CN206053274U - The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose - Google Patents

The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose Download PDF

Info

Publication number
CN206053274U
CN206053274U CN201621013991.8U CN201621013991U CN206053274U CN 206053274 U CN206053274 U CN 206053274U CN 201621013991 U CN201621013991 U CN 201621013991U CN 206053274 U CN206053274 U CN 206053274U
Authority
CN
China
Prior art keywords
scaffold
steel pipe
cantilever beams
type double
fastener type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621013991.8U
Other languages
Chinese (zh)
Inventor
黄源军
李永文
黄斌伟
林少鹏
陈壮飚
张结平
刘钦
周刚
熊龙
何明君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Provincial Architectural Members Engineering Co
Guangdong Construction Engineering Group Co Ltd
Original Assignee
Guangdong Provincial Architectural Members Engineering Co
Guangdong Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Provincial Architectural Members Engineering Co, Guangdong Construction Engineering Group Co Ltd filed Critical Guangdong Provincial Architectural Members Engineering Co
Priority to CN201621013991.8U priority Critical patent/CN206053274U/en
Application granted granted Critical
Publication of CN206053274U publication Critical patent/CN206053274U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

This utility model is related to the external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose, including the Cantilever Beams being fixedly mounted on building structure beam slab, the fastener type double-row steel pipe scaffold being located on Cantilever Beams, Cantilever Beams steel wire rope, segmentation off-load steel wire rope, wire-rope sling and scaffold rigid connecting wall part;Fastener type double-row steel pipe scaffold is arranged on the Cantilever Beams;Fastener type double-row steel pipe scaffold is connected with building structure using scaffold rigid connecting wall part;Every Cantilever Beams outer end is respectively provided with Cantilever Beams steel wire rope, Cantilever Beams steel wire rope and the wire-rope sling oblique pull knot being embedded in last layer architecture beam;In the off-load section of scaffold, fastener type double-row steel pipe scaffold is tied with wire-rope sling oblique pull by being segmented off-load steel wire rope;This utility model can be alternatively arranged as the exterior wall scaffold of skyscraper main structure construction as construction safety work platformses, and support body is consolidated, and shortens the construction period, and efficiency of construction is higher, cost-effective.

Description

The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
Technical field
This utility model is related to the technical field of construction, especially the perpendicular BAIYE outer visor of skyscraper and glass curtain The external scaffolding device of wall dual-purpose.
Background technology
With the popularization of continuous progressive and " green building " theory of Building technology, the outdoor of increasing skyscraper Glass curtain wall will be using BAIYE shading system.Particularly, movable vertical BAIYE external sunshade system is both the effective way of building energy conservation, But also architectural image and facade effect are enriched, it is that city image adds vigor.
As external wall of high-rise building is large-area glass curtain wall, vertical sun-shading louver is located at outside glass curtain wall, in construction During, it is necessary to take into full account that cladding glass installs the sequencing with BAIYE construction, and curtain wall and BAIYE cross-operation are provided Safe and reliable work surface.
Currently used for the work surface for installing cladding glass and the construction of vertical outer visor, construction is inconvenient, and not enough Safety, it is impossible to meet glass curtain wall outside skyscraper room and intert the working condition needed for construction with vertical external sunshade BAIYE.
It is therefore desirable to a kind of device of design, with easy construction, safe and reliable, glass outside skyscraper room can be effectively provided Glass curtain wall interts the safe work platform needed for construction with movable vertical louvres outer visor.
Utility model content
The purpose of this utility model is the out-mould scaffold for providing the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose Rack device, it is intended to solve in prior art, for installing the work surface of cladding glass and the construction of vertical external sunshade BAIYE, construction Inconvenience, and it is not safe enough, it is impossible to meet glass curtain wall outside skyscraper room and intert needed for construction with BAIYE shading system The problem of working condition.
This utility model is achieved in that the external scaffolding of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose Device, including the Cantilever Beams being fixedly mounted on building structure beam slab, the fastener type double-row steel pipe scaffold being located on Cantilever Beams, Cantilever Beams steel wire rope, segmentation off-load steel wire rope, wire-rope sling and scaffold rigid connecting wall part;The fastener type double-row steel pipe foot Hand cradle is arranged on the Cantilever Beams;The fastener type double-row steel pipe scaffold adopts scaffold rigid connecting wall part and building structure Connection;Cantilever Beams steel wire rope is respectively provided with per Cantilever Beams outer end described in root, the Cantilever Beams steel wire rope is built with last layer is embedded in Wire-rope sling oblique pull knot in structural beams;In the off-load section of scaffold, the fastener type double-row steel pipe scaffold is by dividing Section off-load steel wire rope is tied with the wire-rope sling oblique pull.
Further, the fastener type double-row steel pipe scaffold includes scaffold upright rod, transverse horizontal bar and longitudinal water Flat bar, is provided with several transverse horizontal bars between the scaffold upright rod, the transverse horizontal bar is fixed on by right-angle coupler On scaffold upright rod;The vertical equity bar is equidistantly fixed on the transverse horizontal bar;The bottom of the scaffold upright rod It is provided with longitudinal direction to sweep the floor bar, the longitudinal direction is swept the floor and laterally sweep the floor bar.
Further, the scaffold upright rod of the fastener type double-row steel pipe scaffold is each attached on the Cantilever Beams, phase The level interval of the adjacent Cantilever Beams is the longitudinal pitch of the scaffold upright rod, and the material of the Cantilever Beams is 18# or more The I-steel of specification;Canned paragraph is divided into per Cantilever Beams described in root and two parts of section of encorbelmenting, the canned paragraph length is to encorbelment 1.25 times of segment length, the two ends of the canned paragraph of described Cantilever Beams are using two and the U being embedded in floor girder and board of the above Shape round steel reinforcing bar draw ring is fixed with building structure beam slab, a diameter of 20mm of the U-shaped reinforcing bar draw ring;It is outstanding per Cantilever Beams described in root The tail end for choosing section welds two bar dowels, a diameter of 25mm to 30mm of the bar dowel, and length is 200mm, the short steel Muscle inserts the bottom of inside and outside two scaffold upright rods of the fastener type double-row steel pipe scaffold respectively.
Further, width of the longitudinal pitch of the vertical rod of the fastener type double-row steel pipe scaffold more than sunshading board 0.2m, the horizontal spacing of the scaffold upright rod are the level interval of adjacent two pieces of sunshading boards.
Further, the step pitch of the fastener type double-row steel pipe scaffold is in the range of 1.8m, and each floor floor height The fastener type double-row steel pipe scaffold is provided with regulation step pitch, and the regulation step pitch is not more than 1.8m, in every layer of sun-shading louver The step pitch of the fastener type double-row steel pipe scaffold at board support should be 1.8m.
Further, Steel scaffold board, the foot handss are laid on the vertical equity bar of the fastener type double-row steel pipe scaffold Erect and on bar, be respectively provided with railing and wooden foot guard plate, the outside of the fastener type double-row steel pipe scaffold arranges bridging, described Bridging is provided with plug-in safety vertical net.
Further, the steel pipe specification of the fastener type double-row steel pipe scaffold is φ 48 × 3.5, and tubing is Q235 levels Steel, the steel pipe of the fastener type double-row steel pipe scaffold are connected using fastener, and the material of the fastener is malleable cast iron or cast steel, The Steel scaffold board is reinforcing bar grid scaffold board, and the plug-in safety vertical net is the fire-retardant safety net of 2000 mesh.
Further, in the off-load section of scaffold, the segmentation off-load steel wire penetrating is embedded in last layer building knot The wire-rope sling in structure beam, and scaffold upright rod respectively with the fastener type double-row steel pipe scaffold, transverse horizontal The snapping point oblique pull knot of bar and vertical equity bar;The level interval of the segmentation off-load steel wire rope is three floor floor heights and not More than 15m, be segmented off-load steel wire rope level interval be the double-row steel pipe scaffold vertical rod longitudinal pitch, described point Section off-load steel wire rope is 6 × 37 steel wire ropes of the diameter not less than 15.0mm.
Further, the material of the wire-rope sling is HPB235 level reinforcing bars, and which is a diameter of not less than 20mm.
Further, the scaffold rigid connecting wall part is 48 × 3.5 steel pipe wall-connecting pieces of φ, the scaffold rigid connecting wall Part is connected with the scaffold upright rod and the positioning short steel pipes being embedded in concrete structured beam respectively using right-angle coupler.
Compared with prior art, this utility model is provided the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose External scaffolding device, by arranging the double steel of fastener type on the Cantilever Beams being fixedly mounted on building structure beam slab, Cantilever Beams Pin hand cradle, Cantilever Beams steel wire rope, segmentation off-load steel wire rope, wire-rope sling and scaffold rigid connecting wall part, effectively can provide Outside skyscraper room, glass curtain wall interts the required safe work platform of construction with movable vertical louvres outer visor, and can make For the exterior wall scaffold of skyscraper main structure construction, support body is consolidated, and will not be rocked, and shortens the construction period, efficiency of construction It is higher, it is cost-effective.
Description of the drawings
Fig. 1 is the outer foot of the perpendicular BAIYE outer visor of skyscraper that this utility model embodiment is provided and glass curtain wall dual-purpose The main structure diagram of hand cradle device;
Fig. 2 is the outer foot of the perpendicular BAIYE outer visor of skyscraper that this utility model embodiment is provided and glass curtain wall dual-purpose The partial structural diagram one of hand cradle device(Dismounting);
Fig. 3 is the outer foot of the perpendicular BAIYE outer visor of skyscraper that this utility model embodiment is provided and glass curtain wall dual-purpose The partial structural diagram two of hand cradle device(Dismounting);
Fig. 4 is the outer foot of the perpendicular BAIYE outer visor of skyscraper that this utility model embodiment is provided and glass curtain wall dual-purpose The partial structural diagram three of hand cradle device(Dismounting).
Specific embodiment
In order that the purpose of this utility model, technical scheme and advantage become more apparent, below in conjunction with accompanying drawing and enforcement Example, is further elaborated to this utility model.It should be appreciated that specific embodiment described herein is only to explain This utility model, is not used to limit this utility model.
Realization of the present utility model is described in detail below in conjunction with specific embodiment.
With reference to Fig. 1 ~ 4, for the preferred embodiment that this utility model is provided.
The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper that the present embodiment is provided and glass curtain wall dual-purpose, can be with It is during being used in construction, with easy construction, safe and reliable, glass curtain wall 2 outside skyscraper room effectively can be provided With the safe work platform needed for the interspersed construction of movable vertical BAIYE outer visor 3.
The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose, including being fixedly mounted on building Cantilever Beams 4, the fastener type double-row steel pipe scaffold 1, Cantilever Beams steel wire rope 5 being located on Cantilever Beams and segmentation on structure flooring 20 Off-load steel wire rope 5, the wire-rope sling 14 being embedded in floor girder and board and scaffold rigid connecting wall part 17;The fastener type is double Steel pipe scaffold 1 is arranged on the Cantilever Beams 4;The fastener type double-row steel pipe scaffold 1 adopts scaffold rigid connecting wall part 17 are connected with building structure;4 outer end of the Cantilever Beams arranges the Cantilever Beams steel wire rope 5, and be embedded in last layer floor beam 14 oblique pull of wire-rope sling knot in plate;In the off-load section floor 19 of scaffold, the fastener type double-row steel pipe scaffold 1 leads to Cross segmentation off-load steel wire rope 5 and be connected realization segmentation off-load with wire-rope sling 14.
The perpendicular BAIYE outer visor of above-mentioned skyscraper and the external scaffolding device of glass curtain wall dual-purpose, are fixed by arranging Fastener type double-row steel pipe scaffold 1, Cantilever Beams steel wire rope 5 on the Cantilever Beams 4, Cantilever Beams on building structure flooring 20 And segmentation off-load steel wire rope 5, wire-rope sling 14 and scaffold rigid connecting wall part 17, glass outside skyscraper room effectively can be provided Curtain wall 2 and the safe work platform needed for the interspersed construction of movable vertical BAIYE outer visor 3, and can be used as skyscraper body junction The working exterior wall scaffold of structure.Support body is consolidated, and will not be rocked, and shortens the construction period, and efficiency of construction is higher, cost-effective.
Further, above-mentioned fastener type double-row steel pipe scaffold 1, including scaffold upright rod 8, transverse horizontal bar 10 with And vertical equity bar 9;If arterial highway transverse horizontal bar 10 is provided between the double-pole scaffold vertical rod 8 as vertical equity bar 9 Bearing, is fixed on scaffold upright rod 8 with right-angle coupler;The scaffold vertical equity bar 9 is equidistantly fixed on the foot handss On the transverse horizontal bar 10 of frame;The bottom of the scaffold upright rod 8 is provided with longitudinal direction and sweeps the floor bar, and the longitudinal direction is swept the floor Laterally sweep the floor bar.
Further, reinforcing bar grid scaffold board is laid on the vertical equity bar 9 of the fastener type double-row steel pipe scaffold 15, the scaffold often walks and railing 12 and wooden foot guard plate is respectively provided with outer vertical rod 8, and on the outside of the scaffold, full facade continuously sets Put plug-in safety vertical net on bridging 11, and the scaffold.
The external scaffolding device of the perpendicular BAIYE outer visor of the skyscraper of the present embodiment and glass curtain wall dual-purpose, by following Installation method is set up:
Step(1), preparation of construction, pre-buried round steel U-shaped draw ring 13 on flooring 20 during main structure construction, on flooring 20 pacify Dress and fixed Cantilever Beams 4.
Step(2), weld the base positioning bar dowel of scaffold upright rod 8 in 4 end of Cantilever Beams, then vertical installing bottom layer Scaffold upright rod 8, and set up.
Step(3), transverse horizontal bar 10 is installed, set up vertical equity bar 9, every layer of scaffold lays reinforcing bar grid scaffold board 15, and railing 12 and wooden foot guard plate are installed, set up bridging 11, plug-in safety vertical net.
Step(4), scaffold 1 carry out upper walls post construction after handing over circle, when the outer beam 18 of the structure of upper floor is constructed, in advance Wire-rope sling 14 and wall-connecting piece 17 are buried, steel wire rope 5 is tensioned.
Step(5), vertical rod 8 continue up and set up, repeat the(3)Step is put to scaffold off-load floor face 19, in flooring Pre-buried wire-rope sling 14 on 19 upper Stall sandwich beam, segmentation off-load steel wire rope 5 is embedded in last layer building through described Wire-rope sling 14 in structural beams, and the scaffold upright rod transverse horizontal with described fastener type double-row steel pipe scaffold respectively The snapping point oblique pull knot of bar and vertical equity bar, and tensioned branch off-load steel wire rope 5.
Step(6), repeat above step(3)To step(5), it is simultaneous with glass curtain wall to the perpendicular BAIYE outer visor of skyscraper Till the whole installation of external scaffolding device.
When the external scaffolding device of the perpendicular BAIYE outer visor of skyscraper of the present utility model and glass curtain wall dual-purpose is removed, Installation with cladding glass and sunshading board interts to be carried out.I.e. as cladding glass and sunshading board often install one layer from top to bottom, foot Hand cradle just removes one layer.
Common, the dismounting of the fastener type double-row steel pipe scaffold 1 on the Cantilever Beams is carried out by following disassembly sequence Remove:
Step(1), as shown in Fig. 2 the fastener type double-row steel pipe scaffold 1 be layered from top to bottom dismounting before, first install The facing aluminium sheet 6 of the steel structure framework of upper strata sunshade board support, then the cladding glass 2 on upper strata is installed.
Step(2), as shown in figure 3, removing the steel of the fastener type double-row steel pipe scaffold 1 to the sunshade board support of lower floor Under structural framework 7(But the guard rail 12 in outside need to be retained, to ensure the construction safety of upper strata sunshading board 3).
Step(3), as shown in figure 4, install upper strata sunshading board 3.
Step(4), after all glass curtain walls 2 and sunshading board 3 that complete upper strata, repeat above step(1)Extremely Step(3), successively advance downwardly in this order, until the out-mould scaffold of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose Till rack device is removed.
Common, described shaped steel is encorbelmented per layer of fastener type double-row steel pipe scaffold 1 and removes step and need by following Demounting procedure is layered from top to bottom and is removed:
Step(1), remove upper strata plug-in safety vertical net and bridging 11.
Step(2), remove the vertically and horizontally horizon bar on upper strata, reinforced mesh scaffold board 15 and wooden foot guard plate.
Step(3), first remove the wall-connecting piece 17 on upper strata, then the vertical rod 8 for removing upper strata.
Step(4), by step(1)To step(3)The step of remove lower floor scaffold.
Step(5), when removing the double-pole scaffold 1 in off-load floor face 19, first remove the pre-buried wire-rope sling of last layer 14, then segmentation off-load steel wire rope 5 is removed, then by step(1)To step(3)The step of layering remove described double-pole scaffold 1。
Step(6), when removing the double-pole scaffold 1 on I-steel Cantilever Beams 4, the pre-buried steel wire rope for first removing last layer hangs Ring 14, then steel wire rope 5 is removed, then by step(1)To step(3)The step of remove described double-pole scaffold 1.Finally, tear open Except I-steel Cantilever Beams 4.
In addition, in the present embodiment, the steel pipe specification of the fastener type double-row steel pipe scaffold 1 is φ 48 × 3.5, tubing For Q235 level steel.Described scaffolding steel pipe is connected using fastener, and the fastener is that malleable cast iron or cast steel make.The foot handss Plate 15 is reinforcing bar grid scaffold board.The plug-in safety vertical net is the fire-retardant safety net of 2000 mesh.
The scaffold upright rod 8 of the fastener type double-row steel pipe scaffold is each attached on the Cantilever Beams 4, described adjacent outstanding The level interval of outrigger 4 is the longitudinal pitch of the scaffold upright rod 8, and the material of Cantilever Beams 4 is the I-shaped of 18# or more specification Steel;Described every Cantilever Beams 4 are divided into canned paragraph and two parts of section of encorbelmenting, and the canned paragraph length is encorbelmented segment length 1.25 times, the canned paragraph two ends of described Cantilever Beams 4 are using two and the U-shaped round steel reinforcing bar being embedded in floor girder and board of the above Draw ring 13 is fixed with building structure beam slab, 13 a diameter of 20mm of U-shaped reinforcing bar draw ring;The every Cantilever Beams 4 are encorbelmented section Tail end welds two bar dowels, a diameter of 25mm to 30mm of the bar dowel, and length is 200mm, the bar dowel difference Insert the bottom of two scaffold upright rods 8 inside and outside the scaffold.
In the off-load section of scaffold, the level interval of the segmentation off-load steel wire rope 5 is three floor floor heights and does not surpass 15m is crossed, the level interval for being segmented off-load steel wire rope 5 is the longitudinal pitch of the double-row steel pipe scaffold upright rod 8, the segmentation Off-load steel wire rope 5 is 6 × 37 steel wire ropes of the diameter not less than 15.0mm.
The material of the wire-rope sling 14 being embedded in last layer floor girder and board is HPB235 level reinforcing bars, and which is not a diameter of little In 20mm.
The scaffold rigid connecting wall part 17 is 48 × 3.5 steel pipe wall-connecting pieces of φ, and the wall-connecting piece 17 adopts right-angle coupler It is connected with vertical rod 8 in the scaffold and the positioning short steel pipes being embedded in concrete structured beam respectively.
Fastener type double-row steel pipe scaffold 1 on the Cantilever Beams 4 divides some steps, often walks with each floor as unit Away from 1.8m as standard, and arrange in the middle part of floor floor height and adjust step pitch together(The step pitch must not exceed 1.8m), wherein, in layer Between the step pitch of horizon bar in length and breadth at sun-shading louver steel structure support seat 7 should be 1.8m.
Described fastener type double-row steel pipe scaffold 1 reasonably arranges scaffold according to the arrangement mode of vertical sunshading board 3 Vertical rod 8, the scaffold upright rod 8 include interior vertical rod and outer vertical rod, i.e., in rotatable 3 surrounding of the vertical sunshading board difference per piece It is symmetrical arranged interior vertical rod and outer vertical rod is each two, interior vertical rod is located on the outside of curtain wall and the space outside 8 rotating range of sunshading board Between and be interspersed in the steel structure framework 7 of sunshade board support, outer vertical rod is located at the outside outside 8 rotating range of sunshading board, often Any rod member is not set in 8 rotating range of piece sunshading board, vertical equity bar 9 is uniformly located at the centre of adjacent two pieces of sunshading boards, vertical rod 8 Transfer is 8 width+0.2m of sunshading board, and 8 advance of vertical rod is the spacing of adjacent two pieces of sunshading boards 8.
In addition, the external scaffolding device of the perpendicular BAIYE outer visor of skyscraper as shown in Figure 1 and glass curtain wall dual-purpose, its In, three Floor 12s of skyscraper ground, total height 160m, five layers to three Floor 12s are index bed, and floor height h is 4.5m;Curtain Wall glass is LOW-E double layer glasss;Every sun-shading louver 3 is 3.5m(It is high)×1.0m(It is wide)Aluminum BAIYE, aluminum BAIYE Bearing adopts steel frame bearing 7, and from five layers to three eleventh floors, per layer one sets, and aluminum BAIYE level interval is 1.2m.At five layers extremely 19 layers and 20 layers that the perpendicular BAIYE outer visor of two sets of skyscrapers is respectively adopted to three eleventh floors is outer with glass curtain wall dual-purpose Scaffold device, i.e., be respectively provided with I-steel Cantilever Beams at five layers and 20 layers, eight layers, eleventh floor, 14 layers, 17 layers, 23 layers, 27 layers, 30 layers are respectively provided with off-load steel wire rope.
Scaffold upright rod 8, vertical equity bar 9, transverse horizontal bar 10, bar of sweeping the floor, bridging 11 and railing 12 are using rule Lattice are 48 × 3.5 steel pipes of φ.
Width 0.2m of 8 longitudinal pitch of vertical rod of the fastener type double-row steel pipe scaffold more than sunshading board, the foot handss The horizontal spacing for erecting bar 8 is the level interval of adjacent two pieces of sunshading boards 3.
The step pitch of the fastener type double-row steel pipe scaffold 1 is the fastener in the range of 1.8m, and each floor floor height Formula double-row steel pipe scaffold scaffold 1 is provided with regulation step pitch, and the regulation step pitch is not more than 1.8m, in every layer of sun-shading louver plate The step pitch of the fastener type double-row steel pipe scaffold 1 at bearing 7 should be 1.8m.
The installation method during integrally-built concrete application shown in Fig. 1:
Step(1), on five floor faces arrange exterior wall scaffold 1 Cantilever Beams 4, main structure construction is to the floor face When, pre-buried a diameter of 20mm round steel U-shaped draw ring 13, and install and fixed 18# I-steel Cantilever Beams 4.Cantilever Beams 4 are often set across one, The end face of the Cantilever Beams 4 to five floor laminate side supporting-points apart from L1 be 1.8m, the anchoring dot center of Cantilever Beams 4 is to the floor Edges of boards supporting-point apart from L2 be 2.25m.
Step(2), on Cantilever Beams 4 encorbelment section weld 20 bar dowels of φ as scaffold upright rod 8 positioning base, then Installing bottom layer scaffold upright rod 8 is erect, advance B and transfer of vertical rod are 1.2m, and set up.
Step(3), transverse horizontal bar 10 and vertical equity bar 9 are installed, be 1.8m per floor step pitch(Standard step pitch)+0.9m (Adjust step pitch) +1.8m(Standard step pitch), level bridge laying reinforcing bar grid scaffold board 15, and railing 12 and wooden foot guard plate are installed, take If bridging 11, plug-in close mesh flame-retarding founds net.
Step(4), after scaffold 1 hands over circle, when the structural beams in six floor faces are constructed, pre-buried steel wire rope 5 and building structure The diameter 20mm round bars suspension ring of drawknot and wall-connecting piece 17,4 outer end of steel I-beam be tensioned steel wire rope 5, steel wire rope 5 be diameter not Less than 6 × 37 steel wire ropes of 15.0mm.
Step(5), vertical rod 8 continue up and set up, repeat step(3)The flooring corresponding to off-load layer is segmented to scaffold 19, in the wire-rope sling 14 of the pre-buried diameter 20mm round bars of last layer flooring, tensioned branch off-load steel wire rope 5, it is segmented off-load The specification of steel wire rope 5 draws the steel wire rope 5 for hanging steel I-beam 4 identical with overhang layer.
Step(6), vertical rod 8 continue up and set up, repeat above step(3)To step(5)To three eleventh floors.
Method for dismounting during the concrete application of the present embodiment is referred to shown in Fig. 2 to Fig. 4:
Step(1), described fastener type double-pole scaffold 1 be layered from top to bottom dismounting before, three eleventh floor sunshades are first installed The facing aluminium sheet 6 of the steel structure framework of board support, then the cladding glass 2 of three eleventh floors is installed.
Step(2), remove three eleventh floors plug-in safety vertical net and bridging 11.
Step(3), remove the vertical equity bar 9 of three eleventh floors, transverse horizontal bar 10, reinforcing bar grid scaffold board 15 and wood gear Sole.
Step(4), first remove the wall-connecting piece 17 of three eleventh floors, then remove the vertical rod of three eleventh floors to 30 layers of sunshading board Under the steel structure framework 7 of seat(Retain the guard rail 12 on the outside of three eleventh floors).
Step(5), install three eleventh floors sunshading board 3.
Step(6), remove 30 layers(Flooring 19 i.e. corresponding to scaffold segmentation off-load layer)Double-row steel pipe scaffold 1 Before, the pre-buried wire-rope sling 14 of three eleventh floor floorings is first removed, then removes segmentation off-load steel wire rope 5, then by step(1) To step(3)30 layers of facing aluminium sheet 6, cladding glass 2 and sunshading board 3 are respectively mounted, and remove 30 layers of scaffold.
Step(7), repeat above step to remove 20 layers(That is I-steel overhang layer)Double-pole scaffold 1 when, first tear open Except the pre-buried wire-rope sling 14 of two eleventh floor floorings, then steel wire rope 5 is removed, then by step(1)To step(3)Install 20 The facing aluminium sheet 6 of layer, cladding glass 2 and sunshading board 3, and remove 20 layers of double-pole scaffold 1.Finally, 20 floors are removed The I-steel Cantilever Beams 4 in face.
Step(8), successively advance downwardly in the above sequence, until the perpendicular BAIYE outer visor of skyscraper and glass curtain wall and Till external scaffolding device is all removed.
Preferred embodiment of the present utility model is the foregoing is only, it is not to limit this utility model, all at this Any modification, equivalent and improvement made within the spirit and principle of utility model etc., should be included in this utility model Protection domain within.

Claims (10)

1. skyscraper erects the external scaffolding device of BAIYE outer visor and glass curtain wall dual-purpose, it is characterised in that including fixation Cantilever Beams, the fastener type double-row steel pipe scaffold being located on Cantilever Beams, Cantilever Beams steel wire rope on building structure beam slab, Segmentation off-load steel wire rope, wire-rope sling and scaffold rigid connecting wall part;The fastener type double-row steel pipe scaffold is arranged on institute State on Cantilever Beams;The fastener type double-row steel pipe scaffold is connected with building structure using scaffold rigid connecting wall part;The institute per root State Cantilever Beams outer end and be respectively provided with Cantilever Beams steel wire rope, the Cantilever Beams steel wire rope and the steel being embedded in last layer architecture beam Cord suspension ring oblique pull is tied;In the off-load section of scaffold, the fastener type double-row steel pipe scaffold is by being segmented off-load steel wire rope Tie with the wire-rope sling oblique pull.
2. skyscraper as claimed in claim 1 erects the external scaffolding device of BAIYE outer visor and glass curtain wall dual-purpose, its It is characterised by, the fastener type double-row steel pipe scaffold includes scaffold upright rod, transverse horizontal bar and vertical equity bar, described Several transverse horizontal bars are provided between scaffold upright rod, the transverse horizontal bar is fixed on scaffold upright rod by right-angle coupler On;The vertical equity bar is equidistantly fixed on the transverse horizontal bar;The bottom of the scaffold upright rod is provided with longitudinal direction and sweeps The thin end of the scroll, the longitudinal direction are swept the floor and laterally sweep the floor bar.
3. skyscraper as claimed in claim 2 erects the external scaffolding device of BAIYE outer visor and glass curtain wall dual-purpose, its It is characterised by, the scaffold upright rod of the fastener type double-row steel pipe scaffold is each attached on the Cantilever Beams, it is adjacent described outstanding The level interval of outrigger is the longitudinal pitch of the scaffold upright rod, and the material of the Cantilever Beams is the work of 18# or more specification Word steel;Canned paragraph is divided into per Cantilever Beams described in root and two parts of section of encorbelmenting, the canned paragraph length is encorbelmented segment length 1.25 times, the two ends of the canned paragraph of described Cantilever Beams are using two and the U-shaped round steel steel being embedded in floor girder and board of the above Muscle draw ring is fixed with building structure beam slab, a diameter of 20mm of the U-shaped reinforcing bar draw ring;The tail of the section of encorbelmenting per Cantilever Beams described in root End two bar dowels of welding, a diameter of 25mm to 30mm of the bar dowel, length is 200mm, and the bar dowel is inserted respectively Enter the bottom of inside and outside two scaffold upright rods of the fastener type double-row steel pipe scaffold.
4. skyscraper as claimed in claim 3 erects the external scaffolding device of BAIYE outer visor and glass curtain wall dual-purpose, its It is characterised by, the longitudinal pitch of the vertical rod of the fastener type double-row steel pipe scaffold is more than the width 0.2m of sunshading board, the foot The horizontal spacing of hand cradle vertical rod is the level interval of adjacent two pieces of sunshading boards.
5. skyscraper as claimed in claim 4 erects the external scaffolding device of BAIYE outer visor and glass curtain wall dual-purpose, its It is characterised by, the step pitch of the fastener type double-row steel pipe scaffold is the fastener in the range of 1.8m, and each floor floor height Formula double-row steel pipe scaffold is provided with regulation step pitch, and the regulation step pitch is not more than 1.8m, at every layer of sun-shading louver board support The step pitch of the fastener type double-row steel pipe scaffold should be 1.8m.
6. skyscraper as claimed in claim 5 erects the external scaffolding device of BAIYE outer visor and glass curtain wall dual-purpose, its It is characterised by, Steel scaffold board is laid on the vertical equity bar of the fastener type double-row steel pipe scaffold, on the scaffold upright rod Railing and wooden foot guard plate are respectively provided with, the outside of the fastener type double-row steel pipe scaffold arranges bridging, on the bridging It is provided with plug-in safety vertical net.
7. skyscraper as claimed in claim 6 erects the external scaffolding device of BAIYE outer visor and glass curtain wall dual-purpose, its It is characterised by, the steel pipe specification of the fastener type double-row steel pipe scaffold is φ 48 × 3.5, tubing is Q235 level steel, the button The steel pipe of part formula double-row steel pipe scaffold is connected using fastener, and the material of the fastener is malleable cast iron or cast steel, the steel foot Palm is reinforcing bar grid scaffold board, and the plug-in safety vertical net is the fire-retardant safety net of 2000 mesh.
8. skyscraper as claimed in claim 7 erects the external scaffolding device of BAIYE outer visor and glass curtain wall dual-purpose, its It is characterised by, in the off-load section of scaffold, the segmentation off-load steel wire penetrating is embedded in last layer architecture beam The wire-rope sling, and scaffold upright rod respectively with the fastener type double-row steel pipe scaffold, transverse horizontal bar and vertical Tie to the snapping point oblique pull of horizon bar;The level interval of the segmentation off-load steel wire rope is for three floor floor heights and is less than 15m, The level interval of segmentation off-load steel wire rope is the longitudinal pitch of the vertical rod of the double-row steel pipe scaffold, the segmentation off-load steel Cord is 6 × 37 steel wire ropes of the diameter not less than 15.0mm.
9. skyscraper as claimed in claim 8 erects the external scaffolding device of BAIYE outer visor and glass curtain wall dual-purpose, its It is characterised by, the material of the wire-rope sling is HPB235 level reinforcing bars, and which is a diameter of not less than 20mm.
10. skyscraper as claimed in claim 9 erects the external scaffolding device of BAIYE outer visor and glass curtain wall dual-purpose, its It is characterised by, the scaffold rigid connecting wall part is 48 × 3.5 steel pipe wall-connecting pieces of φ, the scaffold rigid connecting wall part is using straight Angle fastener is connected with the scaffold upright rod and the positioning short steel pipes being embedded in concrete structured beam respectively.
CN201621013991.8U 2016-08-31 2016-08-31 The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose Active CN206053274U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621013991.8U CN206053274U (en) 2016-08-31 2016-08-31 The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621013991.8U CN206053274U (en) 2016-08-31 2016-08-31 The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose

Publications (1)

Publication Number Publication Date
CN206053274U true CN206053274U (en) 2017-03-29

Family

ID=58373666

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621013991.8U Active CN206053274U (en) 2016-08-31 2016-08-31 The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose

Country Status (1)

Country Link
CN (1) CN206053274U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108179868A (en) * 2018-02-08 2018-06-19 安徽安兴装饰工程有限责任公司 A kind of aerial construction platform device that special-shaped curtain wall is overhang based on steel construction
CN110924700A (en) * 2019-12-12 2020-03-27 重庆建工住宅建设有限公司 Building protective structure
CN111946042A (en) * 2020-08-25 2020-11-17 中建八局第四建设有限公司 Method for building external scaffold of concrete cantilever structure and external scaffold device
CN113047593A (en) * 2021-05-14 2021-06-29 中铁七局集团郑州工程有限公司 Construction method of cantilever beam scaffold
CN113323395A (en) * 2021-06-11 2021-08-31 中铁十二局集团建筑安装工程有限公司 Winter construction method of steel structure thick-coating type non-expansion fireproof coating
CN113931354A (en) * 2021-04-26 2022-01-14 中国建筑第七工程局有限公司 Cantilever scaffold and curtain wall integrated structure and construction method
CN115126233A (en) * 2022-08-02 2022-09-30 广东中联建建筑工程有限公司 Construction method for using cantilever beam plate high formwork with complex outer vertical surface as outer wall scaffold
CN115897977A (en) * 2022-12-19 2023-04-04 中国建筑第二工程局有限公司 Triple unloading system of non-return self-adhesion atrium decoration scaffold and construction method thereof

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108179868A (en) * 2018-02-08 2018-06-19 安徽安兴装饰工程有限责任公司 A kind of aerial construction platform device that special-shaped curtain wall is overhang based on steel construction
CN108179868B (en) * 2018-02-08 2023-11-03 安徽安兴装饰工程有限责任公司 Air construction platform device based on steel structure overhanging special-shaped curtain wall
CN110924700A (en) * 2019-12-12 2020-03-27 重庆建工住宅建设有限公司 Building protective structure
CN111946042A (en) * 2020-08-25 2020-11-17 中建八局第四建设有限公司 Method for building external scaffold of concrete cantilever structure and external scaffold device
CN113931354A (en) * 2021-04-26 2022-01-14 中国建筑第七工程局有限公司 Cantilever scaffold and curtain wall integrated structure and construction method
CN113931354B (en) * 2021-04-26 2023-10-20 中国建筑第七工程局有限公司 Cantilever scaffold and curtain wall integrated structure and construction method
CN113047593A (en) * 2021-05-14 2021-06-29 中铁七局集团郑州工程有限公司 Construction method of cantilever beam scaffold
CN113323395A (en) * 2021-06-11 2021-08-31 中铁十二局集团建筑安装工程有限公司 Winter construction method of steel structure thick-coating type non-expansion fireproof coating
CN115126233A (en) * 2022-08-02 2022-09-30 广东中联建建筑工程有限公司 Construction method for using cantilever beam plate high formwork with complex outer vertical surface as outer wall scaffold
CN115897977A (en) * 2022-12-19 2023-04-04 中国建筑第二工程局有限公司 Triple unloading system of non-return self-adhesion atrium decoration scaffold and construction method thereof
CN115897977B (en) * 2022-12-19 2024-05-28 中国建筑第二工程局有限公司 Triple unloading system of self-attached atrium decoration scaffold without roof returning and construction method thereof

Similar Documents

Publication Publication Date Title
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN103635643B (en) The construction method of nigh-level synthesis steel bar concrete cylindrical shell
CN101538896B (en) Construction method for jettied structure at high attitude of high-rise building
CN108643544B (en) High-altitude overhanging construction platform support system and construction method
CN106760529B (en) Roof steel truss sliding assembly construction platform and installation method
CN103982040B (en) A kind of construction of super highrise building vertical multi-transportation device
CN202324571U (en) Overhanging type double-row scaffold
CN101397844B (en) Construction method of special section steel concrete composite structure inclined wall mould base engineering
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment
CN206128603U (en) Curtain mounting structure that leads a wandering life cornices
CN111779248A (en) High formwork system and construction method thereof
CN111395730A (en) Curtain wall construction system and method suitable for high-rise building with special-shaped giant columns
CN107327068A (en) Steel construction truss string structure system roof system ceiling structure and its construction method
CN107227814A (en) A kind of large cantilever concrete structure section construction method
CN206319610U (en) Roof system steel truss slipping and assembling construction platform structure
CN205314519U (en) High altitude operation platform based on truss
CN202214974U (en) 5.8 m ultrahigh external lifting scaffold
CN212507296U (en) High formwork system
CN201635377U (en) Rigid suspended type scaffold provided with large-span steel roof equipment pipeline
CN209568688U (en) A kind of elevating construction platform
CN115306137B (en) Operation platform structure for installing suspended ceiling at bottom of high-altitude corridor and construction method thereof
CN202788017U (en) Horizontally-overhung rigid hermetic section steel protective shed for high-rise buildings
CN211923574U (en) Construction device for constructing top floor of building
CN108412033B (en) External vertical forest overhanging balcony structure of building and construction method thereof
CN103015696B (en) Hanging basket outer protective layer for super high-rise building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant