CN106593034A - Rapidly-completed ground shade parking lot and construction method thereof - Google Patents

Rapidly-completed ground shade parking lot and construction method thereof Download PDF

Info

Publication number
CN106593034A
CN106593034A CN201610955078.8A CN201610955078A CN106593034A CN 106593034 A CN106593034 A CN 106593034A CN 201610955078 A CN201610955078 A CN 201610955078A CN 106593034 A CN106593034 A CN 106593034A
Authority
CN
China
Prior art keywords
water
parking
parking lot
water supply
supply line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610955078.8A
Other languages
Chinese (zh)
Other versions
CN106593034B (en
Inventor
谷成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610955078.8A priority Critical patent/CN106593034B/en
Publication of CN106593034A publication Critical patent/CN106593034A/en
Application granted granted Critical
Publication of CN106593034B publication Critical patent/CN106593034B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H6/00Buildings for parking cars, rolling-stock, aircraft, vessels or like vehicles, e.g. garages
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G17/00Cultivation of hops, vines, fruit trees, or like trees
    • A01G17/005Cultivation methods
    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01GHORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
    • A01G25/00Watering gardens, fields, sports grounds or the like
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Environmental Sciences (AREA)
  • Water Supply & Treatment (AREA)
  • Botany (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

Disclosed are a rapidly-completed ground shade parking lot and a construction method thereof. A parking area of the rapidly-completed ground shade parking lot is a slope, and the side near a lane is higher than the side far away from the lane. Planting zones are arranged on the lower side of the parking area and around the parking lot, and arbors are planted in the planting zones at intervals. Water storage zones are arranged near the planting zones and under the ground, and water supply pipelines are buried in the water storage zones. The water supply pipelines include main pipelines and branch pipelines extending from the main pipelines, the main pipelines are arranged along the planting zones, and the water outlet ends of the branch pipelines are buried around the arbors. According to the parking lot, the gentle slope is designed in the direction from parking spaces of the parking lot to the trees, rainwater is concentrated in the place with the trees to be collected, and injected into the underground pipelines through a sedimentation well and the like, and the underground water supply pipelines are arranged on absorbent aggregates with good water absorption and storage effects, so that sufficient nutrients and water are supplied to the trees. The rapidly-completed ground shade parking lot and the construction method thereof not only provide a good parking environment for urban car owners, but also increase the green land area, and by adjusting regional microclimate, the macro-ecology is adjusted, and the heat island phenomenon is relieved in a point-to-area mode.

Description

A kind of rapid-result ground green shade parking lot and its construction method
Technical field
The invention belongs to green shade parking lot technical field of construction, and in particular to a kind of rapid-result ground green shade parking lot and its apply Work method.
Background technology
The present invention is that inventor is alleviated urban heat island and write in many measures and applies at one of Surface parking lots.In recent years due to Ecology is destroyed, and city hot island phenomenon is serious all the more, summer temperature more and more higher, and city is higher than suburb mean temperature 1 degree, portion Up to 6 degree of region-by-region, up to nearly 70 degree of some regional surface temperatures, ground fried egg, self-burning of vehicle, stranded occupant cause Middle administration's phenomenon happens occasionally.
In summer, exposed vehicle interior temperature in the sun can be very high, even as high as nearly 70 degree of some areas, in general;Vapour Car is exposed to the sun more than one hour, and the pollutant such as in-car formaldehyde are doubled and redoubled, and automotive temp is too high mainly following harm:
1st, interior trim noxious substance is released, and, under normal temperature state, in closing 2 hours, in-car formaldehyde is universal exceeded 2 times for car It is unhealthful above, still more it is summer high temperature;
2nd, the aging acceleration of vehicle component, tire, affects vehicle service life;
3rd, circuit high temperature easily melts, and easily causes vehicle spontaneous combustion after short circuit;
4th, car paint gloss it is thin out, fade, affect it is attractive in appearance;
5th, passenger is detained in-car, and the lower high temperature that is exposed to the sun easily produces dizzy fault, and severe patient can cause chronic poisoning;
6th, after vehicle summer is exposed to the sun, in car as food steamer, seat is entered the straight hurricane of antiperspirant, unhealthful.
It is large area hardened ground that Surface parking lots are most of at present, and only a small amount of greenbelt can not be played effectively to parking stall Shade effect, the automobile of Surface parking lots is exposed in the sun.
Moreover, safeguarding for existing greening of parking yard band generally require special garden maintenance workman as irrigated, and wastes Substantial amounts of manpower and water source, virtually increasing the resources such as construction and the maintenance cost in parking lot, rainwater snow water cannot be good Good utilization, and it is unfavorable for the growth of trees in greenbelt.
The content of the invention
It is an object of the invention to provide a kind of rapid-result ground green shade parking lot and its construction method, are forest in parking lot Fast-growth condition is provided, the maintenance for solving existing greening of parking yard band is irrigated and needs special garden maintenance workman, is wasted Substantial amounts of manpower and water source, virtually increasing the resources such as construction and the maintenance cost in parking lot, rainwater snow water cannot be good Good utilization, and it is unfavorable for the problem of the growth of trees in greenbelt.
To realize above-mentioned technical purpose, the present invention is adopted the following technical scheme that:
A kind of rapid-result ground green shade parking lot, including track and parking area, the parking area is divided into some parking stalls, described to stop Parking stall is provided with car stop, it is characterised in that:The parking area is slope, and the side near track is higher than the side away from track; The relatively low side in the parking area and parking lot surrounding are designed with growth belt, and on the growth belt, interval kind is implanted with arbor;It is described Water storage band is provided with below ground beside growth belt, in the water storage band, water supply line is embedded with;The water supply line includes master Pipeline and the lateral stretched out from main pipeline;The main pipeline is arranged along growth belt, upper end connection upper hose;The branched pipe The water side in road is embedded in around arbor.
Used as optimal technical scheme, the parking lot is rectangle, including parallel spaced track and is distributed in track The parking area of both sides, accordingly, the water supply line includes that periphery is stopped along two around the rectangle water supply line in parking lot and centre The yi word pattern water supply line of the growth belt arrangement between car area, the rectangle water supply line are mutually connected with yi word pattern water supply line It is logical.
It is further preferred that sedimentation and water filling port are arranged at intervals with the main pipeline, the sedimentation and water filling port Connected by lateral with main pipeline.Sedimentation has collection rainwater, water storage, and desilting effect is built by laying bricks or stones using building to mix, in parking lot Interior precipitation well lid adopts load-bearing catch basin cover, water filling port to build by laying bricks or stones using brick material, and major function pours into water injection pipe to prevent soil Mouthful.
It is further preferred that the range of grade of the parking area is 0.5%~1%;Preferred slope is 1%.
It is further preferred that 250~350mm below the earth's surface of the water supply line embedment water storage band.
It is further preferred that the top of the water storage band is soil horizon, bottom is water suction aggregate layer.
It is further preferred that the width of the water suction aggregate layer is 250~350mm, thickness is 450~550mm;The confession Waterpipe is horizontally embedded in water suction aggregate layer.
It is further preferred that one layer of braiding material sealing coat is arranged between the water suction aggregate layer and soil horizon.
It is further preferred that the water suction aggregate layer is broken foamed concrete block, broken air-mixed concrete pieces, floats Stone, Vermiculitum or haydite.
Additionally, the present invention also provides the construction method in above-mentioned rapid-result ground green shade parking lot, it is characterised in that including as follows Step:
Step one, parking lot addressing and integral layout are arranged:Parking lot addressing is carried out as needed, and which is laid out sets Put, determine the set location of track, parking area, growth belt and water storage band;
Step 2, setting water storage band simultaneously lay water supply line:Arranging along 1000~1500mm beside the growth belt of parking lot periphery Water storage band, returns including digging tunnel, laying water suction aggregate layer, laying water supply line, laying braiding material sealing coat and carrying out soil Fill out;Sedimentation and water filling port are set during laying water supply line simultaneously;
The construction of step 3, track and parking area:Parking area arranges slope, and the side near track is higher than away from track Side;
The arrangement of step 4, growth belt:After the completion of track and parking area construction, the arrangement of growth belt is carried out, on growth belt Plantation arbor, has 2-4 lateral outlet around every arbor;
Step 5, parking Division parking stall:Parking area is carried out into parking stall division, each parking stall is correspondingly arranged car stop, and simultaneous The effect of sheltering from heat or light of Gu Qiaomu;So far, rapid-result ground green shade parking lot construction is completed.
Compared with prior art, it is of the invention it is a technical advantage that:
1st, the present invention plants trees between Surface parking lots' periphery and parking stall, forms green shade parking lot, and ground divides into water supply line shape Method into underground bank accelerates arboreal growth, and selected seeds are that tree crown is big, and blade is big, the straight forest of trunk, after growing up to Tree crown is connected in the air, plays sunshade effect, with guarantee parking stall below under green shade shielding;
2nd, parking position designs gentle slope to trees direction, rainwater is concentrated to where there is tree and is collected, and by sedimentation etc. Injection underground bank pipeline, can increase and swim on the ground, and subsoil water provides sufficient nutrient, moisture to forest, makes plant growing prosperous Contain, big tree with deep roots is flourishing, accelerate arboreal growth, the tree crown for accelerating adjacent trees is connected in the air.Dry season, water source can Quoted from region tank or municipal water supply to groundwater supply bank, solve ground and water easy Evaporation Phenomenon, water saving, water storage effect It is good;
3rd, water supply line is located on water suction aggregate, above sets coating, is prevented soil from inserting water suction aggregate and is lost water suction water reservation, Water filling port is being set at setting 1.5 meters, is at least ensureing the water source supply in 3 directions of per tree, water suction aggregate water suction water storage effect is good, Lasting moisture can be provided to trees, accelerate arboreal growth;Sedimentation has collection rainwater, water storage, and desilting effect is built using building to mix Build, the precipitation well lid in parking lot adopts load-bearing catch basin cover, water filling port to build by laying bricks or stones using brick material, and major function is prevention soil Pour into the water filling mouth of pipe.
To sum up, by rapid-result green shade parking lot, provide excellent parking environment can not only to city car owner, raising drives, Comfort level, provides healthy clean environment for car owner, and increases greenery area, by adjustment region miniclimate, with point by bus Zone face, adjusts big ecological, alleviates heat island phenomenon.
Description of the drawings
By the detailed description made in conjunction with the following drawings, the present invention above-mentioned and/or other in terms of and advantage will become Become apparent from and be easier to understand, these accompanying drawings are simply schematic, are not intended to limit the present invention, wherein:
Fig. 1 is the facade structures schematic diagram in rapid-result ground green shade parking lot according to the present invention;
Fig. 2 is the integral planar structural representation in rapid-result ground green shade parking lot according to the present invention;
Fig. 3 is sedimentation setting structure schematic diagram;
Fig. 4 is water filling port setting structure schematic diagram;
Fig. 5 is water storage band setting structure schematic diagram.
Reference:1- tracks, 2- parking areas, 3- water supply lines, 31- main pipelines, 32- laterals, 33- upper hoses, 4- car stops, 5- arbors, 6- sedimentations, 7- water storage bands, 8- water filling ports, 9- ground, 10- soil horizons, 11- braiding material sealing coats, 12- Water suction aggregate layer.
Specific embodiment
Hereinafter, the embodiment in the rapid-result ground green shade parking lot of the present invention is described with reference to the accompanying drawings.What here was recorded Embodiment be the present invention specific specific embodiment, for illustrate the present invention design, be it is explanatory and exemplary, Should not be construed as the restriction to embodiment of the present invention and the scope of the invention.Except the enforcement exception that here is recorded, art technology Personnel can also be based on the application claims and description disclosure of that using obvious other technical schemes, These technical schemes include the technical side for making any obvious substitutions and modifications using the embodiment recorded to here Case.
The accompanying drawing of this specification is schematic diagram, aids in illustrating the design of the present invention, it is schematically indicated the shape of each several part And its mutual relation.Note that for the ease of clearly showing the structure of each part of the embodiment of the present invention, between each accompanying drawing Do not draw according to identical ratio.Identical reference marker is used to represent identical part.
The principle and feature of the present invention are described below in conjunction with accompanying drawing, example is served only for explaining the present invention, and It is non-for limiting the scope of the present invention.
Such as Fig. 1 and Fig. 2, the present invention devises a kind of rapid-result ground green shade parking lot, including track 1 and parking area 2, described Parking area 2 is divided into some parking stalls, and the parking stall is provided with car stop 4, it is characterised in that:The parking area 2 is slope, is leaned on The side in nearly track 1 is higher than the side away from track 1;The range of grade of the parking area 2 is 0.5%~1%;Preferred slope is 1%.The relatively low side in the parking area 2 and both side ends are designed with growth belt, and on the growth belt, interval kind is implanted with arbor 5;Institute State beside growth belt on ground 9 to have water storage band 7, in the water storage band 7, be embedded with water supply line 3;The water supply line 3 The lateral 32 stretched out including main pipeline 31 and from main pipeline;The main pipeline 31 is arranged along growth belt, the upper water of upper end connection Pipe 33;The water side of the lateral 32 is embedded in around arbor 5.
The present invention plants trees between Surface parking lots' periphery and parking stall, forms green shade parking lot, and ground divides into water supply line The method for forming underground bank accelerates arboreal growth, and selected seeds are that tree crown is big, and blade is big, the straight forest of trunk, after growing up to Tree crown be connected in the air, play sunshade effect, to ensure parking stall below under green shade shielding.
Parking position designs gentle slope to trees direction, rainwater is concentrated to where there is tree and is collected, and pass through sedimentation In injection underground bank pipeline, can increase and swim on the ground, subsoil water provides sufficient nutrient, moisture to forest, makes plant growing Vigorous, big tree with deep roots is flourishing, accelerates arboreal growth, and the tree crown for accelerating adjacent trees is connected in the air.Dry season, water source Ground can be solved and is watered easy Evaporation Phenomenon quoted from region tank or municipal water supply to groundwater supply bank, water saving, water storage effect It is really good.
Wherein, such as Fig. 2, the parking lot that the present embodiment is related to is rectangle, including parallel spaced track 1 and point Parking area 2 of the cloth in track both sides, accordingly, the water supply line 3 include periphery around parking lot rectangle water supply line and The yi word pattern water supply line of the middle growth belt arrangement between two parking areas 2, the rectangle water supply line and yi word pattern supply water Pipeline is interconnected.
Additionally, sedimentation 6 and water filling port 8 are arranged at intervals with the main pipeline 31, the sedimentation 6 and water filling port 8 with Main pipeline 31 is connected by lateral.250~350mm below embedment earth's surface of the water storage with 7 of the water supply line 3.The storage Water is soil horizon 10 with 7 top, and bottom is water suction aggregate layer 12;One is arranged between the water suction aggregate layer 12 and soil horizon 10 Layer braiding material sealing coat 11, is typically expected with Periostracum Serpentiss braiding.The width of the water suction aggregate layer 12 is 250~350mm, and thickness is 450~550mm;The water supply line 3 is horizontally embedded in water suction aggregate layer 12.The water suction aggregate layer 12 is broken foaming Concrete block, broken air-mixed concrete pieces, Pumex, Vermiculitum or haydite.Water supply line is located on water suction aggregate, above sets covering Layer, prevents soil from inserting water suction aggregate and loses water suction water reservation, and water filling port 8 is preferably located at setting 1.5 meters, at least ensures every The water source supply in 3 directions of tree, water suction aggregate water suction water storage effect are good, provide lasting moisture can to trees, accelerate trees Growth;Sedimentation has collection rainwater, water storage, and desilting effect is built by laying bricks or stones using building to mix, and the precipitation well lid in parking lot adopts load-bearing Catch basin cover, water filling port are built by laying bricks or stones using brick material, and major function pours into the water filling mouth of pipe to prevent soil;
Additionally, the present invention also provides the construction method in above-mentioned rapid-result ground green shade parking lot, it is characterised in that including following step Suddenly:
Step one, parking lot addressing and integral layout are arranged:Parking lot addressing is carried out as needed, and which is laid out sets Put, determine track 1, parking area 2, growth belt and water storage with 7 set location;
Step 2, setting water storage band 7 simultaneously lay water supply line 3:Setting along 1000~1500mm beside the growth belt of parking lot periphery Water storage band 7 is put, sealing coat 11 and is entered including tunnel, laying water suction aggregate layer 12, laying water supply line 3, laying braiding material is dug Row soil is backfilled;Sedimentation 6 and water filling port 8 are set during laying water supply line 3 simultaneously;
The construction of step 3, track 1 and parking area 2:Slope is set along track direct of travel, the side near track entrance is higher than Away from the side of track entrance;
The arrangement of step 4, growth belt:After the completion of track 1 and parking area 2 are constructed, the arrangement of growth belt is carried out, in growth belt Upper plantation arbor 5, has 32 outlet of 2-4 lateral around every arbor 5;
Step 5, parking area 2 divide parking stall:Parking area 2 is carried out into parking stall division, each parking stall is correspondingly arranged car stop 4, and Take into account the effect of sheltering from heat or light of arbor 5;So far, rapid-result ground green shade parking lot construction is completed.
To sum up, by rapid-result green shade parking lot, provide excellent parking environment can not only to city car owner, raising drives, Comfort level, provides healthy clean environment for car owner, and increases greenery area, by adjustment region miniclimate, with point by bus Zone face, adjusts big ecological, alleviates heat island phenomenon.Presently preferred embodiments of the present invention is the foregoing is only, not to limit this Bright, all any modification, equivalent substitution and improvements within the spirit and principles in the present invention, made etc. should be included in the present invention Protection domain within.

Claims (10)

1. a kind of rapid-result ground green shade parking lot, including track(1)And parking area(2), the parking area(2)It is divided into some stopping Parking stall, the parking stall are provided with car stop(4), it is characterised in that:The parking area(2)For slope, close track(1)Side Higher than away from track(1)Side;The parking area(2)Relatively low side and both side ends are designed with growth belt, the plantation Take interval kind and be implanted with arbor(5);On ground beside the growth belt(9)To have water storage band(7), the water storage band(7) Water supply line is embedded with inside(3);The water supply line(3)Including main pipeline(31)With the lateral stretched out from main pipeline (32);The main pipeline(31)Arrange along growth belt, upper end connection upper hose(33);The lateral(32)Water side bury It is located at arbor(5)Around.
2. a kind of rapid-result ground green shade parking lot according to claim 1, it is characterised in that:The parking lot is rectangle, Including parallel spaced track(1)With the parking area for being distributed in track both sides(2), accordingly, the water supply line(3)Bag Periphery is included around the rectangle water supply line in parking lot and centre along two parking areas(2)Between growth belt arrangement yi word pattern supply water Pipeline, the rectangle water supply line and yi word pattern water supply line are interconnected.
3. a kind of rapid-result ground green shade parking lot according to claim 1 and 2, it is characterised in that:The main pipeline(31) On be arranged at intervals with sedimentation(6)And water filling port(8), the sedimentation(6)And water filling port(8)With main pipeline(31)By branch Pipeline communication.
4. a kind of rapid-result ground green shade parking lot according to claim 3, it is characterised in that:The parking area(2)Slope Degree scope is 0.5%~1%;Preferred slope is 1%.
5. a kind of Multifunctional assembled green shade frame according to claim 1, it is characterised in that:The water supply line(3) Embedment water storage band(7)Earth's surface below 250~350mm.
6. a kind of rapid-result ground green shade parking lot according to claim 1, it is characterised in that:The water storage band(7)Top Portion is soil horizon(10), bottom is water suction aggregate layer(12).
7. a kind of rapid-result ground green shade parking lot according to claim 6, it is characterised in that:The water suction aggregate layer(12) Width be 250~350mm, thickness be 450~550mm;The water supply line(3)It is horizontally embedded water suction aggregate layer(12) In.
8. a kind of Multifunctional assembled green shade frame according to claim 6, it is characterised in that:The water suction aggregate layer (12)With soil horizon(10)Between arrange one layer braiding material sealing coat(11).
9. a kind of Multifunctional assembled green shade frame according to claim 6~8 any one, it is characterised in that:It is described Water suction aggregate layer(12)For the foamed concrete block, broken air-mixed concrete pieces, Pumex, Vermiculitum or the haydite that crush.
10. the construction method in a kind of rapid-result ground green shade parking lot according to claim 1-9 any one, its feature exist In comprising the steps:
Step one, parking lot addressing and integral layout are arranged:Parking lot addressing is carried out as needed, and which is laid out sets Put, determine track(1), parking area(2), growth belt and water storage band(7)Set location;
Step 2, setting water storage band(7)And lay water supply line(3):Along parking lot periphery growth belt beside 1000~ 1500mm arranges water storage band(7), including dig tunnel, laying water suction aggregate layer(12), laying water supply line(3), laying braiding Material sealing coat(11)With carry out soil backfill;Laying water supply line(3)When simultaneously sedimentation is set(6), and apart from arbor(5) Water filling port is set at 1.5 meters(8);
Step 3, track(1)And parking area(2)Construction:Parking area(2)Slope is set, near track(1)Side higher than remote From track(1)Side;
The arrangement of step 4, growth belt:In track(1)And parking area(2)The arrangement of growth belt after the completion of construction, is carried out, is being planted Plant takes plantation arbor(5), every arbor(5)Surrounding has 2-4 lateral(32)Outlet;
Step 5, parking area(2)Divide parking stall:By parking area(2)Parking stall division is carried out, each parking stall is correspondingly arranged car stop (4), and take into account arbor(5)Effect of sheltering from heat or light;So far, rapid-result ground green shade parking lot construction is completed.
CN201610955078.8A 2016-11-03 2016-11-03 A kind of short-term training ground green shade parking lot and its construction method Expired - Fee Related CN106593034B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610955078.8A CN106593034B (en) 2016-11-03 2016-11-03 A kind of short-term training ground green shade parking lot and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610955078.8A CN106593034B (en) 2016-11-03 2016-11-03 A kind of short-term training ground green shade parking lot and its construction method

Publications (2)

Publication Number Publication Date
CN106593034A true CN106593034A (en) 2017-04-26
CN106593034B CN106593034B (en) 2019-04-05

Family

ID=58590383

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610955078.8A Expired - Fee Related CN106593034B (en) 2016-11-03 2016-11-03 A kind of short-term training ground green shade parking lot and its construction method

Country Status (1)

Country Link
CN (1) CN106593034B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109296231A (en) * 2018-03-13 2019-02-01 柯磊明 A kind of sponge ecology parking lot

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1632266A (en) * 2005-01-03 2005-06-29 宁波德安城市生态技术集团有限公司 Environmental protection parking lot
EP1837441A1 (en) * 2006-03-20 2007-09-26 Jan Cornelis Parking place
KR20100019644A (en) * 2008-08-11 2010-02-19 김정훈 Outdoor parking lot structure having protecting device for woody plant
CN103864228A (en) * 2014-03-21 2014-06-18 中国环境科学研究院 Minimally invasive excavated multimedium underground percolating in-situ recharge underground water treatment device
CN204024144U (en) * 2014-04-18 2014-12-17 福建省春天园林工程有限公司 A kind of novel Lin Yin parking lot
CN104264773A (en) * 2014-09-16 2015-01-07 苏州德华生态环境科技有限公司 Flow storage wetland system for treating parking lot rainwater and adjusting microclimate
KR20160064622A (en) * 2014-11-28 2016-06-08 김정현 Parking garage have planting area
CN105781167A (en) * 2016-05-19 2016-07-20 苏州大学 Configuratin and energy conservation effect assessment method for inclined type shadeway parking lot tree species
CN105804198A (en) * 2016-04-06 2016-07-27 上海交通大学 Greenbelt structure integrating rainwater storage and utilization
CN205476690U (en) * 2015-04-01 2016-08-17 江苏省林业科学研究院 Ecological parking area of buried pipe type
CN106022611A (en) * 2016-05-19 2016-10-12 苏州大学 Vertical configuration of trees in shaded parking lot and energy-saving effect assessment method for configuration

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1632266A (en) * 2005-01-03 2005-06-29 宁波德安城市生态技术集团有限公司 Environmental protection parking lot
EP1837441A1 (en) * 2006-03-20 2007-09-26 Jan Cornelis Parking place
KR20100019644A (en) * 2008-08-11 2010-02-19 김정훈 Outdoor parking lot structure having protecting device for woody plant
CN103864228A (en) * 2014-03-21 2014-06-18 中国环境科学研究院 Minimally invasive excavated multimedium underground percolating in-situ recharge underground water treatment device
CN204024144U (en) * 2014-04-18 2014-12-17 福建省春天园林工程有限公司 A kind of novel Lin Yin parking lot
CN104264773A (en) * 2014-09-16 2015-01-07 苏州德华生态环境科技有限公司 Flow storage wetland system for treating parking lot rainwater and adjusting microclimate
KR20160064622A (en) * 2014-11-28 2016-06-08 김정현 Parking garage have planting area
CN205476690U (en) * 2015-04-01 2016-08-17 江苏省林业科学研究院 Ecological parking area of buried pipe type
CN105804198A (en) * 2016-04-06 2016-07-27 上海交通大学 Greenbelt structure integrating rainwater storage and utilization
CN105781167A (en) * 2016-05-19 2016-07-20 苏州大学 Configuratin and energy conservation effect assessment method for inclined type shadeway parking lot tree species
CN106022611A (en) * 2016-05-19 2016-10-12 苏州大学 Vertical configuration of trees in shaded parking lot and energy-saving effect assessment method for configuration

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109296231A (en) * 2018-03-13 2019-02-01 柯磊明 A kind of sponge ecology parking lot

Also Published As

Publication number Publication date
CN106593034B (en) 2019-04-05

Similar Documents

Publication Publication Date Title
CN106900342B (en) Integrated semi-lithologic high slope vegetation reconstruction protection method
CN208266847U (en) Quickly repair structure in Gullied suitable for Canal in Loess Area
CN204097967U (en) The ecological quilt of a kind of reinforcement
CN202396194U (en) Vegetation blanket
CN107881875A (en) A kind of karst ecology parking lot and its building method
CN107439320A (en) A kind of greening method of concordant limestone breakage mountain body
CN107100176A (en) A kind of expressway slope greening system
CN112136408B (en) Greening method suitable for sand abrupt slope in high-altitude area
CN201972156U (en) Slope protection system with stereoscopic afforestation vegetation cushions
CN112878278B (en) Ecological bag and construction method of artificial environment landscape wetland revetment thereof
JP2003047346A (en) Planting vessel for vegetation and method for making the same
CN104358229B (en) The green ecological channel network system of soil improvement in sea reclamation sand mud substrate
CN206267161U (en) A kind of three-dimension vegetative net slope protection construction structure suitable for soil-slope
CN106593034A (en) Rapidly-completed ground shade parking lot and construction method thereof
CN108643161B (en) Sand-fixing, tree-planting, rain-collecting, water-retaining and sand-controlling plate
CN106613428A (en) Planting system for preventing water and soil loss
CN108990782A (en) For a long time naturally to the husky core pipe device and implementation method of big tree root supplement rainwater
KR200254952Y1 (en) Device for suppling water of tree
CN114164844A (en) Construction method of square grid type organic material slope protection structure
JP2756095B2 (en) Plant growth inhibiting mat and greening method using the mat
GB2288306A (en) Modular sports field construction
CN205567228U (en) Ecological tree pond
CN111501667A (en) Ecological slope protection structure for hydraulic engineering
JP2000166386A (en) Mat for preventing growth of plant, and a cylindrical body
JPS60188532A (en) Sheathing device of slope

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190405