CN111779248A - High-support formwork system and its construction method - Google Patents

High-support formwork system and its construction method Download PDF

Info

Publication number
CN111779248A
CN111779248A CN202010624701.8A CN202010624701A CN111779248A CN 111779248 A CN111779248 A CN 111779248A CN 202010624701 A CN202010624701 A CN 202010624701A CN 111779248 A CN111779248 A CN 111779248A
Authority
CN
China
Prior art keywords
bracket
steel
platform
fixedly connected
formwork system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010624701.8A
Other languages
Chinese (zh)
Other versions
CN111779248B (en
Inventor
韩晓星
秦毅
陈曦
王云济
白洋
闫和新
张立强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 7 Group Co Ltd
Original Assignee
Shanghai Construction No 7 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 7 Group Co Ltd filed Critical Shanghai Construction No 7 Group Co Ltd
Priority to CN202010624701.8A priority Critical patent/CN111779248B/en
Publication of CN111779248A publication Critical patent/CN111779248A/en
Application granted granted Critical
Publication of CN111779248B publication Critical patent/CN111779248B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/18Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by cantilevers or other provisions mounted in openings in the building, e.g. window openings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/02Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for columns or like pillars; Special tying or clamping means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/04Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/20Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/22Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by roofs or ceilings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/006Scaffold with cantilevered sections, e.g. to accommodate overhangs or recesses in the facade
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/046Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/06Consoles; Brackets
    • E04G5/061Consoles; Brackets specially adapted for attachment to scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/16Struts or stiffening rods, e.g. diagonal rods

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The application provides a high formwork system and a construction method thereof, wherein the high formwork system comprises: the cantilever operation platform, the scaffold, the steel beam bracket and the concrete beam column wood formwork bent frame; the scaffold is erected on the cantilever operation platform, and the steel beam bracket is arranged above the cantilever operation platform and used for supporting the suspended beam structure; the steel beam bracket comprises a bracket main body and a bracket inclined strut, two ends of the bracket main body are respectively inserted into the shear walls and are fixedly connected with the shear walls, one end of the bracket inclined strut is fixedly connected with the bracket main body, and the other end of the bracket inclined strut is fixedly connected with an embedded part of the shear walls; the concrete beam column wood formwork bent is arranged on the steel beam bracket. In the high formwork system and the construction method thereof, the mode that the large-section steel shelving beam is matched with the high-altitude overhanging steel platform is adopted, the problem that the high-altitude large-section reinforced concrete member cannot be constructed is solved, a good practical effect can be obtained, and the high formwork system and the construction method thereof have the advantages of low construction difficulty, economy, environmental protection, high safety factor and the like.

Description

高支模体系及其施工方法High-support formwork system and its construction method

技术领域technical field

本发明涉及建筑施工技术领域,特别涉及一种高支模体系及其施工方法。The invention relates to the technical field of building construction, in particular to a high-support formwork system and a construction method thereof.

背景技术Background technique

在高层住宅建设领域,为了突出单体建筑设计个性化或满足区域整体规划要求,通常在外檐、屋顶等部位设计有不同造型的砼花架梁、立体格栅结构或钢构件造型等,形成具有独特造型,并极具现代感的外观设计,观感效果极好。In the field of high-rise residential construction, in order to highlight the individuality of the individual building design or meet the overall planning requirements of the region, different shapes of concrete flower frame beams, three-dimensional grid structures or steel component shapes are usually designed on the eaves, roofs and other parts, forming a unique design. The shape, and the very modern appearance design, the look and feel effect is excellent.

然而,由此衍生出诸如高空大型钢构件吊装、高空悬空钢筋混凝土结构模架支设、屋面凸出部外檐装饰装修高空作业等土建及装饰装修施工难题,不仅施工工艺本身技术难度高,而且涉及大量高空作业,防坠落安全管控要求同样很高。However, from this, civil construction and decoration construction problems such as the hoisting of high-altitude large-scale steel components, the support of high-altitude suspended reinforced concrete structure formwork, and the high-altitude operation of roof eaves decoration and decoration are derived. Not only the construction process itself is technically difficult, but also It involves a lot of high-altitude operations, and the requirements for anti-fall safety management and control are also very high.

随着建筑规模越大,钢筋混凝土施工中高支模体系的刚度、强度以及稳定性要求就越高,实施模体施工的难度也相应加大,特别是“大截面钢筋混凝土构件高空悬空高支模”,普遍存在施工难度高、安全系数低的缺点。由于对高支模体系施工技术不熟练,或工程经验不足,造成工程事故的现象时有发生,同时危及建筑物的安全,严重的还会造成生命财产的破坏。As the scale of the building increases, the rigidity, strength and stability requirements of the high-support formwork system in the reinforced concrete construction are higher, and the difficulty of implementing the formwork construction also increases accordingly. ”, there are generally disadvantages of high construction difficulty and low safety factor. Due to the unskilled construction technology of the high-support formwork system, or the lack of engineering experience, engineering accidents often occur, and at the same time endanger the safety of buildings, and even cause serious damage to life and property.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供一种高支模体系及其施工方法,以解决现有的高支模体系存在施工难度高、安全系数低的问题。The purpose of the present invention is to provide a high-support formwork system and a construction method thereof, so as to solve the problems of high construction difficulty and low safety factor in the existing high-support formwork system.

为解决上述技术问题,本发明提供一种高支模体系,所述高支模体系包括:悬挑操作平台、脚手架、钢梁托架和砼梁柱木模板排架;In order to solve the above-mentioned technical problems, the present invention provides a high formwork system, the high formwork system includes: a cantilevered operating platform, a scaffold, a steel beam bracket and a concrete beam, column and wood formwork frame;

所述悬挑操作平台包括悬挑主梁、水平联梁和平台板,所述水平联梁与所述悬挑主梁垂直设置,所述悬挑主梁包括锚固段和悬挑段,所述悬挑主梁的锚固段固定于指定楼板上,所述悬挑主梁的悬挑段伸出于所述指定楼板,所述水平联梁和所述平台板均固定于所述悬挑主梁的悬挑段;The cantilevered operation platform includes a cantilevered main beam, a horizontal coupling beam and a platform plate, the horizontal coupling beam is vertically arranged with the cantilevered main beam, the cantilevered main beam includes an anchoring section and a cantilevered section, and the The anchoring section of the cantilevered main beam is fixed on the designated floor, the cantilevered section of the cantilevered main beam protrudes from the designated floor, and the horizontal coupling beam and the platform plate are both fixed to the cantilevered main beam the cantilever section;

所述脚手架搭设于所述悬挑操作平台上,并与所述水平联梁固定连接;The scaffold is erected on the cantilevered operation platform and fixedly connected with the horizontal coupling beam;

所述钢梁托架安装于所述悬挑操作平台的上方,用于承托悬空梁结构;The steel beam bracket is installed above the cantilevered operation platform for supporting the cantilever beam structure;

所述钢梁托架包括托架主体和托架斜撑,所述托架主体的两端分别插入剪力墙预留的搁置凹槽中并与剪力墙固定连接,所述托架斜撑的其中一端与所述托架主体固定连接,所述托架斜撑的另一端与所述剪力墙的预埋件固定连接;The steel beam bracket includes a bracket main body and a bracket diagonal brace. Both ends of the bracket main body are respectively inserted into the shelf grooves reserved by the shear wall and are fixedly connected to the shear wall. The bracket diagonal bracing One end of the bracket is fixedly connected to the bracket main body, and the other end of the bracket diagonal brace is fixedly connected to the embedded part of the shear wall;

所述托架主体上铺设有砼梁柱木模板支设基础,所述砼梁柱木模板排架安装于所述砼梁柱木模板支设基础上。A concrete beam, column and wood formwork support base is laid on the main body of the bracket, and the concrete beam, column and wood formwork bracket is installed on the concrete beam, column and wood formwork support base.

可选的,在所述的高支模体系中,所述悬挑操作平台还包括平台斜撑、系杆和钢丝绳;Optionally, in the high-support formwork system, the cantilevered operation platform further includes a platform diagonal brace, a tie rod and a wire rope;

所述平台斜撑的其中一端与所述悬挑主梁的下表面固定连接,所述平台斜撑的另一端与下层楼板的预埋件固定连接;One end of the platform diagonal brace is fixedly connected to the lower surface of the cantilevered main beam, and the other end of the platform diagonal brace is fixedly connected to the embedded part of the lower floor slab;

所述系杆的其中一端与所述平台斜撑固定连接,所述系杆的另一端与所述悬挑主梁固定连接;One end of the tie rod is fixedly connected to the platform diagonal brace, and the other end of the tie rod is fixedly connected to the cantilevered main beam;

所述悬挑操作平台还包括钢丝绳,所述钢丝绳的一端与所述主梁连接,所述钢丝绳的另一端与上层楼板的预埋件固定连接。The cantilevered operation platform further comprises a steel wire rope, one end of the steel wire rope is connected with the main beam, and the other end of the steel wire rope is fixedly connected with the embedded part of the upper floor slab.

可选的,在所述的高支模体系中,所述砼梁柱木模板支设基础包括多根钢管,所述多根钢管沿着所述钢梁托架的跨度方向间隔设置。Optionally, in the high-support formwork system, the concrete beam-column-wood formwork support base includes a plurality of steel pipes, and the plurality of steel pipes are arranged at intervals along the span direction of the steel beam bracket.

可选的,在所述的高支模体系中,所述脚手架包括:多根立杆、多根横杆、附墙拉接和脚手板;Optionally, in the high-support formwork system, the scaffolding includes: a plurality of vertical bars, a plurality of horizontal bars, a wall-attached connection, and a scaffolding board;

所述多根立杆均为竖直设置,其底端与所述水平联梁固定连接;The plurality of vertical rods are arranged vertically, and the bottom ends thereof are fixedly connected with the horizontal coupling beam;

所述多根横杆均为水平设置,并通过第一扣件与所述多根立杆固定连接;The plurality of horizontal bars are arranged horizontally, and are fixedly connected to the plurality of vertical bars through a first fastener;

所述附墙拉接的其中一端与立杆固定连接,所述附墙拉接的另一端与建筑物的主体结构固定连接;One end of the wall-attached connection is fixedly connected with the vertical rod, and the other end of the wall-attached connection is fixedly connected with the main structure of the building;

所述脚手板铺设于所述水平联梁上。The scaffold board is laid on the horizontal coupling beam.

可选的,在所述的高支模体系中,所述多根立杆均位于所述悬挑主梁与所述水平联梁的交汇点。Optionally, in the high formwork system, the plurality of vertical rods are located at the intersection of the cantilevered main beam and the horizontal coupling beam.

可选的,在所述的高支模体系中,所述脚手架还包括硬隔离和安全网;Optionally, in the high-support formwork system, the scaffold further includes hard isolation and a safety net;

所述硬隔离设置于所述附墙拉接上,所述安全网设置于所述多根立杆的内侧,并与所述多根立杆固定连接。The hard isolation is arranged on the attachment wall and the safety net is arranged on the inner side of the plurality of vertical poles and is fixedly connected with the plurality of vertical poles.

可选的,在所述的高支模体系中,还包括:第一钢管排架和第二钢管排架;Optionally, the high formwork system further includes: a first steel tube bent frame and a second steel tube bent frame;

所述第一钢管排架设置于所述悬挑主梁的上面,用于顶撑所述悬挑主梁和所述指定楼板的上层楼板;The first steel tube bent frame is arranged on the top of the cantilevered main beam, and is used to support the cantilevered main beam and the upper floor slab of the designated floor slab;

所述第二钢管排架设置于主体结构的连廊内,用于顶撑所述指定楼板及其下层楼板。The second steel tube bent frame is arranged in the corridor of the main structure, and is used to support the designated floor and its lower floor.

可选的,在所述的高支模体系中,所述第一钢管排架和第二钢管排架在竖直方向上的投影均落入所述悬挑主梁的锚固段范围内。Optionally, in the high formwork system, the vertical projections of the first steel tube bent frame and the second steel tube bent frame both fall within the range of the anchoring section of the cantilevered main beam.

可选的,在所述的高支模体系中,所述悬挑主梁通过至少四道U型螺栓与所述指定楼板固定连接。Optionally, in the high formwork system, the cantilevered main beam is fixedly connected to the designated floor slab through at least four U-bolts.

可选的,在所述的高支模体系中,所述悬挑主梁采用20号工字钢,所述水平联梁采用16号工字钢,所述托架主体采用56号工字钢,所述托架斜撑采用22号工字钢。Optionally, in the high formwork system, the cantilevered main beam is made of No. 20 I-beam, the horizontal coupling beam is made of No. 16 I-beam, and the bracket body is made of No. 56 I-beam. , the bracket diagonal brace is made of 22-gauge I-beam.

可选的,在所述的高支模体系中,所述平台斜撑采用20号工字钢,所述系杆采用16号槽钢。Optionally, in the high-support formwork system, the platform diagonal brace is made of 20-gauge I-beam, and the tie rod is made of 16-gauge channel steel.

相应的,本发明还提供一种高支模体系的施工方法,所述高支模体系的施工方法包括:Correspondingly, the present invention also provides a construction method of a high-support formwork system, and the construction method of the high-support formwork system includes:

步骤一、施做楼层主体砼结构,并在所述楼层主体砼结构中设置预埋件;Step 1, constructing the main concrete structure of the floor, and setting embedded parts in the main concrete structure of the floor;

步骤二、在指定楼板上安装悬挑操作平台;Step 2. Install the overhanging operation platform on the designated floor;

步骤三、在所述悬挑操作平台上搭设上一层脚手架,并施做上一层主体结构,所述上一层主体结构中预留有钢梁托架的凹槽和第一道悬空梁的凹槽;Step 3. Set up an upper layer of scaffolding on the cantilevered operating platform, and construct the upper layer of the main structure. The upper layer of the main structure is reserved with a groove for a steel beam bracket and a first suspended beam. groove;

步骤四、在所述第一道悬空梁的下方安装钢梁托架;Step 4. Install a steel beam bracket below the first suspended beam;

步骤五、在所述钢梁托架上施做大截面悬空梁。Step 5: Make a large-section suspended beam on the steel beam bracket.

可选的,在所述的高支模体系的施工方法中,在指定楼板上安装悬挑操作平台的过程包括:Optionally, in the construction method of the high formwork system, the process of installing the overhanging operation platform on the designated floor includes:

在地面上对悬挑主梁、平台斜撑和系杆进行加工,并将所述悬挑主梁、平台斜撑和系杆组成多个平台支撑;The cantilevered main beam, the platform diagonal brace and the tie rod are processed on the ground, and the cantilevered main beam, the platform diagonal brace and the tie rod are formed into a plurality of platform supports;

通过塔吊将所述多个平台支撑吊装就位;hoisting the plurality of platform supports in place by a tower crane;

通过至少四道U型螺栓将所述悬挑主梁固定于所述指定楼板上;The cantilevered main beam is fixed to the designated floor by at least four U-bolts;

将所述平台斜撑的下端与下层楼板的预埋件固定连接;The lower end of the platform diagonal brace is fixedly connected with the embedded part of the lower floor slab;

在所述悬挑主梁上依次铺设水平联梁以及平台板;Lay horizontal coupling beams and platform slabs in sequence on the cantilevered main beams;

将钢丝绳连接在所述悬挑主梁与上层楼板的预埋件之间。The steel wire rope is connected between the cantilevered main beam and the embedded part of the upper floor slab.

可选的,在所述的高支模体系的施工方法中,在指定楼板上安装悬挑操作平台之前,在施做楼层主体砼结构之后,还包括:在主体结构的连廊内安装第二钢管排架。Optionally, in the construction method of the high formwork system, before installing the cantilevered operation platform on the designated floor, and after the main concrete structure of the floor is installed, the method further includes: installing a second floor in the corridor of the main structure. Steel tube racks.

可选的,在所述的高支模体系的施工方法中,在所述悬挑操作平台上搭设上一层脚手架之前,在指定楼板上安装悬挑操作平台之后,还包括:在悬挑主梁上安装第一钢管排架。Optionally, in the construction method of the high formwork system, before the upper layer of scaffolding is erected on the overhanging operation platform, and after the overhanging operation platform is installed on the designated floor, the method further includes: A first steel tube bent frame is installed on the beam.

可选的,在所述的高支模体系的施工方法中,在所述悬挑操作平台上搭设上一层脚手架的过程包括:Optionally, in the construction method of the high formwork system, the process of erecting a layer of scaffolding on the overhanging operation platform includes:

将多根立杆固定在水平联梁上,并通过第一扣件将多根横杆与所述多根立杆固定连接;Fixing the plurality of vertical rods on the horizontal coupling beam, and fixedly connecting the plurality of transverse rods to the plurality of vertical rods through the first fastener;

采用两步两跨预埋法或贯穿墙体连接法施做附墙拉接;The two-step two-span embedded method or the through-wall connection method is used to make the wall-attached connection;

将脚手板满铺于所述水平联梁的顶面上;以及spread the scaffolding over the top surface of the horizontal coupling beam; and

依次安装硬隔离、挡脚板和安全网。Install hard isolation, toe guards, and safety net in sequence.

可选的,在所述的高支模体系的施工方法中,在所述第一道悬空梁的下方安装钢梁托架的过程包括:Optionally, in the construction method of the high formwork system, the process of installing a steel beam bracket below the first suspended beam includes:

在地面上对托架主体和托架斜撑进行加工以形成钢梁托架;Machining the bracket body and bracket braces on the ground to form steel beam brackets;

通过塔吊将所述钢梁托架吊装就位;The steel beam bracket is hoisted into place by a tower crane;

将所述托架主体的两端分别插入上一层主体结构预留的搁置凹槽中,并通过焊接方式将托架斜撑的下端与剪力墙的预埋件固定连接;以及Insert the two ends of the bracket main body into the resting grooves reserved by the main structure of the upper layer respectively, and fix the lower end of the bracket diagonal brace and the embedded part of the shear wall by welding; and

找平,并使用高细石混凝土分别浇筑密实所述搁置凹槽。Level and compact the shelving grooves separately with high-fine stone concrete.

可选的,在所述的高支模体系的施工方法中,在所述钢梁托架上施做大截面悬空梁的过程包括:Optionally, in the construction method of the high-support formwork system, the process of applying a large-section suspended beam on the steel beam bracket includes:

在所述钢梁托架上铺设多根钢管作为第一道砼梁柱木模板支设基础;Lay a plurality of steel pipes on the steel beam bracket as the first concrete beam, column and wood formwork support foundation;

在所述第一道砼梁柱木模板支设基础上支设第一道砼梁柱木模板;A first concrete beam, column and wood formwork is supported on the foundation of the first concrete beam, column and wood formwork;

进行砼浇筑;以及carry out concrete placement; and

进行混凝土养护直至第一道悬空梁的砼强度达到设计要求。Concrete curing is carried out until the concrete strength of the first suspended beam meets the design requirements.

可选的,在所述的高支模体系的施工方法中,在进行混凝土养护过程中,还包括:在所述悬挑操作平台上继续搭设脚手架,施做上一层结构砼及第二道悬空梁。Optionally, in the construction method of the high-support formwork system, during the concrete curing process, it also includes: continuing to erect scaffolding on the cantilevered operation platform, and applying the upper layer of structural concrete and the second layer of concrete. Hanging beam.

本发明与现有技术相比,具有如下优点和有益效果:Compared with the prior art, the present invention has the following advantages and beneficial effects:

1、本发明采用大截面型钢搁置梁结合高空悬挑钢平台,解决了高空大截面钢筋混凝土构件无法施工的难题,不但能够取得良好的实用效果,而且具备施工难度低、经济性优良、节材环保、安全系数高等诸多优点;1. The present invention adopts the large-section section steel shelving beam combined with the high-altitude cantilever steel platform to solve the problem that the high-altitude large-section reinforced concrete member cannot be constructed, not only can achieve good practical effects, but also has low construction difficulty, excellent economy, and material saving. Environmental protection, high safety factor and many advantages;

2、本发明的高支模体系除了利用所述悬挑操作平台本身所在的指定楼板作为支撑外,还利用了指定楼板下方的楼板和上方的楼板进行支撑,使得支撑效果更好,支撑更加稳定。2. The high formwork system of the present invention not only uses the designated floor where the cantilever operation platform itself is located as the support, but also uses the floor below the designated floor and the upper floor for support, so that the support effect is better and the support is more stable .

附图说明Description of drawings

图1为本发明实施例的高支模体系的立面布置示意图;1 is a schematic diagram of the elevation layout of a high-support formwork system according to an embodiment of the present invention;

图2为本发明实施例的高支模体系的平面布置示意图;FIG. 2 is a schematic plan view of a high-support formwork system according to an embodiment of the present invention;

图3为本发明实施例的高支模体系的剖面布置示意图;3 is a schematic diagram of a cross-sectional arrangement of a high-support formwork system according to an embodiment of the present invention;

图4为图1中区域A的结构示意图;Fig. 4 is the structural representation of area A in Fig. 1;

图5为图3中区域B的结构示意图;Fig. 5 is the structural representation of area B in Fig. 3;

图6为采用两步两跨预埋法的附墙拉接的结构示意图;FIG. 6 is a schematic structural diagram of a wall-attached connection using a two-step, two-span embedded method;

图7为采用贯穿墙体连接法的附墙拉接的结构示意图;Fig. 7 is the structural schematic diagram of the wall-attached connection adopting the through-wall connection method;

图8为本发明实施例的砼梁柱木模板排架的结构示意图;8 is a schematic structural diagram of a concrete beam, column and timber formwork bent according to an embodiment of the present invention;

图9为本发明实施例的高支模体系的施工方法中步骤一对应的结构示意图;9 is a schematic structural diagram corresponding to step 1 in the construction method of the high-support formwork system according to the embodiment of the present invention;

图10为本发明实施例的高支模体系的施工方法中步骤三对应的结构示意图;10 is a schematic structural diagram corresponding to step 3 in the construction method of the high-support formwork system according to the embodiment of the present invention;

图11为本发明实施例的高支模体系的施工方法中步骤四对应的结构示意图。11 is a schematic structural diagram corresponding to step 4 in the construction method of the high-support formwork system according to the embodiment of the present invention.

具体实施方式Detailed ways

以下结合附图和具体实施例对本发明提出的高支模体系及其施工方法作进一步详细说明。The high-support formwork system and its construction method proposed by the present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

请结合参考图1至图3,其为本发明实施例的高支模体系的结构示意图。如图1至图3所示,所述高支模体系100包括:悬挑操作平台、脚手架、钢梁托架和砼梁柱木模板排架;所述悬挑操作平台包括悬挑主梁11、水平联梁12和平台板(图中未示出),所述水平联梁12与所述悬挑主梁11垂直设置,所述悬挑主梁11包括锚固段和悬挑段,所述悬挑主梁11的锚固段固定于指定楼板上,所述悬挑主梁11的悬挑段伸出于所述指定楼板,所述水平联梁12和所述平台板均固定于所述悬挑主梁11的悬挑段;所述钢梁托架安装于所述悬挑操作平台的上方,所述钢梁托架包括托架主体31和托架斜撑32,所述托架主体31的两端分别插入剪力墙预留的搁置凹槽中并与所述剪力墙固定连接,所述托架斜撑32的其中一端与所述托架主体31固定连接,所述托架斜撑32的另一端与所述剪力墙的预埋件固定连接;所述托架主体31上铺设有砼梁柱木模板支设基础,所述砼梁柱木模板排架安装于所述砼梁柱木模板支设基础上,所述脚手架搭设于所述悬挑操作平台上,并与所述水平联梁12固定连接。Please refer to FIG. 1 to FIG. 3 , which are schematic structural diagrams of a high-support die system according to an embodiment of the present invention. As shown in FIG. 1 to FIG. 3 , the high formwork system 100 includes: a cantilevered operation platform, scaffolding, steel beam brackets, and concrete beams, columns and timber formwork bent frames; the cantilevered operation platform includes a cantilevered main beam 11, a horizontal A coupling beam 12 and a platform plate (not shown in the figure), the horizontal coupling beam 12 is vertically arranged with the cantilevered main beam 11, the cantilevered main beam 11 includes an anchoring section and a cantilevered section, the cantilevered main beam 11 The anchoring section of the main beam 11 is fixed on the designated floor, the cantilevered section of the cantilevered main beam 11 protrudes from the designated floor, and the horizontal coupling beam 12 and the platform plate are both fixed on the cantilevered main beam. The cantilevered section of the beam 11; the steel beam bracket is installed above the cantilever operation platform, and the steel beam bracket includes a bracket main body 31 and a bracket diagonal brace 32. The ends are respectively inserted into the resting grooves reserved by the shear wall and fixedly connected to the shear wall. One end of the bracket diagonal brace 32 is fixedly connected to the bracket main body 31 , and the bracket diagonal brace 32 is fixedly connected. The other end of the frame is fixedly connected with the embedded part of the shear wall; the bracket main body 31 is laid with a concrete beam, column and wood formwork support foundation, and the concrete beam, column and wood formwork rack is installed on the concrete beam, column and wood formwork support foundation. , the scaffold is erected on the cantilevered operation platform and fixedly connected with the horizontal link beam 12 .

具体的,所述悬挑主梁11包括多根型钢,所述多根型钢并排设置且间距相等,每根型钢均包括锚固段和悬挑段,所述锚固段位于指定楼板(例如第26楼的楼板)上并通过锚固件(U型螺栓)与所述指定楼板固定连接,所述悬挑段伸出于所述指定楼板之外。Specifically, the cantilevered main beam 11 includes a plurality of section steels, the plurality of section steels are arranged side by side with equal spacing, each section steel includes an anchoring section and a cantilever section, and the anchoring section is located on a designated floor (for example, the 26th floor). the floor) and fixedly connected with the specified floor by anchors (U-bolts), and the cantilevered section protrudes out of the specified floor.

本实施例中,所述悬挑主梁11的长度为12m,其中锚固段的长度为6.7m,悬挑段的长度为5.3m。In this embodiment, the length of the cantilevered main beam 11 is 12m, wherein the length of the anchoring section is 6.7m, and the length of the cantilever section is 5.3m.

本实施例中,所述悬挑主梁11包括7根20a号工字钢,7根20a号工字钢均沿水平方向设置。In this embodiment, the cantilevered main beam 11 includes seven I-beams of No. 20a, and the seven I-beams of No. 20a are arranged in the horizontal direction.

优选的,所述悬挑主梁11通过至少四道U型螺栓与所述指定楼板固定连接,即每根20a号工字钢通过至少四道U型螺栓与所述指定楼板固定连接。Preferably, the cantilevered main beam 11 is fixedly connected to the designated floor slab through at least four U-shaped bolts, that is, each 20a I-beam is fixedly connected to the designated floor slab through at least four U-shaped bolts.

请参考图5,其为图3中区域B的结构示意图。如图5所示,所述U型螺栓16预埋于所述指定楼板中,所述U型螺栓16的底部被所述指定楼板中预埋的两根钢筋18压住,所述悬挑主梁11插入所述U型螺栓16中,所述悬挑主梁11的侧向由木楔契紧。Please refer to FIG. 5 , which is a schematic structural diagram of the area B in FIG. 3 . As shown in FIG. 5 , the U-shaped bolts 16 are pre-embedded in the designated floor slab, and the bottom of the U-shaped bolts 16 is pressed by two steel bars 18 pre-embedded in the designated floor slab. The beam 11 is inserted into the U-bolt 16 , and the lateral direction of the cantilevered main beam 11 is fastened by wooden wedges.

本实施例中,所述钢筋18的长度为3m,直径为20mm。In this embodiment, the length of the steel bar 18 is 3m and the diameter is 20mm.

请继续参考图3,所述悬挑主梁11的间距(相邻的20a号工字钢之间的距离)D1为1500m,与剪力墙相邻的悬挑主梁11为边梁,所述边梁与所述建剪力墙的间距D2为500mm。Please continue to refer to FIG. 3 , the distance between the cantilevered main beams 11 (the distance between adjacent No. 20a I-beams) D1 is 1500m, and the cantilevered main beams 11 adjacent to the shear wall are side beams, so The distance D2 between the side beam and the built shear wall is 500mm.

请结合参考图2和图3,所述水平联梁12与所述悬挑主梁11垂直设置,所述水平联梁12通过焊接方式固定于所述悬挑主梁11上,所述平台板(图中未示出)铺设于所述悬挑主梁11上,并通过铁丝绑扎与所述悬挑主梁11固定连接。其中,所述水平联梁12同样包括多根型钢,所述多根型钢并排设置且间距相等。Please refer to FIG. 2 and FIG. 3 , the horizontal coupling beam 12 is vertically arranged with the cantilevered main beam 11 , the horizontal coupling beam 12 is fixed on the cantilevered main beam 11 by welding, and the platform plate (not shown in the figure) is laid on the cantilevered main beam 11, and is fixedly connected to the cantilevered main beam 11 through iron wire binding. Wherein, the horizontal coupling beam 12 also includes a plurality of section steels, and the plurality of section steels are arranged side by side with equal intervals.

本实施例中,所述水平联梁12包括6根16号工字钢,6根16号工字钢均沿水平方向设置,所述水平联梁12的长度(即16号工字钢的长度)为10米,所述水平联梁12的间距(相邻的16号工字钢之间的距离)D3在500~800mm之间。In this embodiment, the horizontal coupling beam 12 includes six 16-gauge I-beams, and the six 16-gauge I-beams are arranged in the horizontal direction. The length of the horizontal coupling beam 12 (that is, the length of the 16-gauge I-beam ) is 10 meters, and the distance between the horizontal coupling beams 12 (the distance between adjacent 16-gauge I-beams) D3 is between 500 and 800 mm.

请继续参考图3,所述悬挑操作平台还包括平台斜撑13、系杆14和钢丝绳15,所述平台斜撑13的上端与所述悬挑主梁11的下表面固定连接,所述平台斜撑13的下端与下层楼板(例如第25楼的楼板)的第一预埋件固定连接,所述平台斜撑13与水平面之间的夹角为α,所述系杆14的其中一端与所述平台斜撑13固定连接,所述系杆14的另一端与所述悬挑主梁11的悬挑段固定连接,所述钢丝绳15的一端与所述悬挑主梁11固定连接,所述钢丝绳15的另一端与上层楼板(例如第27楼的楼板)的第二预埋件固定连接,借助于所述钢丝绳15的拉接作用,能够进一步提升所述悬挑操作平台的结构稳定性,防止其倾覆。Please continue to refer to FIG. 3 , the cantilevered operation platform further includes a platform diagonal brace 13 , a tie rod 14 and a wire rope 15 . The upper end of the platform diagonal brace 13 is fixedly connected to the lower surface of the cantilevered main beam 11 . The lower end of the platform diagonal brace 13 is fixedly connected to the first embedded part of the lower floor (for example, the floor slab of the 25th floor), the angle between the platform diagonal brace 13 and the horizontal plane is α, and one end of the tie rod 14 It is fixedly connected to the platform diagonal brace 13, the other end of the tie rod 14 is fixedly connected to the cantilevered section of the cantilevered main beam 11, and one end of the wire rope 15 is fixedly connected to the cantilevered main beam 11, The other end of the wire rope 15 is fixedly connected to the second embedded part of the upper floor (for example, the floor on the 27th floor). With the help of the pulling effect of the wire rope 15, the structural stability of the cantilevered operation platform can be further improved sex to prevent it from overturning.

本实施例中,所述悬挑操作平台为高空悬挑钢平台,每根悬挑主梁11的底部均设置有平台斜撑13和系杆14,如此能够减小斜撑的长细比,确保斜撑安全。In this embodiment, the cantilevered operation platform is a high-altitude cantilevered steel platform, and the bottom of each cantilevered main beam 11 is provided with a platform diagonal brace 13 and a tie rod 14, so that the slenderness ratio of the diagonal brace can be reduced, Make sure the braces are safe.

本实施例中,所述平台斜撑13采用20号工字钢,所述系杆14采用16号槽钢,所述平台斜撑13与水平面之间的夹角为45°。In this embodiment, the platform diagonal brace 13 is made of 20-gauge I-beam, the tie rod 14 is made of 16-gauge channel steel, and the included angle between the platform diagonal brace 13 and the horizontal plane is 45°.

请结合参考图3、图6和图7,所述脚手架包括多根立杆21、多根横杆22、附墙拉接(图中标号未示出)和脚手板(图中未示出),所述多根立杆21均为竖直设置,其底端与所述水平联梁12固定连接,所述多根横杆22均为水平设置,并通过第一扣件(图中未示出)与所述多根立杆21固定连接,所述脚手板满铺于所述水平联梁12的顶面上,所述附墙拉接的其中一端与所述脚手架固定连接,所述附墙拉接的另一端与剪力墙固定连接,所述附墙拉接用于传递所述脚手架在使用过程中产生的拉力和压力,能够加强所述脚手架整体的稳定性。Please refer to Fig. 3, Fig. 6 and Fig. 7 in combination, the scaffolding comprises a plurality of vertical rods 21, a plurality of horizontal rods 22, a wall-attached connection (not shown in the figure) and a scaffolding board (not shown in the figure), The plurality of vertical bars 21 are arranged vertically, and the bottom ends thereof are fixedly connected to the horizontal coupling beam 12. The plurality of horizontal bars 22 are arranged horizontally and pass through a first fastener (not shown in the figure) It is fixedly connected with the plurality of vertical rods 21, the scaffolding board is fully spread on the top surface of the horizontal coupling beam 12, one end of the wall-attaching connection is fixedly connected with the scaffold, and the wall-attaching connection is fixedly connected. The other end of the scaffold is fixedly connected with the shear wall, and the wall attachment is used to transmit the tension and pressure generated by the scaffold during use, which can enhance the overall stability of the scaffold.

本实施例中,所述附墙拉接采用两步两跨预埋法或贯穿墙体连接法施做。如图6所示,采用两步两跨预埋法施做的附墙拉接包括连墙杆231和第二扣件232和预埋钢管233,所述预埋钢管233预埋于剪力墙中,所述连墙杆231的一端通过一第二扣件232与所述预埋钢管233固定连接,所述连墙杆231的另一端通过另一第二扣件232与所述脚手架的立杆21固定连接,由此所述脚手架通过所述附墙拉接与建筑物的主体结构相连接。In this embodiment, the wall attachment is performed by a two-step, two-span embedded method or a through-wall connection method. As shown in FIG. 6 , the attachment wall connection made by the two-step, two-span embedded method includes connecting wall rods 231, second fasteners 232 and embedded steel pipes 233. The embedded steel pipes 233 are embedded in the shear wall. One end of the connecting wall rod 231 is fixedly connected to the embedded steel pipe 233 through a second fastener 232, and the other end of the connecting wall rod 231 is connected to the scaffolding through another second fastener 232. The rods 21 are fixedly connected, whereby the scaffolding is connected with the main structure of the building through the attachment wall pull connection.

如图7所示,采用贯穿墙体连接法施做的附墙拉接包括连墙杆231和第二扣件232,所述连墙杆231的一端贯穿于剪力墙并通过第二扣件232与所述剪力墙固定连接,所述连墙杆231的另一端通过第二扣件232与所述脚手架的立杆21固定连接,由此所述脚手架通过所述附墙拉接与主体结构相连接。As shown in FIG. 7 , the wall-attaching connection performed by the through-wall connection method includes a connecting wall rod 231 and a second fastener 232. One end of the connecting wall rod 231 penetrates through the shear wall and passes through the second fastener. 232 is fixedly connected to the shear wall, and the other end of the connecting wall rod 231 is fixedly connected to the vertical rod 21 of the scaffolding through the second fastener 232, so that the scaffolding is connected to the main body through the attachment wall structure is connected.

本实施例中,所述多根立杆21和所述多根横杆22均为钢管,所述多根立杆21在横向上排成6排,在纵向上排成7排,纵向间距为1.5m,横向间距为500~1500mm,所述多根横杆22的步距为1.5m,所述第一扣件为直角扣件。优选的,所述多根立杆21均位于所述悬挑主梁11与所述水平联梁12的交汇点。In this embodiment, the plurality of vertical bars 21 and the plurality of horizontal bars 22 are steel pipes, and the plurality of vertical bars 21 are arranged in 6 rows in the transverse direction and 7 rows in the longitudinal direction, and the longitudinal spacing is 1.5m , the horizontal spacing is 500-1500 mm, the step distance of the plurality of cross bars 22 is 1.5 m, and the first fastener is a right-angle fastener. Preferably, the plurality of vertical rods 21 are located at the intersection of the cantilevered main beam 11 and the horizontal coupling beam 12 .

请继续参考图3、图6和图7,所述脚手架还包括硬隔离(图中未示出)、挡脚板(图中未示出)和安全网(图中未示出),所述硬隔离设置于所述附墙拉接上,所述硬隔离包括两根钢管、第三扣件和钢笆网,所述两根钢管均为水平设置,并通过所述第三扣件固定连接,所述钢笆网铺设于所述两根钢管上,所述挡脚板设置于所述多根立杆21的底部,并与所述多根立杆21固定连接,所述安全网设置于所述多根立杆21的内侧,并与所述多根立杆21固定连接。Please continue to refer to FIG. 3, FIG. 6 and FIG. 7, the scaffold further includes hard isolation (not shown in the figure), a foot plate (not shown in the figure) and a safety net (not shown in the figure). The isolation is arranged on the attachment wall, and the hard isolation includes two steel pipes, a third fastener and a steel fence. The two steel pipes are arranged horizontally and are fixedly connected by the third fastener. The steel fence is laid on the two steel pipes, the foot guard is arranged at the bottom of the plurality of vertical poles 21, and is fixedly connected with the plurality of vertical poles 21, and the safety net is arranged on the plurality of vertical poles 21. The inner side of the rod 21 is fixedly connected with the plurality of vertical rods 21 .

本实施例中,所述脚手架的四周阳角处沿外架垂直通长全高设置,所述脚手板为钢笆片脚手板,所述挡脚板采用高度为180mm的七夹板,所述七夹板沿着所述脚手板的四周通长设置,所述安全网为绿色密目安全网,所述立杆21全高范围内满挂绿色密目安全网围护,形成全封闭式操作空间,保证工人操作安全。In this embodiment, the surrounding outer corners of the scaffolding are arranged along the vertical length and full height of the outer frame, the scaffolding board is a steel fence piece scaffolding board, and the foot retaining board adopts a seven plywood with a height of 180mm. The safety net is a green dense mesh safety net, and the entire height of the vertical pole 21 is covered with a green dense mesh safety net to form a fully enclosed operating space to ensure that workers operate Safety.

请结合参考图3和图8,所述脚手架还包括扫地杆24、封顶杆25、水平杆26、水平向剪刀撑(图中标号未示出)及竖向剪刀撑,所述扫地杆24设置于该层脚手架的底部,所述封顶杆25设置于该层脚手架的顶部,所述水平杆26设置于所述扫地杆24与所述封顶杆25之间,所述水平向剪刀撑及竖向剪刀撑均按建筑规范要求进行设置。Please refer to FIG. 3 and FIG. 8 , the scaffold also includes a sweeping rod 24 , a capping rod 25 , a horizontal rod 26 , a horizontal scissor support (not shown in the figure) and a vertical scissor support. The sweeping rod 24 is provided with At the bottom of this layer of scaffolding, the capping bar 25 is arranged on the top of the scaffolding, the horizontal bar 26 is arranged between the sweeping bar 24 and the capping bar 25, the horizontal scissor support and the vertical Scissor braces are set according to building code requirements.

本实施例中,所述扫地杆24与所述脚手板的距离为200mm所述封顶杆25与可调顶托的距离小于500mm,所述水平杆26的步距小于1200mm。In this embodiment, the distance between the sweeping rod 24 and the scaffolding board is 200 mm, the distance between the capping rod 25 and the adjustable jack is less than 500 mm, and the step distance of the horizontal rod 26 is less than 1200 mm.

请结合参考图1和图4,所述钢梁托架包括托架主体31和两个托架斜撑32,所述托架主体31为水平设置,其两端分别插入剪力墙预留的搁置凹槽中并与所述剪力墙固定连接,所述两个托架斜撑32的其中一端均与所述托架主体31固定连接,所述两个托架斜撑32的另一端均与所述剪力墙的预埋件固定连接。其中,所述两个托架斜撑32对称设置,且要求能够提供足够的支撑力与支撑面积。Please refer to FIG. 1 and FIG. 4 , the steel beam bracket includes a bracket main body 31 and two bracket diagonal braces 32 , the bracket main body 31 is arranged horizontally, and its two ends are respectively inserted into the shear walls reserved. Resting in the groove and fixedly connected to the shear wall, one end of the two bracket diagonal braces 32 is fixedly connected to the bracket main body 31, and the other ends of the two bracket diagonal braces 32 are both It is fixedly connected with the embedded parts of the shear wall. Wherein, the two bracket diagonal braces 32 are arranged symmetrically, and are required to provide sufficient supporting force and supporting area.

本实施例中,所述托架主体31采用56号工字钢,所述托架斜撑32采用22号工字钢,所述托架斜撑32与水平面的夹角范围为10°~75°。In this embodiment, the bracket main body 31 is made of 56-gauge I-beam, the bracket diagonal support 32 is made of 22-gauge I-beam, and the angle between the bracket diagonal support 32 and the horizontal plane ranges from 10° to 75° °.

优选的,所述两个托架斜撑32的结构尺寸相同,且所述两个托架斜撑32均位于同一高度。Preferably, the structural dimensions of the two bracket diagonal braces 32 are the same, and the two bracket diagonal braces 32 are located at the same height.

请结合参考图1和图8,所述托架主体31上铺设有砼梁柱木模板支设基础,所述砼梁柱木模板支设基础包括多根钢管41,所述多根钢管41平铺放置于所述托架主体31上,且沿着所述钢梁托架的跨度方向依次排列,相邻的钢管41保持一定的间距。Please refer to FIG. 1 and FIG. 8 , the bracket main body 31 is laid with a concrete beam, column and wood formwork support foundation, and the concrete beam, column and wood formwork support foundation includes a plurality of steel pipes 41 , and the plurality of steel pipes 41 are laid flat on the The bracket main body 31 is arranged in sequence along the span direction of the steel beam bracket, and the adjacent steel pipes 41 keep a certain distance.

本实施例中,所述多根钢管41为平行等距设置,且长度均为750mm。In this embodiment, the plurality of steel pipes 41 are arranged in parallel and equidistant, and the lengths are all 750 mm.

本实施例中,所述多根钢管41短钢管兼做模板主龙骨,所述砼梁柱木模板排架42安装于所述多根钢管41上,所述砼梁柱木模板排架42采用常规的木模板排架体系,由水平杆、立杆、扫地杆、胶合板模板、对拉螺栓等构件组成。In this embodiment, the plurality of steel pipes 41 and the short steel pipes are also used as the main keel of the formwork, the concrete beams, columns and wooden formwork brackets 42 are installed on the plurality of steel pipes 41, and the concrete beams, columns and wooden formwork brackets 42 use conventional wood formwork The bent frame system is composed of horizontal rods, vertical rods, sweeping rods, plywood formwork, and tie bolts.

需要说明的是,上述悬挑主梁11、水平联梁12、平台斜撑13、系杆14、立杆21、横杆22、挡脚板、扫地杆24、封顶杆25、水平杆26、托架主体31、托架斜撑32以及钢管41的规格尺寸、角度和间距设置仅为举例,而非限定,本领域技术人员可结合实际需求对所述悬挑主梁11、水平联梁12、平台斜撑13、系杆14、立杆21、横杆22、托架主体31、托架斜撑32以及钢管41的规格尺寸、角度和间距进行设置,只要符合建筑规范要求即可。It should be noted that the above-mentioned cantilevered main beam 11, horizontal coupling beam 12, platform diagonal brace 13, tie rod 14, vertical rod 21, cross rod 22, foot guard, sweeping rod 24, capping rod 25, horizontal rod 26, bracket The specifications, dimensions, angles and spacings of the frame main body 31, the bracket diagonal braces 32 and the steel pipes 41 are only examples and are not limited. The size, angle and spacing of the platform diagonal braces 13, tie rods 14, vertical rods 21, cross rods 22, bracket main body 31, bracket diagonal braces 32 and steel pipes 41 are set as long as they meet the requirements of building codes.

请继续参考图2,所述高支模体系100还包括第一钢管排架51和第二钢管排架52,所述第一钢管排架51的顶端与所述指定楼板的上层楼板相抵,所述第一钢管排架51的底端与所述悬挑主梁11相抵,用于顶撑所述悬挑主梁11和所述指定楼板的上层楼板,所述第二钢管排架52设置于主体结构的连廊内,用于顶撑所述指定楼板及其下层楼板。所述第一钢管排架51对所述悬挑主梁11的锚固段形成有效下压连接,形成附加顶撑措施,用于抵抗锚固段翘曲作用力。所述第二钢管排架52所述第一钢管排架51共同形成附加顶撑措施,防止结构破坏。Please continue to refer to FIG. 2, the high formwork system 100 further includes a first steel tube bent frame 51 and a second steel tube bent frame 52. The top of the first steel tube bent frame 51 is in contact with the upper floor of the designated floor, so The bottom end of the first steel tube bent frame 51 is in contact with the cantilevered main beam 11, and is used to support the cantilevered main beam 11 and the upper floor of the designated floor slab. In the corridor of the main structure, it is used to support the designated floor and the floor below it. The first steel tube bent frame 51 forms an effective press-down connection to the anchoring section of the cantilevered main beam 11 to form an additional top support measure for resisting the warping force of the anchoring section. The second steel tube bent frame 52 and the first steel tube bent frame 51 together form an additional top support measure to prevent structural damage.

优选的,所述第二钢管排架52设置于主体结构的3层连廊内。例如,所述指定楼板为第26楼的楼板,所述第二钢管排架52设置于第24楼、第25楼和第26楼的楼板之间,用于顶撑所述24楼至26楼的楼板。Preferably, the second steel tube bent frame 52 is arranged in the corridor on the third floor of the main structure. For example, the designated floor slab is the floor slab of the 26th floor, and the second steel tube bent frame 52 is arranged between the floor slabs of the 24th floor, the 25th floor and the 26th floor, and is used to support the 24th to 26th floors. floor.

优选的,所述第一钢管排架51和第二钢管排架52在竖直方向上的投影均落入所述悬挑主梁11的锚固段范围内。Preferably, the projections of the first steel tube bent frame 51 and the second steel tube bent frame 52 in the vertical direction both fall within the range of the anchoring section of the cantilevered main beam 11 .

本实施例中,所述悬挑操作平台架设于建筑物的指定楼板上,所述钢梁托架安装于所述悬挑操作平台的上方,作为悬空大截面砼梁柱木模板排架的受力基础,所述悬挑操作平台不但作为施工操作平台,而且承担悬空砼结构自重及全部施工荷载压力。In this embodiment, the cantilevered operation platform is erected on the designated floor of the building, and the steel beam bracket is installed above the cantilevered operation platform as the force-bearing foundation of the suspended large-section concrete beam, column and wood formwork bent frame , The cantilever operation platform not only serves as a construction operation platform, but also bears the dead weight of the suspended concrete structure and all the construction load pressure.

对于大截面悬空梁施工而言,模板支撑是关键环节。在现有技术中,悬空砼结构都是采用落地脚手架或悬挑平台+模板排架进行施工的,但是针对大体量、重量较大的悬空砼结构,现有的施工办法无法保证安全性,即现有的高支模体系不能满足施工要求。For the construction of large-section suspended beams, formwork support is the key link. In the prior art, the suspended concrete structure is constructed by using floor scaffolding or cantilever platform + formwork bent frame, but for the suspended concrete structure with large volume and heavy weight, the existing construction method cannot guarantee the safety, that is, The existing high-support formwork system cannot meet the construction requirements.

在本实施例提供的高支模体系100中,所述钢梁托架为大截面型钢搁置梁,所述大截面型钢搁置梁结合高空悬挑钢平台,解决了高空大截面钢筋混凝土构件(高支模)无法施工的难题,不但能够取得良好的实用效果,而且具备施工难度低、经济性优良、节材环保、安全系数高等诸多优点,在安全性、经济性和实用性方面都很有优势。此外,所述高支模体系100除了利用所述悬挑操作平台本身所在的指定楼板作为支撑外,还利用了指定楼板下方的楼板和上方的楼板进行支撑,使得支撑效果更好,支撑更加稳定。In the high-support formwork system 100 provided in this embodiment, the steel beam bracket is a large-section shaped steel shelving beam, and the large-section shaped steel shelving beam is combined with a high-altitude cantilevered steel platform to solve the problem of high-altitude large-section reinforced concrete components (high It can not only achieve good practical results, but also has many advantages such as low construction difficulty, excellent economy, material saving and environmental protection, and high safety factor. It has advantages in safety, economy and practicability. . In addition, the high formwork system 100 not only uses the designated floor where the cantilever operation platform itself is located as the support, but also uses the floor below the designated floor and the upper floor for support, so that the support effect is better and the support is more stable .

相应的,本申请还提供一种高支模体系的施工方法。请结合参考图1至图3、图9至图11,所述高支模体系100的施工方法包括:Correspondingly, the present application also provides a construction method for a high formwork system. Please refer to FIG. 1 to FIG. 3 and FIG. 9 to FIG. 11 , the construction method of the high-support formwork system 100 includes:

步骤一、施做楼层主体砼结构,并在所述楼层主体砼结构中设置预埋件;Step 1, constructing the main concrete structure of the floor, and setting embedded parts in the main concrete structure of the floor;

步骤二、在指定楼板上安装悬挑操作平台;Step 2. Install the overhanging operation platform on the designated floor;

步骤三、在所述悬挑操作平台上搭设上一层脚手架,并施做上一层主体结构,所述上一层主体结构预留有钢梁托架的凹槽和第一道悬空梁的凹槽;Step 3: Set up an upper layer of scaffolding on the cantilevered operation platform, and construct the upper layer of the main structure. groove;

步骤四、在所述第一道悬空梁的下方安装钢梁托架;Step 4. Install a steel beam bracket below the first suspended beam;

步骤五、在所述钢梁托架上铺设第一道砼梁柱木模板支设基础;Step 5, laying the first concrete beam, column and wood formwork support foundation on the steel beam bracket;

步骤六、在所述第一道砼梁柱木模板支设基础上支设第一道砼梁柱木模板,并进行砼浇筑。Step 6: Support the first concrete beam and column wood formwork on the foundation of the first concrete beam and column wood formwork support, and carry out concrete pouring.

具体的,首先,如图9所示,在施做楼层主体砼结构时,在楼板的边缘分别设置第一预埋件1a和第二预埋件(图中未示出),所述第一预埋件1a位于所述指定楼板的下层楼板上,用作悬挑主梁下部斜撑的焊接点,所述第二预埋件位于所述指定楼板的上层楼板上,用于连接钢丝绳15。Specifically, first, as shown in FIG. 9 , when constructing the main concrete structure of the floor, a first embedded part 1a and a second embedded part (not shown in the figure) are respectively arranged on the edge of the floor slab. The embedded part 1a is located on the lower floor of the designated floor and is used as a welding point for the lower diagonal bracing of the cantilevered main beam.

接着,在指定楼板上安装悬挑操作平台。安装悬挑操作平台的具体过程包括:Next, install the cantilevered operating platform on the designated floor. The specific process of installing the cantilever operating platform includes:

步骤S21、在地面上对悬挑主梁11、平台斜撑13和系杆14进行加工,并通过焊接方式将所述系杆14的一端与所述平台斜撑13固定连接,所述系杆14的另一端与所述悬挑主梁11的悬挑段固定连接,所述平台斜撑13的一端与所述悬挑主梁11的悬挑段固定连接,每个悬挑主梁11(即单根20a号工字钢)与一个平台斜撑13及一个系杆14焊接固定形成一平台支撑;In step S21, the cantilevered main beam 11, the platform diagonal brace 13 and the tie rod 14 are processed on the ground, and one end of the tie rod 14 is fixedly connected to the platform diagonal brace 13 by welding. The other end of 14 is fixedly connected to the cantilevered section of the cantilevered main beam 11, and one end of the platform diagonal brace 13 is fixedly connected to the cantilevered section of the cantilevered main beam 11. Each cantilevered main beam 11 ( That is, a single No. 20a I-beam) is welded and fixed with a platform diagonal brace 13 and a tie rod 14 to form a platform support;

步骤S22、通过塔吊将各个平台支撑吊装就位于指定楼板;Step S22, supporting and hoisting each platform on the designated floor by the tower crane;

步骤S23、通过至少四道U型螺栓将所述悬挑主梁11固定于所述指定楼板(例如第26楼的楼板)上;Step S23, fixing the cantilevered main beam 11 on the designated floor (for example, the floor on the 26th floor) through at least four U-bolts;

步骤S24、通过焊接方式将所述平台斜撑13的下端与下层楼板(例如第25楼的楼板)中的第一预埋件1a固定连接;Step S24, fixing the lower end of the platform bracing 13 to the first embedded part 1a in the lower floor (eg, the floor of the 25th floor) by welding;

步骤S25、在所述悬挑主梁11上依次铺设水平联梁12以及平台板;Step S25, laying the horizontal coupling beam 12 and the platform plate in sequence on the cantilevered main beam 11;

步骤S26、将钢丝绳15连接在所述悬挑主梁11与上层楼板的第二预埋件之间。Step S26, connecting the steel wire rope 15 between the cantilevered main beam 11 and the second embedded part of the upper floor slab.

在安装悬挑操作平台之前,可在已完工的结构楼层内增设附加顶撑措施,以防止结构破坏。增设附加顶撑措施的具体过程包括:在主体结构的连廊内设置第二钢管排架52,用于顶撑所述指定楼板及其下层楼板。Before installing the overhanging operating platform, additional top support measures can be added to the completed structural floor to prevent structural damage. The specific process of adding additional roof support measures includes: arranging a second steel tube bent frame 52 in the corridor of the main structure to support the designated floor slab and its lower floor slabs.

在安装悬挑操作平台之后,还可在已完工的结构楼层内继续增设附加顶撑措施。增设附加顶撑措施的具体过程包括:在所述悬挑主梁11上固定第一钢管排架51,用于顶撑所述悬挑主梁11和所述指定楼板的上层楼板。After the installation of the cantilevered operating platform, additional roof support measures can be continued in the completed structural floor. The specific process of adding additional roof support measures includes: fixing a first steel tube bent frame 51 on the cantilevered main beam 11 to support the cantilevered main beam 11 and the upper floor slab of the designated floor slab.

如图3所示,所述第一钢管排架51和第二钢管排架52在竖直方向上的投影均要求落入所述悬挑主梁11的锚固段范围内。As shown in FIG. 3 , the projections of the first steel tube bent frame 51 and the second steel tube bent frame 52 in the vertical direction are required to fall within the range of the anchoring section of the cantilevered main beam 11 .

然后,在所述悬挑操作平台上搭设上一层脚手架及临边防护架,所述临边防护架用于挂防护网。在所述悬挑操作平台上搭设上一层脚手架的具体过程包括:Then, a layer of scaffolding and a side guard frame are erected on the cantilevered operation platform, and the side guard frame is used for hanging a guard net. The specific process of setting up the upper layer of scaffolding on the cantilevered operating platform includes:

步骤S31、将多根立杆21固定在所述水平联梁12上,并通过第一扣件将多根横杆22与所述多根立杆21固定连接;Step S31, fixing the plurality of vertical rods 21 on the horizontal coupling beam 12, and fixedly connecting the plurality of transverse rods 22 to the plurality of vertical rods 21 through the first fastener;

步骤S32、采用两步两跨预埋法或贯穿墙体连接法施做附墙拉接;Step S32, using the two-step two-span embedded method or the through-wall connection method to perform the wall-attached pull connection;

步骤S33、将脚手板满铺于所述水平联梁12的顶面上;Step S33, fully spread the scaffold board on the top surface of the horizontal coupling beam 12;

步骤S34、依次安装硬隔离、挡脚板和安全网。Step S34, install the hard isolation, the foot guard and the safety net in sequence.

在所述悬挑操作平台上搭设上一层脚手架的过程中,施做上一层主体结构,并在所述上一层主体结构的剪力墙中依据设计预留钢梁托架的凹槽以及第一道悬空梁的凹槽。In the process of erecting the upper layer of scaffolding on the cantilevered operation platform, the upper layer of the main structure is constructed, and grooves for steel beam brackets are reserved in the shear wall of the upper layer of the main structure according to the design. And the groove of the first suspended beam.

请结合参考图1和图10,所述钢梁托架的凹槽包括搁置凹槽102,所述搁置凹槽102位于所述第一道悬空梁的凹槽101的下面,用于搁置所述钢梁托架的托架主体31。1 and 10, the groove of the steel beam bracket includes a resting groove 102, and the resting groove 102 is located below the groove 101 of the first suspended beam for resting the The bracket body 31 of the steel beam bracket.

所述搁置凹槽的模板拆除之后,开始安装钢梁托架。安装钢梁托架的具体过程包括:After the formwork of the resting groove is removed, the steel beam bracket is installed. The specific process of installing the steel beam bracket includes:

步骤S41、在地面上对托架主体31和两个托架斜撑32进行加工,并将两个托架斜撑32的其中一端均固定在所述托架主体31上,以形成钢梁托架;Step S41: Process the bracket main body 31 and the two bracket diagonal braces 32 on the ground, and fix one end of the two bracket diagonal braces 32 on the bracket main body 31 to form a steel beam bracket shelf;

步骤S42、通过塔吊将所述钢梁托架吊装就位;Step S42, hoisting the steel beam bracket in place by a tower crane;

步骤S43、将所述托架主体31的两端分别插入上一层主体结构(剪力墙)预留的搁置凹槽中;Step S43, inserting the two ends of the bracket main body 31 into the reserved recesses of the main body structure (shear wall) on the upper layer respectively;

步骤S44、找平,并使用高细石混凝土分别浇筑密实所述搁置凹槽。Step S44, leveling, and using high-fine stone concrete to pour and compact the resting grooves respectively.

在使用高细石混凝土浇筑密实所述搁置凹槽之前,剪力墙内的水平筋应恢复接长,所述托架斜撑32与剪力墙的预埋件固定连接。如图4所示,所述托架斜撑32的下端通过焊接方式与所述主体结构(剪力墙)的第三预埋件1d固定连接。Before using the high-fine stone concrete to densify the resting groove, the horizontal bars in the shear wall should be resumed to lengthen, and the bracket diagonal braces 32 are fixedly connected to the embedded parts of the shear wall. As shown in FIG. 4 , the lower end of the bracket diagonal brace 32 is fixedly connected to the third embedded part 1d of the main structure (shear wall) by welding.

如图11所示,所述钢梁托架的托架主体31搁置于所述搁置凹槽102中,采用所述高细石混凝土分别浇筑密实所述搁置凹槽102后,所述钢梁托架固定安装于所述第一道悬空梁的凹槽101的下面,并与所述剪力墙连为一体。As shown in FIG. 11 , the bracket main body 31 of the steel beam bracket is placed in the resting groove 102 , and the high-fine stone concrete is used to pour and compact the resting groove 102 respectively. The frame is fixedly installed under the groove 101 of the first suspended beam, and is integrated with the shear wall.

本实施例中,所述搁置凹槽的宽度为200mm、深度为700mm,所述第一道悬空梁的凹槽的宽度为600mm、深度为400mm。In this embodiment, the width of the resting groove is 200 mm and the depth is 700 mm, and the width of the groove of the first suspended beam is 600 mm and the depth is 400 mm.

在所述钢梁托架安装完成之后,开始施做大截面悬空梁结构。施做大截面悬空梁结构的具体过程包括:首先,在所述钢梁托架上铺设多根短钢管,所述多根短钢管沿着所述钢梁托架的跨度方向平铺放置,作为第一道砼梁柱木模板支设基础;接着,在所述第一道砼梁柱木模板支设基础上支设第一道砼梁柱木模板,所述第一道砼梁柱木模板(包括底模及侧模)采用钢筋绑扎;然后,进行砼浇筑,在砼浇筑过程中预留吊柱插筋,之后,进行混凝土养护直至第一道悬空梁及吊柱的砼强度达到设计要求。After the installation of the steel beam bracket is completed, the construction of the large-section suspended beam structure begins. The specific process of constructing the large-section suspended beam structure includes: first, laying a plurality of short steel pipes on the steel beam bracket, and the plurality of short steel pipes are laid flat along the span direction of the steel beam bracket, as The first concrete beam and column wood formwork support foundation; then, on the first concrete beam and column wood formwork support foundation, the first concrete beam and column wood formwork is supported, and the first concrete beam and column wood formwork (including bottom form and side formwork) Reinforcement is used for binding; then, the concrete is poured, and the suspenders are reserved during the concrete pouring process, and then the concrete is cured until the concrete strength of the first suspended beam and the suspenders meet the design requirements.

在进行混凝土养护过程中,可在悬挑操作平台上继续搭设脚手架,施做上一层结构砼及第二道悬空梁及吊柱。在第二道悬空梁及吊柱施做完成之后,可在悬挑操作平台上继续搭设脚手架,施做第三道悬空梁及吊柱,并施做剩余结构剪力墙及楼板至设计结构顶标高。In the process of concrete maintenance, scaffolding can be continued on the cantilevered operating platform, and the upper layer of structural concrete and the second suspended beam and hanging column can be installed. After the construction of the second suspended beam and hanging column is completed, scaffolding can be continued on the cantilevered operation platform, the third suspended beam and hanging column can be installed, and the remaining structural shear walls and floor slabs can be installed to the top of the design structure. elevation.

请继续参考图1,在搭设脚手架时,架体加设钢管硬拉结28等安全防护结构。Please continue to refer to Figure 1. When erecting the scaffold, the frame body is provided with safety protection structures such as steel tube hard-tie knots 28.

本实施例中,共施做三道悬空梁,即第一悬空梁10、第二道悬空梁20以及第三道悬空梁30,所述第一道悬空梁和所述第二道悬空梁的尺寸均为600mm×400mm,所述第三道悬空梁的尺寸为600mm×1000mm。In this embodiment, a total of three suspended beams are implemented, namely the first suspended beam 10, the second suspended beam 20 and the third suspended beam 30. The first suspended beam and the second suspended beam are The dimensions are all 600mm×400mm, and the dimensions of the third suspended beam are 600mm×1000mm.

在其他实施例中,也可根据设计要求仅施做一道悬空梁、两道悬空梁或者四道以上的悬空梁。In other embodiments, only one suspended beam, two suspended beams, or more than four suspended beams may be implemented according to design requirements.

所有的悬空梁及吊柱施做完成之后,依次拆除砼梁柱木模板排架42、钢梁托架、脚手架、水平联梁12与脚手板、悬挑主梁11。After all the suspended beams and hanging columns are completed, remove the concrete beams, columns and wooden formwork brackets 42, steel beam brackets, scaffolding, horizontal coupling beams 12 and scaffolding boards, and cantilevered main beams 11 in sequence.

综上,在本发明提供的高支模体系及其施工方法中,采用大截面型钢搁置梁搭配高空悬挑钢平台的方式,解决了高空大截面钢筋混凝土构件无法施工的难题,不但能够取得良好的实用效果,而且具备施工难度低、经济性优良、节材环保、安全系数高等诸多优点。To sum up, in the high-support formwork system and its construction method provided by the present invention, the large-section section steel shelving beam is used with the high-altitude cantilevered steel platform, which solves the problem that the high-altitude large-section reinforced concrete member cannot be constructed, and not only can achieve good results. It has many advantages such as low construction difficulty, excellent economy, material saving and environmental protection, and high safety factor.

以上内容是结合具体的优选实施方式对本申请所作的进一步详细说明,不能认定本申请的具体实施只局限于这些说明。对于本申请所属技术领域的普通技术人员来说,在不脱离本申请构思的前提下,还可以做出若干简单推演或替换,都应当视为属于本申请的保护范围。The above content is a further detailed description of the present application in conjunction with specific preferred embodiments, and it cannot be considered that the specific implementation of the present application is limited to these descriptions. For those of ordinary skill in the technical field of the present application, without departing from the concept of the present application, some simple deductions or substitutions can be made, which should be regarded as belonging to the protection scope of the present application.

Claims (19)

1. A high formwork system, comprising: the cantilever operation platform, the scaffold, the steel beam bracket and the concrete beam column wood formwork bent frame;
the cantilever operation platform comprises a cantilever girder, a horizontal coupling beam and a platform plate, wherein the horizontal coupling beam is perpendicular to the cantilever girder, the cantilever girder comprises an anchoring section and a cantilever section, the anchoring section of the cantilever girder is fixed on a specified floor slab, the cantilever section of the cantilever girder extends out of the specified floor slab, and the horizontal coupling beam and the platform plate are both fixed on the cantilever section of the cantilever girder;
the scaffold is erected on the overhanging operation platform and is fixedly connected with the horizontal coupling beam;
the steel beam bracket is arranged above the cantilever operation platform and used for supporting a suspended beam structure;
the steel beam bracket comprises a bracket main body and a bracket inclined strut, two ends of the bracket main body are respectively inserted into a reserved laying groove of the shear wall and are fixedly connected with the shear wall, one end of the bracket inclined strut is fixedly connected with the bracket main body, and the other end of the bracket inclined strut is fixedly connected with an embedded part of the shear wall;
concrete beam column wood formwork erection foundation is paved on the bracket main body, and the concrete beam column wood formwork bent is installed on the concrete beam column wood formwork erection foundation.
2. The high formwork system defined in claim 1, wherein the overhanging operation platform further comprises platform diagonal braces, tie bars and wire ropes;
one end of the platform diagonal brace is fixedly connected with the lower surface of the overhanging main beam, and the other end of the platform diagonal brace is fixedly connected with an embedded part of a lower floor slab;
one end of the tie bar is fixedly connected with the platform inclined strut, and the other end of the tie bar is fixedly connected with the overhanging main beam;
the cantilever operation platform further comprises a steel wire rope, one end of the steel wire rope is connected with the main beam, and the other end of the steel wire rope is fixedly connected with the embedded part of the upper floor.
3. The high formwork system of claim 1, wherein the concrete beam column wood formwork support foundation comprises a plurality of steel pipes, and the plurality of steel pipes are arranged at intervals along the span direction of the steel beam bracket.
4. The high formwork system defined in claim 1, wherein the scaffolding comprises: a plurality of upright posts, a plurality of cross rods, wall-attached pulling joints and scaffold boards;
the vertical rods are vertically arranged, and the bottom ends of the vertical rods are fixedly connected with the horizontal coupling beam;
the plurality of cross rods are horizontally arranged and are fixedly connected with the plurality of upright rods through first fasteners;
one end of the wall-attached drawing joint is fixedly connected with the upright stanchion, and the other end of the wall-attached drawing joint is fixedly connected with the main structure of the building;
the scaffold boards are laid on the horizontal coupling beams.
5. The high formwork system defined in claim 4, wherein the vertical rods are located at the intersection of the main cantilever beam and the horizontal coupling beam.
6. A high formwork system according to claim 4, wherein the scaffolding further comprises a hard insulation and safety net;
the hard isolation is arranged on the wall-attached pulling joint, and the safety net is arranged on the inner sides of the upright posts and fixedly connected with the upright posts.
7. The high formwork system defined in claim 1, further comprising: the steel pipe bent frame comprises a first steel pipe bent frame and a second steel pipe bent frame;
the first steel pipe bent is arranged above the cantilever girder and used for propping up the cantilever girder and an upper floor slab of the specified floor slab;
the second steel pipe bent is arranged in the corridor of the main body structure and used for supporting the appointed floor slab and the lower floor slab thereof.
8. The high formwork system of claim 7, wherein the projections of the first steel pipe bent and the second steel pipe bent in the vertical direction both fall within the range of the anchoring section of the cantilever girder.
9. The high formwork system of claim 1, wherein the overhanging main beam is fixedly connected with the designated floor slab through at least four U-shaped bolts.
10. The high formwork system of claim 1, wherein the overhanging main beam is made of 20I-steel, the horizontal coupling beam is made of 16I-steel, the bracket main body is made of 56I-steel, and the bracket diagonal brace is made of 22I-steel.
11. The high formwork system defined in claim 2, wherein the platform diagonal brace is made of 20-gauge I-steel and the tie bar is made of 16-gauge channel steel.
12. A construction method of a high formwork system is characterized by comprising the following steps:
step one, constructing a main floor concrete structure, and arranging an embedded part in the main floor concrete structure;
step two, installing an overhanging operation platform on the appointed floor;
thirdly, building a layer of scaffold on the overhanging operation platform, constructing a layer of main structure, and reserving a groove of the steel beam bracket and a groove of the first suspended beam in the layer of main structure;
fourthly, mounting a steel beam bracket below the first suspended beam;
and fifthly, constructing a large-section suspended beam on the steel beam bracket.
13. The method for constructing a high formwork system, as claimed in claim 12, wherein the process of installing the cantilever operation platform on the designated floor slab comprises:
processing the cantilever main beam, the platform diagonal brace and the tie bars on the ground, and forming a plurality of platform supports by the cantilever main beam, the platform diagonal brace and the tie bars;
hoisting the plurality of platform supports in place through a tower crane;
fixing the cantilever girder on the appointed floor slab through at least four U-shaped bolts;
fixedly connecting the lower end of the platform inclined strut with an embedded part of a lower floor slab;
laying a horizontal coupling beam and a platform plate on the overhanging main beam in sequence;
and connecting the steel wire rope between the overhanging main beam and the embedded part of the upper floor.
14. The method for constructing a high formwork system, as claimed in claim 12, further comprising, before installing the cantilever operation platform on a designated floor, after constructing a floor main concrete structure: and a second steel pipe bent is arranged in the corridor of the main body structure.
15. The method for constructing a high formwork system, according to claim 12, wherein before the step of building a previous scaffold on the overhanging work platform, after the step of installing the overhanging work platform on a specified floor, the method further comprises: and a first steel pipe bent is arranged on the cantilever girder.
16. The method for constructing a high formwork system according to claim 12, wherein the process of building a scaffold on the overhanging work platform comprises:
fixing a plurality of upright posts on the horizontal coupling beam, and fixedly connecting a plurality of cross rods with the upright posts through first fasteners;
adopting a two-step two-span pre-embedding method or a through wall body connecting method to carry out wall attachment pulling connection;
fully paving scaffold boards on the top surfaces of the horizontal coupling beams; and
and a hard isolation plate, a foot baffle plate and a safety net are sequentially installed.
17. A method of constructing a high formwork system as claimed in claim 12, wherein the process of installing a steel beam bracket under the first suspended beam comprises:
processing the bracket main body and the bracket inclined strut on the ground to form a steel beam bracket;
hoisting the steel beam bracket in place through a tower crane;
inserting two ends of the bracket main body into the reserved laying grooves of the upper layer of main body structure respectively, and fixedly connecting the lower end of the bracket diagonal brace with the embedded part of the shear wall in a welding mode; and
leveling, and respectively pouring and compacting the placing grooves by using high and fine stone concrete.
18. The method of constructing a high formwork system as claimed in claim 12, wherein the process of constructing a large-section suspended girder on the girder bracket comprises:
laying a plurality of steel pipes on the steel beam bracket to serve as a first concrete beam column wood formwork supporting foundation;
erecting a first concrete beam column wood formwork on the first concrete beam column wood formwork erecting basis;
pouring concrete; and
and (5) performing concrete curing until the concrete strength of the first suspended beam meets the design requirement.
19. The method for constructing a high formwork system according to claim 18, wherein the concrete curing process further comprises: and continuously erecting a scaffold on the overhanging operation platform, and constructing a previous layer of structural concrete and a second suspended beam.
CN202010624701.8A 2020-07-01 2020-07-01 High formwork system and construction method thereof Active CN111779248B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010624701.8A CN111779248B (en) 2020-07-01 2020-07-01 High formwork system and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010624701.8A CN111779248B (en) 2020-07-01 2020-07-01 High formwork system and construction method thereof

Publications (2)

Publication Number Publication Date
CN111779248A true CN111779248A (en) 2020-10-16
CN111779248B CN111779248B (en) 2024-11-29

Family

ID=72757728

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010624701.8A Active CN111779248B (en) 2020-07-01 2020-07-01 High formwork system and construction method thereof

Country Status (1)

Country Link
CN (1) CN111779248B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113047617A (en) * 2021-03-26 2021-06-29 宁波建工建乐工程有限公司 Formwork supporting platform for high-altitude corridor construction and construction method thereof
CN113323361A (en) * 2021-06-08 2021-08-31 中国建筑第八工程局有限公司 Construction method of high-altitude supporting operation frame based on bottom steel platform
CN113565307A (en) * 2021-07-02 2021-10-29 华北冶建工程建设有限公司 High-altitude suspension modeling construction device and method thereof
CN114033171A (en) * 2021-12-07 2022-02-11 中国建筑第八工程局有限公司 Clamp type triangular support system of overhanging roof panel and construction method thereof
CN114427290A (en) * 2022-01-24 2022-05-03 中铁三局集团建筑安装工程有限公司 Super high-rise reinforced concrete core tube aluminum mold climbing frame and construction method
CN115075530A (en) * 2022-07-01 2022-09-20 中亿丰建设集团股份有限公司 Cantilever structure and construction method thereof
CN117365153A (en) * 2023-12-01 2024-01-09 中建八局第二建设有限公司 A method for reinforcing super high-rise cavity concrete

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102444203A (en) * 2011-09-15 2012-05-09 浙江城建建设集团有限公司 High-altitude large-span cantilever corridor type steel concrete structure and construction method
CN102535845A (en) * 2012-02-14 2012-07-04 浙江省建工集团有限责任公司 Construction method of bearing frame of corridor structure
WO2013185277A1 (en) * 2012-06-11 2013-12-19 浙江省建工集团有限责任公司 Constructing method for concrete cylinder of construction steel bar of high-rise steel structure
CN106150088A (en) * 2016-08-11 2016-11-23 上海嘉实(集团)有限公司 Large cantilever beam slab combined type formwork system and construction method
CN108265965A (en) * 2017-12-29 2018-07-10 上海建工七建集团有限公司 A kind of outrigger platform device in Construction of Steel Structure
CN212507296U (en) * 2020-07-01 2021-02-09 上海建工七建集团有限公司 High formwork system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102444203A (en) * 2011-09-15 2012-05-09 浙江城建建设集团有限公司 High-altitude large-span cantilever corridor type steel concrete structure and construction method
CN102535845A (en) * 2012-02-14 2012-07-04 浙江省建工集团有限责任公司 Construction method of bearing frame of corridor structure
WO2013185277A1 (en) * 2012-06-11 2013-12-19 浙江省建工集团有限责任公司 Constructing method for concrete cylinder of construction steel bar of high-rise steel structure
CN106150088A (en) * 2016-08-11 2016-11-23 上海嘉实(集团)有限公司 Large cantilever beam slab combined type formwork system and construction method
CN108265965A (en) * 2017-12-29 2018-07-10 上海建工七建集团有限公司 A kind of outrigger platform device in Construction of Steel Structure
CN212507296U (en) * 2020-07-01 2021-02-09 上海建工七建集团有限公司 High formwork system

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113047617A (en) * 2021-03-26 2021-06-29 宁波建工建乐工程有限公司 Formwork supporting platform for high-altitude corridor construction and construction method thereof
CN113323361A (en) * 2021-06-08 2021-08-31 中国建筑第八工程局有限公司 Construction method of high-altitude supporting operation frame based on bottom steel platform
CN113323361B (en) * 2021-06-08 2023-02-28 中国建筑第八工程局有限公司 Construction method of high-altitude supporting operation frame based on bottom steel platform
CN113565307A (en) * 2021-07-02 2021-10-29 华北冶建工程建设有限公司 High-altitude suspension modeling construction device and method thereof
CN114033171A (en) * 2021-12-07 2022-02-11 中国建筑第八工程局有限公司 Clamp type triangular support system of overhanging roof panel and construction method thereof
CN114427290A (en) * 2022-01-24 2022-05-03 中铁三局集团建筑安装工程有限公司 Super high-rise reinforced concrete core tube aluminum mold climbing frame and construction method
CN115075530A (en) * 2022-07-01 2022-09-20 中亿丰建设集团股份有限公司 Cantilever structure and construction method thereof
CN115075530B (en) * 2022-07-01 2024-03-22 中亿丰建设集团股份有限公司 Cantilever structure and construction method thereof
CN117365153A (en) * 2023-12-01 2024-01-09 中建八局第二建设有限公司 A method for reinforcing super high-rise cavity concrete

Also Published As

Publication number Publication date
CN111779248B (en) 2024-11-29

Similar Documents

Publication Publication Date Title
CN111779248B (en) High formwork system and construction method thereof
CN108643544B (en) High-altitude overhanging construction platform support system and construction method
CN103452311B (en) A kind of erection method of shaped steel suspended structural support frame
CN202227476U (en) High-altitude large-span overhung corridor-type reinforced concrete structure
CN212507296U (en) High formwork system
CN102392536B (en) Construction method for long-span hanging vestibule type template support system
CN101886466A (en) Construction method of tamping type coke oven coal tower formwork support structure
CN104480922B (en) Space truss formwork system and construction method thereof
CN107090975A (en) Formwork erecting construction method for ultrahigh large-span concrete cast-in-place beam bailey truss
CN116537534A (en) Construction method of high and large formwork engineering supporting system
CN111424948A (en) Construction method and construction platform for cantilever structure layer of high-rise building
CN114658214A (en) High-rise building disc buckle type high-altitude large-cantilever support frame support and anchor pressing integrated construction method
CN115627912A (en) Construction method of assembled externally-mounted flower basket type overhanging scaffold
CN110409624A (en) A large-scale equipment installation and main structure reverse calculation and construction method
CN103334580B (en) Section steel tripod in a kind of overhanging scaffold and connection system for guide rail
CN104831928A (en) Construction method for high-altitude large-span concrete connected structure formwork supporting steel platform
CN208183778U (en) Temporary building foundation structure for complicated landform
CN116254995A (en) A large-span cantilevered concrete beam-slab support structure and its construction method
CN116657875B (en) Cantilever steel structure construction platform with formwork system and construction method
CN219931554U (en) A cantilevered steel structure construction platform with formwork system
CN108019040B (en) A construction method for the Bailey frame platform of the transfer floor of a high-rise building
CN116696055A (en) Construction decoration method for cantilever structure of flat roof framework layer
CN115821940A (en) Construction method of super deep foundation pit permanent combined support frame beam-ring frame slab
CN115788111A (en) Deep foundation pit ladder cage subsection reverse installation method
CN222893950U (en) High-altitude large-span overhanging base

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant