CN107859519A - 掘、锚、护一体化的掘锚护机 - Google Patents
掘、锚、护一体化的掘锚护机 Download PDFInfo
- Publication number
- CN107859519A CN107859519A CN201711288542.3A CN201711288542A CN107859519A CN 107859519 A CN107859519 A CN 107859519A CN 201711288542 A CN201711288542 A CN 201711288542A CN 107859519 A CN107859519 A CN 107859519A
- Authority
- CN
- China
- Prior art keywords
- anchor
- roof
- bolter
- lateral wall
- pick
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000010354 integration Effects 0.000 title claims abstract description 17
- 238000009434 installation Methods 0.000 claims description 3
- 230000000694 effects Effects 0.000 abstract description 3
- 239000002699 waste material Substances 0.000 abstract description 3
- 238000004873 anchoring Methods 0.000 abstract description 2
- 239000003245 coal Substances 0.000 abstract description 2
- 240000007594 Oryza sativa Species 0.000 description 1
- 235000007164 Oryza sativa Nutrition 0.000 description 1
- 238000010009 beating Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000003137 locomotive effect Effects 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 235000009566 rice Nutrition 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D23/00—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
- E21D23/0086—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor in galleries
- E21D23/0095—Temporary supports at the driving front
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D23/00—Mine roof supports for step- by- step movement, e.g. in combination with provisions for shifting of conveyors, mining machines, or guides therefor
- E21D23/04—Structural features of the supporting construction, e.g. linking members between adjacent frames or sets of props; Means for counteracting lateral sliding on inclined floor
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Architecture (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
本发明涉及煤矿巷道掘进开采及支护机械领域,具体为一种掘、锚、护一体化的掘锚护机,解决掘进机、锚杆机、临时支护分体工作造成时间浪费以及人工打锚杆劳动强度大、效率低、安全性差等问题。本发明掘锚护一体机包括有:掘进机、顶锚杆机、侧帮锚杆机、滑道装置、临时支护机构、升降操作台,采用两部顶锚杆机,顶锚杆机通过固定在掘进机前立板上面的滑道装置水平移动,完成顶板锚杆的锚装;两部侧帮锚杆机通过安装侧帮锚杆机的滑道装置上下移动,完成侧帮锚杆的锚装;临时支护机构、升降操作台采用一体化的结构设计,再与安装侧帮锚杆机的滑道装置联为一体设计,前后连续两排同时锚装。从而,实现掘进机、锚杆机、临时支护一体化功效。
Description
技术领域
本发明涉及煤矿巷道掘进开采及支护机械领域,具体为一种掘、锚、护一体化的掘锚护机,实现掘进机、锚杆机、临时支护一体化功效。
背景技术
目前,掘进机巷道掘进后的支护工作,是一项艰苦复杂效率低、安全性差的工作,主要原因是掘进机与锚杆机及临时支护分体式工作造成大量的时间浪费,有效工作时间比例很小。
人工打锚杆不但劳力大,而且效率也很低。所以,非常需要一种掘进机掘进后立即进行锚杆支护工作,提高掘进机的工作效率和工人的安全性,降低操作者的劳动强度的掘锚护一体化设备。
发明内容
本发明的目的在于提供一种掘、锚、护一体化的掘锚护机,安装于掘进机前后两对锚杆机,在临时支护的安全保护下,解决掘进机与锚杆机、临时支护分体工作造成时间浪费以及人工打锚杆劳动强度大、效率低等问题,实现掘进机、锚杆机、临时支护一体化功效。
本发明的技术方案是:
一种掘、锚、护一体化的掘锚护机,掘锚护机包括:掘进机、顶锚杆机、侧帮锚杆机、临时支护机构,采用两部顶锚杆机,顶锚杆机通过固定在掘进机前立板上面的滑道装置水平移动,完成顶板锚杆的锚装;两部侧帮锚杆机通过安装侧帮锚杆机的滑道装置上下移动,完成侧帮锚杆的锚装;临时支护机构与安装侧帮锚杆机的滑道装置联为一体设计,实现前后连续两排同时锚装。
所述的掘、锚、护一体化的掘锚护机,两部顶锚杆机安装在水平滑道装置上面,两部侧帮锚杆机安装在垂直滑道装置上面,顶板锚杆机、侧帮锚杆机分别设计在前后连续两排需要锚杆的位置。
所述的掘、锚、护一体化的掘锚护机,临时支护机构、升降操作台采用一体化的结构设计,再与安装侧帮锚杆机的滑道装置联为一体设计。
本发明的优点及有益效果是:
1、本发明的结构设计,增加顶锚杆机左右滑道移动功能,满足巷道顶板锚杆角度要求;侧帮锚杆机加大锚杆机的移动行程,不但满足侧帮锚杆角度要求,而且实现侧帮1.0米以上所有锚杆的标准锚装;前后连续两排同时锚装的结构设计,提高巷道锚装的安全性,临时支护及升降操作台的设计,也提高操作者的安全性及方便性,使整机锚杆锚装功能达到完美极致,将为掘锚护机市场的推广使用起到决定性作用。
2、本发明掘锚护机可以大幅度提高整机工作效率,极大地降低操作者的工作强度,提高操作者工作时的安全性。
附图说明
图1为本发明掘锚护一体机结构图。图中:1临时支护机构;2顶锚杆机;3水平滑道装置;4升降操作台;5垂直滑道装置;6侧帮锚杆机;7掘进机;8前立板。
具体实施方式
如图1所示,本发明掘、锚、护一体化的掘锚护机,主要包括:掘进机7、顶锚杆机2、侧帮锚杆机6、滑道装置、临时支护机构1、升降操作台4等,具体结构如下:
掘锚护机的前排采用两部安装于水平滑道装置3的顶锚杆机2,顶锚杆机2通过固定在掘进机7的前立板8上面的所述水平滑道装置3水平移动,完成顶板锚杆的锚装;掘锚护机的后排采用两部安装于垂直滑道装置5的侧帮锚杆机6,侧帮锚杆机6通过所述垂直滑道装置5上下移动,完成侧帮锚杆的锚装;临时支护机构1、升降操作台4采用一体化的结构设计,再与垂直滑道装置5联为一体设计,实现前后连续两排同时锚装。
其中,顶锚杆机2具有前后左右摆动、上下升降等功能,侧帮锚杆机6具有上下升降、上下角度调整、左右横向进给功能,临时支护机构1具有上下升降、支护顶板及铺网功能,升降操作台4为操作者锚装锚杆提供安全方便条件。
本发明掘锚护机的垂直滑道装置5与临时支护机构1一体化联接设计,减小前后两排锚杆机(顶锚杆机2、侧帮锚杆机6)之间的距离,实现前后连续两排同时锚装的需求;水平滑道装置3可以使顶锚杆机2从水平滑道装置3的一端水平移动到另一端,加大顶锚杆机2的左右移动行程,满足巷道所有顶板锚杆的角度要求;垂直滑道装置5可以使侧帮锚杆机6从垂直滑道装置5的一端垂直移动到另一端,加大侧帮锚杆机6的上下移动行程,满足巷道所有侧帮锚杆的角度要求。
Claims (3)
1.一种掘、锚、护一体化的掘锚护机,其特征在于,掘锚护机包括:掘进机、顶锚杆机、侧帮锚杆机、临时支护机构,采用两部顶锚杆机,顶锚杆机通过固定在掘进机前立板上面的滑道装置水平移动,完成顶板锚杆的锚装;两部侧帮锚杆机通过安装侧帮锚杆机的滑道装置上下移动,完成侧帮锚杆的锚装;临时支护机构与安装侧帮锚杆机的滑道装置联为一体设计,实现前后连续两排同时锚装。
2.按照权利要求1所述的掘、锚、护一体化的掘锚护机,其特征在于,两部顶锚杆机安装在水平滑道装置上面,两部侧帮锚杆机安装在垂直滑道装置上面,顶板锚杆机、侧帮锚杆机分别设计在前后连续两排需要锚杆的位置。
3.按照权利要求1所述的掘、锚、护一体化的掘锚护机,其特征在于,临时支护机构、升降操作台采用一体化的结构设计,再与安装侧帮锚杆机的滑道装置联为一体设计。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711288542.3A CN107859519A (zh) | 2017-12-07 | 2017-12-07 | 掘、锚、护一体化的掘锚护机 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711288542.3A CN107859519A (zh) | 2017-12-07 | 2017-12-07 | 掘、锚、护一体化的掘锚护机 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107859519A true CN107859519A (zh) | 2018-03-30 |
Family
ID=61705047
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711288542.3A Pending CN107859519A (zh) | 2017-12-07 | 2017-12-07 | 掘、锚、护一体化的掘锚护机 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107859519A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109372524A (zh) * | 2018-12-27 | 2019-02-22 | 山东兖煤黑豹矿业装备有限公司 | 掘锚护一体机的模块化锚杆机组 |
CN112392520A (zh) * | 2020-11-16 | 2021-02-23 | 中国铁建重工集团股份有限公司 | 一种锚杆支护组件及锚杆钻车 |
CN113236320A (zh) * | 2021-06-28 | 2021-08-10 | 中国铁建重工集团股份有限公司 | 一种掘进装置及其锚杆支护装置 |
CN113374475A (zh) * | 2021-06-28 | 2021-09-10 | 中国铁建重工集团股份有限公司 | 一种探掘支运一体机 |
CN115929368A (zh) * | 2022-11-11 | 2023-04-07 | 江苏中贵重工有限公司 | 适用于拱形巷道的锚杆转载机组、组合装置及施工方法 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101046152A (zh) * | 2006-03-29 | 2007-10-03 | 三一重型装备有限公司 | 掘锚一体化的掘锚机 |
CN201344039Y (zh) * | 2008-12-30 | 2009-11-11 | 三一重型装备有限公司 | 锚杆台车 |
CN201443396U (zh) * | 2009-08-07 | 2010-04-28 | 三一重型装备有限公司 | 掘锚护一体机 |
US20100119310A1 (en) * | 2007-10-01 | 2010-05-13 | Zhendong Yan | crawler-type and height adjustment drilling machine for setting roof and side wall anchor bolts and anchor cables |
CN202500562U (zh) * | 2012-01-11 | 2012-10-24 | 中国矿业大学(北京) | 掘、护、锚平行作业系统 |
CN102817610A (zh) * | 2012-08-22 | 2012-12-12 | 中传重型装备有限公司 | 一种掘锚护一体机 |
CN203403900U (zh) * | 2013-08-02 | 2014-01-22 | 天地上海采掘装备科技有限公司 | 吊装自移式锚杆锚索支护设备 |
CN207538833U (zh) * | 2017-12-07 | 2018-06-26 | 顾天祥 | 掘、锚、护一体化的掘锚护机 |
-
2017
- 2017-12-07 CN CN201711288542.3A patent/CN107859519A/zh active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101046152A (zh) * | 2006-03-29 | 2007-10-03 | 三一重型装备有限公司 | 掘锚一体化的掘锚机 |
US20100119310A1 (en) * | 2007-10-01 | 2010-05-13 | Zhendong Yan | crawler-type and height adjustment drilling machine for setting roof and side wall anchor bolts and anchor cables |
CN201344039Y (zh) * | 2008-12-30 | 2009-11-11 | 三一重型装备有限公司 | 锚杆台车 |
CN201443396U (zh) * | 2009-08-07 | 2010-04-28 | 三一重型装备有限公司 | 掘锚护一体机 |
CN202500562U (zh) * | 2012-01-11 | 2012-10-24 | 中国矿业大学(北京) | 掘、护、锚平行作业系统 |
CN102817610A (zh) * | 2012-08-22 | 2012-12-12 | 中传重型装备有限公司 | 一种掘锚护一体机 |
CN203403900U (zh) * | 2013-08-02 | 2014-01-22 | 天地上海采掘装备科技有限公司 | 吊装自移式锚杆锚索支护设备 |
CN207538833U (zh) * | 2017-12-07 | 2018-06-26 | 顾天祥 | 掘、锚、护一体化的掘锚护机 |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109372524A (zh) * | 2018-12-27 | 2019-02-22 | 山东兖煤黑豹矿业装备有限公司 | 掘锚护一体机的模块化锚杆机组 |
CN112392520A (zh) * | 2020-11-16 | 2021-02-23 | 中国铁建重工集团股份有限公司 | 一种锚杆支护组件及锚杆钻车 |
CN113236320A (zh) * | 2021-06-28 | 2021-08-10 | 中国铁建重工集团股份有限公司 | 一种掘进装置及其锚杆支护装置 |
CN113374475A (zh) * | 2021-06-28 | 2021-09-10 | 中国铁建重工集团股份有限公司 | 一种探掘支运一体机 |
CN113236320B (zh) * | 2021-06-28 | 2023-01-20 | 中国铁建重工集团股份有限公司 | 一种掘进装置及其锚杆支护装置 |
CN113374475B (zh) * | 2021-06-28 | 2024-04-23 | 中国铁建重工集团股份有限公司 | 一种探掘支运一体机 |
CN115929368A (zh) * | 2022-11-11 | 2023-04-07 | 江苏中贵重工有限公司 | 适用于拱形巷道的锚杆转载机组、组合装置及施工方法 |
CN115929368B (zh) * | 2022-11-11 | 2023-10-10 | 江苏中贵重工有限公司 | 适用于拱形巷道的锚杆转载机组、组合装置及施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107859519A (zh) | 掘、锚、护一体化的掘锚护机 | |
CN102587945B (zh) | 掘进巷道液压迈步式多级临时支护装备 | |
CN201460935U (zh) | 充填支护一体化液压支架 | |
CN101514633A (zh) | 无巷旁支护的沿空留巷工艺 | |
CN210530828U (zh) | 掘、锚、护一体化的掘锚护机 | |
CN102251789A (zh) | 一种急倾斜巷道放顶煤组合式自移液压支架 | |
CN202391424U (zh) | 支护式综合掘锚机 | |
CN105041357A (zh) | 单轨吊运尾变首式超前支护系统 | |
CN207538833U (zh) | 掘、锚、护一体化的掘锚护机 | |
CN102562112A (zh) | 四柱悬挂摆梁式矸石填充液压支架 | |
CN203362198U (zh) | 履带行走式综掘巷道及时支护装置 | |
CN202220614U (zh) | 一种急倾斜巷道放顶煤组合式自移液压支架 | |
CN105952462A (zh) | 邻近工程建设过程中的盾构隧道变形控制方法 | |
CN203783620U (zh) | 一种自移式拱形掩护支架、锚网喷防尘一体机 | |
CN106677806B (zh) | 一种用于井下巷道、隧道的管式棚架支护结构 | |
CN103104277B (zh) | 一种多步距带尾梁支撑式充填液压支架 | |
CN205100527U (zh) | 用于超高挡土墙的悬臂施工平台 | |
CN202628142U (zh) | 掘进巷道液压迈步式多级临时支护装备 | |
CN105421458B (zh) | 一种混凝土布料机浇筑系统 | |
CN102587977A (zh) | 四柱双摆梁式矸石填充液压支架 | |
CN205605219U (zh) | 分体始发盾构机及临时出渣系统 | |
CN109281697A (zh) | 一种掘进支护设备 | |
CN205422781U (zh) | 单轨吊运尾变首式超前支护系统 | |
CN204492865U (zh) | 一种铝土矿巷道综掘机施工机载前探支护装置 | |
CN102926781A (zh) | 一种沿空留巷用反连杆机构支护设备 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20180330 Assignee: JIANGSU ZINGO HEAVY INDUSTRY Co.,Ltd. Assignor: Gu Tianxiang Contract record no.: X2020990000153 Denomination of invention: Tunneling, anchoring and protecting integrated tunneling-anchoring-protecting machine License type: Exclusive License Record date: 20200402 |
|
EE01 | Entry into force of recordation of patent licensing contract | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20180330 |
|
WD01 | Invention patent application deemed withdrawn after publication |