CN106592810A - Construction method of wrapping fair brick masonry for concrete structure of historic building - Google Patents

Construction method of wrapping fair brick masonry for concrete structure of historic building Download PDF

Info

Publication number
CN106592810A
CN106592810A CN201611124455.XA CN201611124455A CN106592810A CN 106592810 A CN106592810 A CN 106592810A CN 201611124455 A CN201611124455 A CN 201611124455A CN 106592810 A CN106592810 A CN 106592810A
Authority
CN
China
Prior art keywords
clear water
water masonry
masonry
bricks
blue bricks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611124455.XA
Other languages
Chinese (zh)
Other versions
CN106592810B (en
Inventor
王奇维
赵沛亮
李建
王永冬
郭钦涛
温飞峰
张江南
杨辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Work San Construction Group Co Ltd Is Built In Shaanxi
Original Assignee
Work San Construction Group Co Ltd Is Built In Shaanxi
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Work San Construction Group Co Ltd Is Built In Shaanxi filed Critical Work San Construction Group Co Ltd Is Built In Shaanxi
Priority to CN201611124455.XA priority Critical patent/CN106592810B/en
Publication of CN106592810A publication Critical patent/CN106592810A/en
Application granted granted Critical
Publication of CN106592810B publication Critical patent/CN106592810B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Retaining Walls (AREA)

Abstract

The invention discloses a construction method of wrapping fair brick masonry for a concrete structure of a historic building. The method comprises following steps: step 1, deepening design of joints, wherein joints composed of the fair brick masonry and a concrete framework structure comprise framework columns, framework beams, door and window opening beams, structure columns, wall surface ornaments and special-shaped windows; step 2, cutting of black bricks and pre-burying of lacing and anchoring steel bars; step 3, construction of the fair brick masonry with joints wrapped for the concrete framework structure; step 4, pointing: pointing from the top to the bottom after the wrapped fair brick masonry of the concrete framework structure is finished after the bricklaying of the wrapped fair brick masonry of the concrete framework structure is finished, wherein the pointing form is flush joint at the depth of 6mm. The construction method of wrapping the fair brick masonry for the concrete structure of the historic building has the following beneficial effects: the construction method is simple in step, reasonable in design, easy and convenient in construction and good in application effect; the fair brick masonry is wrapped by utilizing black bricks processed after deepening design of all joints according to the concrete framework structure such that the wall surface of the historic building looks more exquisite.

Description

A kind of ancient building xoncrete structure outsourcing clear water masonry construction method
Technical field
The invention belongs to building masonry structure field of engineering technology, and in particular to a kind of ancient building xoncrete structure outsourcing is clear Water masonry construction method.
Background technology
The clear water masonry face of Chinese ancient architecture is substantially built by laying bricks or stones by building stones or blue bricks and is formed, and does not have building structure on its surface Material exposes.Modern ancient building primary structural material adopts armored concrete, includes using main portions:Building frame construction, The positions such as exterior wall collar tie beam, door-window opening beam, the vertical moulding of exterior wall level, outer wall column.In order to restore outside ancient building masonry See effect, it is necessary to using building stones or blue bricks, above-mentioned visual concrete construction is carried out it is hidden, while material therefor and way will also Meet current designs and construction inspection rules requirement.
Usually said clear water masonry traditional method, is primarily referred to as the construction party of clear water masonry 50~eighties of last century Method.When building by laying bricks or stones, mainly masonry is carried out using cement mortar, lime mortar and clear water building block and build and use jointing by laying bricks or stones, its is main There is following defect:
1st, wall body structure:The body of wall gray seam thickness of modern architecture masonry structure is usually 8mm~12mm, and using magma letter Single jointing;And the seam width that ancient architecture masonry close joint is built by laying bricks or stones in way is only 2mm~3mm, and cracked and jointing way using fine, So that the way gap of two kinds of bodies of wall is larger.To solve this contradiction, it is necessary to using wall body structure treatment measures be improved with it is complete It is kind.
2nd, wall body node:In concrete frame structure blue bricks surface building frame construction, exterior wall collar tie beam, lintel, The positions such as the vertical moulding of exterior wall level, outer wall column are processed without process or using cement mortar rendering substantially, this simple and crude Processing mode can not at all meet the requirement of ancient building masonry appearance, it is necessary to take construction measure to enter as body of wall special joint Row is processed.
3rd, wall decoration:Stickup is carried out during ancient building block wall decoration construction with cement mortar to build by laying bricks or stones, between body of wall Without construction measure, resistance to overturning is poor.
4th, building materials:Most building materials are made using craft or light instrument on market, cause material Size disunity, surface impression quality is poor, when handling, transport and site operation, the matter such as losing fangle, surface contamination easily occurs Amount defect, thus causes finished product surface of wall impression quality to reach traditional ancient building clear water masonry face appearance.Therefore, It is not fine enough compared with traditional ancient architecture wall surface perception effect.
The content of the invention
It is an object of the invention to overcome above-mentioned technical disadvantages, there is provided a kind of ancient building xoncrete structure outsourcing clear water masonry Construction method, the method had both met ancient building masonry close joint and had built appearance by laying bricks or stones, also carried out masonry with concrete frame structure Drawknot simultaneously meets shockproof requirements, while other correlations of relevant masonry structure and filling masonry in existing national regulation can also be met Performance requirement.
To solve above-mentioned technical problem, the technical solution used in the present invention is:A kind of ancient building xoncrete structure outsourcing is clear Water masonry construction method, it is characterised in that the method is comprised the following steps:
The Deepen Design of step one, node:Actual size, structural working drawing according to concrete on construction site frame structure And architectural working drawing, design the construction and the clear water masonry and concrete frame knot of concrete frame structure outsourcing clear water masonry The drawknot anchoring structure of the node that structure is constituted;
The clear water masonry includes frame column, Vierendeel girder, door-window opening beam, structure with the node that concrete frame structure is constituted Post, metope carve and shaped window are made, the door-window opening beam is collar tie beam or lintel, and it is tile carving or embossment that the metope is overwrought;
Step 2, the cutting of blue bricks and drawknot anchor bar it is pre-buried:According to the design result of step one, each node is processed Required various sizes of blue bricks;
Step 3, concrete frame structure configuration node outsourcing clear water masonry construction:From the concrete frame structure Carry out building by laying bricks or stones for clear water masonry at the absolute altitude of bottom surface upwards successively, in the building process of clear water masonry, clear water masonry and concrete It is as follows that the bag of the node that frame structure is constituted builds work progress:
Clear water masonry bag builds the work progress of framework Column border node:According to the design result of step one, pre-buried drawknot anchoring Reinforcing bar, the drawknot anchor bar is pressure joist;The blue bricks that step 2 is cut is built by row's hot line and the facing bond of one fourth of marked rod one The crust of parcel frame column;
Clear water masonry bag builds the work progress of framework girder connection:According to the design result of step one, pre-buried drawknot anchoring Reinforcing bar, the drawknot anchor bar is pressure joist;A circle reinforced concrete band is chosen outside Vierendeel girder crust;The armored concrete Built with the blue bricks bag that step 2 is cut with periphery, the Vierendeel girder remainder is built by row's hot line and the fourth one of marked rod one along bag;
Clear water masonry bag builds the work progress of door-window opening girder connection:The clear water masonry is built by laying bricks or stones to door-window opening beam bottom After the absolute altitude in portion, the door-window opening beam steel of the door-window opening beam is installed in colligation, and the blue bricks that step 2 is cut is by row's hot line The door-window opening beam periphery is built to the top of the door-window opening beam, microlith coagulation is used after 24h with the facing bond of one fourth of marked rod one Soil pours door and window hole lintel, and employing is manually vibrated;
Clear water masonry bag builds the work progress of construction Column border node:The constructional column reinforcing bar of the constructional column is installed in colligation, will The blue bricks of step 2 cutting is built the periphery of the constructional column reinforcing bar by row's hot line and the facing bond of one fourth of marked rod one, often builds 250mm by laying bricks or stones Height pours a pea gravel concreten, and artificial vibration compacting, until constructional column bag is finished building into;
Metope carve node work progress be:When clear water masonry is built by laying bricks or stones to metope overwrought bottom absolute altitude, carved according to metope The thickness of decorations builds the overwrought back body of wall of metope by laying bricks or stones, and dark beam is provided with the back body of wall, pre-buried metope carving in the dark beam The tension member of decorations;
Clear water masonry bag builds the work progress of shaped window node:The clear water masonry is built by laying bricks or stones to the special-shaped window opening bottom and is marked Gao Hou, installs the shaped window cranse;Surrounding's body of wall of shaped window cranse is built by laying bricks or stones with three methods that skins one are leaned on and five skins one hang;
Step 4, jointing:After the completion of concrete frame structure outsourcing clear water masonry is built by laying bricks or stones, jointing, institute are unified from top to bottom It is flush joint to state jointing form, and the depth of the jointing is 6mm.
A kind of above-mentioned ancient building xoncrete structure outsourcing clear water masonry construction method, is characterized in that:To coagulation in step one The arrangement when tectonic sieving of native frame structure outsourcing clear water masonry includes being designed the size of blue bricks and building by laying bricks or stones to blue bricks It is designed, specifically includes following steps:
Step 101, the actual size according to concrete on construction site frame structure, structural working drawing and architectural working drawing, To needing pre-buried drawknot anchor bar position to position using measurer and instrument;
Step 102, the size for determining blue bricks and arrangement mode when building by laying bricks or stones;
Step 103, levelling positioning, comprise the following steps:
The benchmark mortar joint of step 1031, the unification concrete frame structure, the exterior wall of the concrete frame structure is equal For horizontal straight joint;
Step 1032, full sized brick THICKNESS CALCULATION clear water masonry skin number is pressed according to floor height, the blue bricks skin number is adjusted to into integer;
Step 1033, by the blue bricks metope and ORIENTED DOOR AND WINDOW DESIGN size for having sequenced, adjust the blue bricks arrangement of the door window side, institute Blue bricks is stated for full sized brick;
Step 104, row's brick put down bottom, comprise the following steps:
Step 1041, the length for calculating every section of clear water masonry along full sized brick by a fourth one are long by the calculating of every section of clear water masonry Degree is adjusted to identical with design length;
Step 1042, the blue bricks of the top of a wall inner corner trim for adjusting the clear water masonry gable are full sized brick.
A kind of above-mentioned ancient building xoncrete structure outsourcing clear water masonry construction method, is characterized in that:By institute in step 1032 The skin number for stating blue bricks is adjusted to integer, and its adjustment mode is:The leveling mortar thickness of the clear water masonry bottom is adjusted first, such as When really skin number is still unsatisfactory for integer by way of adjustment leveling mortar thickness, by the thickness for adjusting horizontal mortar joint, each institute State the adjustment amount≤1mm of horizontal mortar joint;
The blue bricks arrangement of the door window side is adjusted in step 1033, the blue bricks is full sized brick, and its adjustment mode is:Fine setting institute The plan-position of door-window opening and the width and height of the door-window opening are stated, the absolute altitude after adjustment at the top of the door and window is constant;
The computational length that every section of clear water masonry is adjusted in step 1041 is identical with design length, and adjustment mode is:Adjust first The vertical mortar joint of the whole clear water masonry, if being still unsatisfactory for clear water masonry computational length with design length by the vertical mortar joint of adjustment When spending identical, the brick of the blue bricks by arranging along length direction in the adjustment clear water masonry is long, and the brick length per blue bricks described in block subtracts On a small quantity≤5mm, and symmetrically adjust during blue bricks is livable;
The blue bricks that the inner corner trim of the gable the top of a wall of the clear water masonry is adjusted in step 1042 is full sized brick, and adjustment mode is:It is first The mortar joint of the clear water masonry is first adjusted, if by adjusting the green grass or young crops that the mortar joint of clear water masonry is still unsatisfactory for the inner corner trim of the gable the top of a wall Brick is full sized brick, should adjust the top of a wall length of the gable, and readjusts gable row's brick according to step 1041.
A kind of above-mentioned ancient building xoncrete structure outsourcing clear water masonry construction method, is characterized in that:Institute is laid in being adjacent to When the blue bricks for stating upper and lower two skin of pressure joist is cut, the V-arrangement matched with the pressure joist size is opened up on the blue bricks Groove, the size of the V-shaped groove and the match specifications of the pressure joist, are entered to various special shaped bricks and seven separately using cutting machine Row clip.
A kind of above-mentioned ancient building xoncrete structure outsourcing clear water masonry construction method, is characterized in that:The clear water masonry is built Build to away from it is described pressure joist one skin brick of absolute altitude when, using offer V-shaped groove blue bricks and the notch court of the blue bricks of V-shaped groove will be opened up On, the length direction along the pressure joist is built by laying bricks or stones;After the pressure joist is pre-buried, adopts the blue bricks for offering V-shaped groove and will open If the notch of the blue bricks of V-shaped groove is down, the length direction along the pressure joist is built by laying bricks or stones.
A kind of above-mentioned ancient building xoncrete structure outsourcing clear water masonry construction method, is characterized in that:Clear water masonry bag builds frame In the work progress of trestle node, built according to the suitable mode of row's hot line and the fourth one of marked rod one according to the blue bricks of step 2 cutting The crust for wrapping up the frame column is built, the clear water masonry and framework Column border node are anchored by pre-buried pressure joist, described Pressure joist inserts one end of the clear water masonry and is arranged to bend anchoring section, and the bending anchoring section is laid in the V of the blue bricks In shape groove.
A kind of above-mentioned ancient building xoncrete structure outsourcing clear water masonry construction method, is characterized in that:Clear water masonry bag builds frame Set a roof beam in place in node construction, one layer of Vierendeel girder of the frame structure is disposed in the outdoor under absolute altitude -0.070m, the bottom of the clear water masonry Portion's absolute altitude exposes the low skin of absolute altitude than one layer of Vierendeel girder;According to the blue bricks of step 2 cutting according to row's hot line and marked rod The suitable mode of one fourth one builds the crust for wrapping up the Vierendeel girder by laying bricks or stones, and the clear water masonry and framework girder connection are by pre-buried pressure wall Muscle is anchored, and one end that the pressure joist inserts the clear water masonry is arranged to bend anchoring section, the bending anchoring section cloth It is located in the V-shaped groove of the blue bricks.
A kind of above-mentioned ancient building xoncrete structure outsourcing clear water masonry construction method, is characterized in that:Clear water masonry bag builds door In the construction of window hole girder connection, when the deck-molding of the door-window opening beam is more than 200mm, formwork reinforcement institute is used before casting concrete State the door-window opening beam steel of colligation installation.
A kind of above-mentioned ancient building xoncrete structure outsourcing clear water masonry construction method, is characterized in that:Metope carve node In construction, the groove laid for tension member is offered in the metope carve, the groove is opened along the overwrought short transverse of the metope If the position relative with the groove is provided with dark beam during the back building wall, and the back body of wall is clear water masonry, described Tension member is T-shaped tension rib, and one end of the T-shaped tension rib is arranged in the groove, and the other end of the T-shaped tension rib is laid In the dark beam.
A kind of above-mentioned ancient building xoncrete structure outsourcing clear water masonry construction method, is characterized in that:The shaped window cranse Filled up with mortar between surrounding and the blue bricks.
The present invention has compared with prior art advantages below:
1st, method and step is simple, reasonable in design and easy construction, and input construction cost is relatively low.
2nd, efficiency of construction is high and speed of application is fast.
3rd, after the completion of concrete frame structure outsourcing blue bricks is built by laying bricks or stones, jointing is unified from top to bottom, the form of jointing is flush joint And the depth of jointing is 6mm, easy construction is cost-effective and can make that body of wall is more attractive in appearance, solid.
4th, to the frame column in concrete frame structure, Vierendeel girder, door-window opening beam, constructional column, wall decoration and abnormal shape The bag of each node of window is built and has made corresponding Deepen Design one by one, meets the requirement of ancient building masonry appearance.
5th, wall decoration:When wall decoration is constructed, tension member is provided between back body of wall, increased wall decoration Resistance to overturning and durability.
6th, clear water masonry carries out bag block using according to the blue bricks processed after each node Deepen Design of concrete frame structure, and Cutting is processed using specific rattler, dimensional standard, surface impression quality is high, makes ancient architecture wall surface perception effect It is finer.
In sum, the inventive method step is simple, reasonable in design and easy construction using effect is good, reduces work strong Degree, shorten the construction period its have more operability, preferably improve security, the durability of building, clear water masonry adopts root Bag block is carried out according to the blue bricks processed after each node Deepen Design of concrete frame structure, ancient architecture wall surface perception effect is made more Plus it is fine.
Below by drawings and Examples, technical scheme is described in further detail.
Description of the drawings
Fig. 1 is the construction method FB(flow block) of the present invention.
Fig. 2 is the structural representation of clear water masonry of the present invention.
Fig. 2-1 is the A-A profiles of Fig. 2.
Fig. 2-2 is enlarged drawing at the A of Fig. 2-1.
Fig. 3-1 is the structural representation that the bag of clear water masonry of the present invention half builds external corner part framework Column border node.
Fig. 3-2 is the B-B profiles of Fig. 3-1.
Fig. 3-3 is that clear water masonry of the present invention wraps the structural representation for building external corner part framework Column border node entirely.
Fig. 3-4 is the structural representation that the bag of clear water masonry of the present invention half builds gable the top of a wall framework Column border node.
Fig. 3-5 is that clear water masonry of the present invention wraps the structural representation for building gable the top of a wall framework Column border node entirely.
Fig. 3-6 is the structural representation that the bag of clear water masonry of the present invention half builds middle part framework Column border node.
Fig. 3-7 is that clear water masonry of the present invention wraps the structural representation for building middle part framework Column border node entirely.
Fig. 4-1 is the structural representation that clear water masonry bag of the present invention builds one layer of framework girder connection.
Fig. 4-2 is the structural representation that clear water masonry bag of the present invention builds two layers of framework girder connection.
Fig. 5-1 is the structural representation that clear water masonry bag of the present invention builds door opening girder connection.
Fig. 5-2 is the C-C sectional views of Fig. 5-1.
Fig. 5-3 is the structural representation that clear water masonry bag of the present invention builds window hole girder connection.
Fig. 5-4 is the D-D sectional views of Fig. 5-3.
Fig. 6 is the E-E sectional views of Fig. 2.
Fig. 7 is the structural representation of metope carve node of the present invention.
Fig. 8 is the structural representation that clear water masonry bag of the present invention builds shaped window node.
Description of reference numerals:
1-blue bricks;2-pressure joist;3-frame column;
4-Vierendeel girder;5-grade;6-pea gravel concreten;
7-door-window opening beam;8-door-window opening beam steel;9-door opening;
10-window hole;11-constructional column reinforcing bar;12-constructional column;
13-tension member;14-wall decoration;15-dark beam;
16-shaped window cranse.
Specific embodiment
A kind of ancient building xoncrete structure outsourcing clear water masonry construction method as shown in Fig. 1~Fig. 8, the method include with Lower step:
The Deepen Design of step one, node:Actual size, structural working drawing according to concrete on construction site frame structure And architectural working drawing, design the construction and the clear water masonry and concrete frame knot of concrete frame structure outsourcing clear water masonry The drawknot anchoring structure of the node that structure is constituted;
The clear water masonry includes frame column 3, Vierendeel girder 4, door-window opening beam with the node that concrete frame structure is constituted 7th, constructional column 3, metope overwrought 14 and shaped window, the door-window opening Liangmen window hole beam 7 is collar tie beam or lintel, and the metope is carved Decorations 14 are tile carving or embossment;
Step 2, the cutting of blue bricks and drawknot anchor bar it is pre-buried:According to the design result of step one, each node is processed Required various sizes of blue bricks;
Step 3, concrete frame structure node outsourcing clear water masonry construction:From the bottom surface of the concrete frame structure Carry out building by laying bricks or stones for clear water masonry at absolute altitude upwards successively, in the building process of clear water masonry, clear water masonry and concrete frame It is as follows that the bag of the node that structure is constituted builds work progress:
As shown in Fig. 3-1~Fig. 3-7, clear water masonry bag builds the work progress of framework Column border node and is:Setting according to step one Meter result, pre-buried drawknot anchor bar, the drawknot anchor bar is pressure joist 2;The blue bricks 1 that step 2 is cut is by row's hot line The parcel crust of frame column 3 is built with the facing bond of one fourth of marked rod one;
As shown in Fig. 4-1, Fig. 4-2, clear water masonry bag builds the work progress of framework girder connection and is:According to the design of step one As a result, pre-buried drawknot anchor bar, the drawknot anchor bar is pressure joist 2;A circle reinforced concrete is chosen outside the crust of Vierendeel girder 4 Soil zone;The bag of blue bricks 1 that the reinforced concrete band periphery step 2 is cut is built, and the remainder of the Vierendeel girder 4 is by row's hot line Build along bag with the fourth one of marked rod one;
As shown in Fig. 5-1, Fig. 5-2, Fig. 5-3, Fig. 5-4, clear water masonry bag builds the work progress of door-window opening girder connection and is: The clear water masonry is built by laying bricks or stones to the absolute altitude of the bottom of door-window opening beam 7, and the door-window opening beam of the door-window opening beam 7 is installed in colligation Reinforcing bar 8, the blue bricks that step 2 is cut builds the periphery of door-window opening beam 7 to described by row's hot line and the facing bond of one fourth of marked rod one The top of door-window opening beam 7, door and window hole lintel is poured after 24h with pea gravel concreten, and using manually vibrating, it is excellent when vibrating Vibrating for reinforcing rod for choosing, forbids machinery to vibrate;
As shown in fig. 6, the work progress that clear water masonry bag builds construction Column border node is:The structure of the constructional column 12 is installed in colligation Post reinforcing bar 11 is made, the blue bricks 1 that step 2 is cut builds the constructional column reinforcing bar 11 by row's hot line and the facing bond of one fourth of marked rod one Periphery, often builds 250mm height by laying bricks or stones and pours a pea gravel concreten, and artificial vibration compacting, forbids machinery to vibrate, until constructional column 12 Bag is finished building into;
During practice of construction, constructional column 12 along blues brick wall described in the width ratio of wall thickness direction the little 80mm of thickness, along the blue bricks Wall length direction is determined that the size of the blue bricks 1 is 240mm × 60mm × 53mm, 120mm × 60mm × 53mm by calculating is designed, The blues brick wall often builds concrete of 250mm HTs by laying bricks or stones, and the concrete is pea gravel concreten, the pea gravel concreten Slump≤80mm.
As shown in fig. 7, the work progress of metope carve node is:Clear water masonry is built by laying bricks or stones to the bottom absolute altitude of metope carve 14 When, the back body of wall of metope carve 14 is built by laying bricks or stones according to the thickness of metope carve 14, dark beam 15, institute are provided with the back body of wall State the tension member 13 of pre-buried metope carve 14 in dark beam 15;
As shown in figure 8, the work progress that clear water masonry bag builds shaped window node is:The blue bricks is built by laying bricks or stones to the shaped window After the absolute altitude of hole bottom, the shaped window cranse 16 is installed;Body of wall around shaped window is built by laying bricks or stones with three methods that skin one is leaned on and five skins one hang;
During practice of construction, after the completion of clear water masonry is built by laying bricks or stones around shaped window, with mortar by the seam of the periphery of shaped window cranse 16 Gap filling is real.
Step 4, jointing:After the completion of the outer clear water masonry of concrete frame structure is built by laying bricks or stones, jointing, the hook are unified from top to bottom Slit formula is flush joint, and the depth of the jointing is 6mm;
During practice of construction, jointing using plus slurry jointing, with the lime mortar of M15, the denseness of the lime mortar be 4cm~ 5cm, the sand sieved fine sand of sieve of the lime mortar, metope is clearly demarcated with mortar joint color, increases attractive in appearance;
During practice of construction, the jointing is horizontal joint and vertically stitches that the horizontal joint will smooth handing-over with vertically seam, neatly Smooth, must not there is fluctuation in depth unification, a mao raft must not occur, and corner and turning also must be upright, angular, Forbid to pollute metope during jointing.
In the present embodiment, the tectonic sieving of concrete frame structure outsourcing clear water masonry is included to blue bricks in step one The arrangement of blue bricks when size is designed and builds by laying bricks or stones is designed, and specifically includes following steps:
Step 101, the actual size according to concrete on construction site frame structure, structural working drawing and architectural working drawing, To needing pre-buried drawknot anchor bar position to position using measurer and instrument;Guarantee pre-buried position accurately, should be by construction Structure reinforcing bars fixation, prevents displacement, pre-buried deviation to be more than 3mm;
Step 102, the size for determining blue bricks and arrangement mode when building by laying bricks or stones;During practice of construction, using rattler to blue bricks 1 Finished, two rattlers are a set of, and the thickness by blue bricks 1 is milled to 53mm, another thickness by blue bricks 1 It is milled to 40mm, it is ensured that the dimensions of blue bricks 1 is consistent, corner angle are straight, and the blue bricks 1 of milled is wrapped up in per five with cotton felt one, is pricked with rope Get up, handle with care, a point heap is piled up, and carries out protection work of the blue bricks 1 before building by laying bricks or stones;
During practice of construction, the concrete size of the blue bricks is:The pressure joist 2 is located in the clear water masonry upper and lower The V-shaped groove being used in combination with the pressure joist 2 is offered on two skin blue bricks 1;Clear water masonry bag is built in frame column node construction, The size of the blue bricks 1 is 240mm × 60mm × 53mm, 120mm × 60mm × 53mm;Clear water masonry bag is built framework girder connection and is applied In work, the size of the blue bricks 1 be 240mm × 60mm × 53mm, 120mm × 60mm × 53mm, 240mm × 60mm × 10mm, 120mm×60mm×10mm;Clear water masonry bag is built in the lintel or collar tie beam node construction of door-window opening, the size of the blue bricks 1 For 240mm × 60mm × 40mm, 120mm × 60mm × 40mm;Clear water masonry bag is built in constructional column node construction, the blue bricks 1 Size be 240mm × 60mm × 40mm, 120mm × 60mm × 40mm;
Step 103, levelling positioning, comprise the following steps:
The benchmark mortar joint of step 1031, the unification concrete frame structure, the exterior wall of the concrete frame structure is equal For horizontal straight joint;
Step 1032, full sized brick THICKNESS CALCULATION clear water masonry skin number is pressed according to floor height, the skin number of the blue bricks 1 is adjusted to integer;
Step 1033, by the blue bricks metope and ORIENTED DOOR AND WINDOW DESIGN size for having sequenced, the blue bricks 1 for adjusting the door window side is arranged, The blue bricks 1 is full sized brick;
Step 104, row's brick put down bottom, comprise the following steps:
Step 1041, the length for calculating every section of clear water masonry along full sized brick by a fourth one, adjust the calculating of every section of clear water masonry Length is identical with design length;
Step 1042, the top of a wall inner corner trim blue bricks 1 of the adjustment clear water masonry gable are full sized brick.
In the present embodiment, the skin number of blue bricks 1 described in step 1032 is adjusted to integer, and its adjustment mode is as follows:Adjust first The leveling mortar thickness of the whole clear water masonry bottom, if skin number is unsatisfactory for integer by way of adjusting leveling mortar thickness When, then by the thickness of adjustment horizontal mortar joint, the adjustment amount≤1mm of each horizontal mortar joint is adjusted to whole by many skins Number is required;
The blue bricks 1 that the door window side is adjusted in step 1033 is arranged, and the blue bricks 1 is full sized brick, and its adjustment mode is as follows:It is micro- The plan-position of the door-window opening and width, the height of the door-window opening are adjusted, the absolute altitude after adjustment at the top of the door and window is not Become;
The computational length that every section of clear water masonry is adjusted in step 1041 is identical with design length, and adjustment mode is as follows:First The vertical mortar joint of the clear water masonry is adjusted, if being still unsatisfactory for clear water masonry computational length with design by the vertical mortar joint of adjustment When length is identical, by long along the brick of the blue bricks 1 of length direction arrangement in the adjustment clear water masonry, per the brick of blue bricks described in block 1 Long decrement≤5mm, and symmetrically adjust during blue bricks 1 is livable;
The blue bricks 1 that the inner corner trim of the gable the top of a wall of the clear water masonry is adjusted in step 1042 is full sized brick, and adjustment mode is as follows: The mortar joint of the clear water masonry is adjusted first, if the blue bricks 1 for being still unsatisfactory for the inner corner trim of the gable the top of a wall is full sized brick, should adjust described The top of a wall length of gable, and readjust gable row's brick according to step 1041.
As shown in Fig. 2-1, Fig. 2-2, in the present embodiment, to being adjacent to the blue bricks 1 for being laid in upper and lower two skin of the pressure joist 2 When being cut, open up on the blue bricks 1 and the pressure V-shaped groove that match of the size of joist 2, the size of the V-shaped groove and The match specifications of the pressure joist, using cutting machine clip are carried out to various special shaped bricks and seven separately, during practice of construction, institute The diameter for stating pressure joist 2 is preferably φ 6.5, the groove depth >=5mm of V-shaped groove, groove width >=10mm.
In the present embodiment, the clear water masonry wall build by laying bricks or stones to away from pressure joist 2 absolute altitude, the one skin brick when, using offering V The blue bricks 1 of shape groove and by the notch for opening up the blue bricks 1 of V-shaped groove upward, along it is described pressure joist 2 length direction build by laying bricks or stones, Ran Houpu Slurry, after the pressure joist 2 is pre-buried, using the blue bricks 1 for offering V-shaped groove and by the notch for opening up the blue bricks 1 of V-shaped groove down, Length direction along the pressure joist 2 is built by laying bricks or stones.
In the present embodiment, clear water masonry bag is built in the work progress of framework Column border node, is pressed according to the blue bricks 1 of step 2 cutting The suitable mode of phototypesetting hot line and the fourth one of marked rod one is building the crust that wraps up the frame column 3, the clear water masonry wall and frame by laying bricks or stones The node of trestle 3 is anchored by pre-buried pressure joist 2, and one end that the pressure joist 2 inserts the clear water masonry wall is arranged to Bending anchoring section, the bending anchoring section is laid in the V-shaped groove of the blue bricks 1;
As shown in Fig. 3-1~Fig. 3-7, during practice of construction, the clear water masonry bag builds external corner part frame column node construction In, external corner part framework Column border node bag enters as shown in Fig. 3-1~Fig. 3-3 when building to the internal corner part of the frame column 3 of the external corner When row bag is built, the blue bricks 1 of the internal corner part clear water masonry of the frame column 3 is full sized brick;When gable the top of a wall framework Column border node bag is built such as When carrying out bag block to the internal corner part of the frame column 3 of the gable the top of a wall shown in Fig. 3-4, Fig. 3-5, the inner corner trim portion of the frame column 3 The blue bricks 1 of position clear water masonry is full sized brick;To the pars intermedia as shown in Fig. 3-6, Fig. 3-7 when gable the top of a wall framework Column border node bag is built When the internal corner part of the frame column 3 of position carries out bag block, the blue bricks 1 of the internal corner part clear water masonry of the frame column 3 is full sized brick;
The size of the blue bricks 1 be 240mm × 60mm × 53mm, 120mm × 60mm × 53mm, the frame column 3 cut Face size>During 500mm, the pressure joist 2 it is horizontal and vertical, be implanted into pressure joist successively from the bottom up of the frame column 3 2, it is described pressure joist 2 laying specification be:The@500 of φ 6.5, it is described bending anchoring section specification be:The long crotch of 90 ° of 3d.
In the present embodiment, clear water masonry bag is built in Vierendeel girder node construction, as shown in Fig. 4-1, one layer of the frame structure Vierendeel girder is disposed in the outdoor under absolute altitude -0.070m, elevation of bottom the exposing than one layer of Vierendeel girder of the clear water masonry wall The low skin of absolute altitude;According to the blue bricks 1 of step 2 cutting builds parcel by laying bricks or stones according to the suitable mode of row's hot line and the fourth one of marked rod one The crust of Vierendeel girder 4, the clear water masonry wall and the node of Vierendeel girder 4 are anchored by pre-buried pressure joist 2, the pressure joist One end of the 2 insertions clear water masonry wall is arranged to bend anchoring section, and the bending anchoring section is laid in the V-arrangement of the blue bricks 1 In groove;
During practice of construction, the size of the blue bricks 1 is 240mm × 60mm × 53mm, 120mm × 60mm × 53mm, 240mm × 60mm × 10mm, 120mm × 60mm × 10mm, the sectional dimension of the frame column 4>During 500mm, the horizontal stroke of the pressure joist 2 To and longitudinal direction, from the bottom up of the frame column 4 be implanted into successively pressure joist 2, it is described pressure joist 2 laying specification be:φ 6.5@500, it is described bending anchoring section specification be:The long crotch of 90 ° of 3d;
During practice of construction, beam based on one layer of Vierendeel girder;
During practice of construction, as shown in Fig. 4-1, the reinforced concrete band of one layer of Vierendeel girder of the frame structure is arranged on described The bottom in the deck-molding direction of Vierendeel girder 4, it is therefore an objective to support is played to the blue bricks 1 that bag builds the Vierendeel girder 4 and support is acted on, such as Fig. 4- Shown in 2, the reinforced concrete band of two layers of Vierendeel girder of the frame structure is arranged on the top in the deck-molding direction of the Vierendeel girder 4, institute The gap pea gravel concreten 6 stated between two layers of Vierendeel girder bottom and clear water masonry is filled up, the size of the reinforced concrete band For:Width × height=50mm × 60mm, the reinforced concrete band position 240mm × 60mm × 10mm, 120mm × 60mm × Two kinds of specification brick bats of 10mm are pasted, the remaining Vierendeel girder 4 adopt size for 240mm × 60mm × 53mm, 120mm × 60mm × The blue bricks 1 of 53mm carries out bag block.
In the present embodiment, clear water masonry bag is built in the construction of door-window opening girder connection, and the deck-molding of the door-window opening beam 7 surpasses When crossing 200mm, the door-window opening beam steel 8 installed with colligation described in formwork reinforcement before casting concrete.
During practice of construction, the door-window opening Liangmen window hole beam 7 is collar tie beam or lintel;
As shown in Fig. 5-1, Fig. 5-2, during practice of construction, the width ratio of the collar tie beam at the lintel OR gate hole 11 of door opening 11 is clear The little 80mm of width of water masonry, the circle depth of beam at the lintel OR gate hole 11 of door opening 11 determined by designing to calculate, the green grass or young crops The size of brick 1 is 240mm × 60mm × 40mm, 120mm × 60mm × 40mm.
As shown in Fig. 5-3, Fig. 5-4, during practice of construction, the width ratio of the lintel of window hole 12 or the collar tie beam of window hole 12 is clear The little 80mm of width of water masonry, the lintel of window hole 12 or the circle depth of beam of window hole 12 by design calculate determine, the green grass or young crops The size of brick 1 is 240mm × 60mm × 40mm, 120mm × 60mm × 40mm;
In the present embodiment, in the construction of metope carve node, offer in the metope carve 14 and laid for tension member 13 Groove, the groove opens up along the short transverse of the metope carve 14, the position relative with the groove during back building wall Install and be equipped with dark beam 15, the back body of wall is clear water masonry, the tension member 13 is T-shaped tension rib, the T-shaped tension rib One end is arranged in the groove, and the other end of the T-shaped tension rib is laid in the dark beam 15;
During practice of construction, the metope overwrought 14 is tile carving or embossment, the height of the dark beam 15 according to the tile carving or The height of embossment monolithic is arranged;
During practice of construction, first fill up in anchor slot plus glairin cement mortar when patch is hung, then using 1:2 cement mortar are special Pasted with tile paste mortar, and by the insertion groove of tension member 13, patch hangs after finishing that the cement mortar cleaning overflowed is dry Only, building adhesive is mixed in the cement mortar;
During practice of construction, the tile carving or embossment want level, vertical direction bracing wire when installing, and the daily height installed is not 1m~1.2m must be more than.
During practice of construction, the tile carving or embossment are pasted after hanging, and the piece of the tile carving or embossment uses 1:1 plain cement is hooked Seam.
The above, is only presently preferred embodiments of the present invention, and not the present invention is imposed any restrictions, every according to the present invention Any simple modification, change and equivalent structure change that technical spirit is made to above example, still fall within skill of the present invention In the protection domain of art scheme.

Claims (10)

1. a kind of ancient building xoncrete structure outsourcing clear water masonry construction method, it is characterised in that the method is comprised the following steps:
The Deepen Design of step one, node:Actual size, structural working drawing according to concrete on construction site frame structure and build Construction drawing is built, the construction and the clear water masonry and concrete frame structure structure of concrete frame structure outsourcing clear water masonry is designed Into node drawknot anchoring structure;
The clear water masonry includes frame column (3), Vierendeel girder (4), door-window opening beam with the node that concrete frame structure is constituted (7), constructional column (3), metope carve (14) and shaped window, the door-window opening beam (7) is collar tie beam or lintel, and the metope is overwrought (14) it is tile carving or embossment;
Step 2, the cutting of blue bricks and drawknot anchor bar it is pre-buried:According to the design result of step one, needed for processing each node Various sizes of blue bricks;
Step 3, concrete frame structure configuration node outsourcing clear water masonry construction:From the bottom surface of the concrete frame structure Carry out building by laying bricks or stones for clear water masonry at absolute altitude upwards successively, in the building process of clear water masonry, clear water masonry and concrete frame It is as follows that the bag of the node that structure is constituted builds work progress:
Clear water masonry bag builds the work progress of framework Column border node:According to the design result of step one, pre-buried drawknot anchor bar, The drawknot anchor bar is pressure joist;The blue bricks that step 2 is cut builds parcel frame by row's hot line and the facing bond of one fourth of marked rod one The crust of trestle (3);
Clear water masonry bag builds the work progress of framework girder connection:According to the design result of step one, pre-buried drawknot anchor bar, The drawknot anchor bar is pressure joist;A circle reinforced concrete band is chosen outside Vierendeel girder (4) crust;The reinforced concrete band The blue bricks bag that periphery step 2 is cut is built, and Vierendeel girder (4) remainder is built by row's hot line and the fourth one of marked rod one along bag;
Clear water masonry bag builds the work progress of door-window opening girder connection:The clear water masonry is built by laying bricks or stones to door-window opening beam (7) bottom After the absolute altitude in portion, the door-window opening beam steel (8) of the door-window opening beam (7) is installed in colligation, and the blue bricks that step 2 is cut is pressed The top of door-window opening beam (7) periphery to the door-window opening beam (7), 24h are built in row's hot line and the facing bond of one fourth of marked rod one Afterwards door and window hole lintel is poured with pea gravel concreten, and employing is manually vibrated;
Clear water masonry bag builds the work progress of construction Column border node:The constructional column reinforcing bar of the constructional column (12) is installed in colligation (11) blue bricks that, step 2 is cut is built the periphery of the constructional column reinforcing bar (11) by row's hot line and the facing bond of one fourth of marked rod one, Often build 250mm height by laying bricks or stones and pour a pea gravel concreten, and artificial vibration compacting, until constructional column (12) bag is finished building into;
Metope carve node work progress be:Clear water masonry build by laying bricks or stones to metope carve (14) bottom absolute altitude when, according to metope carve The thickness of decorations (14) builds the back body of wall of metope carve (14) by laying bricks or stones, and dark beam (15), the dark beam are provided with the back body of wall (15) tension member (13) of pre-buried metope carve (14) in;
Clear water masonry bag builds the work progress of shaped window node:The clear water masonry is built by laying bricks or stones to the special-shaped window opening bottom absolute altitude Afterwards, the shaped window cranse (16) is installed;Built by laying bricks or stones around shaped window cranse (16) with three methods that skin one is leaned on and five skins one hang Body of wall;
Step 4, jointing:After the completion of concrete frame structure outsourcing clear water masonry is built by laying bricks or stones, jointing, the hook are unified from top to bottom Slit formula is flush joint, and the depth of the jointing is 6mm.
2. according to a kind of ancient building xoncrete structure outsourcing clear water masonry construction method described in claim 1, it is characterised in that: In step one tectonic sieving of concrete frame structure outsourcing clear water masonry is included the size of blue bricks is designed and is built by laying bricks or stones When the arrangement of blue bricks is designed, specifically include following steps:
Step 101, the actual size according to concrete on construction site frame structure, structural working drawing and architectural working drawing, to needing Pre-buried drawknot anchor bar position is positioned using measurer and instrument;
Step 102, the size for determining blue bricks and arrangement mode when building by laying bricks or stones;
Step 103, levelling positioning, comprise the following steps:
The benchmark mortar joint of step 1031, the unification concrete frame structure, the exterior wall of the concrete frame structure is water Flat straight joint;
Step 1032, full sized brick THICKNESS CALCULATION clear water masonry skin number is pressed according to floor height, the blue bricks skin number is adjusted to into integer;
Step 1033, by the blue bricks metope and ORIENTED DOOR AND WINDOW DESIGN size for having sequenced, adjust the blue bricks arrangement of the door window side, the green grass or young crops Brick is full sized brick;
Step 104, row's brick put down bottom, comprise the following steps:
Step 1041, the length for calculating every section of clear water masonry along full sized brick by a fourth one, by the computational length of every section of clear water masonry with Design length is adjusted to identical;
Step 1042, the blue bricks of the top of a wall inner corner trim for adjusting the clear water masonry gable are full sized brick.
3. according to a kind of ancient building xoncrete structure outsourcing clear water masonry construction method described in claim 2, it is characterised in that: The skin number of the blue bricks is adjusted to into integer in step 1032, its adjustment mode is:The clear water masonry bottom is adjusted first Leveling mortar thickness, if skin number is still unsatisfactory for integer by way of adjusting leveling mortar thickness, by adjusting level ash The thickness of seam, the adjustment amount≤1mm of each horizontal mortar joint;
The blue bricks arrangement of the door window side is adjusted in step 1033, the blue bricks is full sized brick, and its adjustment mode is:Finely tune the door The plan-position of window hole and the width and height of the door-window opening, the absolute altitude after adjustment at the top of the door and window is constant;
The computational length that every section of clear water masonry is adjusted in step 1041 is identical with design length, and adjustment mode is:Institute is adjusted first The vertical mortar joint of clear water masonry is stated, if being still unsatisfactory for clear water masonry computational length with design length phase by the vertical mortar joint of adjustment Meanwhile, by long along the brick of the blue bricks of length direction arrangement in the adjustment clear water masonry, per the long decrement of the brick of blue bricks described in block ≤ 5mm, and symmetrically adjust during blue bricks is livable;
The blue bricks that the inner corner trim of the gable the top of a wall of the clear water masonry is adjusted in step 1042 is full sized brick, and adjustment mode is:Adjust first The mortar joint of the whole clear water masonry, if being by adjusting the blue bricks of the inner corner trim that the mortar joint of clear water masonry is still unsatisfactory for the gable the top of a wall Full sized brick, should adjust the top of a wall length of the gable, and readjust gable row's brick according to step 1041.
4. according to a kind of ancient building xoncrete structure outsourcing clear water masonry construction method described in claim 1, it is characterised in that: When cutting to being adjacent to the blue bricks for being laid in upper and lower two skin of the pressure joist, open up on the blue bricks and the pressure joist The V-shaped groove of size matching, the match specifications of the size of the V-shaped groove and the pressure joist, to various special shaped bricks and seven separately, Clip is carried out using cutting machine.
5. according to a kind of ancient building xoncrete structure outsourcing clear water masonry construction method described in claim 4, it is characterised in that: The clear water masonry build by laying bricks or stones to away from it is described pressure joist one skin brick of absolute altitude when, using offer V-shaped groove blue bricks and V-shaped groove will be opened up Blue bricks notch upward, along it is described pressure joist length direction build by laying bricks or stones;After the pressure joist is pre-buried, adopts and offer V-arrangement The blue bricks of groove and by the notch for opening up the blue bricks of V-shaped groove down, along it is described pressure joist length direction build by laying bricks or stones.
6. according to a kind of ancient building xoncrete structure outsourcing clear water masonry construction method described in claim 4, it is characterised in that: Clear water masonry bag is built in the work progress of framework Column border node, according to the blue bricks of step 2 cutting according to the row's hot line and fourth of marked rod one One suitable mode wraps up the crust of the frame column (3) building by laying bricks or stones, and the clear water masonry and framework Column border node are by pre-buried pressure Joist is anchored, and one end that the pressure joist inserts the clear water masonry is arranged to bend anchoring section, the bending anchoring section It is laid in the V-shaped groove of the blue bricks.
7. according to a kind of ancient building xoncrete structure outsourcing clear water masonry construction method described in claim 4, it is characterised in that: Clear water masonry bag is built in Vierendeel girder node construction, and one layer of Vierendeel girder (4) of the frame structure is disposed in the outdoor absolute altitude -0.070m Under, the elevation of bottom of the clear water masonry exposes the low skin of absolute altitude than one layer of Vierendeel girder (4);According to step 2 cutting Blue bricks builds the crust for wrapping up the Vierendeel girder (4), the clear water masonry by laying bricks or stones according to the suitable mode of row's hot line and the fourth one of marked rod one Anchored by pre-buried pressure joist with framework girder connection, one end that the pressure joist inserts the clear water masonry is arranged to curved Folding anchoring section, the bending anchoring section is laid in the V-shaped groove of the blue bricks.
8. according to a kind of ancient building xoncrete structure outsourcing clear water masonry construction method described in claim 1, it is characterised in that: Clear water masonry bag is built in the construction of door-window opening girder connection, when the deck-molding of the door-window opening beam (7) is more than 200mm, is poured mixed The door-window opening beam steel (8) that colligation described in solidifying native front formwork reinforcement is installed.
9. according to a kind of ancient building xoncrete structure outsourcing clear water masonry construction method described in claim 1, it is characterised in that: In the construction of metope carve node, the groove laid for tension member (13) is offered on metope carve (14), the groove is along institute The short transverse for stating metope carve (14) is opened up, and the position relative with the groove is provided with dark beam during the back building wall (15), the back body of wall is clear water masonry, and the tension member (13) is T-shaped tension rib, and one end of the T-shaped tension rib is arranged In the groove, the other end of the T-shaped tension rib is laid in the dark beam (15).
10., according to a kind of ancient building xoncrete structure outsourcing clear water masonry construction method described in claim 1, its feature exists In:Filled up with mortar and the blue bricks between around the shaped window cranse (16).
CN201611124455.XA 2016-12-08 2016-12-08 A kind of ancient building concrete structure outsourcing clear water masonry construction method Active CN106592810B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611124455.XA CN106592810B (en) 2016-12-08 2016-12-08 A kind of ancient building concrete structure outsourcing clear water masonry construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611124455.XA CN106592810B (en) 2016-12-08 2016-12-08 A kind of ancient building concrete structure outsourcing clear water masonry construction method

Publications (2)

Publication Number Publication Date
CN106592810A true CN106592810A (en) 2017-04-26
CN106592810B CN106592810B (en) 2018-09-21

Family

ID=58598642

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611124455.XA Active CN106592810B (en) 2016-12-08 2016-12-08 A kind of ancient building concrete structure outsourcing clear water masonry construction method

Country Status (1)

Country Link
CN (1) CN106592810B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107391831A (en) * 2017-07-14 2017-11-24 上海嘉实(集团)有限公司 Vertical layout method, system and the storage medium and terminal of building block
CN108343181A (en) * 2018-01-13 2018-07-31 银广厦集团有限公司 A kind of novel clay brick exterior wall and construction method
CN110565882A (en) * 2019-08-15 2019-12-13 中国建筑一局(集团)有限公司 building gable and construction method thereof
CN113775081A (en) * 2021-09-18 2021-12-10 陕西建工第三建设集团有限公司 Construction method of inner and outer leaf composite wall of pseudo-classic building
CN114991492A (en) * 2022-05-31 2022-09-02 山西一建集团有限公司 Construction method for connecting archaized building outer wall and ancient building blue brick wall body with main structure
WO2023035803A1 (en) * 2021-09-10 2023-03-16 上海建为历保科技股份有限公司 Stability reinforcement construction method suitable for historic building partition wall of wooden structure

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1584264A (en) * 2004-06-16 2005-02-23 李国雄 Fastening method for high-strength concrete epibolic thin-layer and coupled columns
CN101338583A (en) * 2008-06-25 2009-01-07 孔繁军 Before-masonry and after-frame-shear-resisting antivibration and thermal insulation design and construction
CN101769008A (en) * 2010-01-11 2010-07-07 郑州大学 Method for constructing quake-proof masonry house by utilizing prefabricated constructional column ring beams
CN102116061A (en) * 2009-12-30 2011-07-06 中铁建工集团有限公司 Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN102505763A (en) * 2011-10-21 2012-06-20 沈阳建筑大学 Externally laid masonry composite heat-insulating sintered building block exterior wall heat insulating system
CN103015717A (en) * 2012-12-01 2013-04-03 中国建筑第七工程局有限公司 Construction process for coating faced concrete outside ultrahigh steel tube column after floor is closed
CN103696578A (en) * 2014-01-16 2014-04-02 天津天一建设集团有限公司 Method for constructing insulating chained built block outer decorated dry wall
CN104278761A (en) * 2014-09-02 2015-01-14 绿建科技集团新型建材高技术有限公司 Novel semi-outer wrapping double-row building type wall self thermal insulation system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1584264A (en) * 2004-06-16 2005-02-23 李国雄 Fastening method for high-strength concrete epibolic thin-layer and coupled columns
CN101338583A (en) * 2008-06-25 2009-01-07 孔繁军 Before-masonry and after-frame-shear-resisting antivibration and thermal insulation design and construction
CN102116061A (en) * 2009-12-30 2011-07-06 中铁建工集团有限公司 Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN101769008A (en) * 2010-01-11 2010-07-07 郑州大学 Method for constructing quake-proof masonry house by utilizing prefabricated constructional column ring beams
CN102505763A (en) * 2011-10-21 2012-06-20 沈阳建筑大学 Externally laid masonry composite heat-insulating sintered building block exterior wall heat insulating system
CN103015717A (en) * 2012-12-01 2013-04-03 中国建筑第七工程局有限公司 Construction process for coating faced concrete outside ultrahigh steel tube column after floor is closed
CN103696578A (en) * 2014-01-16 2014-04-02 天津天一建设集团有限公司 Method for constructing insulating chained built block outer decorated dry wall
CN104278761A (en) * 2014-09-02 2015-01-14 绿建科技集团新型建材高技术有限公司 Novel semi-outer wrapping double-row building type wall self thermal insulation system

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107391831A (en) * 2017-07-14 2017-11-24 上海嘉实(集团)有限公司 Vertical layout method, system and the storage medium and terminal of building block
CN108343181A (en) * 2018-01-13 2018-07-31 银广厦集团有限公司 A kind of novel clay brick exterior wall and construction method
CN110565882A (en) * 2019-08-15 2019-12-13 中国建筑一局(集团)有限公司 building gable and construction method thereof
CN110565882B (en) * 2019-08-15 2021-02-26 中国建筑一局(集团)有限公司 Building gable and construction method thereof
WO2023035803A1 (en) * 2021-09-10 2023-03-16 上海建为历保科技股份有限公司 Stability reinforcement construction method suitable for historic building partition wall of wooden structure
CN113775081A (en) * 2021-09-18 2021-12-10 陕西建工第三建设集团有限公司 Construction method of inner and outer leaf composite wall of pseudo-classic building
CN114991492A (en) * 2022-05-31 2022-09-02 山西一建集团有限公司 Construction method for connecting archaized building outer wall and ancient building blue brick wall body with main structure

Also Published As

Publication number Publication date
CN106592810B (en) 2018-09-21

Similar Documents

Publication Publication Date Title
CN106592810A (en) Construction method of wrapping fair brick masonry for concrete structure of historic building
CN103410332B (en) A kind of concrete hollow block reinforcement wall construction technology
CN106121039B (en) Villages and small towns masonry structure assembled integral ring beam and construction column combined method
CN103821364A (en) Method for constructing reinforced concrete pond
CN207959612U (en) A kind of frame, shear wall cast-in-place structural fill wall with assembled light
CN102116061A (en) Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN105002976B (en) A kind of prefabricated assembled inlet for stom water and construction method thereof
CN107268834A (en) Without construction column combination hollow out plain brick wall and its construction method
CN208934190U (en) A kind of assembled steel frame wall filled with masonry structural system
CN106894538A (en) Filling wall and agent structure concrete integral shaping method
CN205742642U (en) One exempts from the concrete prefabricated wallboard of side form assembled integral and splicing structure thereof
CN108560949A (en) Adobe wall alien invasion ruggedized construction and adobe wall alien invasion reinforcement means
CN108130992A (en) Rubble plate, styrofoam and porous brick compound thermal-insulating decorative external wall construction engineering method
CN104594633A (en) Construction method and template structure for umbrella-shaped spatial curved-surface bare concrete
CN109898698A (en) A kind of construction method of pseudo-classic architecture silk seam wall
CN103790168A (en) Application method of soil nailing wall in deep foundation pit supporting
CN113374295A (en) Old steel-wood structure roof truss dismantling and rebuilding construction method
CN205894358U (en) Aerated concrete block wall body structure
CN207092299U (en) A kind of cast-in-place hollow armored concrete filling wall
CN108412143A (en) Standard decoration hollow body railing and its construction method after a kind of
CN110219366A (en) Assembled architecture heat preserving formwork integral structure and construction method
CN104763158A (en) Joggle joint type lightweight aggregate interlocking block construction method
CN211172565U (en) A ram for argil brick facade
CN103255872A (en) Hollow building block
CN107586068A (en) A kind of construction method of column concrete and concrete column

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant