CN108412506A - Ground fissure region tunnel lining structure based on shield tunnel and its construction method - Google Patents

Ground fissure region tunnel lining structure based on shield tunnel and its construction method Download PDF

Info

Publication number
CN108412506A
CN108412506A CN201810140210.9A CN201810140210A CN108412506A CN 108412506 A CN108412506 A CN 108412506A CN 201810140210 A CN201810140210 A CN 201810140210A CN 108412506 A CN108412506 A CN 108412506A
Authority
CN
China
Prior art keywords
tunnel
shield tunnel
idio
morphosis
lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810140210.9A
Other languages
Chinese (zh)
Inventor
戴志仁
胡瑞青
王俊
王立新
马晓波
康华
王天明
李谈
高志宏
李润轩
郭亮
李储军
贾少春
曹伟
杨沛敏
王博
翁木生
毛念华
张海
汪珂
王春希
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN201810140210.9A priority Critical patent/CN108412506A/en
Publication of CN108412506A publication Critical patent/CN108412506A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/385Sealing means positioned between adjacent lining members

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to ground fissure region tunnel lining structures and its construction method based on shield tunnel, circumferential idio-morphosis seam is reserved on secondary lining inside the shield tunnel, secondary lining at idio-morphosis seam convexes to form inner convexed to inner circumference and expands header structure, and inner convexed expands is provided with built-in slip casting pipe at enlarged footing on header structure.The present invention will directly be passed through at ground fissure using shield tunnel, by performing secondary lining in shield tunnel, meet stratum large deformation demand, improve construction quality and safety of surrounding environment simultaneously, the beginning that domestic and international ground fissure region uses shield tunnel crossing construction has been started in the effective control for realizing the continuous and engineering risk of section engineering method.

Description

Ground fissure region tunnel lining structure based on shield tunnel and its construction method
Technical field
The present invention relates to Tunnel Engineering technical fields, and in particular to a kind of ground fissure region tunnel based on shield tunnel Liner structure and its construction method.
Background technology
For the railway traffic engineering of current cities in China, due to geological structure and mankind's activity, in stratum There are different degrees of fracture belt or fracture areas, and certain unstable and continuous deformation characteristic is presented in long process, It is a big control selector for this city track traffic engineering extremely limited to bounded qualification.
Based on stratum activity characteristic and shield tunnel technical characterstic, in Tunnel Engineering by generally being pressed when ground fissure region Tunneling by mining method considers that tunnel clearance is accordingly done greatly under the premise of considering stratum maximum deformation quantity in design period, but due to Ground fissure Regional Geological Conditions are poor, and Tunneling by mining method is unfavorable for engineering risk control and environmental protection, is unfavorable for construction investment Control, is less useful for Engineering Quality Control, and as similar engineering in all parts of the country continuously emerges, conventional Tunneling by mining method scheme is brought The drawbacks of be more and more obvious.
Invention content
The object of the present invention is to provide a kind of ground fissure region tunnel lining structure and its structure based on shield tunnel Method, realizes ground fissure region shield method tunnel construction, utmostly reduces construction risk, improves construction quality.
The technical solution adopted in the present invention is:
Ground fissure region tunnel lining structure based on shield tunnel, it is characterised in that:
Circumferential idio-morphosis seam is reserved on secondary lining inside the shield tunnel, the secondary lining at idio-morphosis seam to Inner circumference convexes to form inner convexed and expands header structure, and inner convexed expands is provided with built-in slip casting pipe at enlarged footing on header structure.
Shield tunnel is precast assembly liner structure, is formed by several pieces of pipe sheet assemblings per endless tube piece, and section of jurisdiction circumferential weld is indulged It is connected by bolt between seam.
It is provided with pre-installed and inverted adhered waterproof roll between the segment assembly and secondary lining of shield tunnel.
Waterproof construction is provided at idio-morphosis seam, ecto-entad includes external labeling type waterstop, middle buried water stop and connects Sink.
The construction method of ground fissure region tunnel lining structure based on shield tunnel, it is characterised in that:
Include the following steps:
Step 1:Arrangement is raised according to work, for the main influence area of ground fissure, using Shield Construction Method Used, shield tunneling process In timely segment assembly, formed shield tunnel liner structure;
Step 2:After shield driving completion, Tunnel are logical, tunnel internal is cleared up in time, and secondary lining is poured Shield duct piece circumferential weld bolt in range takes out;
Step 3:Within the scope of the ground fissure zone of influence tunneling boring be laid with waterproof layer, pre-installed and inverted adhered waterproof roll, reinforcing bar binding, formwork erection, It pours secondary lining, in secondary lining casting process, idio-morphosis need to be stitched and carry out reservation process with interior convex enlarged footing position, Subsequent post-cast strip processing;
Step 4:After the completion of waiting for that the general section of secondary lining pours, idio-morphosis seam and liner structure at interior convex enlarged footing are performed, The built-in slip casting pipe on interior convex enlarged footing, three water-tight devices of setting from outside to inside at idio-morphosis seam, including outer patch Formula waterstop, middle buried water stop and water receiving tank, idio-morphosis slit width degree can be considered by 100mm, meet idio-morphosis seam both sides Structure freely up and down activity and structurally waterproof requirement;
Step 5:After the completion of waiting for that secondary lining, shield tunnel pipe-plate lining and additional waterproofing layer perform, secondary lining, shield Method is separated between tunnel by waterproof material, is only transmitted axle power not Transfer of Shear and moment of flexure, is formed typical composite lining knot Structure;
Step 6:Railway roadbed is performed in time, is laid with track, installing contact net and other equipment, is met rail transit train operation and is wanted It asks;
Step 7:During tunnel normal use, larger geological movement such as occurs at ground fissure, idio-morphosis is caused to stitch both sides There is the changing of the relative positions in structure, using built-in slip casting pipe on interior convex enlarged footing, the sky that tunnel vault region is formed due to the structure changing of the relative positions Hole carries out slip casting filling, it is ensured that lining cutting is closely knit behind.
The present invention has the following advantages:
The present invention provides a kind of novel ground fissure region shield tunnel Structural design ideas, enrich ground fissure region tunnel Road liner structure processing method.Either ground fissure region or general subterranean formation zone, are all made of shield construction, for ground Crack area large deformation situation that may be present is poured inside the shield tunnel and is handled by the way of secondary lining, together When setting idio-morphosis seam and inner convexed enlarged footing, meet structural bearing and waterproof requirement.The shield tunnel section of jurisdiction in outside Lining cutting, the internal secondary lining poured, the tunneling boring waterproof roll being laid between secondary lining and pipe-plate lining, idio-morphosis The cement mortar, liner structure of pressure injection are used in pre-buried Grouting Pipe and slip casting ductule on seam waterproof material, inner convexed enlarged footing Steel and concrete etc., the steel being related to, cement mortar, water-proof concrete and slip casting ductule set mechanical equipment etc. used It is conventional material(Equipment), corresponding size is general type, manufacture easy to process;Arrangement, quantity and the length of Grouting Pipe It can be adjusted according to condition of construction;Stratum deformation is mainly set up defences section and length, the quantity of changeover portion, can base area characteristic of crack Deflection is estimated with a century flexibly to determine.It is more based on being arranged in the idio-morphosis seam and deformation joint at interior convex enlarged footing Road antipriming is, it can be achieved that in the case of deformation joint structure on two sides maximum changing of the relative positions amount, structurally waterproof demand.It is pre- in enlarged footing simultaneously The Grouting Pipe buried is, it can be achieved that sinking section enlarged footing outside filling and injecting slurry, it is ensured that liner structure is effectively contacted with country rock, realizes structure With country rock sharing lood.Shield tunnel one-time continuous passes through ground fissure region and shield tunnel segment lining and secondary lining The composite component formed is built, significant increase construction quality is horizontal with risk management and control, has higher economic benefit and society Benefit has wide practical use in the engineerings such as urban track traffic, railway, highway.
Description of the drawings
Fig. 1 ground fissures region shield tunnel vertical section layout drawing
Fig. 2 ground fissures region shield tunnel optimal crosssection figure
In figure, 1- shield tunnels, 2- secondary linings, 3- idio-morphosis seam, 4- inner convexeds expand header structure, and 5- pre-installed and inverted adhereds are anti- Water coiled material, built-in slip casting pipe at 6- enlarged footings.
Specific implementation mode
The present invention will be described in detail With reference to embodiment.
The present invention relates to the ground fissure region tunnel lining structures based on shield tunnel, inside shield tunnel 1 Circumferential idio-morphosis seam 3 is reserved on secondary lining 2, the secondary lining 2 at idio-morphosis seam 3 convexes to form convex to inner circumference Formula expands header structure 4, and inner convexed expands is provided with built-in slip casting pipe 6 at enlarged footing on header structure 4.Secondary lining 2 includes special Deformation joint 3 and interior convex enlarged footing structure 4, pouring construction after the completion of shield tunnel 1 tunnels of secondary lining 2.Interior convex expands Big header structure 4 needs to consider reserved post-cast strip during secondary lining 2 pours, and it is laggard to wait for that other parts liner structure pours completion Row is secondary to be poured.
3 both sides maximum changing of the relative positions amounts are stitched to meet idio-morphosis, two lining structures, 2 effective thickness is not less than standard section lining cutting knot Structure thickness meets structure entirety stress and longitudinal stability requirement.
Shield tunnel 1 is precast assembly liner structure, is formed by several pieces of pipe sheet assemblings per endless tube piece, section of jurisdiction circumferential weld, It is connected by bolt between longitudinal joint.Secondary lining 2 is formed by steel bar stress and waterproof concrete entirety continuous placing, the thickness of secondary lining 2 Degree can be integrated according to strata condition, edpth of tunnel, earth's surface overload and secondary lining 2 with 1 sharing lood effect of shield tunnel Consider to determine.
It needs to consider special waterproof material and water-proof system at idio-morphosis seam 3, meets idio-morphosis and stitch 3 both sides maximum Structurally waterproof requirement in the case of changing of the relative positions amount.It is provided with pre-installed and inverted adhered between the segment assembly and secondary lining 2 of shield tunnel 1 Waterproof roll 5.
It is provided with waterproof construction at idio-morphosis seam 3, ecto-entad includes external labeling type waterstop, middle buried water stop and connects Sink.
Secondary lining 2 mainly deforms main influence area in ground fissure(Main region of setting up defences)Setting, every section of length of setting up defences (L1, consider by the integral multiple of section of jurisdiction ring width)With whole length of setting up defences(n×L1)Base area Cracks character is determined with coverage; One section of stratum deformation changeover portion of setting is also needed to outside main influence area(L2), it is n × L that secondary lining 2, which performs length,1+2× L2
To meet the changing of the relative positions of region of fracture stratum and deformation requirements, on stratum, primary deformable is set up defences in region, in secondary lining 2 Before pouring, shield duct piece circumferential weld bolt needs to take out, it is ensured that outside shield tunnel is coordinated with stratum deformation, while reducing knot to the greatest extent The Additional Stress of Structure and crack that structure deformation is likely to form.
It needs to pour secondary lining 2 inside shield tunnel 1, on the basis of considering interior convex enlarged footing 4, in secondary lining 2 Portion's headroom needs to meet driving and facilities clearance requirement, and 1 cross dimensions of shield tunnel accordingly expands.
The construction method of ground fissure region tunnel lining structure based on shield tunnel, it is characterised in that:
Include the following steps:
Step 1:Arrangement is raised according to work, for the main influence area of ground fissure, using Shield Construction Method Used, shield tunneling process In timely segment assembly, formed 1 liner structure of shield tunnel;
Step 2:After shield driving completion, Tunnel are logical, tunnel internal is cleared up in time, and secondary lining 2 is poured Shield duct piece circumferential weld bolt in range takes out;
Step 3:Within the scope of the ground fissure zone of influence tunneling boring be laid with waterproof layer, pre-installed and inverted adhered waterproof roll, reinforcing bar binding, formwork erection, It pours secondary lining 2, in 2 casting process of secondary lining, idio-morphosis need to be stitched 3 and be reserved with interior 4 position of convex enlarged footing Processing, subsequent post-cast strip processing;
Step 4:After the completion of waiting for that 2 general section of secondary lining pours, idio-morphosis seam 3 and lining cutting knot at interior convex enlarged footing 4 are performed Structure, the built-in slip casting pipe on interior convex enlarged footing 4, three water-tight devices of setting from outside to inside at idio-morphosis seam 3, including External labeling type waterstop, middle buried water stop and water receiving tank, 3 width are stitched in idio-morphosis to be considered by 100mm, meet idio-morphosis seam Structure on two sides freely up and down activity and structurally waterproof requirement;
Step 5:After the completion of waiting for that secondary lining 2,1 pipe-plate lining of shield tunnel and additional waterproofing layer perform, secondary lining 2, shield It is separated by waterproof material between structure method tunnel 1, only transmits axle power not Transfer of Shear and moment of flexure, form typical composite lining Structure;
Step 6:Railway roadbed is performed in time, is laid with track, installing contact net and other equipment, is met rail transit train operation and is wanted It asks;
Step 7:During tunnel normal use, larger geological movement such as occurs at ground fissure, idio-morphosis is caused to stitch 3 liang There is the changing of the relative positions in side structure, using built-in slip casting pipe 6 on interior convex enlarged footing 4, to tunnel vault region since the structure changing of the relative positions is formed Cavity carry out slip casting filling, it is ensured that lining cutting behind it is closely knit.
Shield tunnel 1 tunnels and pipe-plate lining assembly is all common process, and involved shield machine is set with other auxiliary Apply all is conventional machinery arrangement;Reinforcing bar, water-proof concrete, steel form, waterproof used by secondary lining 2, interior convex enlarged footing 4 Coiled material is all conventional material, and reinforcing bar used generally uses P10 or P12, steel form to adopt using three-level anti-seismic steel bar, water-proof concrete With Q235 steel, waterproof roll uses pre-installed and inverted adhered coiled material;Three water-tight devices being arranged at idio-morphosis seam 3 are respectively outer paving formula Additional waterproofing layer, it is U-shaped with and type waterstop and water receiving tank, involved splash guard, rubber and steel plate etc. are all conventional materials.
The pipe-plate lining that shield tunnel 1 is related to during performing(C50 waterproof reinforced concretes), seam waterproof material(Ternary second Third EPDM), segment bolt(M30)And injecting paste material(Single liquid cement mortar)It is common process and conventional material.
The slip casting steel pipe pre-buried when performing of inner convexed enlarged footing 4 is using diameter 42mm, circumferential spacing 2.0m, internal pressure injection water Mud, slip casting steel pipe and 2 reinforcement welding of secondary lining are secured, it is ensured that and it is closely connected between secondary lining 2, shield tunnel 1 and country rock, it is full Sufficient structure entirety force request.
After three be arranged in idio-morphosis seam 3 are closed the measures of preventing water of cyclization, it is entirely capable of meeting structurally waterproof requirement;Together When convex enlarged footing in pre-buried Grouting Pipe, can meet after fracture occurs, slip casting demand on the outside of sinking segment structure, it is ensured that lining cutting knot It is closely connected between structure and country rock, realize stratum stabilization and safety of surrounding environment.
Present disclosure is not limited to cited by embodiment, and those of ordinary skill in the art are by reading description of the invention And to any equivalent transformation that technical solution of the present invention is taken, it is that claim of the invention is covered.

Claims (5)

1. the ground fissure region tunnel lining structure based on shield tunnel, it is characterised in that:
In shield tunnel(1)Internal secondary lining(2)It is upper to reserve circumferential idio-morphosis seam(3), idio-morphosis seam(3)Place Secondary lining(2)Inner convexed, which is convexed to form, to inner circumference expands header structure(4), inner convexed expansion header structure(4)On be provided with Built-in slip casting pipe at enlarged footing(6).
2. the ground fissure region tunnel lining structure according to claim 1 based on shield tunnel, it is characterised in that:
Shield tunnel(1)It for precast assembly liner structure, is formed by several pieces of pipe sheet assemblings per endless tube piece, section of jurisdiction circumferential weld is indulged It is connected by bolt between seam.
3. the ground fissure region tunnel lining structure according to claim 1 based on shield tunnel, it is characterised in that:
Shield tunnel(1)Segment assembly and secondary lining(2)Between be provided with pre-installed and inverted adhered waterproof roll(5).
4. the ground fissure region tunnel lining structure according to claim 1 based on shield tunnel, it is characterised in that:
Idio-morphosis is stitched(3)Place is provided with waterproof construction, and ecto-entad includes external labeling type waterstop, middle buried water stop and water receiving Slot.
5. the construction method of the ground fissure region tunnel lining structure based on shield tunnel, it is characterised in that:
Include the following steps:
Step 1:Arrangement is raised according to work, for the main influence area of ground fissure, using Shield Construction Method Used, shield tunneling process In timely segment assembly, formed shield tunnel(1)Liner structure;
Step 2:After shield driving completion, Tunnel are logical, tunnel internal is cleared up in time, and by secondary lining(2)It pours The shield duct piece circumferential weld bolt built in range takes out;
Step 3:Within the scope of the ground fissure zone of influence tunneling boring be laid with waterproof layer, pre-installed and inverted adhered waterproof roll, reinforcing bar binding, formwork erection, Pour secondary lining(2), secondary lining(2)In casting process, idio-morphosis need to be stitched(3)With interior convex enlarged footing(4)Position Carry out reservation process, subsequent post-cast strip processing;
Step 4:Wait for secondary lining(2)After the completion of general section pours, idio-morphosis seam is performed(3)With interior convex enlarged footing(4)Place Liner structure, in interior convex enlarged footing(4)Upper built-in slip casting pipe is stitched in idio-morphosis(3)Place's setting from outside to inside three anti- Water installations, including external labeling type waterstop, middle buried water stop and water receiving tank, idio-morphosis seam(3)Width can consider by 100mm, Meet the freely up and down activity of idio-morphosis seam structure on two sides and structurally waterproof requirement;
Step 5:Wait for secondary lining(2), shield tunnel(1)After the completion of pipe-plate lining and additional waterproofing layer perform, secondary lining (2), shield tunnel(1)Between separated by waterproof material, only transmit axle power not Transfer of Shear and moment of flexure, formed typical multiple Box-like liner structure;
Step 6:Railway roadbed is performed in time, is laid with track, installing contact net and other equipment, is met rail transit train operation and is wanted It asks;
Step 7:During tunnel normal use, larger geological movement such as occurs at ground fissure, idio-morphosis is caused to be stitched(3) There is the changing of the relative positions in structure on two sides, utilizes interior convex enlarged footing(4)Upper built-in slip casting pipe(6), to tunnel vault region due to structure mistake The dynamic cavity formed carries out slip casting filling, it is ensured that lining cutting is closely knit behind.
CN201810140210.9A 2018-02-11 2018-02-11 Ground fissure region tunnel lining structure based on shield tunnel and its construction method Pending CN108412506A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810140210.9A CN108412506A (en) 2018-02-11 2018-02-11 Ground fissure region tunnel lining structure based on shield tunnel and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810140210.9A CN108412506A (en) 2018-02-11 2018-02-11 Ground fissure region tunnel lining structure based on shield tunnel and its construction method

Publications (1)

Publication Number Publication Date
CN108412506A true CN108412506A (en) 2018-08-17

Family

ID=63128398

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810140210.9A Pending CN108412506A (en) 2018-02-11 2018-02-11 Ground fissure region tunnel lining structure based on shield tunnel and its construction method

Country Status (1)

Country Link
CN (1) CN108412506A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109236319A (en) * 2018-08-20 2019-01-18 中铁第勘察设计院集团有限公司 The ground fissure region shield tunnel and its construction method of enlarged footing pattern are poured based on after
CN109812020A (en) * 2019-04-04 2019-05-28 中建八局第一建设有限公司 A kind of band-like Full-face pouring tube assembly and construction method
CN110017145A (en) * 2019-04-28 2019-07-16 中铁第六勘察设计院集团有限公司 A kind of sea area shield mine joins jointing and its construction method in Tunnel
CN110985040A (en) * 2019-12-26 2020-04-10 长安大学 Composite support lining structure device and support lining method for tunnel at ground fissure section
CN111828019A (en) * 2020-07-17 2020-10-27 北京市政路桥股份有限公司 Construction method for large-section special deformation joint based on earthquake fracture zone
CN115324614A (en) * 2022-09-16 2022-11-11 清华大学 Steel plate concrete composite lining structure, construction method and lining system

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006226062A (en) * 2005-02-21 2006-08-31 Bridgestone Corp Earthquakeproof joint for concrete structure and its execution method
CN101298790A (en) * 2008-05-27 2008-11-05 葛加君 Rubber water stop U anchor construction method
CN101603429A (en) * 2009-07-09 2009-12-16 西安理工大学 Anti-seepage structure of composite lining deformation joints of ground fissure stratum tunnel and construction method thereof
CN101737063A (en) * 2009-11-16 2010-06-16 西安理工大学 Ground fissure tunnel asphalt concrete composite lining and supporting method thereof
CN101748755A (en) * 2009-12-14 2010-06-23 中铁第一勘察设计院集团有限公司 Flexible connecting and sealing bitumastic impervious structure of tunnel deformation joint and constructing method
CN103628895A (en) * 2013-12-12 2014-03-12 中铁第一勘察设计院集团有限公司 Large-deformation ground fissure section tunnel lining joint structure and construction method thereof
CN204098937U (en) * 2014-06-20 2015-01-14 山西省交通科学研究院 Tunnel deformation joint waterproof construction and constructing tunnel structure
CN106337690A (en) * 2016-11-16 2017-01-18 中国科学院武汉岩土力学研究所 Waterproof joint structure of tunnel lining in cross fault area and construction method thereof
CN208040386U (en) * 2018-02-11 2018-11-02 中铁第一勘察设计院集团有限公司 A kind of ground fissure region tunnel lining structure based on shield tunnel

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006226062A (en) * 2005-02-21 2006-08-31 Bridgestone Corp Earthquakeproof joint for concrete structure and its execution method
CN101298790A (en) * 2008-05-27 2008-11-05 葛加君 Rubber water stop U anchor construction method
CN101603429A (en) * 2009-07-09 2009-12-16 西安理工大学 Anti-seepage structure of composite lining deformation joints of ground fissure stratum tunnel and construction method thereof
CN101737063A (en) * 2009-11-16 2010-06-16 西安理工大学 Ground fissure tunnel asphalt concrete composite lining and supporting method thereof
CN101748755A (en) * 2009-12-14 2010-06-23 中铁第一勘察设计院集团有限公司 Flexible connecting and sealing bitumastic impervious structure of tunnel deformation joint and constructing method
CN103628895A (en) * 2013-12-12 2014-03-12 中铁第一勘察设计院集团有限公司 Large-deformation ground fissure section tunnel lining joint structure and construction method thereof
CN204098937U (en) * 2014-06-20 2015-01-14 山西省交通科学研究院 Tunnel deformation joint waterproof construction and constructing tunnel structure
CN106337690A (en) * 2016-11-16 2017-01-18 中国科学院武汉岩土力学研究所 Waterproof joint structure of tunnel lining in cross fault area and construction method thereof
CN208040386U (en) * 2018-02-11 2018-11-02 中铁第一勘察设计院集团有限公司 A kind of ground fissure region tunnel lining structure based on shield tunnel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄强兵;彭建兵;樊红卫;杨沛敏;门玉明;: "西安地裂缝对地铁隧道的危害及防治措施研究" *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109236319A (en) * 2018-08-20 2019-01-18 中铁第勘察设计院集团有限公司 The ground fissure region shield tunnel and its construction method of enlarged footing pattern are poured based on after
CN109236319B (en) * 2018-08-20 2023-09-15 中铁第一勘察设计院集团有限公司 Post-pouring enlarged head type ground crack area shield tunnel and construction method thereof
CN109812020A (en) * 2019-04-04 2019-05-28 中建八局第一建设有限公司 A kind of band-like Full-face pouring tube assembly and construction method
CN109812020B (en) * 2019-04-04 2023-10-20 中建八局第一建设有限公司 Strip-shaped full-section grouting pipe assembly and construction method
CN110017145A (en) * 2019-04-28 2019-07-16 中铁第六勘察设计院集团有限公司 A kind of sea area shield mine joins jointing and its construction method in Tunnel
CN110017145B (en) * 2019-04-28 2024-02-09 中铁第六勘察设计院集团有限公司 Sea area shield mine junction tunnel intra-cavity connection joint and construction method thereof
CN110985040A (en) * 2019-12-26 2020-04-10 长安大学 Composite support lining structure device and support lining method for tunnel at ground fissure section
CN110985040B (en) * 2019-12-26 2024-04-09 长安大学 Composite support lining structure device and support lining method for ground crack section tunnel
CN111828019A (en) * 2020-07-17 2020-10-27 北京市政路桥股份有限公司 Construction method for large-section special deformation joint based on earthquake fracture zone
CN115324614A (en) * 2022-09-16 2022-11-11 清华大学 Steel plate concrete composite lining structure, construction method and lining system

Similar Documents

Publication Publication Date Title
CN108412506A (en) Ground fissure region tunnel lining structure based on shield tunnel and its construction method
WO2021223573A1 (en) Construction structure for communication and connection between newly added mined channel and existing station hall layer
CN101737063B (en) Ground fissure tunnel asphalt concrete composite lining and supporting method thereof
CN108019222B (en) A kind of tunnel lining structure and construction method using haydite filling
CN105064397B (en) Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation
JP7394252B1 (en) Protruding type wind duct structure perpendicular to the vertical direction and construction method at deep subway station
CN106930777B (en) The construction method that Bored Section of Metro main track assembled two serves as a contrast
CN105201516B (en) A kind of main structure of subway station and its tetrad arch PBA excavating construction methods
CN108868778A (en) A kind of Large Underground Structure no-dig technique construction method
CN104675403A (en) Underground space construction method and supporting structure
CN101603429A (en) Anti-seepage structure of composite lining deformation joints of ground fissure stratum tunnel and construction method thereof
CN105089670B (en) Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel
CN208040386U (en) A kind of ground fissure region tunnel lining structure based on shield tunnel
CN110042862A (en) The prefabricated rail in subway station against the wind road, with prefabricated middle plate connecting node and construction method
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN108589737A (en) Underground speedy way hands over the construction method that section is built jointly with rail under a kind of major urban arterial highway
CN108180025A (en) A kind of circular cross section tunnel lining construction method three times
CN105464685A (en) Cave-pile method bored tunnel waterproof curtain and construction method thereof
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN112012763B (en) Construction method of double-layer primary support multi-arch tunnel structure
CN112012762B (en) Construction method of double-layer secondary lining multi-arch tunnel structure
CN203247838U (en) Fully-buried basement side wall post-pouring belt advance water stop formwork
CN106088758B (en) A kind of bilayer assembled underground granary
CN109236319A (en) The ground fissure region shield tunnel and its construction method of enlarged footing pattern are poured based on after
CN205036388U (en) Block of four encircles knot hunch construction structures that PBA secretly dug subway station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180817