CN201908429U - Assembly integral building overhanging discharging platform - Google Patents

Assembly integral building overhanging discharging platform Download PDF

Info

Publication number
CN201908429U
CN201908429U CN2011200276564U CN201120027656U CN201908429U CN 201908429 U CN201908429 U CN 201908429U CN 2011200276564 U CN2011200276564 U CN 2011200276564U CN 201120027656 U CN201120027656 U CN 201120027656U CN 201908429 U CN201908429 U CN 201908429U
Authority
CN
China
Prior art keywords
secondary beam
beams
discharging platform
girder
fastener
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2011200276564U
Other languages
Chinese (zh)
Inventor
谢杨斐
杨俊伟
王红军
周志允
杨俊峰
周建军
楚新永
王山峰
李淑红
吕红丽
李梅英
郭玉太
王红亮
陆新杰
颜社旗
刘志中
刘静鹤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XUCHANG ZHONGYUAN CONSTRUCTION (GROUP) CO Ltd
Original Assignee
XUCHANG ZHONGYUAN CONSTRUCTION (GROUP) CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XUCHANG ZHONGYUAN CONSTRUCTION (GROUP) CO Ltd filed Critical XUCHANG ZHONGYUAN CONSTRUCTION (GROUP) CO Ltd
Priority to CN2011200276564U priority Critical patent/CN201908429U/en
Application granted granted Critical
Publication of CN201908429U publication Critical patent/CN201908429U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Abstract

The utility model relates to an assembly integral building overhanging discharging platform, which comprises two main beams and a plurality of secondary beams, wherein the main beams and the secondary beams are directly vertically connected, the main beams are made of channel steel, and the secondary beams are produced by steel pipes; secondary beam holes in corresponding positions are arranged on the two main beams, two ends of each secondary beam penetrate the secondary beam holes on the main beams, and one part of each end of each secondary beam is exposed; fasteners are mounted at the parts on the two sides of the secondary beam holes on the secondary beams for fixing the main beams with the secondary beams; and the end parts of the secondary beams are fixedly connected with the lower ends of vertical rods of a guardrail through the fasteners. The main beams and the secondary beams of the assembly integral building overhanging discharging platform are assembled and connected through the fasteners, thereby being easy to detach and mount and being conductive to transferring; compared with the original welding type structure, the building speed and the dismantling speed are fast, and the cost is low.

Description

Assembled integral is built the discharging platform of encorbelmenting
Technical field
The utility model relates to building operations material transferring equipment technical field, particularly relates to a kind of assembled integral and builds the discharging platform of encorbelmenting.
Background technology
All kinds of discharging platforms are in the construction site extensive use, are the eminence construction operation condition of providing convenience.The mode of setting up of existing discharging platform has following several mode: 1. the discharging platform of setting up by steel pipe scaffold, and discharging platform underframe, guardrail form by the steel pipe clamping, and wherein mode is not suitable for high-building construction; 2. be welded into the platform underframe by shaped steel, back welded steel pipe on underframe, guardrail is that steel pipe is made, and fixes by reinforcing bar at last, uses four road wire rope inclined-pulling unloadings, the underframe construction back transportation of shaped steel welding is inconvenient.
The utility model content
The purpose of this utility model is in order to address the above problem, to provide a kind of assembled integral to build the discharging platform of encorbelmenting.
The technical solution of the utility model is: a kind of assembled integral is built the discharging platform of encorbelmenting, and contains two girders and several secondary beams, and girder directly vertically is connected with secondary beam, and described girder is a channel-section steel, and secondary beam is a steel pipe; Described two girders are provided with the secondary beam hole of position correspondence, and the secondary beam hole on the girder is passed at the two ends of described secondary beam, and expose a part of termination; The position that is positioned at these both sides, secondary beam hole on the described secondary beam is equipped with fastener, and girder and secondary beam are fixed; Fixedly connected with the vertical rod lower end of guardrail by fastener in the end of described secondary beam.
Be provided with between described two girders and the approximately parallel channel-section steel reinforcement of girder, also be provided with several secondary beam holes on this reinforcement, described several secondary beams also pass the secondary beam hole on this reinforcement, on the secondary beam of the both sides in this secondary beam hole fastener are installed also, and reinforcement and secondary beam are fixed.
At least be connected with steel cable on described two girders.
Described guardrail contains by fastener and is connected to each other together vertical rod and cross bar, and applies the safety net on guardrail.
The beneficial effects of the utility model
This assembled integral building is encorbelmented and connect by the fastener set load between the girder of discharging platform and the secondary beam, and is easy to removal and installation, equally also is beneficial to transhipment, compares with original welded structure, and it is built and dismounting speed is fast, cost is low.
Description of drawings
Fig. 1 builds the discharging platform master TV structure schematic diagram of encorbelmenting for this assembled integral;
Fig. 2 builds the discharging platform plan structure schematic diagram of encorbelmenting for this assembled integral;
Fig. 3 builds the discharging platform user mode schematic diagram of encorbelmenting for this assembled integral.
The specific embodiment
Referring to Fig. 1-Fig. 3,1. girders among the figure, 2. secondary beam, 3. reinforcement, 4. fastener, 5. vertical rod, 6. cross bar, 7. safety net, 8. wire rope, 9. embedded bar, 10. floor plates, the 11. pre-buried suspension ring of guardrail of guardrail.
Embodiment: referring to Fig. 1-Fig. 3, a kind of assembled integral is built the discharging platform of encorbelmenting among the figure, contains two girders and several secondary beams, and girder directly vertically is connected with secondary beam, and described girder is a channel-section steel, and secondary beam is a steel pipe; Described two girders are provided with the secondary beam hole of position correspondence, and the secondary beam hole on the girder is passed at the two ends of described secondary beam, and expose a part of termination; The position that is positioned at these both sides, secondary beam hole on the described secondary beam is equipped with fastener, and girder and secondary beam are fixed; Fixedly connected with the vertical rod lower end of guardrail by fastener in the end of described secondary beam.
Be provided with between described two girders and the approximately parallel channel-section steel reinforcement of girder, also be provided with several secondary beam holes on this reinforcement, described several secondary beams also pass the secondary beam hole on this reinforcement, on the secondary beam of the both sides in this secondary beam hole fastener are installed also, and reinforcement and secondary beam are fixed.
At least be connected with steel cable on described two girders.
Described guardrail contains by fastener and is connected to each other together vertical rod and cross bar, and applies the safety net on guardrail.

Claims (4)

1. an assembled integral is built the discharging platform of encorbelmenting, and contains two girders and several secondary beams, and girder directly vertically is connected with secondary beam, and it is characterized in that: described girder is a channel-section steel, and secondary beam is a steel pipe; Described two girders are provided with the secondary beam hole of position correspondence, and the secondary beam hole on the girder is passed at the two ends of described secondary beam, and expose a part of termination; The position that is positioned at these both sides, secondary beam hole on the described secondary beam is equipped with fastener, and girder and secondary beam are fixed; Fixedly connected with the vertical rod lower end of guardrail by fastener in the end of described secondary beam.
2. assembled integral according to claim 1 is built the discharging platform of encorbelmenting, it is characterized in that: be provided with between described two girders and the approximately parallel channel-section steel reinforcement of girder, also be provided with several secondary beam holes on this reinforcement, described several secondary beams also pass the secondary beam hole on this reinforcement, on the secondary beam of the both sides in this secondary beam hole, fastener is installed also, reinforcement and secondary beam are fixed.
3. assembled integral according to claim 1 is built the discharging platform of encorbelmenting, and it is characterized in that: be connected with steel cable at least on described two girders.
4. the assembled integral according to claim 1 building discharging platform of encorbelmenting is characterized in that: described guardrail contains by fastener and is connected to each other together vertical rod and cross bar, and applies the safety net on guardrail.
CN2011200276564U 2011-01-27 2011-01-27 Assembly integral building overhanging discharging platform Expired - Lifetime CN201908429U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011200276564U CN201908429U (en) 2011-01-27 2011-01-27 Assembly integral building overhanging discharging platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011200276564U CN201908429U (en) 2011-01-27 2011-01-27 Assembly integral building overhanging discharging platform

Publications (1)

Publication Number Publication Date
CN201908429U true CN201908429U (en) 2011-07-27

Family

ID=44300632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011200276564U Expired - Lifetime CN201908429U (en) 2011-01-27 2011-01-27 Assembly integral building overhanging discharging platform

Country Status (1)

Country Link
CN (1) CN201908429U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102359262A (en) * 2011-08-11 2012-02-22 中国建筑股份有限公司 Rope net scaffold
CN103216095A (en) * 2013-05-15 2013-07-24 南通海洲建设集团有限公司 Safety device for building overhanging discharging platform
CN110397155A (en) * 2016-10-20 2019-11-01 徐州乐泰机电科技有限公司 A kind of green balcony for multi-storey building
CN110644611A (en) * 2016-10-20 2020-01-03 徐州乐泰机电科技有限公司 Can dismantle green balcony

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102359262A (en) * 2011-08-11 2012-02-22 中国建筑股份有限公司 Rope net scaffold
CN103216095A (en) * 2013-05-15 2013-07-24 南通海洲建设集团有限公司 Safety device for building overhanging discharging platform
CN110397155A (en) * 2016-10-20 2019-11-01 徐州乐泰机电科技有限公司 A kind of green balcony for multi-storey building
CN110644611A (en) * 2016-10-20 2020-01-03 徐州乐泰机电科技有限公司 Can dismantle green balcony
CN110397155B (en) * 2016-10-20 2020-12-18 安徽嘉禾植保科技有限公司 Green balcony for multi-storey house
CN110644611B (en) * 2016-10-20 2021-06-25 徐州乐泰机电科技有限公司 Can dismantle green balcony

Similar Documents

Publication Publication Date Title
CN202706503U (en) Electric lifting discharging platform for main building construction
CN205012629U (en) Assembled modularization platform of unloading of encorbelmenting
CN201908429U (en) Assembly integral building overhanging discharging platform
CN102252911B (en) Loading device for high formwork support system full-scale test
CN202227701U (en) Spliced type horizontal channel device
CN203947421U (en) Compound beam cable stayed bridge direction across bridge prestress application device
CN203199913U (en) Assembling and disassembling type hoisting truss
CN102251666B (en) Overhanging type discharging platform
CN202944998U (en) Attached installation and maintenance platform of calibrated tower crane
CN204212065U (en) Bridge crossing anticollision barrier punching block erection equipment
CN201511439U (en) System for integrally binding and hoisting box girder steel reinforcement framework
CN203022328U (en) Climbing operation platform
CN203373666U (en) Bracket pull-counter loading prepressing device
CN103046743A (en) High-rise conversion layer type steel concrete girder hanging type template supporting system and construction method
CN102913007B (en) Steel reinforcement processing shed and construction method therefor
CN203113868U (en) Gantry tower for construction cableway
CN203361596U (en) Auxiliary support of integrated lifting operation platform
CN209941512U (en) Supporting shear part for lower cross beam of inclined tower of cable-stayed bridge
CN202705932U (en) T-beam reinforced hanger frame structure
CN206205768U (en) Combined type hangs cat ladder
CN219411454U (en) Reinforced truss building carrier plate reinforced structure that encorbelments
CN103452109A (en) Steel stranded wire anchor gear installing device for foundation pit supporting inner supporting system
CN203452071U (en) Steel strand anchorage mounting device and anchorage seat thereof
CN203808486U (en) Steel pipe scaffold follow-up platform
CN203452073U (en) Steel strand anchorage mounting device of foundation pit supporting inner support system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20110727