CN107190990A - 一种局限空间下厂房钢柱安装方法 - Google Patents
一种局限空间下厂房钢柱安装方法 Download PDFInfo
- Publication number
- CN107190990A CN107190990A CN201710412469.XA CN201710412469A CN107190990A CN 107190990 A CN107190990 A CN 107190990A CN 201710412469 A CN201710412469 A CN 201710412469A CN 107190990 A CN107190990 A CN 107190990A
- Authority
- CN
- China
- Prior art keywords
- steel column
- jack
- opposite direction
- installation
- factory building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/165—Tools or apparatus specially adapted for in situ prefabricated building elements to be tilted up in position
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种局限空间下厂房钢柱安装方法,属于局限区域空间内钢柱安装技术领域。钢柱安装流程:一台倒链牵引钢柱至安装位置→一台倒链从顶部提升钢柱,同时另一台倒链反方向固定从底部提升钢柱→反方向再增加一台倒链从顶部提升钢柱,同时底部倒链缓慢释放倒链→三台倒链协调配合→钢柱安装就位。优点在于:通过多台倒链接力协调配合,钢柱顺利安装就位,避免了拆除屋面及大型吊车的安装使用,在施工安全、工期、质量上得到充足保障,而且大大降低了安装成本,为公司取得了良好的经济效益。
Description
技术领域
本发明属于局限区域空间内厂房钢柱安装技术领域,特别是提供了一种局限空间下厂房钢柱安装方法。
背景技术
厂房钢柱安装一般情况下都是在厂房封闭前进行,但是有些特殊及意外情况使得钢柱不能满足厂房封闭前安装,我单位所施工的北京平谷物流仓库封闭后,由于后续增加功能需要,在仓库中间跨增设一定置观察平台,用于人工观测货物流通情况,平台由4根500*300焊接H型钢为主要支撑,小型槽钢及角钢为附属支撑,上铺花纹钢板,平台高10.5米,库房最高点19.5米。施工重点为4根钢柱的安装,钢柱单重1.1t。本施工难点为厂房完全封闭,除了倒运货物的小型叉车外,库房无天车,且库房周围为高台,汽车吊不能进入厂房安装,按照常规施工经验,对仓库安装平台的正上部屋面进行区域拆除,再利用大型吊车站位库房外侧道路进行吊装就位,此传统安装方式不但时间较长(拆除恢复彩板),而且成本较大(拆除的彩板不能再利用,需使用新的彩板,且大型吊车费用较高),我单位经过多年施工经验积累,以保证安全、缩短工期、降低成本为宗旨,探索总结出了一套新的局限空间钢柱安装工艺,并在平谷物流仓库新增钢柱的安装中成功加以应用。
发明内容
本发明的目的在于提供一种局限空间下厂房钢柱安装方法,通过对钢柱安装区域空间综合考虑,采用多台倒链接力配合的方式,使钢柱顺利安装就位;避免了拆除屋面板及大型吊车的使用,降低了施工工期,节约了施工成本。
本发明的钢柱安装流程:一台倒链牵引钢柱至安装位置→一台倒链从顶部提升钢柱,同时另一台倒链反方向固定从底部提升钢柱→反方向再增加一台倒链从顶部提升钢柱,同时底部倒链缓慢释放倒链→三台倒链协调配合→钢柱安装就位。具体步骤如下:
第一步,利用一台5t倒链以钢柱为支撑点将钢柱拖至安装基础位置(见图1);
第二步,将5t倒链固定在屋顶柱间托梁上,以托梁为支撑点,在钢柱顶端设吊点,利用该倒链缓慢匀速吊起钢柱,同时利用另一台5t倒链反方向从钢柱底部位置设吊点,提起钢柱,避免破坏基础;(见图2)
第三步,在钢柱反方向再增加一台倒链从顶部提升钢柱,同时底部倒链缓慢释放倒链(见图3);
第四步,三台倒链协调配合(顶部两台倒链提升钢柱,底部一台倒链缓慢释放倒链),钢柱安装就位(见图4)。
本发明的优点在于:通过多台倒链接力协调配合,钢柱顺利安装就位,避免了拆除屋面及大型吊车的安装使用,在施工安全、工期、质量上得到充足保障,而且大大降低了安装成本,为公司取得了良好的经济效益。
附图说明
图1为钢柱受一台倒链牵引横向受力位移图。
图2为钢柱受二台倒链双向配合向上提升图。
图3为钢柱受三台倒链双向配合向上提升图。
图4为钢柱受三台倒链协调配合安装就位图。
具体实施方式
图1-图4为本发明的一种具体实施方式。具体步骤如下:
第一步,利用一台5t倒链以钢柱为支撑点将钢柱拖至安装基础位置(见图1);
第二步,将5t倒链固定在屋顶柱间托梁上,以托梁为支撑点,在钢柱顶端设吊点,利用该倒链缓慢匀速吊起钢柱,同时利用另一台5t倒链反方向从钢柱底部位置设吊点,提起钢柱,避免破坏基础;(见图2)
第三步,在钢柱反方向再增加一台倒链从顶部提升钢柱,同时底部倒链缓慢释放倒链(见图3);
第四步,三台倒链协调配合(顶部两台倒链提升钢柱,底部一台倒链缓慢释放倒链),钢柱安装就位(见图4)。
Claims (1)
1.一种局限空间下厂房钢柱安装方法,其特征在于,具体步骤如下:
第一步,利用一台5t倒链以钢柱为支撑点将钢柱拖至安装基础位置;
第二步,将5t倒链固定在屋顶柱间托梁上,以托梁为支撑点,在钢柱顶端设吊点,利用该倒链吊起钢柱,同时利用另一台5t倒链反方向从钢柱底部位置设吊点,提起钢柱,避免破坏钢柱基础;
第三步,在钢柱反方向再增加一台倒链从顶部提升钢柱,同时底部倒链缓慢释放倒链;
第四步,三台倒链协调配合:顶部两台倒链提升钢柱,底部一台倒链释放倒链,钢柱安装就位。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710412469.XA CN107190990A (zh) | 2017-06-02 | 2017-06-02 | 一种局限空间下厂房钢柱安装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710412469.XA CN107190990A (zh) | 2017-06-02 | 2017-06-02 | 一种局限空间下厂房钢柱安装方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107190990A true CN107190990A (zh) | 2017-09-22 |
Family
ID=59877087
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710412469.XA Pending CN107190990A (zh) | 2017-06-02 | 2017-06-02 | 一种局限空间下厂房钢柱安装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107190990A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110984611A (zh) * | 2019-11-29 | 2020-04-10 | 中国二十二冶集团有限公司 | 狭窄空间钢柱安装方法 |
CN112696083A (zh) * | 2020-12-20 | 2021-04-23 | 北京首钢建设集团有限公司 | 一种局限区域内的烟囱安装方法 |
CN113445777A (zh) * | 2021-07-12 | 2021-09-28 | 中国二十冶集团有限公司 | 酸洗厂房废气排气筒移位更新改造方法 |
CN114776038A (zh) * | 2022-04-13 | 2022-07-22 | 北京首钢建设集团有限公司 | 一种钢桁架安装结构及其阶梯卸载方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09184294A (ja) * | 1995-12-28 | 1997-07-15 | Penta Ocean Constr Co Ltd | 柱材の建て起こし方法及び装置 |
JP2001089076A (ja) * | 1999-09-24 | 2001-04-03 | Hitachi Building Systems Co Ltd | 重量物揚重雇およびその設置方法 |
CN102372228A (zh) * | 2010-08-19 | 2012-03-14 | 中冶天工集团有限公司 | 大跨度吊车梁平移安装方法 |
CN103669882A (zh) * | 2013-10-31 | 2014-03-26 | 中冶天工集团有限公司 | 工业厂房内利用钢丝绳做轨道进行构件安装的方法 |
CN104264781A (zh) * | 2014-10-31 | 2015-01-07 | 中国建筑第二工程局有限公司 | 网格状柱面钢结构网壳及其施工方法 |
CN105569351A (zh) * | 2015-12-20 | 2016-05-11 | 安徽伟宏钢结构集团股份有限公司 | 一种钢结构钢柱的安装施工工艺 |
-
2017
- 2017-06-02 CN CN201710412469.XA patent/CN107190990A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09184294A (ja) * | 1995-12-28 | 1997-07-15 | Penta Ocean Constr Co Ltd | 柱材の建て起こし方法及び装置 |
JP2001089076A (ja) * | 1999-09-24 | 2001-04-03 | Hitachi Building Systems Co Ltd | 重量物揚重雇およびその設置方法 |
CN102372228A (zh) * | 2010-08-19 | 2012-03-14 | 中冶天工集团有限公司 | 大跨度吊车梁平移安装方法 |
CN103669882A (zh) * | 2013-10-31 | 2014-03-26 | 中冶天工集团有限公司 | 工业厂房内利用钢丝绳做轨道进行构件安装的方法 |
CN104264781A (zh) * | 2014-10-31 | 2015-01-07 | 中国建筑第二工程局有限公司 | 网格状柱面钢结构网壳及其施工方法 |
CN105569351A (zh) * | 2015-12-20 | 2016-05-11 | 安徽伟宏钢结构集团股份有限公司 | 一种钢结构钢柱的安装施工工艺 |
Non-Patent Citations (1)
Title |
---|
潘家山: "三机抬吊钢筋混凝土柱", 《施工技术》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110984611A (zh) * | 2019-11-29 | 2020-04-10 | 中国二十二冶集团有限公司 | 狭窄空间钢柱安装方法 |
CN112696083A (zh) * | 2020-12-20 | 2021-04-23 | 北京首钢建设集团有限公司 | 一种局限区域内的烟囱安装方法 |
CN113445777A (zh) * | 2021-07-12 | 2021-09-28 | 中国二十冶集团有限公司 | 酸洗厂房废气排气筒移位更新改造方法 |
CN113445777B (zh) * | 2021-07-12 | 2023-09-15 | 中国二十冶集团有限公司 | 酸洗厂房废气排气筒移位更新改造方法 |
CN114776038A (zh) * | 2022-04-13 | 2022-07-22 | 北京首钢建设集团有限公司 | 一种钢桁架安装结构及其阶梯卸载方法 |
CN114776038B (zh) * | 2022-04-13 | 2024-03-29 | 北京首钢建设集团有限公司 | 一种钢桁架安装结构及其阶梯卸载方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107190990A (zh) | 一种局限空间下厂房钢柱安装方法 | |
CN101518784B (zh) | 大型轧机牌坊在吊装高度受限下的吊装方法 | |
CN104695337B (zh) | 自提升滑翻施工系统及施工方法 | |
CN205772984U (zh) | 一种单片钢桁架的吊装装置 | |
CN103967284B (zh) | 预留柱头对接的钢柱安装方法 | |
CN204185120U (zh) | 移动式设备就位小车 | |
CN106285019B (zh) | 一种局限空间下的天车安装方法 | |
CN106758872A (zh) | 波形钢腹板scc工法随车回旋吊移动挂篮及利用其施工的方法 | |
CN104989111B (zh) | 钢结构高层吊装施工方法 | |
CN103669882B (zh) | 工业厂房内利用钢丝绳做轨道进行构件安装的方法 | |
CN105781210A (zh) | 一种锥形塔架及其工具节辅助穿心式整体提升施工方法 | |
CN107419907B (zh) | 一种炼钢塔楼钢结构平台的交错安装焊接方法 | |
CN105756368A (zh) | 一种简便的重型工业厂房托梁拔柱施工方法 | |
CN103086276A (zh) | 一种吊装高层井塔型建筑物内桥式起重机的施工方法 | |
CN102587676B (zh) | 安装核电站核岛内主梁结构的方法 | |
CN103821084A (zh) | 梁底作业设备及梁底作业方法 | |
CN208563122U (zh) | 一种“行走式”盖梁施工作业平台 | |
CN110130653A (zh) | 一种局限区域内框架钢梁利用卷扬吊装的施工方法 | |
CN102259794B (zh) | 整体组合式吊车梁的安装方法 | |
CN204185146U (zh) | 高层建筑双塔楼间钢结构施工用悬挂起重机 | |
CN108545629A (zh) | 利用塔式起重机顶升桁架梁的施工方法 | |
CN105113801B (zh) | 一种大跨度钢结构吊装方法 | |
CN106522361A (zh) | 多层重型空中钢连廊的组合安装方法 | |
CN104912339B (zh) | 长距离多跨段焊接h型钢屋面梁就位方法 | |
CN105253793A (zh) | 一种镀锌车间锌锅牵引运输吊装的施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170922 |
|
RJ01 | Rejection of invention patent application after publication |