China
Prior art keywords
cable wire
fixed
platform framework
pull bar
tube head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610914356.5A
Other languages
Chinese (zh)
Other versions
CN106638933B (en
Inventor
孙跃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Huaxia Tiancheng Construction Co., Ltd.
Original Assignee
Xuzhou Joy Electromechanical Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xuzhou Joy Electromechanical Technology Co Ltd filed Critical Xuzhou Joy Electromechanical Technology Co Ltd
Priority to CN201610914356.5A priority Critical patent/CN106638933B/en
Priority to CN201910924597.1A priority patent/CN110644611B/en
Publication of CN106638933A publication Critical patent/CN106638933A/en
Application granted granted Critical
Publication of CN106638933B publication Critical patent/CN106638933B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/003Balconies; Decks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/343Structures characterised by movable, separable, or collapsible parts, e.g. for transport
    • E04B1/34315Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
  • Steps, Ramps, And Handrails (AREA)

Abstract

The invention discloses a detachable green terrace with a garden carrier. The terrace comprises a platform frame formed by welding shape steel frameworks, the platform frame is connected with a concrete beam column of a house through a hinge device, the hinge device comprises u-shaped anchor parts and shaft pin type connecting pieces, the shaft pin type connecting pieces are installed in the u-shaped anchor parts and fixed through shaft pins so that the u-shaped anchor parts and the shaft pin type connecting pieces can be hinged together, the shaft pin type connecting pieces are fixed to one end of the platform frame, the u-shaped anchor parts are fixed to the concrete beam column of the house, and movable tube heads are arranged on the front side of the platform frame and connected with steel cable handrails. The terrace is attractive in appearance design, flexible and convenient to disassemble and assemble and reliable in safety performance, and the terrace, pulling rods, a pool, a leisure platform and the guardrails can all be detached and repeatedly used in different places.

Description

It is a kind of to possess detachable green balcony of garden carrier and preparation method thereof
Technical field
The present invention relates to a kind of possess detachable green balcony of garden carrier and preparation method thereof.
Background technology
As the continuous improvement of living standards of the people, urbanization process are accelerated, skyscraper, intensive transportation network are continuous Ground corrodes the limited green space in city, and it is so to lack that at this moment we just really experience life Green.In order to improve This bad development model, allows city full of green, and people start to spatial development, from plot planning, layout design when just Start to envision and a super large green yard is supplied to into each household resident, allow ancient Chinese style garden love knot to obtain in high residential building To extend.
Country's residential quarters greening at present, flowers and plants, landscape, trees are typically each provided at the public-land in cell courtyard On, also there is the situation that garden is built on roofing.Community resident can only go to one layer of ground or roofing is viewed and admired, and cannot participate in planting The overall process such as train, water, pruning, nursing, cannot more meet the privacy that occupant is liked the individual character of flowers and plants and private savings is exclusive Require.Particularly the residential architecture of early stage, can only on balcony put several flowerpots, although balcony area very little, the work(for carrying Can be again especially many, common balcony be both enjoy the cool, the institute of view, be again to do washing, shine where clothing, storing debris.With inhabitation product The continuous improvement of matter and the increase of living space, the present invention is exactly to provide one for resident to meet colourful leisure at home Living space, the living space of this super large can not only cultivate the flowers and plants worm for fishing of personal like, but also as view, body-building, read Read, receive a visitor, playing chess is used.This courtyard-style afforests balcony, or the ground of landscape generation, with the indoor sky that it builds as core Between, indoor and outdoor is mutually blended, flowing and it is changeable.
In greening cell environment, in terms of changing cityscape, act in accordance with once for trend, change that thousand city one in the past The design pattern in face, sets about from the design in Unit Residential building, the old traditional design theory of optimizing design scheme and change, is Society provides more green buildings and the ecological environment of gracefulness is extremely urgent.
Assembled afforests balcony, and exterior design is attractive in appearance, dismounts and mounts flexible, security performance reliability, balcony, pull bar, pond, Reuse in the dismountable rear strange land of leisure platform, guardrail.
The content of the invention
For the problem that above-mentioned prior art is present, the present invention provides a kind of detachable green dew for possessing garden carrier Platform, belongs to assembled greening balcony, and exterior design is attractive in appearance, dismounts and mounts flexible, security performance reliability, balcony, pull bar, pond, Reuse in the dismountable rear strange land of leisure platform, guardrail.
To achieve these goals, the technical solution used in the present invention is:A kind of detachable green for possessing garden carrier Balcony, a kind of detachable green balcony for possessing garden carrier, it is characterised in that including platform framework, described platform framework It is welded by type steel skeleton, platform framework is connected by articulated mounting with the beam column built from concrete in house, described platform framework Including garden areas and aisle.
Described articulated mounting is u-shaped anchor and axial pin type connector, and axial pin type connector is arranged on the interior of u-shaped anchor Portion is fixed by pivot pin so that u-shaped anchor and axial pin type connector are hinged, and described axial pin type connector is fixed on One end of platform framework, described u-shaped anchor is fixed on the beam column built from concrete in house, and u-shaped anchor exposes outside hinge bar.
The both sides of platform framework are mounted on some updip formula cable wires and hang nose, and corresponding beam column built from concrete is provided with dipping type Anchor, dipping type anchor has square anchor slab, and square anchor slab is fixed on inside beam column built from concrete, and updip formula cable wire hangs nose and has a down dip Formula anchor is fixedly connected by cap cable pull bar.
The both sides of platform framework are provided with guardrail grafting base and fixed auxiliary cable wire tube head, and auxiliary cable wire pull bar passes through per layer Corresponding fixed auxiliary cable wire tube head, the two ends for aiding in cable wire pull bar are fixed on top and the bottom to roof panel framework On fixed auxiliary cable wire tube head,
The installed in front of described platform framework has two removable tube heads,
Cable wire pull bar passes through corresponding removable tube head, one end of cable wire pull bar to be fixed on Cantilever Beams, and the other end is fixed on bottom On portion's fixture, described removable tube head includes sliding shoe, and the tube head on the outside of sliding shoe, before platform framework Side is provided with chute, and sliding shoe can be moved along chute, and evenly distributed fixing hole, fixing hole are additionally provided with front side of platform framework Parallel to chute, it is hinged on sliding shoe and is provided with hole clipping bar, hole clipping bar can be put in fixing hole.
Described Cantilever Beams are arranged on the top of floor.
A kind of preparation method of the detachable green balcony for possessing garden carrier:Comprise the following steps:
(1)Cantilever Beams are set:Cantilever Beams are set on the top of floor, if house is newly constructed house, Cantilever Beams can be with house master Body makes reinforced beam, if aging blocks room, can adopt steelwork, is reliably connected with room thing top layer;
(2)In the metope pre-embedded u-shaped anchor and dipping type anchor of the floor for installing balcony, in each floor, dipping type anchor Position height of the position height more than u-shaped anchor;
(3)Suitable platform framework is selected, and axial pin type connector is welded near the both sides of metope one end in platform framework, put down Least one set updip formula cable wire is symmetrically installed with the body of rod of two sides of table frame and hangs nose, be fixed with front side of platform framework Complementary cable wire pull bar connects tube head,
And the floor of installation, two axial pin type connectors and the metope pre-embedded u-shaped anchor of platform framework are placed on by hanging device Part is hinged by pivot pin,
Then the updip formula cable wire on the body of rod of two sides of platform framework is hung into nose and dipping type anchor with cap cable pull bar Connection;
(4)Floor is selected to continue that balcony, repeat step are installed(2)And step(3), until floor in need platform framework it is equal Installation, then with auxiliary cable wire pull bar through the corresponding fixed auxiliary cable wire tube head of all platform framework avris, will be all Platform framework be connected as one overall, auxiliary cable wire pull bar draws through per layer of corresponding fixed auxiliary cable wire tube head, auxiliary cable wire The two ends of bar are fixed on top and the bottom on the fixed auxiliary cable wire tube head of roof panel framework, from hanging that top is fixed Two cable wire pull bars are drawn on outrigger, each cable wire pull bar passes through the corresponding removable tube head of each platform framework, Zhi Daogang Rope pull bar passes through the corresponding removable tube head of all platform frameworks, finally determines the position of the cable wire pull bar other end, described position Put on the fixture on ground so that cable wire pull bar is tight firmly, two cable wire pull bars are all fixed after finishing, two cable wire pull bars The removable tube head that the angle for being formed is fixed on each platform framework between 30-90 °, finally so that so that movable pipe Head is fixed on platform framework and cannot move.
7th, the preparation method of a kind of detachable green balcony for possessing garden carrier according to claim 6:It is special Levy and be, step(4)In, cable wire pull bar, will with two cable wire dops through after the corresponding removable tube head of all platform frameworks Mobile link tube head is fixed on cable wire pull bar.
The present invention has advantages below, and overhanging type green balcony will be made in processing factory of four adjustable steel ropes The assembled steel balcony oblique pull that completes, horizontally suspend outside the building side.Because balcony is in processing factory's scale production, process velocity Hurry up, high precision, quality it is good.When transporting in-site installation, noiselessness and ambient influnence condition is little, security performance reliability.The greening Balcony can simultaneously design with house, while construction, while being delivered for use.Again can for existing building by the direction to house, After the comprehensive analysis such as body coefficient, daylighting requirement, special design and production customization are carried out.The present invention passes through Cantilever Beams, many bar steels Multiple balconies are fixed as an entirety by rope pull bar and removable tube head, and structure is firm, due to moving tube head energy before fixed It is enough flexible mobile, it is possible to being adapted to the balcony of various height and the fixed installation of floor.
Description of the drawings
Accompanying drawing 1 is floor map of the present invention;
Accompanying drawing 2 installs lateral side view for greening balcony;
Accompanying drawing 3 is the side view of steel platform;
Accompanying drawing 4 is that dipping type anchor and square anchor slab enter concrete node drawing;
Accompanying drawing 5 is that platform mounts node drawing with body of wall level.
Fig. 6 is the cable wire pull bar connection diagram of multiple balconies.
Fig. 7 is movable pipe header structure figure.
1st, platform framework;2nd, lie fallow platform;3rd, garden;4th, aisle;5 axial pin type connectors;6th, updip formula cable wire hangs nose;7、 U-shaped anchor;8th, beam column built from concrete;9th, pivot pin;10th, guardrail grafting base;11st, cap cable pull bar;12nd, dipping type anchor;13rd, side Shape anchor slab;14th, Cantilever Beams;15th, cable wire pull bar;16th, fixed auxiliary cable wire pull bar tube head, 17, fixture, 18, removable tube head, 19 auxiliary cable wire pull bars, 20, removable tube head, 101, chute, 102, fixing hole, 201, slide block, 202, tube head, 203, hole clipping Bar.
Specific embodiment
Below in conjunction with the accompanying drawings the invention will be further described.
A kind of detachable green balcony for possessing garden carrier, including platform framework 1, described platform framework 1 is by shaped steel Skeleton is welded, and platform framework is connected by articulated mounting with the beam column built from concrete 8 in house, and described platform framework includes flower Garden 3 and aisle 4, leisure platform 2.
Described articulated mounting is u-shaped anchor 7 and axial pin type connector 5, and axial pin type connector is arranged on u-shaped anchor Inside is fixed by pivot pin 9 so that u-shaped anchor and axial pin type connector are hinged, and described axial pin type connector is consolidated One end of platform framework is scheduled on, described u-shaped anchor is fixed on the beam column built from concrete in house, and u-shaped anchor exposes outside hinge bar.
The both sides of platform framework 1 are mounted on some updip formula cable wires and hang nose 6, and corresponding beam column built from concrete 8 is provided with down Formula of inclining anchor 12, dipping type anchor 12 has square anchor slab 13, and square anchor slab 13 is fixed on inside beam column built from concrete 8, updip formula Cable wire is hung nose 6 and is fixedly connected by cap cable pull bar 11 with dipping type anchor 12.
The both sides of platform framework 1 are provided with guardrail grafting base 10 and fixed auxiliary cable wire pull bar tube head 16, and auxiliary cable wire draws Through per layer of corresponding fixed auxiliary cable wire tube head 16, the two ends for aiding in cable wire pull bar 19 are fixed on top and most bottom to bar 19 Layer is aided on cable wire tube head 16 the fixed of roof panel framework,
The installed in front of described platform framework has two removable tube heads, as shown in fig. 7, specific structure is removable tube head Including sliding shoe 201, and the tube head 202 on the outside of sliding shoe, chute 101, sliding shoe are provided with front side of platform framework Can move along chute, evenly distributed fixing hole 102 is additionally provided with front side of platform framework, fixing hole is sliding parallel to chute It is hinged on motion block and is provided with hole clipping bar 203, hole clipping bar can be put in fixing hole, be achieved in that the mobile fixation of slide block, shelves is needed When wanting slide block to be fixed on the position of needs, it is only necessary to before slide block to be moved to the fixing hole for changing position, hole clipping bar 203 is put in and is changed Fixing hole is realized fixing, and in order to preferably fix, hole clipping rod end head is provided with lockhole, and hole clipping bar 203 puts in and changes after fixing hole, then Lockhole is pinned with lock, reaches more preferable fixed effect.
Cable wire pull bar passes through corresponding removable tube head, one end of cable wire pull bar to be fixed on Cantilever Beams, and the other end is fixed On bottom fixture 17.
Described Cantilever Beams are arranged on the top of floor.
A kind of preparation method of the detachable green balcony for possessing garden carrier:Comprise the following steps:
(1)Cantilever Beams are set:Cantilever Beams are set on the top of floor, if house is newly constructed house, Cantilever Beams can be with house master Body makes reinforced beam, if aging blocks room, can adopt steelwork, is reliably connected with room thing top layer;
(2)In the metope pre-embedded u-shaped anchor and dipping type anchor of the floor for installing balcony, in each floor, dipping type anchor Position height of the position height more than u-shaped anchor;
(3)Suitable platform framework is selected, and axial pin type connector is welded near the both sides of metope one end in platform framework, put down Least one set updip formula cable wire is symmetrically installed with the body of rod of two sides of table frame and hangs nose, be fixed with front side of platform framework Complementary cable wire pull bar connects tube head,
And the floor of installation, two axial pin type connectors and the metope pre-embedded u-shaped anchor of platform framework are placed on by hanging device Part is hinged by pivot pin,
Then the updip formula cable wire on the body of rod of two sides of platform framework is hung into nose and dipping type anchor with cap cable pull bar Connection;
(4)Floor is selected to continue that balcony, repeat step are installed(2)And step(3), until floor in need platform framework it is equal Installation, then with auxiliary cable wire pull bar through the corresponding fixed auxiliary cable wire tube head of all platform framework avris, will be all Platform framework be connected as one overall, auxiliary cable wire pull bar draws through per layer of corresponding fixed auxiliary cable wire tube head, auxiliary cable wire The two ends of bar are fixed on the fixed auxiliary cable wire tube head of the corresponding platform framework of top and the bottom,
(5)Two cable wire pull bars are drawn on the outside of the Cantilever Beams fixed from top, each cable wire pull bar passes through each platform The corresponding removable tube head of framework, until cable wire pull bar passes through the corresponding removable tube head of all platform frameworks, finally determines steel The position of the rope pull bar other end, because removable tube head can freely slide, this design causes to determine the cable wire pull bar other end Position when it is more easy, it is only necessary to determine on the fixture on ground, then the cable wire pull bar other end directly is pulled Straight line can be formed, and two cable wire pull bars can draw from the same place of Cantilever Beams, and such Cantilever Beams can not Too big width is needed, without the need for big as the area of balcony, it is only necessary to the extension elongation one of its extension elongation and platform framework Cause, can just reach good fixed effect.
So that cable wire pull bar is tightened firmly, two cable wire pull bars are all tightened after fixed finishing, and two cable wire pull bars are formed Angle between 30-90 °, the structure of triangle is more consolidated, the removable tube head finally fixed on each platform framework, So that removable tube head is fixed on platform framework and cannot move, then mobile link tube head is fixed on two cable wire dops On cable wire pull bar, the removable tube head so after several platforms, two cable wire pull bars, fixations is just fixed as an entirety, shape Conveniently adjust into a firm structure, and this removable tube head, be adapted to differing heights, the domestic floor of length, such as Shown in Fig. 6.

Claims (7)

1. a kind of detachable green balcony for possessing garden carrier, it is characterised in that including platform framework, described platform framework It is welded by type steel skeleton, platform framework is connected by articulated mounting with the beam column built from concrete in house, described platform framework Including garden areas and aisle.
2. a kind of detachable green balcony for possessing garden carrier according to claim 1, it is characterised in that described hinge Tipping is set to u-shaped anchor and axial pin type connector, and axial pin type connector is arranged on the inside of u-shaped anchor and is fixed by pivot pin, So that u-shaped anchor and axial pin type connector are hinged, described axial pin type connector is fixed on one end of platform framework, Described u-shaped anchor is fixed on the beam column built from concrete in house, and u-shaped anchor exposes outside hinge bar.
3. a kind of detachable green balcony for possessing garden carrier according to claim 1, it is characterised in that platform frame The both sides of frame are mounted on some updip formula cable wires and hang nose, and corresponding beam column built from concrete is provided with dipping type anchor, dipping type anchor Part has square anchor slab, and square anchor slab is fixed on inside beam column built from concrete, and updip formula cable wire hangs nose and dipping type anchor by short Cable wire pull bar is fixedly connected.
4. a kind of detachable green balcony for possessing garden carrier according to claim 1, it is characterised in that platform framework Both sides be provided with guardrail grafting base and fixed auxiliary cable wire tube head, auxiliary cable wire pull bar is through per layer of corresponding fixed auxiliary steel Suo Guantou, the two ends for aiding in cable wire pull bar are separately fixed at the corresponding fixed auxiliary steel of the platform framework of top and the bottom On Suo Guantou, the installed in front of described platform framework has two removable tube heads,
Cable wire pull bar passes through corresponding removable tube head, one end of cable wire pull bar to be fixed on Cantilever Beams, and the other end is fixed on bottom On portion's fixture, described removable tube head includes sliding shoe, and the tube head on the outside of sliding shoe, before platform framework Side is provided with chute, and sliding shoe can be moved along chute, and evenly distributed fixing hole, fixing hole are additionally provided with front side of platform framework Parallel to chute, it is hinged on sliding shoe and is provided with hole clipping bar, hole clipping bar can be put in fixing hole.
5. a kind of detachable green balcony for possessing garden carrier according to claim 4, it is characterised in that described is outstanding Outrigger is arranged on the top of floor.
6. a kind of preparation method of the detachable green balcony for possessing garden carrier:Characterized in that, comprising the following steps:
(1)Cantilever Beams are set:Cantilever Beams are set on the top of floor, if house is newly constructed house, Cantilever Beams can be with house master Body makes reinforced beam, if aging blocks room, can adopt steelwork, is reliably connected with room thing top layer;
(2)In the metope pre-embedded u-shaped anchor and dipping type anchor of the floor for installing balcony, in each floor, dipping type anchor Position height of the position height more than u-shaped anchor;
(3)Suitable platform framework is selected, and axial pin type connector is welded near the both sides of metope one end in platform framework, put down Least one set updip formula cable wire is symmetrically installed with the body of rod of two sides of table frame and hangs nose, be fixed with front side of platform framework Complementary cable wire pull bar connects tube head,
And the floor of installation, two axial pin type connectors and the metope pre-embedded u-shaped anchor of platform framework are placed on by hanging device Part is hinged by pivot pin,
Then the updip formula cable wire on the body of rod of two sides of platform framework is hung into nose and dipping type anchor with cap cable pull bar Connection;
(4)Floor is selected to continue that balcony, repeat step are installed(2)And step(3), until floor in need platform framework it is equal Installation, then with auxiliary cable wire pull bar through the corresponding fixed auxiliary cable wire tube head of all platform framework avris, will be all Platform framework be connected as one overall, auxiliary cable wire pull bar draws through per layer of corresponding fixed auxiliary cable wire tube head, auxiliary cable wire The two ends of bar are fixed on the fixed auxiliary cable wire tube head of the correspondence of the platform framework of top and the bottom, are fixed from top Two cable wire pull bars are drawn on Cantilever Beams, each cable wire pull bar passes through the corresponding removable tube head of each platform framework, until Cable wire pull bar passes through the corresponding removable tube head of all platform frameworks, finally determines the position of the cable wire pull bar other end, described Position is on the fixture on ground so that cable wire pull bar is tight firmly, and two cable wire pull bars are all fixed after finishing, and two cable wires draw The removable tube head that the angle that bar is formed is fixed on each platform framework between 30-90 °, finally so that removable tube head Being fixed on platform framework to move.
7. the preparation method of a kind of detachable green balcony for possessing garden carrier according to claim 6:Its feature exists In step(4)In, cable wire pull bar, will be mobile with two cable wire dops through after the corresponding removable tube head of all platform frameworks Connection tube head is fixed on cable wire pull bar.
CN201610914356.5A 2016-10-20 2016-10-20 Detachable green terrace with garden carrier and manufacturing method thereof Active CN106638933B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201610914356.5A CN106638933B (en) 2016-10-20 2016-10-20 Detachable green terrace with garden carrier and manufacturing method thereof
CN201910924597.1A CN110644611B (en) 2016-10-20 2016-10-20 Can dismantle green balcony

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610914356.5A CN106638933B (en) 2016-10-20 2016-10-20 Detachable green terrace with garden carrier and manufacturing method thereof

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201910924597.1A Division CN110644611B (en) 2016-10-20 2016-10-20 Can dismantle green balcony

Publications (2)

Publication Number Publication Date
CN106638933A true CN106638933A (en) 2017-05-10
CN106638933B CN106638933B (en) 2019-12-17

Family

ID=58856323

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201910924597.1A Active CN110644611B (en) 2016-10-20 2016-10-20 Can dismantle green balcony
CN201610914356.5A Active CN106638933B (en) 2016-10-20 2016-10-20 Detachable green terrace with garden carrier and manufacturing method thereof

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201910924597.1A Active CN110644611B (en) 2016-10-20 2016-10-20 Can dismantle green balcony

Country Status (1)

Country Link
CN (2) CN110644611B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012340A (en) * 2020-09-25 2020-12-01 中建一局集团第三建筑有限公司 Suspension connection node for large-span cantilever steel truss and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU757666A1 (en) * 1978-05-15 1980-08-23 Kh Gorodskoe Zhilishchnoe Upra Apparatus for insuring balconys
KR20090086928A (en) * 2009-07-27 2009-08-14 문근술 A rail of balcony for fire escape
CN201297036Y (en) * 2008-11-19 2009-08-26 常州第一建筑工程有限公司 Discharging platform
CN201801953U (en) * 2010-08-17 2011-04-20 俞天阳 Aerated balcony
CN203429783U (en) * 2013-07-25 2014-02-12 中国建筑第八工程局有限公司 Tower crane driver high-altitude walking passageway
CN105233433A (en) * 2015-11-02 2016-01-13 袁锡良 Emergent fire fighting self-saving movable balcony for storied house

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07268950A (en) * 1994-04-04 1995-10-17 Sekisui Chem Co Ltd Roof balcony unit and lifting lug
JP2000145129A (en) * 1998-11-16 2000-05-26 Nippon Gijutsu Center:Kk Staging provided with load lifter
CN2765979Y (en) * 2005-01-27 2006-03-22 万科企业股份有限公司 Assembled balcony
KR100928671B1 (en) * 2007-11-27 2009-11-27 문동해 Fall accident prevention device with emergency escape device
CN201908429U (en) * 2011-01-27 2011-07-27 许昌中原建设(集团)有限公司 Assembly integral building overhanging discharging platform
CN202745352U (en) * 2012-05-24 2013-02-20 浙江精工钢结构有限公司 Combined-type high-altitude operation platform easy for assembly and disassembly
CN104389419B (en) * 2014-11-18 2016-06-08 杭州江润科技有限公司 Encorbelment and prop up mould structure for mounting platform and a constructional method
CN104481166B (en) * 2014-12-12 2017-01-11 北京筑福国际工程技术有限责任公司 Additionally assembled type balcony structure for old community and construction method of additionally assembled type balcony structure
CN104712056A (en) * 2015-03-22 2015-06-17 徐林波 Semi-fixed and semi-movable high-rise escape balcony
CN105003070A (en) * 2015-07-31 2015-10-28 重庆渝发建设有限公司 Bilayer extensible unloading platform for building construction
CN105756186A (en) * 2016-05-04 2016-07-13 四川省建筑设计研究院 Assembly type prefabricated truss balcony and installation method therefor

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU757666A1 (en) * 1978-05-15 1980-08-23 Kh Gorodskoe Zhilishchnoe Upra Apparatus for insuring balconys
CN201297036Y (en) * 2008-11-19 2009-08-26 常州第一建筑工程有限公司 Discharging platform
KR20090086928A (en) * 2009-07-27 2009-08-14 문근술 A rail of balcony for fire escape
CN201801953U (en) * 2010-08-17 2011-04-20 俞天阳 Aerated balcony
CN203429783U (en) * 2013-07-25 2014-02-12 中国建筑第八工程局有限公司 Tower crane driver high-altitude walking passageway
CN105233433A (en) * 2015-11-02 2016-01-13 袁锡良 Emergent fire fighting self-saving movable balcony for storied house

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012340A (en) * 2020-09-25 2020-12-01 中建一局集团第三建筑有限公司 Suspension connection node for large-span cantilever steel truss and construction method thereof
WO2022062294A1 (en) * 2020-09-25 2022-03-31 中建一局集团第三建筑有限公司 Suspension connection node for large-span cantilever steel truss and construction method therefor

Also Published As

Publication number Publication date
CN106638933B (en) 2019-12-17
CN110644611A (en) 2020-01-03
CN110644611B (en) 2021-06-25

Similar Documents

Publication Publication Date Title
JP2003531985A (en) Design and construction method of prefabricated eco-friendly and community-based building-type building
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN205777664U (en) Urban forests high level villa
JP2008289462A (en) Wall surface greening method for construction such as building allowing plant unit to go up and down
CN201695660U (en) Miniature multi-functional interior decoration scaffold
CN106368310B (en) Detachable green balcony for multi-storey building building and preparation method thereof
CN106638933A (en) Detachable green terrace with garden carrier and manufacturing method of terrace
CN106436891B (en) Detachable balcony of multi-storey building and preparation method thereof
CN106638934B (en) A kind of green balcony and preparation method thereof for multi-storey building
CN210856905U (en) Pedestrian landscape cable-stayed bridge based on bridge tower structure of sightseeing tower
CN209145351U (en) A kind of case type sports training type heat preservation energy-saving house
JP2014087315A (en) Supporting trellis for climbing plant
CN214531083U (en) Multi-functional gardens corridor frame
CN219352557U (en) Simple net wall device for isolating diaphorina citri and supporting upright post thereof
CN203008349U (en) Basket outer protection layer used for super high-rise building
CN211646699U (en) Three-dimensional balcony garden
CN213806876U (en) Typhoon-proof color steel house
CN211257933U (en) Building with trapezoidal step-shaped roof and quadrangle composed of building
CN203724731U (en) Multifunctional stereo encircled golf driving range
CN212642239U (en) Garden entertainment experience house
CN210746749U (en) Multifunctional movable aquaculture pond
CN2434879Y (en) Rack
CN206070729U (en) A kind of overhanging type green balcony
TWM609071U (en) Simple combination framework for parent-child interaction
CN205688889U (en) A kind of transformator protective frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20191106

Address after: 210000 Room 301, No.156, Mengdu street, Jianye District, Nanjing City, Jiangsu Province

Applicant after: Nanjing Huaxia Tiancheng Construction Co., Ltd.

Address before: 221000 Jiangsu city of Xuzhou province Xuzhou high tech Industrial Development Zone, Second Industrial Park, Qianjiang Road No. 23

Applicant before: Xuzhou joy Electromechanical Technology Co., Ltd.

GR01 Patent grant