A kind of mobile factory of airduct processing
Technical field
The utility model is related to a kind of airduct processing mounting production line, and in particular to a kind of mobile factory of airduct processing.
Background technology
In recent years, the electromechanical direction installed just towards batch production and assembling of modern architecture is developed, its basic characteristics be by
All work is divided into prefabricated and two parts of assembling.
Prefabricated being advantageous in that of batch production be both protected from weather influences, also do not limited by civil engineering and equipment mounting condition,
When field condition possesses, you can prefabricated tube section and sub-assembly are transported into scene and say capable installation.This duration for shortening construction,
Ensure construction quality and safety, improve all tools such as project management level and balance construction manpower and be of great significance.
But at present, because pre-fabricated factory is typically provided with the different region of functional character, such as processing district, warehouse area,
This is accomplished by a considerable amount of factory building facilities, but the pre-fabricated factory under prior art various zones, it is impossible to project scale
Adjust and adjust, increased the prefabricated cost of batch production.
Utility model content
The purpose of this utility model is to overcome the disadvantages mentioned above of existing production technology, there is provided a kind of airduct processing is moved
Start building factory, and the technical solution adopted in the utility model is:
A kind of mobile factory of airduct processing, it is characterised in that:It includes that removable enclosing is covered steel plate and enclose the construction covered
Operation area, the work zone includes the prefabricated machining center of airduct and airduct machinery processing district;
The prefabricated machining center of airduct includes airduct predefined region and material memory block again;
The airduct predefined region includes some moveable containers with material memory block;
The container is used to place process equipment or material, and the side perpendicular to ground of the container is retractable
The shutter door of closing, the airduct machinery processing district is provided with removable machining shed;
Further, the material memory block, airduct predefined region and airduct machinery processing district are according to virtual work set in advance
Factory's model forms airduct machining production line.
Preferably, the airduct predefined region and material memory block transverse direction laid out in parallel, the airduct machinery processing district arrangement
In the side of the material memory block and airduct predefined region, the airduct predefined region include for place airduct production two wires the
One container, for place tear the second container of side machine, the 3rd container for placing CUT open and for putting
The 4th container of rumble bone machine is put, the material memory block includes being used as the 5th container in warehouse and being used to place flange finished product
6th container in area, first container and the second container longitudinal direction laid out in parallel, the 3rd packaging and the 4th packaging
Case transverse direction laid out in parallel, and the 3rd container and the 4th packaging are close to side of second container away from the first container,
5th container is laterally arranged with the 6th container.
Preferably, the airduct machinery processing district is vertically arranged with region of paint, flange processing district, airduct processing district.
Preferably, the virtual factory model is the BIM dummy models set up based on BIM technology.
The beneficial effects of the utility model are:
The mobile factory of the utility model airduct processing is fixed on corresponding packaging by the mechanized equipment processing each operation
In case, in project under construction appropriate location assembling combination, directly according to corresponding time predetermined number positioning, corresponding position is stored in,
Production line is formed, realizes that batch production is prefabricated, be that later assembly work is provided a great convenience.When inventory is pressed by factory
After completing a component processing for project, you can to decompose production line in units of container, each packaging tank module
Be transported to next item, and can in new project place rapid recombination, form new production line.
Brief description of the drawings
Fig. 1 is the top view of the mobile factory of the utility model airduct processing.
Specific embodiment
The utility model is explained below.
As shown in figure 1, the mobile factory of the utility model airduct processing includes that removable enclosing is covered steel plate and enclose applying of covering
Work operation area, the work zone includes the prefabricated machining center 1 of airduct with airduct machinery processing district 2;The airduct is prefabricated to be added
Work center 1 includes airduct predefined region A and material memory block B again.The airduct predefined region A and material memory block B include it is some can
Mobile container, the container is used to place process equipment or material, and the container is perpendicular to the side on ground can
The shutter door that folding is closed, the airduct machinery processing district 2 is provided with removable machining shed, and material memory block B, airduct are prefabricated
Area A and airduct machinery processing district 2 form airduct machining production line according to virtual factory model set in advance, in the present embodiment
In, then it is pre-designed virtual BIM models, airduct machining production line is then set up according to virtual BIM plant models.
Specifically, in embodiment of the present utility model, the airduct predefined region A is laterally arranged side by side with B with material memory block
Arrangement, the airduct machinery processing district 2 is arranged in the right side of the material memory block B and airduct predefined region A, and the airduct is prefabricated
Area include for place airduct production two wires the first container 11, for place tear the second container 12 of side machine open, for putting
The 3rd container 13 and the 4th container 14 for placing rumble bone machine of CUT are put, the material memory block includes
It is used as the 5th container 15 and the 6th container 16 for placing flange finished product area in warehouse, first container 11 and the
The longitudinal laid out in parallel of two container 12, the 3rd packaging 13 and the horizontal laid out in parallel of the 4th container 14, and the 3rd container
13 and the 4th container 14 be arranged in second container 12, the 5th container 15 and the 6th container 16 are side by side laterally
Arrange, the airduct machinery processing district 2 is vertically arranged with airduct processing district 21, flange processing district 22, region of paint 23.
The airduct predefined region A is used for the preprocessing of airduct finished product;The material memory block is used for storage and has processed
Airduct, support and flange.The finished product that the airduct machinery processing district 2 is used for airduct is processed.
The mobile factory of the utility model airduct processing is fixed on corresponding packaging by the mechanized equipment processing each operation
In case, in project under construction appropriate location assembling combination, directly according to corresponding time predetermined number positioning, corresponding position is stored in,
Production line is formed, realizes that batch production is prefabricated, be that later assembly work is provided a great convenience.When inventory is pressed by factory
After completing a component processing for project, you can to decompose production line in units of container, each packaging tank module
Be transported to next item, and can in new project place rapid recombination, form new production line.
The announcement and teaching of book according to the above description, the utility model those skilled in the art can also be to above-mentioned reality
The mode of applying is changed and changed.Therefore, the utility model is not limited to specific embodiment disclosed and described above, right
Some modifications and changes of the present utility model should also be as falling into scope of the claims of the present utility model.Additionally, to the greatest extent
Some specific terms have been used in pipe this specification, but these terms are merely for convenience of description, not to the utility model