CN107419052A - 120t转炉更换炉衬耐火材料后的烘炉方法 - Google Patents

120t转炉更换炉衬耐火材料后的烘炉方法 Download PDF

Info

Publication number
CN107419052A
CN107419052A CN201710576527.2A CN201710576527A CN107419052A CN 107419052 A CN107419052 A CN 107419052A CN 201710576527 A CN201710576527 A CN 201710576527A CN 107419052 A CN107419052 A CN 107419052A
Authority
CN
China
Prior art keywords
furnace
coke
oxygen
baker
furnace lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710576527.2A
Other languages
English (en)
Inventor
卜志胜
徐栋
郭庆华
汤新彦
陈刚
郭鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Bayi Iron and Steel Co Ltd
Original Assignee
Xinjiang Bayi Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Bayi Iron and Steel Co Ltd filed Critical Xinjiang Bayi Iron and Steel Co Ltd
Priority to CN201710576527.2A priority Critical patent/CN107419052A/zh
Publication of CN107419052A publication Critical patent/CN107419052A/zh
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C21METALLURGY OF IRON
    • C21CPROCESSING OF PIG-IRON, e.g. REFINING, MANUFACTURE OF WROUGHT-IRON OR STEEL; TREATMENT IN MOLTEN STATE OF FERROUS ALLOYS
    • C21C5/00Manufacture of carbon-steel, e.g. plain mild steel, medium carbon steel or cast steel or stainless steel
    • C21C5/28Manufacture of steel in the converter
    • C21C5/42Constructional features of converters
    • C21C5/44Refractory linings
    • C21C5/441Equipment used for making or repairing linings

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Manufacturing & Machinery (AREA)
  • Materials Engineering (AREA)
  • Metallurgy (AREA)
  • Organic Chemistry (AREA)
  • Coke Industry (AREA)

Abstract

本发明公开了一种120t转炉更换炉衬耐火材料后的烘炉方法,包括如下步骤:(1)烘炉前向炉内加入8吨焦炭,1吨废旧木材,将木材引燃;(2)下枪吹氧待木材着火后,从炉顶料仓分批向炉内加焦炭,(3)氧流量的控制,下枪前将流量设定在5000m³/h,根据燃烧情况将流量调整到8000m³/h,(4)氧枪枪位控制,开吹前氧枪距炉内焦炭顶面的高度为2.5m,20分钟之后,提高氧枪枪位,保持炉衬温度均匀升高;(5)底吹控制:打开底吹装置吹氮气,(6)烘炉结束:烘炉后期炉衬温度达到780℃‑820℃,烘炉结束,提枪后立即兑铁水吹炼。本发明实现烘炉匀速升温,使炉衬耐火材料中的自然水和结晶水完全脱除,烘炉后炉衬转结合紧密,炉膛温度达到设计要求,缩短烘炉时间,延长炉衬的使用寿命。

Description

120t转炉更换炉衬耐火材料后的烘炉方法
技术领域
本发明属于炼钢企业120吨转炉更换炉衬耐火材料后的烘炉方法,特别是一种120t转炉更换炉衬耐火材料后的烘炉方法。
背景技术
转炉烘炉的目的是为了脱除炉衬耐火材料中的自然水和结晶水,以免在冶炼钢水时由于炉温上升太快,水份大量膨胀造成炉体胀裂、鼓泡或变形甚至炉墙倒塌,影响转炉炉衬的强度和使用寿命。
120t转炉开新炉烘炉时间4小时,不但烘炉时间长而且炉温升温不均匀,造成烘炉效果效果差,炉衬寿命缩短。
发明内容
本发明的目的在于提供一种120t转炉更换炉衬耐火材料后的烘炉方法,可以实现烘炉匀速升温,使炉衬耐火材料中的自然水和结晶水完全脱除,烘炉后炉衬转结合紧密,炉膛温度达到设计要求,可以缩短烘炉时间,延长炉衬的使用寿命。
本发明的目的是这样实现的:一种120t转炉更换炉衬耐火材料后的烘炉方法,包括如下步骤:
(1)烘炉前向炉内加入8吨焦炭,1吨废旧木材,用棉纱浸柴油点燃从炉口投入,将木材引燃;
(2)下枪吹氧待木材着火后,从炉顶料仓分批向炉内加焦炭,第一批焦炭,前120分钟内分3次加入,每次加入一吨焦炭,以后每批间隔20分钟加入0.5吨焦炭,烘炉时间为2.5-3.5小时;
(3)氧流量的控制,下枪前将流量设定在5000m³/h,根据烘烤时间、枪位及焦炭燃烧的情况,流量调整到8000m³/h,焦炭均匀燃烧之后流量保持不变;
(4)氧枪枪位控制,开吹前氧枪距炉内焦炭顶面的高度为2.5m,在氧枪开吹20分钟之后,随着炉内温度和炉衬温度的升高,及时加入焦炭,同时提高氧枪枪位以减缓炉内温度的升高趋势,保持炉衬温度均匀升高;
(5)底吹控制:打开底吹装置吹氮气,每块透气砖供气量为38-42m³/h;
(6)烘炉结束:烘炉后期炉衬温度达到780°C -820°C,烘炉结束,提枪后立即兑铁水吹炼。
烘炉的焦炭分11批加入,其中第一批分3次加入3吨焦炭,以后的批次每批分别加入0.5吨焦炭。
第一批加入焦炭的吹氧时间为120分钟,以后每加一批焦炭的吹氧时间为15分钟。
炉衬温度均匀升高的数值为每分钟升高3°C。
烘炉氧枪吹氧的供氧氧气的压力为0.2Mpa,氧气流量为5000-8000 m³/h。
烘炉时有关参数控制见表1:
表1:
转炉烘炉期间,测量风机入口烟气温度,适当提高风机转速,检查风机在高速运转时大于1100转/分钟,液力偶合器的油温是否在控制范围内波动(小于70摄氏度),检查电机电流情况,是否运行在额定电流范围内(149A),控制烟罩的位置,保证将其停放在下限位范围(0~+50mm)。
本发明的实施效果:
1、烘炉后炉衬砖紧密结合,炉膛温度达到预定要求。
2、缩短了烘炉时间,由原先的4小时减少到3小时。
3、炉衬寿命延长,炉衬寿命最高达到11000炉。
本发明实现了烘炉匀速升温,使炉衬耐火材料中的自然水和结晶水完全脱除,烘炉后炉衬转结合紧密,炉膛温度达到设计要求,缩短了烘炉时间,延长了炉衬的使用寿命。
具体实施方式
一种120t转炉更换炉衬耐火材料后的烘炉方法,该方法包括以下操作步骤:
(1)烘炉前向炉内加入8吨大焦,1吨废旧木材,用棉纱浸柴油点燃从炉口投入,将木材引燃。
(2)下枪吹氧待木材着火后,从炉顶料仓分批向炉内加焦碳,第一批焦碳,前120分钟内分3次,每次加1吨,间隔时间为40分钟,共加入3吨焦碳,以后每隔20分钟加入0.5t焦碳,烘炉时间为3小时左右。
(3)氧流量的控制,下枪前将流量设定在5000m3/h,根据烘烤时间、枪位及焦炭燃烧的情况,调整流量到 8000m3/h,焦炭均匀燃烧之后流量基本保持不变。
(4)氧枪枪位控制,开吹前20分钟氧枪距炉内焦炭顶面的距离为2.5m(距炉底3.8m),整个烘炉过程在开吹20分钟之后,随着炉内温度和炉衬温度的升高趋势及时加入焦炭,并且改变氧枪枪位。动枪依据是:当炉内温度升高过快时,每分钟炉内温度升高超过10°C时,加入焦炭,同时提高氧枪以减缓炉内温度的升高趋势,同时增加炉内固定热值使炉衬温度均匀升高;均匀升高的数量为分钟升高3°C,当炉内温度升高速度降低时,降低氧枪枪位以加速炉内焦炭的燃烧速度,迅速提高炉内温度使炉衬温度继续匀速稳定的升高。
(5)底吹控制:底吹开氮气,每块透气砖供气量为40m3/h左右。
(6)烘炉结束:烘炉后期炉衬温度应达到800±10℃左右为最佳。烘炉结束提枪后,前后来回小角度摇炉,小角度为5度以内,从炉口观察,如残焦不多,不倒炉内残渣立即兑铁吹炼。

Claims (5)

1.一种120t转炉更换炉衬耐火材料后的烘炉方法,其特征是包括如下步骤:
(1)烘炉前向炉内加入8吨焦炭,1吨废旧木材,用棉纱浸柴油点燃从炉口投入,将木材引燃;
(2)下枪吹氧待木材着火后,从炉顶料仓分批向炉内加焦炭,第一批焦炭,前120分钟内分3次加入,每次加入一吨焦炭,以后每批间隔20分钟加入0.5吨焦炭,烘炉时间为2.5-3.5小时;
(3)氧流量的控制,下枪前将流量设定在5000m³/h,根据烘烤时间、枪位及焦炭燃烧的情况,流量调整到8000m³/h,焦炭均匀燃烧之后流量保持不变;
(4)氧枪枪位控制,开吹前氧枪距炉内焦炭顶面的高度为2.5m,在氧枪开吹20分钟之后,随着炉内温度和炉衬温度的升高,及时加入焦炭,同时提高氧枪枪位以减缓炉内温度的升高趋势,保持炉衬温度均匀升高;
(5)底吹控制:打开底吹装置吹氮气,每块透气砖供气量为38-42m³/h;
(6)烘炉结束:烘炉后期炉衬温度达到780°C -820°C,烘炉结束,提枪后立即兑铁水吹炼。
2.根据权利要求1所述的120t转炉更换炉衬耐火材料后的烘炉方法,其特征是:烘炉的焦炭分11批加入,其中第一批分3次加入3吨焦炭,以后的批次每批分别加入0.5吨焦炭。
3.根据权利要求1所述的120t转炉更换炉衬耐火材料后的烘炉方法,其特征是:第一批加入焦炭的吹氧时间为120分钟,以后每加一批焦炭的吹氧时间为15分钟。
4.根据权利要求1所述的120t转炉更换炉衬耐火材料后的烘炉方法,其特征是:炉衬温度均匀升高的数值为每分钟升高3°C。
5.根据权利要求1所述的120t转炉更换炉衬耐火材料后的烘炉方法,其特征是:烘炉氧枪吹氧的供氧氧气的压力为0.2Mpa,氧气流量为5000-8000 m³/h。
CN201710576527.2A 2017-07-14 2017-07-14 120t转炉更换炉衬耐火材料后的烘炉方法 Pending CN107419052A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710576527.2A CN107419052A (zh) 2017-07-14 2017-07-14 120t转炉更换炉衬耐火材料后的烘炉方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710576527.2A CN107419052A (zh) 2017-07-14 2017-07-14 120t转炉更换炉衬耐火材料后的烘炉方法

Publications (1)

Publication Number Publication Date
CN107419052A true CN107419052A (zh) 2017-12-01

Family

ID=60426495

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710576527.2A Pending CN107419052A (zh) 2017-07-14 2017-07-14 120t转炉更换炉衬耐火材料后的烘炉方法

Country Status (1)

Country Link
CN (1) CN107419052A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109988590A (zh) * 2017-12-29 2019-07-09 新疆八一钢铁股份有限公司 一种大型高炉使用低热态强度焦炭的冶炼方法
CN111928674A (zh) * 2020-08-13 2020-11-13 楚雄滇中有色金属有限责任公司 一种精准控制ps转炉烘炉温度的方法
CN114152093A (zh) * 2021-09-23 2022-03-08 贵州金源锰业股份有限公司 一种直流电炉烘炉方法
CN114350885A (zh) * 2022-01-07 2022-04-15 鞍钢股份有限公司 一种顶底复吹转炉开炉方法
CN114737016A (zh) * 2022-04-29 2022-07-12 马鞍山钢铁股份有限公司 一种大型转炉的烘炉方法
CN115418433A (zh) * 2022-09-09 2022-12-02 甘肃酒钢集团宏兴钢铁股份有限公司 一种转炉开新炉高温烘炉方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5935408B2 (ja) * 1978-12-18 1984-08-28 川崎製鉄株式会社 底吹き転炉の炉内昇熱方法
CN102719591A (zh) * 2011-03-30 2012-10-10 鞍钢股份有限公司 一种转炉多步骤烘炉方法
CN103397139A (zh) * 2013-08-11 2013-11-20 山西太钢不锈钢股份有限公司 一种中频炉炉衬的烘烤方法
CN104673955A (zh) * 2015-03-05 2015-06-03 山东钢铁股份有限公司 一种转炉停炉保温方法
CN104928433A (zh) * 2015-06-01 2015-09-23 山东钢铁股份有限公司 一种顶底复吹转炉的烘炉方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5935408B2 (ja) * 1978-12-18 1984-08-28 川崎製鉄株式会社 底吹き転炉の炉内昇熱方法
CN102719591A (zh) * 2011-03-30 2012-10-10 鞍钢股份有限公司 一种转炉多步骤烘炉方法
CN103397139A (zh) * 2013-08-11 2013-11-20 山西太钢不锈钢股份有限公司 一种中频炉炉衬的烘烤方法
CN104673955A (zh) * 2015-03-05 2015-06-03 山东钢铁股份有限公司 一种转炉停炉保温方法
CN104928433A (zh) * 2015-06-01 2015-09-23 山东钢铁股份有限公司 一种顶底复吹转炉的烘炉方法

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109988590A (zh) * 2017-12-29 2019-07-09 新疆八一钢铁股份有限公司 一种大型高炉使用低热态强度焦炭的冶炼方法
CN111928674A (zh) * 2020-08-13 2020-11-13 楚雄滇中有色金属有限责任公司 一种精准控制ps转炉烘炉温度的方法
CN114152093A (zh) * 2021-09-23 2022-03-08 贵州金源锰业股份有限公司 一种直流电炉烘炉方法
CN114152093B (zh) * 2021-09-23 2024-04-12 贵州金源锰业股份有限公司 一种直流电炉烘炉方法
CN114350885A (zh) * 2022-01-07 2022-04-15 鞍钢股份有限公司 一种顶底复吹转炉开炉方法
CN114737016A (zh) * 2022-04-29 2022-07-12 马鞍山钢铁股份有限公司 一种大型转炉的烘炉方法
CN114737016B (zh) * 2022-04-29 2023-10-27 马鞍山钢铁股份有限公司 一种大型转炉的烘炉方法
CN115418433A (zh) * 2022-09-09 2022-12-02 甘肃酒钢集团宏兴钢铁股份有限公司 一种转炉开新炉高温烘炉方法
CN115418433B (zh) * 2022-09-09 2023-09-26 甘肃酒钢集团宏兴钢铁股份有限公司 一种转炉开新炉高温烘炉方法

Similar Documents

Publication Publication Date Title
CN107419052A (zh) 120t转炉更换炉衬耐火材料后的烘炉方法
CN104928433B (zh) 一种顶底复吹转炉的烘炉方法
CN101619375B (zh) 顶底复吹转炉防止电除尘泄爆的方法
CN102745651A (zh) 一种节能、环保的沸腾炉升温方法
CN106967448A (zh) 一种干熄焦系统耐材大面积更换后的烘炉方法
CN111020086A (zh) 一种高炉开炉快速引煤气的方法
CN101353579B (zh) 一种7.63米焦炉负压炉内烘炉方法
CN104611487A (zh) 一种高炉烘炉控制炉顶温度的方法
JPS5822527B2 (ja) ペレツトを焼成する方法および装置
CN108411064A (zh) 电炉废钢预热的方法
CN102559994A (zh) 电炉铁水烘炉方法
CN107326201A (zh) 一种预合金粉熔炼中频炉新炉的烘炉方法
CN1361290A (zh) 一种高炉开炉方法
CN106048115A (zh) 一种高炉休风后炉顶点火的方法
CN115418433B (zh) 一种转炉开新炉高温烘炉方法
CN111440913A (zh) 一种熔融还原炉灌铁水启动的方法
CN1301871A (zh) 高炉预热炉缸开炉法
CN110499402A (zh) 一种冶金设备使用改进方案
CN116987837A (zh) 转炉的烘炉工艺
CN219772158U (zh) 一种使用纯高炉煤气烘热风炉系统
SU933705A1 (ru) Способ задувки доменной печи
CN116929082A (zh) 一种利用富氧侧吹熔炼炉及电热前床烘炉方法
KR100435563B1 (ko) 전기로에서 탈탄속도 향상을 통한 용강제조방법
CN106643137A (zh) 一种新的节能环保型台车炉
SU431219A1 (ru) Способ сушки воздухонагревателей доменных печей

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20171201

WD01 Invention patent application deemed withdrawn after publication