CN108071239B - Pc楼梯锚固钢筋即时植入方法 - Google Patents
Pc楼梯锚固钢筋即时植入方法 Download PDFInfo
- Publication number
- CN108071239B CN108071239B CN201711393234.7A CN201711393234A CN108071239B CN 108071239 B CN108071239 B CN 108071239B CN 201711393234 A CN201711393234 A CN 201711393234A CN 108071239 B CN108071239 B CN 108071239B
- Authority
- CN
- China
- Prior art keywords
- stair
- hoisting
- anchoring
- component
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G23/00—Working measures on existing buildings
- E04G23/02—Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
- E04G23/0218—Increasing or restoring the load-bearing capacity of building construction elements
Abstract
一种PC楼梯锚固钢筋即时植入方法,用在吊装时将锚固钢筋直接在PC楼梯锚固孔位置植入,PC楼梯吊装对位经粗调及微调完成后,吊装钢丝绳不拆除,锚固钢筋植入后方可进行拆除,避免PC楼梯因无锚固钢筋问题掉落出现安全事故,且大大减少对位调整时PC楼梯的悬停时间,每梯段在空中的悬停调整时间约减少10分钟,减少安全风险。
Description
技术领域
本发明涉及一种锚固钢筋即时植入的施工方法,特别是PC构件精确吊装的锚固方法。
背景技术
根据楼梯PC构件的安装精度需求,楼梯在施工中须要将锚固孔对准楼梯梁上的预埋锚固钢筋,但现有施工方法多为在绑扎楼梯梁时将锚固钢筋直接绑扎,浇筑时露出部分即为锚固段,该方法虽然能最大程度发挥锚固钢筋的稳定性,但在绑扎时的定位不精确和浇筑过程中钢筋的晃动,使该锚固钢筋位置偏差过大,导致在楼梯PC构件吊装对位时构件上的锚固孔和楼梯梁上的锚固钢筋不能正常进行锚固,需将有误差的预埋的锚固钢筋割断,再重新钻孔进行植入锚固钢筋,不能满足现场施工进度需求。而且模板刚度较差,受荷载易偏位,还有在浇筑混凝土过程中振动较大,都导致预埋的锚固钢筋偏位,现场实际预埋钢筋均出现不同程度的偏位情况,还有工人操作问题导致锚固钢筋丢失、忘记及脱落等,不易管理,浇筑后常出现吊装前对预埋的锚固钢筋进行整改处理的情况,如PC楼梯已经起吊,对位时发现预埋锚固钢筋偏位,则需立即进行整改,加大吊装时间同时增加安装成本及安全风险。此外传统施工方法施工人员需将PC楼梯预留锚固孔调整至楼梯梁上的预埋钢筋位置后再下落, PC楼梯悬停调整时间较长,安全风险较大。
发明内容
本发明创造提出一种PC楼梯锚固钢筋即时植入方法,用在吊装时将锚固钢筋直接在PC楼梯锚固孔位置植入,PC楼梯吊装对位经粗调及微调完成后,吊装钢丝绳不拆除,锚固钢筋植入后方可进行拆除,避免PC楼梯因无锚固钢筋问题掉落出现安全事故,且大大减少对位调整时PC楼梯的悬停时间,每梯段在空中的悬停调整时间约减少10分钟,减少安全风险。
为了解决上述问题,本发明创造采用的技术方案为:PC楼梯锚固钢筋即时植入方法,其步骤为:
1)、施工准备:设定吊装先后顺序,保证能够按照既定安装顺序及时吊装与安装;
2)、吊起对位调整:按照步骤1)中设定的吊装顺序,吊装时先将楼梯构件吊离地面,检查吊钩确保为正常工作状态,然后升至高于安装位置,人工将楼梯构件稳定;稳定后使其缓慢下降就位在楼梯梁上,就位时确保楼梯构件两端支座搁置于楼梯梁上的长度满足设计要求,对搁置长度偏差较大的构件用撬棍微调整,按楼梯梁上弹出的控制线将允许偏差调整至5mm内;此时楼梯构件已经放置于楼梯梁上,但还未与楼梯梁进行植筋锚固;
3)、植入锚固钢筋:使用钻头,对准楼梯构件的锚固孔的中心位置,在其下部楼梯梁上进行钻孔,钻头始终与梁面保持垂直;植入强力植筋胶后立即将锚固钢筋单向旋入,植入孔内,直至钢筋深入孔底;强力植筋胶完全固化后进行楼梯锚固孔灌浆封堵;
4)、吊装完成:在进行步骤2)和步骤3)过程中,吊装钢丝绳保持绷直,步骤3)完成后,拆除钢丝绳,完成吊装锚固施工。
所述的步骤3)中,强力植筋胶在孔内注胶达到80%后,将Φ20的钢筋注入孔内;待50h后强力植筋胶完全固化后进行楼梯锚固孔灌浆封堵即可。
所述的步骤3)中锚固孔深11cm。
本发明创造的有益效果是:
本发明专利采用PC楼梯锚固钢筋,即时植入方法植入的锚固钢筋位置为PC楼梯预留锚固孔的中心,从而从根本上解决预埋造成的误差偏位,避免了以往为加快吊装速度而提前预埋锚固钢筋但又有误差偏位的弊端,采用锚固钢筋即时植入事故方法使得施工无偏差、无需整改,整体施工速度加快,降低安全风险。
具体实施方式
PC楼梯锚固钢筋即时植入方法,其步骤为:
1)、施工准备:设定吊装先后顺序,保证能够按照既定安装顺序及时吊装与安装;
2)、吊起对位调整:按照步骤1)中设定的吊装顺序,对楼梯进行吊装。吊装时先将楼梯构件吊离地面,约 500mm,检查吊钩是否有歪扭或卡死现象及各吊点受力是否均匀,然后徐徐升至高于安装位置约900mm-1100mm,优选的为1000mm,人工将楼梯构件稳定,稳定后使其缓慢下降就位在楼梯梁上,就位时确保楼梯构件两端支座搁置于楼梯梁上的长度满足设计要求,对搁置长度偏差较大的构件用撬棍微调整,按楼梯梁上弹出的控制线将允许偏差调整至5mm内。此时楼梯构件已经放置于楼梯梁上,但还未与楼梯梁进行植筋锚固,所以吊装钢丝绳保持绷直状态即可,避免楼梯构件突然失稳造成安全事故;
3)、植入锚固钢筋:使用钻头,对准楼梯构件的锚固孔的中心位置,在其下部楼梯梁上进行钻孔,钻头始终与梁面保持垂直;植入强力植筋胶后立即将锚固钢筋单向旋入,植入孔内,直至钢筋深入孔底;强力植筋胶完全固化后进行楼梯锚固孔灌浆封堵;
4)、吊装完成:在进行步骤2)和步骤3)过程中,吊装钢丝绳保持绷直,步骤3)完成后,拆除钢丝绳,完成吊装锚固施工。
所述的步骤3)中,强力植筋胶在孔内注胶达到80%后,将Φ20的钢筋注入孔内;待50h后强力植筋胶完全固化后进行楼梯锚固孔灌浆封堵即可。
所述的步骤3)中锚固孔深11cm。
具体施工时:
1、施工准备:
楼梯构件进场阶段需要组织各方进行验收,并经各方验收合格后签字确认后用于施工现场,检查构件外观的完整性,构件施工现场编号核对,构件的外观尺寸进行核对,构件细部尺寸核对,不合格构件及时退场。
待施工前,设定吊装先后顺序,确保能够按照既定安装顺序及时吊装与安装。
2、起吊对位调整:
吊装前应确认楼梯构件标识。构件吊装前应确保吊点连接牢固,平衡梁系统及塔吊连接钢丝绳连接牢固,吊装连接件经 过项目安全部门等验收合格后方可使用。同时对于需要临时支撑构件应提前准备支撑构件,并满足安全验收标准要求,验收合格后方可使用,吊装应采用“垂直”或“水平”就位方法。就位后对楼梯构件进行调整后下落在楼梯梁上,进行微调整。
3、植入锚固钢筋:
采用Φ22长度35cm钻头在楼梯锚固孔内中心位置钻孔,要求钻头始终与梁面保持垂直,钻孔深度11cm,钻成孔后将孔内灰粉、灰渣等杂物清理干净,注入强力植筋胶,孔内注胶达到80%即可,立即将Φ20钢筋植入孔内,慢慢单向旋入,不可中途逆向反转,直至钢筋伸入孔底,植入后不振动钢筋,待50h后强力植筋胶完全固化后进行楼梯锚固孔灌浆封堵即可。
4、吊装完成:
在对位调整、植入锚固筋环节中,吊装钢丝绳始终保持绷直,待锚固钢筋植入后方可拆除钢丝绳。
实施例1:汪家馨城二期回迁房项目,位于沈阳市沈抚新城中部,东至金枫街,南至沈抚大道,西至规划路,北至汪家一期。二层起楼板及楼梯为PC构件,共计1988块,采用即时植入锚固钢筋的方法,精度较高、且锚固性也较稳定,能减少定位不准带来的钢筋损耗及人工浪费,减少吊装时PC楼梯悬停调整时间,降低安全风险,本工法在此工程施工中得到了成功的运用,在质量、安全、成本方面均取得了良好的效果。
施工步骤如下:
PC楼梯起吊,吊装至楼梯梁处进行对位调整,下落至楼梯梁上进行微调,在PC楼梯端部预留锚固孔位置中心钻孔,孔深11cm,钻孔后将孔内灰渣灰尘清理干净,锚固钢筋长35cm,在孔内注入植筋胶,旋入锚固钢筋,拆除钢丝绳,锚固准确无误差,现场楼梯与楼梯梁对位速度快,大致对位后即可落下进行微调,使PC楼梯悬停调整时间大大减少,即能满足使用安全需求,又能提高作业效率,每梯段的吊装对位时间与传统相比能节省10分钟,共1988块,大幅度减少悬停期间安全风险。
Claims (1)
1.PC楼梯锚固钢筋即时植入方法,其步骤为:
1)、施工准备:设定吊装先后顺序,保证能够按照既定安装顺序及时吊装与安装;
2)、吊起对位调整:按照步骤1)中设定的吊装顺序,对楼梯进行吊装:吊装时先将楼梯构件吊离地,检查吊钩确保为正常工作状态,然后升至高于安装位置,人工将楼梯构件稳定;稳定后使其缓慢下降就位在楼梯梁上,就位时确保楼梯构件两端支座搁置于楼梯梁上的长度满足设计要求,对搁置长度偏差较大的构件用撬棍微调整,按楼梯梁上弹出的控制线将允许偏差调整至5mm内;此时楼梯构件已经放置于楼梯梁上,但还未与楼梯梁进行植筋锚固;
3)、植入锚固钢筋:使用钻头,对准楼梯构件的锚固孔的中心位置,在其下部楼梯梁上进行钻孔,钻头始终与梁面保持垂直;植入强力植筋胶后立即将锚固钢筋单向旋入,植入孔内,直至钢筋深入孔底;强力植筋胶完全固化后进行楼梯锚固孔灌浆封堵;
所述的强力植筋胶在孔内注胶达到80%后,将Φ20的钢筋注入孔内;待50h后强力植筋胶完全固化后进行楼梯锚固孔灌浆封堵即可;步骤3)中锚固孔深11cm;
4)、吊装完成:在进行步骤2)和步骤3)过程中,吊装钢丝绳保持绷直,步骤3)完成后,拆除钢丝绳,完成吊装锚固施工。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711393234.7A CN108071239B (zh) | 2017-12-21 | 2017-12-21 | Pc楼梯锚固钢筋即时植入方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711393234.7A CN108071239B (zh) | 2017-12-21 | 2017-12-21 | Pc楼梯锚固钢筋即时植入方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108071239A CN108071239A (zh) | 2018-05-25 |
CN108071239B true CN108071239B (zh) | 2021-03-05 |
Family
ID=62158813
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711393234.7A Active CN108071239B (zh) | 2017-12-21 | 2017-12-21 | Pc楼梯锚固钢筋即时植入方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108071239B (zh) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0978786A (ja) * | 1995-09-19 | 1997-03-25 | Taisei Corp | プレキャスト製階段ユニットの取付け構造 |
KR100875960B1 (ko) * | 2008-06-27 | 2008-12-26 | 대림산업 주식회사 | Pc계단의 시공방법 |
CN205399856U (zh) * | 2016-03-17 | 2016-07-27 | 三新房屋制造股份有限公司 | 一种空心梯板组合楼梯 |
CN106121145A (zh) * | 2016-07-15 | 2016-11-16 | 江苏中南建筑产业集团有限责任公司 | 一种分片式装配楼梯及其制作方法与装配方法 |
CN106150001A (zh) * | 2015-04-28 | 2016-11-23 | 重庆建工住宅建设有限公司 | 一种预制装配整体式楼梯施工方法 |
CN106639197A (zh) * | 2016-10-20 | 2017-05-10 | 中国建筑第七工程局有限公司 | 一种分片式装配楼梯施工方法 |
CN106894587A (zh) * | 2017-01-13 | 2017-06-27 | 沈阳建筑大学 | 预制楼梯连接方法 |
-
2017
- 2017-12-21 CN CN201711393234.7A patent/CN108071239B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0978786A (ja) * | 1995-09-19 | 1997-03-25 | Taisei Corp | プレキャスト製階段ユニットの取付け構造 |
KR100875960B1 (ko) * | 2008-06-27 | 2008-12-26 | 대림산업 주식회사 | Pc계단의 시공방법 |
CN106150001A (zh) * | 2015-04-28 | 2016-11-23 | 重庆建工住宅建设有限公司 | 一种预制装配整体式楼梯施工方法 |
CN205399856U (zh) * | 2016-03-17 | 2016-07-27 | 三新房屋制造股份有限公司 | 一种空心梯板组合楼梯 |
CN106121145A (zh) * | 2016-07-15 | 2016-11-16 | 江苏中南建筑产业集团有限责任公司 | 一种分片式装配楼梯及其制作方法与装配方法 |
CN106639197A (zh) * | 2016-10-20 | 2017-05-10 | 中国建筑第七工程局有限公司 | 一种分片式装配楼梯施工方法 |
CN106894587A (zh) * | 2017-01-13 | 2017-06-27 | 沈阳建筑大学 | 预制楼梯连接方法 |
Also Published As
Publication number | Publication date |
---|---|
CN108071239A (zh) | 2018-05-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102767288A (zh) | 一种钢筋混凝土预制楼梯的安装方法及结构 | |
CN208310140U (zh) | 一种预制楼梯精确装配辅助组件 | |
CN105484157B (zh) | 预制装配桥梁盖梁定位装置及预制装配桥梁盖梁施工方法 | |
CN111851565B (zh) | 一种带杯口型基础钢结构立柱找正结构及其施工方法 | |
CN204225145U (zh) | 一种用于基础地脚螺栓预埋的简易定位工具 | |
CN103774854A (zh) | 一种重型超高钢构件的吊装施工方法 | |
CN105780995B (zh) | 一种曲面空间管桁架结构及其安装方法 | |
CN110528390B (zh) | 临近既有线狭窄空间架设t梁施工方法 | |
CN104895335B (zh) | 一种吊柱的安装方法 | |
CN206692235U (zh) | 一种钢结构穹顶起吊安装装置 | |
CN110817678A (zh) | 一种预制柱的吊装方法 | |
CN112647590A (zh) | 预制装配式钢筋混凝土梁柱钢节点预制组合柱的施工方法 | |
US5359829A (en) | Fabrication and installation of steel reinforcement cages for pier foundations | |
CN111485573A (zh) | 一种输电工程预制基础安装、铁塔组立连贯施工方法 | |
CN108071239B (zh) | Pc楼梯锚固钢筋即时植入方法 | |
CN106759943A (zh) | 一种预组装钢柱脚锚栓结构 | |
CN106337520A (zh) | 大单元点式玻璃幕墙施工工艺 | |
CN102777044A (zh) | 尿素造粒塔钢结构喷淋层吊装方法 | |
CN104404888A (zh) | 一种大型空中坡度调整吊装系统及应用 | |
CN109457814B (zh) | 基于贝雷架结构的高耸及大直径建筑物顶盖施工方法 | |
CN114439242B (zh) | 装配式悬挑复杂构件优化及吊装加固施工工法 | |
CN103174155A (zh) | 先立钢柱后浇混凝土基础逆作施工方法及施工用钢支架 | |
CN210597297U (zh) | 一种移动平台式桥梁立柱施工缆风绳地锚 | |
CN210152143U (zh) | 用于混凝土外挂板吊装施工的连接结构 | |
CN108792963A (zh) | 一种用于高层屋面构架的空间钢桁架式塔吊附墙支座方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |