CN103669882B - 工业厂房内利用钢丝绳做轨道进行构件安装的方法 - Google Patents
工业厂房内利用钢丝绳做轨道进行构件安装的方法 Download PDFInfo
- Publication number
- CN103669882B CN103669882B CN201310533704.0A CN201310533704A CN103669882B CN 103669882 B CN103669882 B CN 103669882B CN 201310533704 A CN201310533704 A CN 201310533704A CN 103669882 B CN103669882 B CN 103669882B
- Authority
- CN
- China
- Prior art keywords
- wire rope
- jack
- pulley
- industrial premises
- carries out
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009434 installation Methods 0.000 title claims abstract description 23
- 238000000034 method Methods 0.000 title claims abstract description 18
- 238000010276 construction Methods 0.000 claims abstract description 13
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明涉及一种工业厂房内利用钢丝绳做轨道进行构件安装的方法,其方法的步骤如下:⑴、工业厂房内框架梁的施工;⑵、在已安装好的同跨相邻两内侧框架梁上对称均布固装四个立柱并安装立柱钢丝绳转动轮;⑶、将两条钢丝绳轨道分别安装在同排的立柱钢丝绳转动轮,钢丝绳轨道连接相邻外侧框架梁,在两个立柱之间的钢丝绳轨道上安装滑轮,在滑轮下端连接吊装倒链,滑轮左端通过左侧倒链连接相应立柱,滑轮右端通过右侧倒链连接相应立柱;⑷、将构件吊装到相应位置后,开始构件与梁的栓焊,构件安装完毕。本发明能够快速便捷的安装构件,提高了施工速度,降低了施工成本,缩短了施工时间,提高了施工效率。
Description
技术领域
本发明属于构件安装领域,尤其是一种工业厂房内利用钢丝绳做轨道进行构件安装的方法。
背景技术
在通常情况下,钢构件一般直接由吊车吊装,但是常常会因为施工场地的局限性及施工环境的多样性、复杂性,遇到一些无法使用吊车的特殊情况。另外还有些情况为安装现场吊车占位条件差,不得已用大型吊车进行吊装,造成吊装费用过高,导致施工成本加大,或者即使使用大型吊车也无法完成吊装。
发明内容
本发明的目的在于克服现有技术的不足,提供一种工业厂房内利用钢丝绳做轨道进行构件安装的方法,本方法在工程的施工条件及环境无法使用正常机械设备进行安装的情况下,快速便捷的安装构件,提高了施工速度,降低了施工成本,缩短了施工时间,提高了施工效率。
本发明解决其技术问题是通过以下技术方案实现的:
一种工业厂房内利用钢丝绳做轨道进行构件安装的方法,其方法的步骤如下:
⑴、工业厂房内框架梁的施工;
⑵、在已安装好的同跨相邻两内侧框架梁上对称均布固装四个立柱并通过螺栓锁紧,每个立柱上端设置有立柱钢丝绳转动轮;
⑶、将两条钢丝绳轨道分别安装在同排的立柱钢丝绳转动轮,钢丝绳轨道一端连接相邻外侧框架梁,另一端通过轨道控制倒链连接另外一侧外侧框架梁,在两个立柱之间的钢丝绳轨道上安装滑轮,在滑轮下端连接吊装倒链,滑轮左端通过左侧倒链连接相应立柱,滑轮右端通过右侧倒链连接相应立柱;
⑷、将构件倒运到需要的吊装位置的下方,通过吊装倒链起吊构件,通过人工拉动吊装倒链将构件抬吊到对应的安装高度,通过人工拉动滑轮两端的左侧倒链以及右侧倒链调节构件的水平位置,待构件高度和水平位置都调节到相应位置后,开始构件与梁的栓焊,构件安装完毕;
上述的吊装倒链下端连接起吊钢丝绳。
上述的吊装倒链为5吨倒链。
上述的左侧倒链以及右侧倒链均分别为2吨倒链。
上述的轨道控制倒链为5吨倒链。
本发明的优点和有益效果为:
本发明能充分的利用工业厂房内现场的条件,制作简单、安装方便,既保证了安装工期也保证了安装质量,同时也节约了大量的资金。实际证明了这种安装方法是安全可靠的、经济实用的。本发明在工程的施工条件及环境无法使用正常机械设备进行安装的情况下,快速便捷的安装构件,提高了施工速度,降低了施工成本,缩短了施工时间,提高了施工效率。
附图说明
图1为本发明安装结构示意图;
图2为图1的俯视图。
具体实施方式
下面通过具体实施例对本发明作进一步详述,以下实施例只是描述性的,不是限定性的,不能以此限定本发明的保护范围。
一种工业厂房内利用钢丝绳做轨道进行构件安装的方法,其方法的步骤如下:
⑴、工业厂房内框架梁的施工;
⑵、在已安装好的同跨相邻两内侧框架梁4上对称均布固装四个立柱10并通过螺栓锁紧,每个立柱上端设置有立柱钢丝绳转动轮2;
⑶、将两条钢丝绳轨道8分别安装在同排的立柱钢丝绳转动轮,钢丝绳轨道一端连接相邻外侧框架梁1,另一端通过轨道控制倒链11连接另外一侧外侧框架梁,在两个立柱之间的钢丝绳轨道上安装滑轮5,在滑轮下端连接吊装倒链6,滑轮左端通过左侧倒链3连接相应立柱,滑轮右端通过右侧倒链9连接相应立柱;
⑷、将构件倒运到需要的吊装位置的下方,通过吊装倒链起吊构件,通过人工拉动吊装倒链将构件抬吊到对应的安装高度,通过人工拉动滑轮两端的左侧倒链以及右侧倒链调节构件的水平位置,待构件高度和水平位置都调节到相应位置后,开始构件与梁的栓焊,构件安装完毕;吊装倒链下端连接起吊钢丝绳7,该起吊钢丝绳绑扎构件,吊装倒链为5吨倒链,左侧倒链以及右侧倒链均分别为2吨倒链,轨道控制倒链为5吨倒链。
Claims (5)
1.一种工业厂房内利用钢丝绳做轨道进行构件安装的方法,其特征在于:该方法的步骤如下:
⑴、工业厂房内框架梁的施工;
⑵、在已安装好的同跨相邻两内侧框架梁上对称均布固装四个立柱并通过螺栓锁紧,每个立柱上端设置有立柱钢丝绳转动轮;
⑶、将两条钢丝绳轨道分别安装在同排的立柱钢丝绳转动轮,钢丝绳轨道一端连接相邻外侧框架梁,另一端通过轨道控制倒链连接另外一侧外侧框架梁,在两个立柱之间的钢丝绳轨道上安装滑轮,在滑轮下端连接吊装倒链,滑轮左端通过左侧倒链连接相应立柱,滑轮右端通过右侧倒链连接相应立柱;
⑷、将构件倒运到需要的吊装位置的下方,通过吊装倒链起吊构件,通过人工拉动吊装倒链将构件抬吊到对应的安装高度,通过人工拉动滑轮两端的左侧倒链以及右侧倒链调节构件的水平位置,待构件高度和水平位置都调节到相应位置后,开始构件与梁的栓焊,构件安装完毕。
2.根据权利要求1所述的工业厂房内利用钢丝绳做轨道进行构件安装的方法,其特征在于:所述的吊装倒链下端连接起吊钢丝绳。
3.根据权利要求1所述的工业厂房内利用钢丝绳做轨道进行构件安装的方法,其特征在于:所述的吊装倒链为5吨倒链。
4.根据权利要求1所述的工业厂房内利用钢丝绳做轨道进行构件安装的方法,其特征在于:所述的左侧倒链以及右侧倒链均分别为2吨倒链。
5.根据权利要求1所述的工业厂房内利用钢丝绳做轨道进行构件安装的方法,其特征在于:所述的轨道控制倒链为5吨倒链。
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310533704.0A CN103669882B (zh) | 2013-10-31 | 2013-10-31 | 工业厂房内利用钢丝绳做轨道进行构件安装的方法 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310533704.0A CN103669882B (zh) | 2013-10-31 | 2013-10-31 | 工业厂房内利用钢丝绳做轨道进行构件安装的方法 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN103669882A CN103669882A (zh) | 2014-03-26 |
| CN103669882B true CN103669882B (zh) | 2016-02-03 |
Family
ID=50308591
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201310533704.0A Active CN103669882B (zh) | 2013-10-31 | 2013-10-31 | 工业厂房内利用钢丝绳做轨道进行构件安装的方法 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN103669882B (zh) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104003314A (zh) * | 2014-06-12 | 2014-08-27 | 中建六局工业设备安装有限公司 | 一种用于狭小空间长距离起重运输的方法 |
| CN107190990A (zh) * | 2017-06-02 | 2017-09-22 | 北京首钢建设集团有限公司 | 一种局限空间下厂房钢柱安装方法 |
| CN107416670B (zh) * | 2017-09-07 | 2019-04-16 | 安徽涌诚机械有限公司 | 钢丝绳及吊带定点定位回收装置 |
| CN108756262A (zh) * | 2018-07-06 | 2018-11-06 | 上海宝冶集团有限公司 | 一种基坑大跨度自动覆盖系统 |
| CN110562689A (zh) * | 2019-09-09 | 2019-12-13 | 天津卡利欧玛热能设备制造有限公司 | 一种球形网架内的燃气红外辐射加热管的安装结构及方法 |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH1162079A (ja) * | 1997-08-18 | 1999-03-05 | Taisei Corp | 鉄骨造架構におけるフロアブロック工法 |
| CN102383613A (zh) * | 2011-11-11 | 2012-03-21 | 天津电力工程监理有限公司 | 发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置 |
| CN102677907A (zh) * | 2012-05-11 | 2012-09-19 | 中国十七冶集团有限公司 | 人工安装筒库库顶钢梁的方法 |
| CN103122658A (zh) * | 2012-11-26 | 2013-05-29 | 北京工业大学 | 一种工业化装配式多层钢框架结构及其施工方法 |
-
2013
- 2013-10-31 CN CN201310533704.0A patent/CN103669882B/zh active Active
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH1162079A (ja) * | 1997-08-18 | 1999-03-05 | Taisei Corp | 鉄骨造架構におけるフロアブロック工法 |
| CN102383613A (zh) * | 2011-11-11 | 2012-03-21 | 天津电力工程监理有限公司 | 发电厂主厂房钢屋架吊装施工方法及专用吊装起重装置 |
| CN102677907A (zh) * | 2012-05-11 | 2012-09-19 | 中国十七冶集团有限公司 | 人工安装筒库库顶钢梁的方法 |
| CN103122658A (zh) * | 2012-11-26 | 2013-05-29 | 北京工业大学 | 一种工业化装配式多层钢框架结构及其施工方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN103669882A (zh) | 2014-03-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103669882B (zh) | 工业厂房内利用钢丝绳做轨道进行构件安装的方法 | |
| CN204899238U (zh) | 一种单元式幕墙板块吊装装置 | |
| CN103437563B (zh) | 一种用于大型钢结构厂房钢骨架的安装方法 | |
| CN103899093A (zh) | 巨型框架钢桁架梁分步吊装施工工法 | |
| CN103288002B (zh) | 简易组合门架高空重物吊装装置 | |
| CN201292776Y (zh) | 一种海洋石油钻井平台井架 | |
| CN205634654U (zh) | 缆索吊起重机的跑车结构 | |
| CN104989111B (zh) | 钢结构高层吊装施工方法 | |
| CN102372228B (zh) | 大跨度吊车梁平移安装方法 | |
| CN204455842U (zh) | 桥梁预制梁板起梁架 | |
| CN107190990A (zh) | 一种局限空间下厂房钢柱安装方法 | |
| CN203284126U (zh) | 简易组合门架高空重物吊装装置 | |
| CN201770429U (zh) | 一种吊装、滑移用的门形框架 | |
| CN203867198U (zh) | 高层钢结构转换层桁架的滑移设备 | |
| CN201544837U (zh) | 快速组装卸车运输装置 | |
| CN103556837B (zh) | 一种在裙楼处实现钢柱安装的方法 | |
| CN203079487U (zh) | 一种大吨位电梯轿厢底 | |
| CN203475317U (zh) | 高墩系梁施工用托架 | |
| CN109138272B (zh) | 一种超高层钢棒群连接固定装置及方法 | |
| CN203229334U (zh) | 用于提升及平移单根钢构件的起重构架 | |
| CN204238443U (zh) | 一种可拆卸柱脚固定装置 | |
| CN204823735U (zh) | 一种起重机主梁结构 | |
| CN201406250Y (zh) | 升降机多节标准节加减装置 | |
| CN202810177U (zh) | 一种附着升降脚手架 | |
| CN203452056U (zh) | 一种导流洞闸门启吊装置 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |