horizontal jet grouting Deformation control construction method | |
CN109595004B (en) | Tunnel two-expansion four-expansion excavation method | |
JP7257086B2 (en) | Comprehensive Construction Method for Low Overburden Sections of Tunnels | |
CN113669073B (en) | Construction method for controlling adjacent building deformation of water-rich sandy stratum by tunneling before station | |
CN105822312A (en) | Construction method for earth pressure balance shield construction pressure launching in subway tunnel engineering | |
CN105804758A (en) | Shallow-earthing, large-section and small-distance construction method for rectangular pipe jacking overpass subway tunnel | |
WO2020259059A1 (en) | Tbm parallel heading tunnel trunk construction method | |
CN108691552B (en) | Construction method of receiving large-section horseshoe-shaped shield cutting | |
CN101929340A (en) | Pre-grouting advance support construction process for pipe shed of underground flat inclined roadway of coal mine | |
CN110080789A (en) | A kind of shield sky, which pushes away, spells section of jurisdiction construction | |
CN113107501B (en) | A Construction Method of Excavation Excavation by Extending the Steel Ring of the Portal | |
CN109578035A (en) | Steel pipe draining lock foot stake and construction method | |
CN113847050A (en) | Construction method of extra-long highway tunnel in lava mountain area | |
CN112145203A (en) | Full-face advancing type sectional grouting construction method and overlapped tunnel construction method | |
CN104453915B (en) | Big cross section vertical shaft pre-pouring grout reinforces Rapid Excavation method | |
CN113216975B (en) | Construction method for ventilation raise to pass through complex water-rich broken zone in mining area | |
CN113137235B (en) | Construction method of high-ground-stress soft rock extrusion large-deformation tunnel | |
CN112177635A (en) | Construction method of step multiple advanced small guide pipe and construction method of overlapped tunnel | |
CN109505612A (en) | Big descending bored tunnel shield sky selection structure and construction technology | |
CN109973115B (en) | Construction method for drainage of vault of tunnel in karst area | |
CN108049876A (en) | A kind of construction method of compound stratum tunneling close range down bored tunnel | |
CN118292891A (en) | Double-side proximity bias tunnel bad geological section hole entering construction method | |
CN110985017A (en) | Construction method for penetrating rainwater box culvert under expansive soil stratum shield |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20191021 Address after: Wangjiang Road in Baohe District of Hefei city of Anhui Province, No. 96 230022 Applicant after: CHINA TIESIJU CIVIL ENGINEERING GROUP Co.,Ltd. Applicant after: MENGXI HUAZHONG RAILWAY CO.,LTD. Applicant after: SOUTHWEST JIAOTONG University Address before: Wangjiang Road in Baohe District of Hefei city of Anhui Province, No. 96 230022 Applicant before: CHINA TIESIJU CIVIL ENGINEERING GROUP Co.,Ltd. Applicant before: Southwest Jiaotong University |
|
TA01 | Transfer of patent application right | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200317 Termination date: 20210511 |
|
CF01 | Termination of patent right due to non-payment of annual fee |