CN107104394B - The method of blow-off line is crossed in a kind of extra-high-tension cable process of deployment - Google Patents

The method of blow-off line is crossed in a kind of extra-high-tension cable process of deployment Download PDF

Info

Publication number
CN107104394B
CN107104394B CN201710298166.XA CN201710298166A CN107104394B CN 107104394 B CN107104394 B CN 107104394B CN 201710298166 A CN201710298166 A CN 201710298166A CN 107104394 B CN107104394 B CN 107104394B
Authority
CN
China
Prior art keywords
metallic rod
cable
blow
line
crossing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710298166.XA
Other languages
Chinese (zh)
Other versions
CN107104394A (en
Inventor
陶霞霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Electric Power Research Institute of Guangdong Power Grid Co Ltd
Original Assignee
Wuhu Tai Qing Electronic Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhu Tai Qing Electronic Technology Co Ltd filed Critical Wuhu Tai Qing Electronic Technology Co Ltd
Priority to CN201710298166.XA priority Critical patent/CN107104394B/en
Publication of CN107104394A publication Critical patent/CN107104394A/en
Application granted granted Critical
Publication of CN107104394B publication Critical patent/CN107104394B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle

Abstract

The invention discloses a kind of methods that blow-off line is crossed in extra-high-tension cable process of deployment, which is characterized in that the first step prepares cable crossing blow-off line device;Second step covers cable crossing blow-off line device on blow-off line, while being firmly tied together cable crossing blow-off line device with blow-off line using rope;The end of cable to be laid is passed through the first metallic rod, the second metallic rod and third metallic rod, while guaranteeing that cable is located at the top of the first metallic rod, the lower section of the second metallic rod and third metallic rod by third step;The end of cable to be laid is fixed on mechanical traction device by the 4th step, and mechanical traction device moves towards to start to pull cable along groove.

Description

The method of blow-off line is crossed in a kind of extra-high-tension cable process of deployment
Technical field
The present invention relates to a kind of methods that blow-off line is crossed in extra-high-tension cable process of deployment.
Background technique
In the process of deployment of buried cable approximately as: firstly, establishment officer carry out topographic(al) reconnaissance, determine cable trench Excavate route;Then groove excavates in establishment officer, finally carries out cable laying, and the common method of cable laying is that mechanical traction is applied If.In order to guarantee the safety and cable construction quality of construction personnel, all first cable reel is steadily erected on pay off rack, frame If cable disk, cable disk is rolled to the predetermined area by the arrow direction on drum, then steel shaft is through in drum axis hole, The intensity and length of steel shaft should be combined with cable disk weight and width, enable drum activity freely, then led using machinery Gravitation draws cable, and guidance cable moves forward, by cable laying into groove after, be finally exactly by groove soil-burial.
But it is frequently encountered blow-off line during excavating groove, cable to be laid is placed in groove in this way Later using mechanical traction power draw cable if be easy for so that whole cable all vacantly.
Summary of the invention
The technical problem to be solved by the present invention is how to guarantee when mechanical traction power trailing cable encounters blow-off line whole Root cable will not be suspended.
The above technical problem is solved in order to realize, the technical scheme adopted by the invention is that: a kind of extra-high-tension cable laying The method of blow-off line is crossed in the process, which is characterized in that
The first step prepares cable crossing blow-off line device;
The cable crossing blow-off line device includes semicircle annulus, the first metallic rod, the second metallic rod, third gold Belong to bar;
One end of first metallic rod connects the highest point of semicircle annulus, and one end of the second metallic rod connects semicircle One minimum point of shape annulus, another minimum point of the semicircle annulus of one end connection of third metallic rod, and the first metallic rod, Second metallic rod and third metallic rod are each perpendicular to the plane where semicircle annulus;
Second step covers cable crossing blow-off line device on blow-off line, while being arranged cable crossing using rope Dirty plumbing installation is firmly tied together with blow-off line;
The end of cable to be laid is passed through the first metallic rod, the second metallic rod and third metallic rod, simultaneously by third step Guarantee that cable is located at the top of the first metallic rod, the lower section of the second metallic rod and third metallic rod;
The end of cable to be laid is fixed on mechanical traction device by the 4th step, and mechanical traction device is along groove Trend starts to pull cable.
Compared with the prior art, the advantages of the present invention are as follows: method disclosed by the invention can guarantee cable laying process In not to be suspended under the action of mechanical traction power be that still cable can be made to move towards along groove under the action of tractive force It is laid with.
Detailed description of the invention
Fig. 1 is the case where cable encounters blow-off line under the effect of mechanical traction power;
Fig. 2 is cable crossing blow-off line schematic device;
Fig. 3 is the effect diagram using cable laying after cable crossing blow-off line device.
Wherein, 1 is cable;2 be blow-off line;3 be the first metallic rod;4 be the second metallic rod;5 be third metallic rod.
Specific embodiment
Invention is described in further detail with reference to the accompanying drawing.
Embodiment: the method for blow-off line is crossed in extra-high-tension cable process of deployment, which is characterized in that
The first step prepares cable crossing blow-off line device;
The cable crossing blow-off line device includes semicircle annulus, the first metallic rod, the second metallic rod, third gold Belong to bar;
One end of first metallic rod connects the highest point of semicircle annulus, and one end of the second metallic rod connects semicircle One minimum point of shape annulus, another minimum point of the semicircle annulus of one end connection of third metallic rod, and the first metallic rod, Second metallic rod and third metallic rod are each perpendicular to the plane where semicircle annulus;
Second step covers cable crossing blow-off line device on blow-off line, while being arranged cable crossing using rope Dirty plumbing installation is firmly tied together with blow-off line;
The end of cable to be laid is passed through the first metallic rod, the second metallic rod and third metallic rod, simultaneously by third step Guarantee that cable is located at the top of the first metallic rod, the lower section of the second metallic rod and third metallic rod;
The end of cable to be laid is fixed on mechanical traction device by the 4th step, and mechanical traction device is along groove Trend starts to pull cable.

Claims (1)

1. crossing over the method for blow-off line in a kind of extra-high-tension cable process of deployment, which is characterized in that
The first step prepares cable crossing blow-off line device;
The cable crossing blow-off line device includes semicircle annulus, the first metallic rod, the second metallic rod, third metal Bar;
One end of first metallic rod connects the highest point of semicircle annulus, the semicircle circle of one end connection of the second metallic rod One minimum point of ring, another minimum point of the semicircle annulus of one end connection of third metallic rod, and the first metallic rod, second Metallic rod and third metallic rod are each perpendicular to the plane where semicircle annulus;
Second step covers cable crossing blow-off line device on blow-off line, while using rope by cable crossing sewage pipe Road device is firmly tied together with blow-off line;
The end of cable to be laid is passed through the first metallic rod, the second metallic rod and third metallic rod, guaranteed simultaneously by third step Cable is located at the top of the first metallic rod, the lower section of the second metallic rod and third metallic rod.
The end of cable to be laid is fixed on mechanical traction device by the 4th step, and mechanical traction device moves towards along groove Start to pull cable.
CN201710298166.XA 2017-04-30 2017-04-30 The method of blow-off line is crossed in a kind of extra-high-tension cable process of deployment Active CN107104394B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710298166.XA CN107104394B (en) 2017-04-30 2017-04-30 The method of blow-off line is crossed in a kind of extra-high-tension cable process of deployment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710298166.XA CN107104394B (en) 2017-04-30 2017-04-30 The method of blow-off line is crossed in a kind of extra-high-tension cable process of deployment

Publications (2)

Publication Number Publication Date
CN107104394A CN107104394A (en) 2017-08-29
CN107104394B true CN107104394B (en) 2019-01-04

Family

ID=59656505

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710298166.XA Active CN107104394B (en) 2017-04-30 2017-04-30 The method of blow-off line is crossed in a kind of extra-high-tension cable process of deployment

Country Status (1)

Country Link
CN (1) CN107104394B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1237282A (en) * 1997-02-06 1999-12-01 北卡罗莱纳康姆斯科彼公司 Aerially installed communications cable
JP2002271935A (en) * 2001-03-06 2002-09-20 Sumitomo Wiring Syst Ltd Method for inserting wires through net tube
CN102493524A (en) * 2011-11-29 2012-06-13 沈福兴 Cable stretching device
CN205407131U (en) * 2016-02-25 2016-07-27 迪尔集团有限公司 Cable laying device

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6392208A (en) * 1986-10-03 1988-04-22 未来工業株式会社 Cable pulling-in tool
CN201590623U (en) * 2009-11-03 2010-09-22 河南省电力公司洛阳供电公司 Well mouth cable protector
CN102332691B (en) * 2011-09-19 2014-02-19 中建五局工业设备安装有限公司 Auxiliary device capable of paying off cable from top to bottom in building construction and cable paying off method
CN203456805U (en) * 2013-09-25 2014-02-26 中国化学工程第六建设有限公司 Large cross-section cable mechanization laying device
CN103730866B (en) * 2014-01-26 2016-04-13 宁波甬城配电网建设有限公司 A kind of cable-laying gear

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1237282A (en) * 1997-02-06 1999-12-01 北卡罗莱纳康姆斯科彼公司 Aerially installed communications cable
JP2002271935A (en) * 2001-03-06 2002-09-20 Sumitomo Wiring Syst Ltd Method for inserting wires through net tube
CN102493524A (en) * 2011-11-29 2012-06-13 沈福兴 Cable stretching device
CN205407131U (en) * 2016-02-25 2016-07-27 迪尔集团有限公司 Cable laying device

Also Published As

Publication number Publication date
CN107104394A (en) 2017-08-29

Similar Documents

Publication Publication Date Title
CN104167694A (en) Method for laying cable with hemp ropes in vertical shaft of mine
JPS62189215A (en) Penetrating equipment for draining core
JP5923071B2 (en) Method of passing working line to transverse pipe in fluid conduit and apparatus used in the method
CN203270577U (en) Underground pile removing apparatus with door plate clamp
CN206736987U (en) A kind of long detection device of more piece pile for prestressed pipe stake
CN109973130B (en) Construction system and method for realizing one-time traction of extra-long tunnel anchor narrow space by main cable strand
US8727319B2 (en) System and method for installing fiber optic cable
CN107104394B (en) The method of blow-off line is crossed in a kind of extra-high-tension cable process of deployment
CN203270578U (en) Underground pile removing apparatus provided with steel wire rope clamps
CN202090349U (en) Device for removing square pile
CN202416554U (en) Dredging device
RU52966U1 (en) PIPELINE PUSHING DEVICE
CN104718328B (en) Multi-stage expansion arm assembly and there is the deep excavator of multi-stage expansion arm assembly
CN205477629U (en) T -shaped undercut tunnel shield constructs owner's machine translation system that goes into well
CN102296610B (en) Device for removing square pile and construction method thereof
RU2205923C1 (en) Process of erection of pipe-line, process of dragging-through of pipe-line with protective envelope and facility for its implementation
CN103742717A (en) Parallel protection bracket for submarine pipelines and submarine cables
CN107154600B (en) The method whether cable stretches is judged in a kind of extra-high-tension cable process of deployment
CN102635115B (en) Method for efficiently recycling anchor bars
CN110282486A (en) Power construction actinobacillus device
CN105932608B (en) A kind of support device and line-putting method for power cable unwrapping wire
CN207368577U (en) Device for pushing or pulling cable through tubing or conduit
CN202730764U (en) Immersed tube pile ramming and expanding machine
CN105970826B (en) A kind of easy device and its operating method for realizing the quick poling of overlength reinforcing pull rod
JP6441871B2 (en) Box roof deflection reduction method for box roof method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20181114

Address after: 241000 Service Outsourcing Industry Park, Wuhu High-tech Industrial Development Zone, Anhui Province

Applicant after: Wuhu Tai Qing Electronic Technology Co., Ltd.

Address before: 241000 17-2-101 room, Chun Chun Road, spring garden, Jinghu District, Wuhu, Anhui

Applicant before: Tao Xiaxia

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191120

Address after: 510080 Dongfeng East Road, Dongfeng, Guangdong, Guangzhou, Zhejiang Province, No. 8

Patentee after: ELECTRIC POWER RESEARCH INSTITUTE, GUANGDONG POWER GRID CO., LTD.

Address before: 241000 Service Outsourcing Industry Park, Wuhu High-tech Industrial Development Zone, Anhui Province

Patentee before: Wuhu Tai Qing Electronic Technology Co., Ltd.