CN106639197A - 一种分片式装配楼梯施工方法 - Google Patents
一种分片式装配楼梯施工方法 Download PDFInfo
- Publication number
- CN106639197A CN106639197A CN201610914834.2A CN201610914834A CN106639197A CN 106639197 A CN106639197 A CN 106639197A CN 201610914834 A CN201610914834 A CN 201610914834A CN 106639197 A CN106639197 A CN 106639197A
- Authority
- CN
- China
- Prior art keywords
- waist slab
- single flight
- pin
- stair
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F11/00—Stairways, ramps, or like structures; Balustrades; Handrails
- E04F11/02—Stairways; Layouts thereof
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Abstract
本发明公开了一种分片式装配楼梯施工方法,将常规单跑梯段板沿板宽方向分成两片单独预制,两片梯段板在安装阶段拼合成一跑楼梯,并通过跨中设置的两根抗剪销连为一体,该施工方法工艺简单,可实现楼梯板批量工厂化预制,混凝土浇筑和外观成型质量易控制;采用分片预制的方式,单片楼梯板自重小,易吊装,比大跨度整体式预制楼梯的适用范围更广。
Description
技术领域
本发明属于建筑施工领域,特别涉及一种分片式装配楼梯施工方法。
背景技术
目前高层住宅楼梯主要有现浇楼梯和装配楼梯,现浇楼梯主要采用现浇施工,存在楼梯模板支设困难、劳动强度大、施工周期长、经济性欠佳且施工质量不易保障等缺点。装配式楼梯主要有分段式、抽空式、整体式等,分段式需要楼梯中部增加梯梁,增加施工难度,经济性欠佳;抽空式需加大梯板厚度,减重效果并不明显;整体式存在自重较大、吊装困难的问题。以上几种类型均不利于施工,均需要较大型号的吊装设备方可施工。
发明内容
本发明提出一种分片式装配楼梯施工方法,该施工方法工艺简单,可实现楼梯板批量工厂化预制,混凝土浇筑和外观成型质量易控制;采用分片预制的方式,单片楼梯板自重小,易吊装,比大跨度整体式预制楼梯的适用范围更广。
本发明的技术方案是这样实现的:一种分片式装配楼梯施工方法,包括如下步骤:
(1)通过商品混凝土预制两片单跑梯段板,混凝土中粗骨料粒径控制在5-25mm内,混凝土入模时塌落度控制在140-180mm,浇筑时投料高度小于500mm,混凝土振捣采用插入式振捣棒,振捣间距小于400mm,单跑梯段板内部设置有环形加强筋,混凝土浇筑完毕经静停后进行蒸汽养护;
(2)制成的每片单跑梯段板中部开设抗剪销预留孔,其中一单跑梯段板的抗剪销预留孔为通孔,另一单跑梯段板的抗剪销预留孔设置有50mm厚的封底;
(3)在每片单跑梯段板的顶部台阶踏板和底部台阶踏板上均预留竖直设置的销栓孔,在每片单跑梯段板的顶部台阶踏板和底部台阶踏板中设置有销栓孔加强筋;
(4)分别在每片单跑梯段板的上半段和下半段的其中一台阶踏板的上表面分别预埋2枚吊钉,在台阶预埋枚吊钉的位置还预埋有枚吊钉加强筋;
(5)在用以安装单跑梯段板的支承梯梁上预埋固定螺钉,并铺设水泥砂浆找平层,所述水泥砂浆找平层厚度为20mm;
(6)通过塔吊上的钢铰链和吊环与单跑梯段板预埋枚吊钉连接该钢铰链包括钢丝绳和可调节刚铰链,当确认牢固后方可继续缓慢起吊,在梯段板两端悬挂牵引绳,由辅助人员牵引以保证平稳吊装,避免碰撞,待塔吊将梯段板吊至支承梯梁上方适当位置后,改变可调节刚铰链长度使梯段板调整至设计角度,缓慢就位,同时根据控制线利用撬棍微调、校正,整个吊装过程中,钢绞链最大扩张角不得超过120°,最后将两片单跑梯段板吊装到相应位置并通过其上设置的销栓孔连接在支承梯梁的固定螺钉上,两片单跑梯段板并排设置,并在销栓孔和固定螺钉之间的空隙中灌注浆料,并通过花钢管和抗剪销预留孔将两片单跑楼梯板进行连接,并在抗剪销预留孔的空隙中灌入浆料,在单跑梯段板顶部台阶侧壁和支撑梯梁侧壁的空隙进行注胶。
进一步的,所述浆料采用C40级CGM。
进一步的,所述抗剪销预留孔设置两个。
进一步的,所述花钢管上设置有渗浆孔和支撑肋。
本发明的有益效果如下:该施工方法工艺简单,可实现楼梯板批量工厂化预制,混凝土浇筑和外观成型质量易控制;采用分片预制的方式,单片楼梯板自重小,易吊装,比大跨度整体式预制楼梯的适用范围更广。
附图说明
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图。
图1为采用本发明的施工方法建造的分片式装配楼梯结构示意图;
图2为塔吊起吊单板梯段板的结构示意图;
图3为塔吊将吊单板梯段板安装在指定位置时候的结构示意图;
图4为两单跑梯段装配后的俯视图;
图5为单跑梯段板的底部台阶踏板的结构示意图;
图6为单跑梯段板和支承梯梁连接的结构示意图;
图7为花钢管的结构示意图。
具体实施方式
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有作出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
参见图1到图7所示的一种分片式装配楼梯施工方法,包括如下步骤:
(1)通过商品混凝土预制两片单跑梯段板1,混凝土中粗骨料粒径控制在5-25mm内,混凝土入模时塌落度控制在140-180mm,浇筑时投料高度小于500mm,混凝土振捣采用插入式振捣棒,振捣间距小于400mm,单跑梯段板内部设置有环形加强筋,混凝土浇筑完毕经静停后进行蒸汽养护,通入水蒸汽使混凝土升温,加速水泥和辅助胶凝材料水化硬化进程,快速达到脱模强度。
(2)制成的每片单跑梯段板1中部开设抗剪销预留孔3,其中一单跑梯段板的抗剪销预留孔为通孔,另一单跑梯段板的抗剪销预留孔设置有50mm厚的封底;
(3)在每片单跑梯段板的顶部台阶踏板和底部台阶踏板上均预留竖直设置的销栓孔5,在每片单跑梯段板的顶部台阶踏板和底部台阶踏板中设置有销栓孔加强筋14;
(4)分别在每片单跑梯段板的上半段和下半段的其中一台阶踏板的上表面分别预埋2枚吊钉6,在台阶预埋枚吊钉的位置还预埋有枚吊钉加强筋15;
(5)在用以安装单跑梯段板的支承梯梁18上预埋固定螺钉,然后通过塔吊上的钢铰链和吊环与单跑梯段板预埋枚吊钉6连接,该钢铰链包括钢丝绳7和可调节刚铰链8,当确认牢固后方可继续缓慢起吊,在梯段板两端悬挂牵引绳,由辅助人员牵引以保证平稳吊装,避免碰撞,待塔吊将梯段板吊至支承梯梁18上方适当位置后,改变可调节刚铰链8长度使梯段板调整至设计角度,缓慢就位,同时根据控制线利用撬棍微调、校正,整个吊装过程中,钢绞链最大扩张角不得超过120°,最后将两片单跑梯段板吊装到相应位置并通过其上设置的销栓孔连接在支承梯梁的固定螺钉4上,两片单跑梯段板并排设置,并在销栓孔和固定螺钉之间的空隙中灌注浆料,并通过花钢管16和抗剪销预留孔将两片单跑楼梯板进行连接,并在抗剪销预留孔的空隙中灌入浆料9,在单跑梯段板顶部台阶侧壁和支撑梯梁侧壁的空隙进行注胶11;
(6)在梯梁上表面设置水泥砂浆找平层10,所述水泥砂浆找平层厚度为20mm。
进一步的,所述浆料采用C40级CGM,该浆料由高强胶结材料、多种外加剂复合和特选骨料经特殊工艺配制而成,具有大流动度、无收缩、早强及高强等特点
进一步的,所述抗剪销预留孔设置两个。
进一步的,为了增加两片单跑梯段板的强度,所述花钢管16上设置有渗浆孔12和支撑肋13。
本发明的基本原理为将常规单跑梯段板沿板宽方向分成两片单独预制,两片梯段板在安装阶段拼合成一跑楼梯,并通过跨中设置的两根花钢管连为一体,利用刚性连接强化协同受力;拼合一体的整跑梯段板通过螺栓与主体结构梯梁形成固定铰接,可有效减小地震波对梯段板产生的集中应力。
分片式装配楼梯体系由2片单跑梯段板组成,梯段板中部预留2处Φ50抗剪销预留孔(后期拼装阶段,植入花钢管并灌浆,形成抗剪销),每片梯段板两端各预留2个销栓孔(与主体结构梯梁上预埋的固定螺钉对应,后期用高强度灌浆料灌实)。
本发明的优点在于:可实现楼梯板批量工厂化预制,混凝土浇筑和外观成型质量易控制;采用分片预制的方式,单片楼梯板自重小,易吊装,比大跨度整体式预制楼梯的适用范围更广。
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。
Claims (4)
1.一种分片式装配楼梯施工方法,其特征在于,包括如下步骤,
(1)通过商品混凝土预制两片单跑梯段板,混凝土中粗骨料粒径控制在5-25mm内,混凝土入模时塌落度控制在140-180mm,浇筑时投料高度小于500mm,混凝土振捣采用插入式振捣棒,振捣间距小于400mm,单跑梯段板内部设置有环形加强筋,混凝土浇筑完毕经静停后进行蒸汽养护;
(2)制成的每片单跑梯段板中部开设抗剪销预留孔,其中一单跑梯段板的抗剪销预留孔为通孔,另一单跑梯段板的抗剪销预留孔设置有50mm厚的封底;
(3)在每片单跑梯段板的顶部台阶踏板和底部台阶踏板上均预留竖直设置的销栓孔,在每片单跑梯段板的顶部台阶踏板和底部台阶踏板中设置有销栓孔加强筋;
(4)分别在每片单跑梯段板的上半段和下半段的其中一台阶踏板的上表面分别预埋2枚吊钉,在台阶预埋枚吊钉的位置还预埋有枚吊钉加强筋;
(5)在用以安装单跑梯段板的支承梯梁上预埋固定螺钉,并铺设水泥砂浆找平层,所述水泥砂浆找平层厚度为20mm;
(6)通过塔吊上的钢铰链和吊环与单跑梯段板预埋枚吊钉连接该钢铰链包括钢丝绳和可调节刚铰链,当确认牢固后方可继续缓慢起吊,在梯段板两端悬挂牵引绳,由辅助人员牵引以保证平稳吊装,避免碰撞,待塔吊将梯段板吊至支承梯梁上方适当位置后,改变可调节刚铰链长度使梯段板调整至设计角度,缓慢就位,同时根据控制线利用撬棍微调、校正,整个吊装过程中,钢绞链最大扩张角不得超过120°,最后将两片单跑梯段板吊装到相应位置并通过其上设置的销栓孔连接在支承梯梁的固定螺钉上,两片单跑梯段板并排设置,并在销栓孔和固定螺钉之间的空隙中灌注浆料,并通过花钢管和抗剪销预留孔将两片单跑楼梯板进行连接,并在抗剪销预留孔的空隙中灌入浆料,在单跑梯段板顶部台阶侧壁和支撑梯梁侧壁的空隙进行注胶。
2.根据权利要求1所述的分片式装配楼梯施工方法,其特征在于,所述浆料采用C40级CGM。
3.根据权利要求2所述的分片式装配楼梯施工方法,其特征在于,所述抗剪销预留孔设置两个。
4.根据权利要求2所述的分片式装配楼梯施工方法,其特征在于,所述花钢管上设置有渗浆孔和支撑肋。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610914834.2A CN106639197B (zh) | 2016-10-20 | 2016-10-20 | 一种分片式装配楼梯施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610914834.2A CN106639197B (zh) | 2016-10-20 | 2016-10-20 | 一种分片式装配楼梯施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106639197A true CN106639197A (zh) | 2017-05-10 |
CN106639197B CN106639197B (zh) | 2019-01-18 |
Family
ID=58856013
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610914834.2A Active CN106639197B (zh) | 2016-10-20 | 2016-10-20 | 一种分片式装配楼梯施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106639197B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108071239A (zh) * | 2017-12-21 | 2018-05-25 | 中冶东北建设(沈阳)工程技术有限公司 | Pc楼梯锚固钢筋即时植入方法 |
CN109025291A (zh) * | 2018-07-25 | 2018-12-18 | 中国十七冶集团有限公司 | 一种分离式预制楼梯的施工方法 |
CN109505386A (zh) * | 2017-09-15 | 2019-03-22 | 赵会荣 | 一种新式楼梯及其实现方法 |
CN113027053A (zh) * | 2021-03-10 | 2021-06-25 | 盛新建设集团有限公司 | 一种梯井内用预制装配式楼梯及吊装施工工艺 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2848078A1 (de) * | 1978-11-06 | 1980-05-14 | Bruno Heibges | Bauteilesatz fuer eine im oberen teil abgewinkelte treppe aus stahlbeton-fertigteilen |
CN104499663A (zh) * | 2014-12-11 | 2015-04-08 | 济南轨道交通集团有限公司 | 一种混凝土楼梯及混凝土楼梯的组装方法 |
CN204590456U (zh) * | 2015-03-25 | 2015-08-26 | 华南理工大学 | 一种预制拼装式板式楼梯 |
CN204609155U (zh) * | 2015-04-28 | 2015-09-02 | 重庆建工住宅建设有限公司 | 一种预制装配分段式楼梯结构 |
CN204960180U (zh) * | 2015-08-20 | 2016-01-13 | 中国建筑第七工程局有限公司 | 一种分片式楼梯 |
CN105298040A (zh) * | 2015-10-30 | 2016-02-03 | 中汇建筑集团有限公司 | 一种轻质装配式楼梯及其施工方法 |
CN105544895A (zh) * | 2016-02-15 | 2016-05-04 | 济南汇富住宅工业有限公司 | 一种混凝土预制楼梯 |
-
2016
- 2016-10-20 CN CN201610914834.2A patent/CN106639197B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2848078A1 (de) * | 1978-11-06 | 1980-05-14 | Bruno Heibges | Bauteilesatz fuer eine im oberen teil abgewinkelte treppe aus stahlbeton-fertigteilen |
CN104499663A (zh) * | 2014-12-11 | 2015-04-08 | 济南轨道交通集团有限公司 | 一种混凝土楼梯及混凝土楼梯的组装方法 |
CN204590456U (zh) * | 2015-03-25 | 2015-08-26 | 华南理工大学 | 一种预制拼装式板式楼梯 |
CN204609155U (zh) * | 2015-04-28 | 2015-09-02 | 重庆建工住宅建设有限公司 | 一种预制装配分段式楼梯结构 |
CN204960180U (zh) * | 2015-08-20 | 2016-01-13 | 中国建筑第七工程局有限公司 | 一种分片式楼梯 |
CN105298040A (zh) * | 2015-10-30 | 2016-02-03 | 中汇建筑集团有限公司 | 一种轻质装配式楼梯及其施工方法 |
CN105544895A (zh) * | 2016-02-15 | 2016-05-04 | 济南汇富住宅工业有限公司 | 一种混凝土预制楼梯 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109505386A (zh) * | 2017-09-15 | 2019-03-22 | 赵会荣 | 一种新式楼梯及其实现方法 |
CN108071239A (zh) * | 2017-12-21 | 2018-05-25 | 中冶东北建设(沈阳)工程技术有限公司 | Pc楼梯锚固钢筋即时植入方法 |
CN108071239B (zh) * | 2017-12-21 | 2021-03-05 | 中冶东北建设(沈阳)工程技术有限公司 | Pc楼梯锚固钢筋即时植入方法 |
CN109025291A (zh) * | 2018-07-25 | 2018-12-18 | 中国十七冶集团有限公司 | 一种分离式预制楼梯的施工方法 |
CN113027053A (zh) * | 2021-03-10 | 2021-06-25 | 盛新建设集团有限公司 | 一种梯井内用预制装配式楼梯及吊装施工工艺 |
Also Published As
Publication number | Publication date |
---|---|
CN106639197B (zh) | 2019-01-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106121145B (zh) | 一种分片式装配楼梯及其制作方法与装配方法 | |
CN106639197B (zh) | 一种分片式装配楼梯施工方法 | |
US20020059763A1 (en) | Pre-fabricated bathroom | |
CN101139849A (zh) | 一种组装式建筑物构件及现场吊装的建筑方法 | |
CN107605177A (zh) | 高效预制楼板的施工方法及其独立支撑架 | |
CN101487293A (zh) | 梁柱节点不同强度等级混凝土浇筑方法 | |
CN108708394A (zh) | 一种全断面免支撑的叠合装配式综合管廊结构及施工方法 | |
CN101597920A (zh) | 装配式房屋构造及其方法 | |
CN111734018A (zh) | 一种模壳结构、免拆模具以及混凝土墙施工方法 | |
CN110005104A (zh) | 一种装配式的保温装饰一体化叠合楼板及其施工方法 | |
CN106193340B (zh) | 现浇无粘结预应力超长楼盖组合式加强带防裂结构的施工方法 | |
CN110005200A (zh) | 水平暗梁混凝土浇筑密实的施工工艺 | |
CN204753834U (zh) | 一种剪刀楼梯的隔墙板与楼层梁的连接结构 | |
CN211421637U (zh) | 一种预制天沟的连接结构 | |
CN200952187Y (zh) | 一种组装式建筑物构件 | |
CN207959747U (zh) | 一种预制预应力混凝土板式楼梯 | |
CN208415928U (zh) | 一种与铝模结合使用的预制内墙板 | |
CN113235798B (zh) | 装配式叠合板安装方法 | |
CN205444514U (zh) | 一种承重轻质保温一体板 | |
CN102322022B (zh) | 一种斜拉桥装饰罩混凝土施工方法 | |
CN108691381A (zh) | 一种新型建筑用叠合楼板 | |
CN104775550A (zh) | 预吊装内隔墙板与建筑结构一体化施工墙体体系 | |
CN109372105A (zh) | 带预制钢筋砼凸形支座的装配式建筑 | |
CN204609048U (zh) | 预吊装内隔墙板与建筑结构一体化施工墙体体系 | |
CN208763209U (zh) | 梁端连接的装配整体式混凝土框架结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |