CN108457504A - A kind of building method of BIM assembly integrated intelligents substation - Google Patents

A kind of building method of BIM assembly integrated intelligents substation Download PDF

Info

Publication number
CN108457504A
CN108457504A CN201810259854.XA CN201810259854A CN108457504A CN 108457504 A CN108457504 A CN 108457504A CN 201810259854 A CN201810259854 A CN 201810259854A CN 108457504 A CN108457504 A CN 108457504A
Authority
CN
China
Prior art keywords
substation
construction
bim
building method
assembly integrated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810259854.XA
Other languages
Chinese (zh)
Inventor
陈伟其
刘风桐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiangneng Chutian Power Technology Co., Ltd.
Original Assignee
Xiang Neng Chutian Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiang Neng Chutian Electric Power Co Ltd filed Critical Xiang Neng Chutian Electric Power Co Ltd
Priority to CN201810259854.XA priority Critical patent/CN108457504A/en
Publication of CN108457504A publication Critical patent/CN108457504A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
    • E04H5/04Transformer houses; Substations or switchgear houses

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Power Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application discloses a kind of building method of BIM assembly integrated intelligents substation, including:Early period is designed, and design early period is specially that substation's agent structure, equipment built-in fitting and related pipeline are designed as modularization prefabricated components;Modularization prefabricated components are prefabricated in the factory, and it is pre-buried after the completion of transport to construction site;Prefabricated components assembly is carried out in construction site, completes substation's main structure construction;Wherein, BIM assembles the electrical construction progress synchronous with civil construction of integrated intelligent substation.The building method of BIM assembly integrated intelligents provided by the present application substation, the pipelining of manufacturer's standard part, batch production assembly or assembled in situ can be achieved, it breaks through conventional substation and builds thinking, reach construction, O&M, service standardization, high efficiency, compared with prior art, it is not only able to significantly shorten the construction period, and reduces construction site airborne dust, noise is reduced, to creating energy saving building, green building site plays good facilitation.

Description

A kind of building method of BIM assembly integrated intelligents substation
Technical field
This application involves substation's integrated suppliers technical fields, and more specifically more particularly to a kind of BIM assembly integrates intelligence The building method of energy substation.
Background technology
Substation is the place for changing voltage, for electrical energy transportation that power plant is issued to place farther out, it is necessary to Voltage is increased, high-voltage electricity is become, nearby voltage is reduced on demand again to user, substation is leaned in the work of this buck/boost To complete.
Intelligent substation includes mainly intelligent high-voltage equipment and substation's integration information platform two parts.Intelligent high-voltage equipment Include mainly intelligent transformer, Intelligent high voltage switch device, electronic mutual inductor etc..Intelligent transformer is with control system by logical Believe that optical fiber is connected, transformer state parameter and operation data can be grasped in time.When the method for operation changes, equipment is according to being Voltage, the power situation of system decide whether to adjust tap;When equipment when something goes wrong, early warning can be sent out and provide state ginseng Number etc. reduces operational management cost to a certain extent, reduces hidden danger, improves transformer station high-voltage side bus reliability.
Intelligent high voltage switch device is the switchgear and control device for having superior performance, equipped with electronic equipment, sensing Device and actuator have monitoring and diagnostic function.Electronic mutual inductor refers to pure optical fiber mutual inductor, magneto-optic glass mutual inductor etc., The shortcomings that conventional electromagnetic mutual inductor can effectively be overcome.There are two substation's integration information platform functions, first, system is laterally believed Breath is shared, is mainly shown as in management system that various upper layer applications unitize to information acquisition;Second is that system longitudinal direction information Standardization, is mainly shown as the transparence that each layer supports its upper layer application.
As its name suggests, intelligent substation is exactly that imaging people is in substation to adjust equally, when low-voltage load amount increases Substation sends out the electricity for meeting and increasing load, and when low-voltage load amount reduces, substation sends out electricity and reduces therewith, it is ensured that Save the energy.Intelligent substation is mainly made of mechanical floor, system layer, and three sides are embodied in traditional substation's maximum differential Face:Primary equipment intelligence, overhaul of the equipments conditioning and secondary device networking.
It is long in time limit, construction efficiency is low currently, the construction of intelligent substation will not only expend a large amount of manpower and materials, and consume Can be big, it is unfavorable for environmental protection.
Therefore it provides a kind of high efficiency, can save the duration, environmental protection and energy saving BIM assembly integrated intelligent substation construction Method leads industrialization house to build, has become those skilled in the art's technical problem urgently to be resolved hurrily.
Invention content
In order to solve the above technical problems, the application provide a kind of high efficiency, can save the duration, environmental protection and energy saving BIM assembly The building method of integrated intelligent substation.
Technical solution provided by the present application is as follows:
A kind of building method of BIM assembly integrated intelligents substation, includes the following steps:Early period is designed, design early period tool Body is that substation's agent structure, equipment built-in fitting and related pipeline are designed as modularization prefabricated components;
Modularization prefabricated components are prefabricated in the factory, and it is pre-buried after the completion of transport to construction site;
Prefabricated components assembly is carried out in construction site, completes substation's main structure construction;
Wherein, BIM assembles the electrical construction progress synchronous with civil construction of integrated intelligent substation.
Further, in a kind of preferred mode of the present invention, BIM assembles the electrical construction and soil of integrated intelligent substation It builds construction and synchronizes and be specially:BIM assembles the agent structure modular assembly construction of integrated intelligent substation, indoor dry wall Plate installation, construction electrical equipment installation progress synchronous with cable threading.
Further, in a kind of preferred mode of the present invention, substation's agent structure includes:Cylinder, beam body, floor, Inside and outside wall board modular structure.
Further, in a kind of preferred mode of the present invention, BIM assembles the electrical construction and soil of integrated intelligent substation It builds construction and synchronizes and be specially:The prefabricated transport after the completion in factory by cylinder, beam body, floor, inside and outside wall board modular structure It is assembled to construction site;
The various related spools that BIM assembly integrated intelligent substation needs are embedded in respective modules component, and with it is right The reinforcing bar in modular structure is answered to offset one from another;
In, with modular structure pouring molding simultaneously, while the disengaging of corresponding related pipeline being arranged on modular structure in factory Mouthful;
Equipment built-in fitting is embedded in respective modules component and is fixed with the bar connecting in respective modules in advance, and in work Pouring molding to improve pre-buried precision and improves the bonding strength of equipment built-in fitting simultaneously with modular structure in factory.
Further, it in a kind of preferred mode of the present invention, is produced cylinder, beam body, floor, inner-outer wall in precast plant The same period of template die module component also carries out the operation of painting wall, window frame installation exercise and face brick paving.
Further, in a kind of preferred mode of the present invention, window frame, facing tile, embedded thermal insulation material with it is prefabricated Concrete members pour simultaneously, are formed whole.
Further, in a kind of preferred mode of the present invention, carrying out the production of modularization prefabricated components in factory is specially: Make size, variform PC steel molds;Make steel reinforcement cage in PC;It is pre- to be laid with finishing material;It is placed in built-in fitting;Inspection is tested It receives;Casting concrete;It checks again for being transported to building site by building site progress entrucking after qualification.
Further, further include step after step " casting concrete " in a kind of preferred mode of the present invention:Into Row type concrete steam maintenance is handled.
Further, in a kind of preferred mode of the present invention, carrying out type concrete steam maintenance processing is specially:Steam is supported Shield 6~9 hours, demoulds after concrete strength reaches 70%.
Further, in a kind of preferred mode of the present invention, the building method of BIM assembly integrated intelligents substation includes Following construction process:Early-stage preparations;By design prefabrication;Site operation prepares;The lifting of first floor floor, first floor equipment hoisting, First floor metope lifts;Two layers of floor lifting, two layers of ground lifting, synchronous first floor multiple line;Two-layer equipment lifting, two layers of metope are hung Dress, two layers of top plate lifting, synchronous two layers of multiple line;Main component is checked and accepted;Synchronous electrical apparatus interstar connection;Power engineering is tested and is tested It receives;Final acceptance of construction.
A kind of building method of BIM assembly integrated intelligents substation provided by the invention, compared with prior art, the present invention The building method for the BIM assembly integrated intelligents substation being related to includes the following steps:By substation's agent structure, equipment built-in fitting And related pipeline is designed as modularization prefabricated components, and modularization prefabricated components are prefabricated in the factory, and pre-buried transport after the completion To construction site, prefabricated components assembly is carried out in construction site, completes substation's main structure construction;Wherein, BIM assembly is integrated The electrical construction of intelligent substation is synchronous with civil construction to carry out, realize manufacturer's standard part pipelining, batch production assembly or Assembled in situ breaks through conventional substation and builds thinking, reaches construction, O&M, service standardization, high efficiency, with prior art phase Than being not only able to significantly shorten the construction period, and reduce construction site airborne dust, reducing noise, played to creating green building site Good facilitation.
Specific implementation mode
In order to make those skilled in the art more fully understand the technical solution in the application, the application will be implemented below Technical solution in example is clearly and completely described, it is clear that described embodiment is only that the part of the application is implemented Example, instead of all the embodiments.Based on the embodiment in the application, those of ordinary skill in the art are not making creativeness The every other embodiment obtained under the premise of labour, shall fall in the protection scope of this application.
The embodiment of the present invention provides a kind of building method of BIM assembly integrated intelligents substation, including:Early period is designed, preceding Phase design is specially that substation's agent structure, equipment built-in fitting and related pipeline are designed as modularization prefabricated components;
Modularization prefabricated components are prefabricated in the factory, and it is pre-buried after the completion of transport to construction site;
Prefabricated components assembly is carried out in construction site, completes substation's main structure construction;
Wherein, BIM assembles the electrical construction progress synchronous with civil construction of integrated intelligent substation.
The building method of BIM assembly integrated intelligents provided in an embodiment of the present invention substation, compared with prior art, this hair The building method for the BIM assembly integrated intelligents substation that bright embodiment is related to includes the following steps:By substation's agent structure, set Standby built-in fitting and related pipeline are designed as modularization prefabricated components, modularization prefabricated components are prefabricated in the factory, and pre-buried complete At rear transport to construction site, prefabricated components assembly is carried out in construction site, completes substation's main structure construction;Wherein, BIM The electrical construction progress synchronous with civil construction for assembling integrated intelligent substation, realizes the pipelining of manufacturer's standard part, factory Makeup is matched or assembled in situ, is broken through conventional substation and is built thinking, reaches construction, O&M, service standardization, high efficiency, and existing There is technology to compare, be not only able to significantly shorten the construction period, and reduce construction site airborne dust, reduce noise, to creating green work Ground plays good facilitation.
In the embodiment of the present invention, the electrical construction progress synchronous with civil construction that BIM assembles integrated intelligent substation is specific For:The agent structure modular assembly construction of BIM assembly integrated intelligents substation, indoor prefabricated panel installation, construction are electrically set It is standby that carry out synchronous with cable threading is installed.
Specifically, in embodiments of the present invention, substation's agent structure includes:Cylinder, beam body, floor, inner-outer wall template die Module component.
Specifically, in embodiments of the present invention, the electrical construction of BIM assembly integrated intelligents substation is synchronous with civil construction It is specially:By cylinder, beam body, floor, inside and outside wall board modular structure in factory it is prefabricated after the completion of transport to construction site It is assembled;
The various related spools that BIM assembly integrated intelligent substation needs are embedded in respective modules component, and with it is right The reinforcing bar in modular structure is answered to offset one from another;
In, with modular structure pouring molding simultaneously, while the disengaging of corresponding related pipeline being arranged on modular structure in factory Mouthful;
Equipment built-in fitting is embedded in respective modules component and is fixed with the bar connecting in respective modules in advance, and in work Pouring molding to improve pre-buried precision and improves the bonding strength of equipment built-in fitting simultaneously with modular structure in factory.
Wherein, the prefabricated components of columnar part are preferably poured by pump high strength concrete, in embodiments of the present invention The special pump high strength concrete provided includes following component:Cementitious material, fine aggregate, coarse aggregate, polycarboxylate high performance subtract The unit weight of aqua and water, concrete is 2400 kilograms per cubic meter~2600 kilograms per cubic meter, is gelled in every cubic meter of concrete The dosage of material is 350kg~4500kg, and water-cement ratio is 0.25~0.35, and sand coarse aggregate ratio 40%-46%, polycarboxylate high performance subtracts The solid volume of aqua is the 0.3%~0.4% of the cementitious material weight.
Specifically, cementitious material is the mixture of cement or cement with admixture according to 1: 0.5 composition.
Specifically, admixture is levigate sand.
Can certainly be that admixture is any one or more in miberal powder or flyash.
Column member is poured using high-strength concrete provided in this embodiment, the compaction rate of cylinder significantly improves, Intensity and durability are significantly improved.
Wherein, include step during inside and outside wall board modular structure prefabricated construction:Concrete mixing;Concreting;It is mixed Solidifying soil surface is heat-insulated.
Specifically, in embodiments of the present invention, concrete mixing is mixed using the raw material of following parts by weight as concrete Close raw material:32~38 parts of portland cement, 16~28 parts of flyash, 4~6 parts of water-reducing agent, 4~6 parts of retarder, air entraining agent 4~6 Part, 5~8 parts of swelling agent, 8~10 parts of plasticiser, 70~90 parts of rubble, 80~90 parts of sand, mix after mixing, water ash when mix Than being 0.4~0.6, mix temperature is 6~7 DEG C;
Specifically, in embodiments of the present invention, casting process carries out concrete vibrating, placement layer by layer and vibrates.
Specifically, in embodiments of the present invention, concrete surface is heat-insulated specifically, concrete overlying plastics after pouring Film sprays plastic foil cooling by cold water, and cold water temperature is 12~14 DEG C, is sprayed 70~90 minutes every time.In this way, concrete pours Internal-external temperature difference after building is small, and the flyash and water-reducing agent added during concrete mixing can reduce cement consumption, reduces The endurance of the heat expansion of concrete, the prefabricated components such as floor, inside and outside wall board is improved.
Specifically, in the present embodiment of the present invention, exterior wall prefabricated components embed thermal insulation material, have self-heat conserving performance, by It is produced in batches in precast plant in prefabricated components, reduces engineering site wet construction, reduce airborne dust, reduce noise, to creating Green building site plays good facilitation.
Wherein, it is prefabricated in the factory during floor member, the component and part ratio of prefabrication cast-in-place concrete floor is: Silicon cement:320~340 parts;80~88 parts of flyash;760~800 parts of sand;960~1000 parts of stone;180~220 parts of water;HX is multiple Close 9 parts of pumping admixture.
It is significantly dropped according to the incidence of the floor member that scheme provided in this embodiment is poured, micro-crack Low, floor strength improves, and is transporting and can keep preferable globality in hoisting process, is being readily transported, to be conducive to improve Later stage efficiency of assembling.
In embodiments of the present invention, it can realize that substation is various by concrete slab block transforms different location and use function Design, concrete slab load module can be needed to carry out according to production it is vertical or laterally from changed by combination, formed one big Concrete slab module load module, can carry out being decomposed to form standalone feature fit drawing die according to function, geographical environment etc. is used Block, to achieve the effect that save duration, environmental protection and energy saving.
In the embodiment of the present invention, in precast plant's production by cylinder, the same period of beam body, floor, inside and outside wall board modular structure, also Carry out the operation of painting wall, window frame installation exercise and face brick paving.
Specifically, in embodiments of the present invention, window frame, facing tile, embedded thermal insulation material and prefabricated components concrete It pours, is formed whole simultaneously.
Specifically, in embodiments of the present invention, carrying out the production of modularization prefabricated components in factory is specially:Making size, Variform PC steel molds;Make steel reinforcement cage in PC;It is pre- to be laid with finishing material;It is placed in built-in fitting;Inspection is checked and accepted;Pour coagulation Soil;It checks again for being transported to building site by building site progress entrucking after qualification.In embodiments of the present invention, prefabricated components precast plant into While row mass production, by wall plastering, heat preservation, the work such as window frame installation, face brick paving are completed, are effectively shortened Construction period saves time cost, improves construction efficiency.
Further include step after step " casting concrete " in the embodiment of the present invention:It carries out at type concrete steam maintenance Reason.
Specifically, in embodiments of the present invention, carrying out type concrete steam maintenance processing is specially:Steam curing 6~9 is small When, it is demoulded after concrete strength reaches 70%.
In the embodiment of the present invention, the construction process of the building method of BIM assembly integrated intelligents substation is:Early-stage preparations; By design prefabrication;Site operation prepares;The lifting of first floor floor, the lifting of first floor equipment hoisting, first floor metope;It hangs on two layers of floor Dress, two layers of ground lifting, synchronous first floor multiple line;Two-layer equipment lifting, two layers of metope lifting, two layers of top plate lifting, synchronous two Layer multiple line;Main component is checked and accepted;Synchronous electrical apparatus interstar connection;Power engineering is tested and is checked and accepted;Final acceptance of construction.
In the building method of BIM provided in this embodiment assembly integrated intelligents substation, prefabricated components construction technology is logical It crosses using production plant, lifting device, assembly node processing standardization, specialized " four change " management measure of construction team, Construction quality is set to obtain powerful guarantee, while because window frame, facing tile, embedded thermal insulation material and prefabricated component concrete pour simultaneously It builds, forms entirety, avoid the generation in relation to common quality defect.
It should be noted that in the building method of BIM provided in this embodiment assembly integrated intelligents substation, prefabricated structure The weight of part is not preferably greater than 8 tons generally, and width is no more than 2.4m, is such as more than dimensions above highly no more than 3.2m, it will The increase of larger difficulty and cost is brought to construction, therefore prefabricated component type, model should not be excessive, in the less situation of house type type Under, preferably unify to less than 40 kinds templates, self-control may be used from safe operation platform is risen, without setting up scaffold, platform is adopted With the more temporary construction measure such as steel form, the share the expenses of temporary facility is reduced, it is cost-effective to reduce cost.
It should be noted that prefabricated component integrated biological pond system refers to promote industrialization, guiding low-carbon building The mode of construction of construction and technology makes every effort to the new way and the new mould of site operation of finding low-carbon mode and housing industrialization construction Formula.As the approach for realizing low-carbon mode, green construction, the construction of BIM assembly integrated intelligents provided in this embodiment substation Method embodies sustainable development idea in advance, is to overturn traditional construction method, with prefabricated component construction technology Ripe and all-round popularization, cost will be lower and lower, using the construction of BIM provided in this embodiment assembly integrated intelligents substation Method is not only able to significantly shorten the construction period, saves production cost, and reduces construction site airborne dust, reduces noise, to creating Energy saving building, green building site play the role of greatly facilitating.
The embodiment of the present invention further relate to it is a kind of BIM threedimensional models are combined with operation management system, design one kind be based on The BIM intelligent substation operation management systems of BIM technology build " internet+electric power O&M " information system management platform, promote generation Safeguard service quality, reduction substation maintenance work amoun, raising maintenance work efficiency, the operation management standardization of realization substation, O&M process standard, operation/maintenance data electronization, O&M analysis science, the shortcomings that overcoming traditional operation management system, are realized Intuitive information system management keeps manager clear, effectively, intuitively effectively managed space resources.
The embodiment of the present invention by BIM intelligent substation operation management systems, including:
Data collection layer, for acquiring Project Management Information and space measurement information;
Communication network layer, including LAN, VPN private networks or common network;
Data resource layer, data resource layer include BIM models, are stored in public cloud, private clound and mixed cloud, wherein BIM Model includes BIM integrated databases.
Include BIM engineering management platform and data interchange platform using supporting layer using supporting layer;
Service application layer, service application layer include BIM information inquiries, process of construction BIM management and the output of BIM information.
In addition, in embodiments of the present invention, also providing the application process of BIM intelligent substation operation management systems, specifically Including data acquisition, data processing and data application three parts.
Wherein, data, which acquire, includes:It is surveyed from construction site and the collected Project Management Information of construction participant and space Information is measured, Project Management Information includes basic management data, Budgetary Estimates data, engineering contract data, engineering progress data, work Journey qualitative data;Space measurement information includes terrain data, engineering design data, project planning data;Collected data warp It is sent to the BIM models in data resource layer by LAN, VPN private networks or common network after the reorganization of construction participant or arrangement In.
Wherein, data processing includes:Project Management Information and space measurement use of information cloud computing of the BIM models to acquisition Overall process is checked oneself, is checked, is transmitted, audited and is put in storage with big data technology;Space measurement information is in BIM engineering management platforms Start to be digitized processing before applying, information system is two-dimensionally or three-dimensionally managed in generation, and engineering is carried out based on reality environment Planning, budgetary estimate, the processing of contract, progress, quality service;When carrying out the load of space measurement information, it is excellent to carry out corresponding data Change to improve the efficiency and bandwagon effect of system operation;For the Project Management Information that Process of Engineering Construction generates, according to business Management ownership establishes taxonomy database, and establishes the service logic relationship between data, and assigns data mode property parameters, with Support the relationship type analysis of the independent process and interaction of all kinds of management business.
Wherein, data application includes:BIM information inquiries, process of construction BIM management and the output of BIM information.
BIM information inquiries include:Based on BIM engineering management platforms, using multimedia technology as means, inquiry BIM processes letter Breath and/or BIM spatial informations.
Process of construction BIM is managed:Implementation management relation management, engineering data management, project planning management, engineering are built If progress control, construction quality process management, Budgetary Estimates control management, engineering contract classification, control management;Each operation system Required data source carries out corresponding business processing in BIM integrated databases, according to Process of Engineering Construction management business ownership, and leads to It crosses BIM engineering management platform environments and carries out process of construction information or achievements exhibition, generate various management of engineering construction schemes, carry out Scheme comparison or amount point counting analysis.
BIM information exports:BIM engineering management platforms provide the data output of multiple format, are organized for construction unit Engineering project final acceptance of construction and operational management unit, engineering R&D institution, superior administrative unit and public user provide Initial data, process management data and spatial data product.
Specifically, in embodiments of the present invention, platform hardware network infrastructure development includes mainly that platform building is required Database server, application server, storage device, optical fiber switch etc. also may be selected rental cloud platform and built certainly.
Specifically, in embodiments of the present invention, it includes mainly O&M industry that the operation management software platform based on SAAS, which is built, Business, the construction of three big sub-platform of back-stage management and the mandate of frequency platform;O&M business includes mainly equipment-patrolling, overhaul management, double vote The 19 big function modules such as management;Back-stage management mainly includes the construction in universal standard library, template library;Platform mandate is mainly completed Platform feature mandate to different members.
Specifically, in embodiments of the present invention, BIM intelligent substations operation management platform supports mobile APP O&Ms, supports Substation's operation maintenance personnel carries out substation by tablet computer, mobile phone and moves O&M business.
It should be noted that the master-plan of BIM intelligent substation operation management platform projects includes mainly:System of systems Structure design and hardware net topology design two parts.
Wherein, architecture Design includes:Operation management platform uses n-layer B/S frameworks, follows MVC design pattern;Basis Service layer is made of server resource, storage resource and Internet resources;Data service layer provides shared data service for platform, by The compositions such as device databases, standard database, template database, Test database;Application service layer provides soft for platform user Part service, such as make an inspection tour management, double vote management, overhaul management etc.;Platform client supports PC, various tablet computers, mobile phone etc. Terminal.
Wherein, hardware net topology design required service device resource includes:Application server 1;Database server 1 Platform;2 sets of server OS software.
Server configuration requirement is as follows:
Database server configuration instruction:Processor is IntelXeonE5-2630 V5;Processor quantity is 4;Memory For 8 × 8GDDR4,2133MHz;Hard-disk capacity:2×500G10KRPM2.5;RAID card:Support RAID0,1,10,5,50;Net Network:4 gigabit Ethernet mouths;CD-ROM drive type is DVD;Power supply is single supply.
Application server configuration explanation:Processor is IntelXeonE5-2630 V5;Processor quantity is 4;Memory:8 × 8GDDR4,2133MHz, hard-disk capacity:2×500G10KRPM2.5;RAID card:Support RAID0,1,10,5,50;Network:4 A gigabit Ethernet mouth;CD-ROM drive type is DVD;Power supply is single supply.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest range caused.

Claims (10)

1. a kind of building method of BIM assembly integrated intelligents substation, which is characterized in that include the following steps:
Early period is designed, and design early period is specially to be designed as substation's agent structure, equipment built-in fitting and related pipeline Modularization prefabricated components;
The modularization prefabricated components are prefabricated in the factory, and it is pre-buried after the completion of transport to construction site;
Prefabricated components assembly is carried out in construction site, completes substation's main structure construction;
Wherein, the electrical construction of BIM assembly integrated intelligents substation is synchronous with civil construction carries out.
2. the building method of BIM assembly integrated intelligents according to claim 1 substation, which is characterized in that BIM assembly collection At intelligent substation electrical construction and civil construction synchronize be specially:The master of BIM assembly integrated intelligents substation Body structural module assembly construction, indoor prefabricated panel, which are installed, construction electrical equipment installation is synchronous with cable threading carries out.
3. the building method of BIM assembly integrated intelligents according to claim 2 substation, which is characterized in that the power transformation Agent structure of standing includes:Cylinder, beam body, floor, inside and outside wall board modular structure.
4. the building method of BIM assembly integrated intelligents according to claim 2 substation, which is characterized in that BIM assembly collection At intelligent substation electrical construction and civil construction synchronize be specially:By cylinder, beam body, floor, inside and outside wall board module Transport to construction site is assembled after the completion of component is prefabricated in factory;
The various related spools that BIM assembly integrated intelligent substation needs are embedded in respective modules component, and with corresponding mould Reinforcing bar in module component offsets one from another;
In, with modular structure pouring molding simultaneously, while the inlet and outlet of corresponding related pipeline being arranged on modular structure in factory;
Equipment built-in fitting is embedded in respective modules component and is fixed with the bar connecting in respective modules in advance, and in factory Pouring molding to improve pre-buried precision and improves the bonding strength of equipment built-in fitting simultaneously with modular structure.
5. the building method of BIM assembly integrated intelligents according to claim 4 substation, which is characterized in that in precast plant Produce cylinder, beam body, floor, inside and outside wall board modular structure the same period, also carry out painting wall operation, window frame installation exercise and Face brick paving.
6. the building method of BIM assembly integrated intelligents according to claim 5 substation, which is characterized in that window frame, exterior wall Face brick, embedded thermal insulation material and prefabricated components concrete pour simultaneously, are formed whole.
7. the building method of BIM according to claim 1 assembly integrated intelligent substation, which is characterized in that factory into Row modularization prefabricated components produce:Make size, variform PC steel molds;Make steel reinforcement cage in PC;It is pre- to be laid with Finishing material;It is placed in built-in fitting;Inspection is checked and accepted;Casting concrete;It checks again for being transported to work by building site progress entrucking after qualification Ground.
8. the building method of BIM assembly integrated intelligents according to claim 7 substation, which is characterized in that " poured in step Build concrete " further include later step:Carry out type concrete steam maintenance processing.
9. the building method of BIM assembly integrated intelligents according to claim 8 substation, which is characterized in that carry out coagulation Native steam curing is handled:Steam curing 6~9 hours, demoulds after concrete strength reaches 70%.
10. the building method of BIM assembly integrated intelligents according to claim 1 substation, which is characterized in that the BIM The building method for assembling integrated intelligent substation has following below scheme:Early-stage preparations;By design prefabrication;Site operation is accurate It is standby;The lifting of first floor floor, the lifting of first floor equipment hoisting, first floor metope;Two layers of floor lifting, two layers of ground lifting, the synchronous first floor Multiple line;Two-layer equipment lifting, two layers of metope lifting, two layers of top plate lifting, synchronous two layers of multiple line;Main component is checked and accepted;It is synchronous Electrical apparatus interstar connection;Power engineering is tested and is checked and accepted;Final acceptance of construction.
CN201810259854.XA 2018-03-27 2018-03-27 A kind of building method of BIM assembly integrated intelligents substation Pending CN108457504A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810259854.XA CN108457504A (en) 2018-03-27 2018-03-27 A kind of building method of BIM assembly integrated intelligents substation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810259854.XA CN108457504A (en) 2018-03-27 2018-03-27 A kind of building method of BIM assembly integrated intelligents substation

Publications (1)

Publication Number Publication Date
CN108457504A true CN108457504A (en) 2018-08-28

Family

ID=63236986

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810259854.XA Pending CN108457504A (en) 2018-03-27 2018-03-27 A kind of building method of BIM assembly integrated intelligents substation

Country Status (1)

Country Link
CN (1) CN108457504A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111622545A (en) * 2020-04-24 2020-09-04 中宜建安科技有限公司 Transformer substation construction technology
CN111706127A (en) * 2020-05-29 2020-09-25 南京南瑞继保工程技术有限公司 Indoor transformer substation construction method

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120265707A1 (en) * 2011-04-13 2012-10-18 Bushnell Christopher G Systems and Methods for Propagating Information Between Various Levels of a Construction Specification
KR101396795B1 (en) * 2013-10-14 2014-05-21 한국건설기술연구원 Bim system and modeling method
CN105888248A (en) * 2016-04-27 2016-08-24 河北建筑工程学院 Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology
CN106803162A (en) * 2016-12-02 2017-06-06 中铁四局集团第二工程有限公司 A kind of three-dimensional construction operation guidance method based on BIM technology
CN206309077U (en) * 2016-11-02 2017-07-07 广州鸥特鸥供应链管理有限公司 A kind of mobile factory of airduct processing
CN107060396A (en) * 2017-01-23 2017-08-18 深圳市粤网电力建设发展有限公司 A kind of fully-prefabricated assembled construction of transformer substation method and structure
CN107092739A (en) * 2017-04-12 2017-08-25 四川云图瑞科技有限公司 Execution management method therefor during using model to prefabricated components on-site consolidation
CN107103151A (en) * 2017-05-15 2017-08-29 贵州精正检测有限公司 A kind of method and apparatus of the fabricated construction based on BIM
CN107227870A (en) * 2017-07-25 2017-10-03 深圳供电局有限公司 Transformer substation building spliced by prefabricated parts
CN107301269A (en) * 2017-05-19 2017-10-27 河北省电力勘测设计研究院 The method that power distribution equipment data interaction is carried out based on BIM technology
CN107330140A (en) * 2017-05-19 2017-11-07 河北省电力勘测设计研究院 The method that transformer station is quickly vertically arranged is realized based on BIM technology
CN107357981A (en) * 2017-06-30 2017-11-17 大连理工大学 A kind of integrated standard engineering structure based on BIM creates and design method

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120265707A1 (en) * 2011-04-13 2012-10-18 Bushnell Christopher G Systems and Methods for Propagating Information Between Various Levels of a Construction Specification
KR101396795B1 (en) * 2013-10-14 2014-05-21 한국건설기술연구원 Bim system and modeling method
CN105888248A (en) * 2016-04-27 2016-08-24 河北建筑工程学院 Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology
CN206309077U (en) * 2016-11-02 2017-07-07 广州鸥特鸥供应链管理有限公司 A kind of mobile factory of airduct processing
CN106803162A (en) * 2016-12-02 2017-06-06 中铁四局集团第二工程有限公司 A kind of three-dimensional construction operation guidance method based on BIM technology
CN107060396A (en) * 2017-01-23 2017-08-18 深圳市粤网电力建设发展有限公司 A kind of fully-prefabricated assembled construction of transformer substation method and structure
CN107092739A (en) * 2017-04-12 2017-08-25 四川云图瑞科技有限公司 Execution management method therefor during using model to prefabricated components on-site consolidation
CN107103151A (en) * 2017-05-15 2017-08-29 贵州精正检测有限公司 A kind of method and apparatus of the fabricated construction based on BIM
CN107301269A (en) * 2017-05-19 2017-10-27 河北省电力勘测设计研究院 The method that power distribution equipment data interaction is carried out based on BIM technology
CN107330140A (en) * 2017-05-19 2017-11-07 河北省电力勘测设计研究院 The method that transformer station is quickly vertically arranged is realized based on BIM technology
CN107357981A (en) * 2017-06-30 2017-11-17 大连理工大学 A kind of integrated standard engineering structure based on BIM creates and design method
CN107227870A (en) * 2017-07-25 2017-10-03 深圳供电局有限公司 Transformer substation building spliced by prefabricated parts

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111622545A (en) * 2020-04-24 2020-09-04 中宜建安科技有限公司 Transformer substation construction technology
CN111706127A (en) * 2020-05-29 2020-09-25 南京南瑞继保工程技术有限公司 Indoor transformer substation construction method

Similar Documents

Publication Publication Date Title
Chen et al. Modular composite building in urgent emergency engineering projects: A case study of accelerated design and construction of Wuhan Thunder God Mountain/Leishenshan hospital to COVID-19 pandemic
CN107958101A (en) A kind of assembled architecture Information Management System and method based on BIM
WO2018145510A1 (en) Bim-based construction and decoration method
CN108532953B (en) BIM-based cantilever plate construction method and building construction method
CN110056189B (en) Method for monitoring and controlling large-volume concrete construction by using Internet of things
CN108457504A (en) A kind of building method of BIM assembly integrated intelligents substation
CN108428032A (en) A kind of formulating method and device of the component production schedule
CN105201101A (en) Light aggregate concrete small hollow block building masonry construction method
CN100570757C (en) The modular construction method that is used for nuclear island of nuclear power station
Rosenfeld Innovative construction methods
CN101752017B (en) Modularization construction method for nuclear power station nuclear island
CN101736925B (en) Modular construction method for nuclear island of nuclear power station
CN111395744A (en) Construction method of aluminum template in horizontal flowing section process of villa
CN207110029U (en) A kind of assembled house
CN111188407A (en) Construction process for solving cracks caused by temperature difference of mass concrete
CN109797977A (en) A kind of cement mortar masonry building system and its working method based on BIM buildings model
CN109138149A (en) The construction method of installation of assembled architecture PC component and its assembled architecture obtained
CN108687945A (en) A kind of test specimen makes fog room and maintenance process
CN208468685U (en) A kind of test specimen production fog room
CN207176736U (en) A kind of pipe gallery formwork for placing unit and by its assembled formwork for placing
CN207846756U (en) A kind of image decorating wall
Li et al. Three-dimensional (3D) printing for building and construction
Gao et al. Assembly process based on supply chain management of prefabricated houses using BIM
Guo et al. Application of assembly project based on BIM technology
Liu Research on Construction of Bill of Quantities of Prefabricated Buildings Based on BIM

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20200514

Address after: 410000 Room 626, 6th Floor, Venture Center, Hunan Environmental Science and Technology Industrial Park, 199 Zhenhua Road, Yuhua District, Changsha City, Hunan Province

Applicant after: Xiangneng Chutian Power Technology Co., Ltd.

Address before: 410007 Room 302, 10 innovation and design Industrial Park, 579 Zhenhua Road, Yuhua District, Changsha, Hunan, China (10)

Applicant before: XIANGNENG CHUTIAN ELECTRIC POWER Co.,Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20180828

RJ01 Rejection of invention patent application after publication