CN102116061A - Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure - Google Patents
Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure Download PDFInfo
- Publication number
- CN102116061A CN102116061A CN2009102476577A CN200910247657A CN102116061A CN 102116061 A CN102116061 A CN 102116061A CN 2009102476577 A CN2009102476577 A CN 2009102476577A CN 200910247657 A CN200910247657 A CN 200910247657A CN 102116061 A CN102116061 A CN 102116061A
- Authority
- CN
- China
- Prior art keywords
- core
- wall
- masonry
- blocks
- core column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Retaining Walls (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
本发明涉及一种框架结构中填充墙芯柱、芯梁、砌块砌筑施工方法。包括以下步骤:施工准备工作、砌筑安装、同步检验、依据砌体墙面状况刮腻子;其中砌筑安装步骤中描述了芯柱、芯梁的施工方式,利用混凝土小型空心砌块的空心,代替构造柱圈、过梁模板,省去了模板施工带来的问题,施工中采用国家建筑标准图集的砼空心砌块、轻质实心砌块、U型砼砌块一起砌筑墙体,按预先设定的位置,将芯柱及芯梁钢筋按设计要求的规格数量植筋与原结构层连接,将砼空心砌块放入钢筋中,等砌体砂浆达到一定强度后,向孔洞浇注混凝土,与墙体形成牢固的整体,取得了非常理想的效果。不但取得了很好的经济效益,而且得到了广泛的社会好评。
The invention relates to a construction method for filling wall core columns, core beams and blocks in a frame structure. It includes the following steps: construction preparation, masonry installation, simultaneous inspection, and puttying according to the condition of the masonry wall surface; the construction method of core columns and core beams is described in the masonry installation steps, and the hollow of small concrete hollow blocks is used. Instead of structural column circles and lintel formwork, the problems caused by formwork construction are eliminated. During construction, concrete hollow blocks, lightweight solid blocks, and U-shaped concrete blocks from the National Building Standard Atlas are used to build walls together. According to the pre-set position, the steel bars of the core column and the core beam are connected with the original structural layer according to the specifications and quantities required by the design, and the concrete hollow blocks are placed in the steel bars. After the masonry mortar reaches a certain strength, it is poured into the hole. Concrete, forming a solid whole with the wall, achieved very desirable results. Not only has achieved good economic benefits, but also has been widely praised by the society.
Description
技术领域:Technical field:
本发明涉及一种房屋建造中的墙体施工方法。更具体地说涉及一种框架结构中填充墙芯柱、芯梁、砌块砌筑施工方法。The invention relates to a wall construction method in house construction. More specifically, it relates to a construction method for filling wall core columns, core beams and blocks in a frame structure.
背景技术:Background technique:
随着经济的发展、人们生活水平的提高,对建筑的要求越来越高,与日益紧缺土地资源的矛盾,工业厂房、商住用房的小高层、高层、超高层等框架剪力墙的建筑越来越多,从节能减排考虑,以及保护耕地为目的,禁用或限用粘土砖,加上轻质实心砌块重量轻、隔音及保温效果好、可加工性好等众多优点,作为填充墙,采用的越来越多。在现有技术中,采用轻质实心砌块存在的问题是:轻质实心砌块对圈梁构造柱设置要求更严格,根据抗震抗裂要求及墙体的长度、高度,需增加圈梁构造柱。其范围包括:墙体端部、转角处、十字交叉、丁字交叉处要设置构造柱。另外在门窗洞口四周,为保证门窗安装牢固,也需要采用加固墙体措施,增设过梁、压顶梁、构造柱等。With the development of the economy and the improvement of people's living standards, the requirements for buildings are getting higher and higher, and the contradiction with the increasingly scarce land resources, the small high-rise, high-rise, super high-rise and other frame shear walls of industrial plants There are more and more buildings. From the consideration of energy saving and emission reduction, as well as the purpose of protecting cultivated land, clay bricks are banned or restricted. In addition, lightweight solid blocks have many advantages such as light weight, good sound insulation and heat insulation effects, and good machinability. Filled walls are used more and more. In the prior art, the problem with the use of lightweight solid blocks is that the lightweight solid blocks have stricter requirements on the setting of ring beam structural columns, and the ring beam structure needs to be added according to the seismic and crack resistance requirements and the length and height of the wall. column. Its scope includes: structural columns should be set at the end of the wall, at the corner, at the cross, and at the T-shaped intersection. In addition, around the openings of doors and windows, in order to ensure that the doors and windows are installed firmly, it is also necessary to adopt measures to strengthen the wall, and add lintels, top beams, structural columns, etc.
增加圈梁构造柱的不足之处表现在:1)在砌体质量方面,构造柱圈梁的模板支设和加固,最容易造成墙体开裂甚至变形,影响整体性牢固性;圈梁构造柱也最容易造成涨模,影响墙面整体平整度垂直度;2)在施工工期方面,圈梁构造柱支模虽然用工不多,但多工序,人员多了窝工,少了时间比较长,影响总体进度;3)在施工安全方面,木工机械、用电、模板木枋易燃、交叉作业等不利因素多,安全隐患也就增加;4)在经济效益方面,圈梁构造柱支模人工费、机械费、材料费用等都增加了施工成本。需对现有的墙体施工工艺中传统的圈梁构造柱的施工方法进行改革和创新。The shortcomings of adding ring beam structural columns are as follows: 1) In terms of masonry quality, the formwork support and reinforcement of structural column ring beams are most likely to cause cracks or even deformation of the wall, which affects the overall firmness; ring beam structural columns It is also the most likely to cause mold expansion, which affects the overall flatness and verticality of the wall; 2) In terms of construction period, although the formwork of the ring beam structural column does not require much labor, but there are many processes, there are too many workers, and the time is relatively long. 3) In terms of construction safety, there are many unfavorable factors such as woodworking machinery, electricity consumption, flammable formwork beams, and cross operations, which will increase potential safety hazards; 4) In terms of economic benefits, the manual Fees, machinery costs, material costs, etc. have increased the construction cost. It is necessary to reform and innovate the construction method of the traditional ring beam construction column in the existing wall construction technology.
发明内容:Invention content:
本发明的目的是针对现有技术不足之处而提供一种改变传统的圈梁构造柱的施工方法、采用芯柱及芯梁的方式从根本上提高施工质量加快施工进度的框架结构中填充墙芯柱、芯梁、砌块砌筑施工方法。The object of the present invention is to provide a filling wall in a frame structure that changes the traditional construction method of ring-beam structural columns and uses core columns and core beams to fundamentally improve the construction quality and speed up the construction progress. Core column, core beam, block masonry construction method.
本发明的目的是通过以下措施来实现:一种框架结构中填充墙芯柱、芯梁、砌块砌筑施工方法,其特殊之处在于,包括以下步骤:The object of the present invention is to realize by following measure: a kind of filling wall core column, core beam, block masonry construction method in frame structure, its special feature is, comprise the following steps:
步骤1,施工准备工作:
①对砼空心砌块、轻质实心砌块、U型砼砌块验收,砌块尺寸偏差≤3mm,且无缺棱掉角;① For the acceptance of concrete hollow blocks, lightweight solid blocks, and U-shaped concrete blocks, the size deviation of the blocks is ≤ 3mm, and there are no missing edges and corners;
②清理基础表面,弹好砌块墙身墙边线、门窗洞口线,并设置芯柱、芯梁位置线;②Clean up the surface of the foundation, play the sidelines of the block walls, the opening lines of doors and windows, and set the position lines of core columns and core beams;
③在芯柱处植芯柱钢筋,芯柱截面大于90mm×120mm,芯柱内植筋为HPB235、HRB335级,钢筋≥2Φ12,芯梁截面大于90mm×150mm,钢筋≥4Φ12;③Put core column reinforcement at the core column, the cross section of the core column is greater than 90mm×120mm, the internal reinforcement of the core column is HPB235, HRB335 grade, the steel bar is ≥2Φ12, the core beam section is greater than 90mm×150mm, and the steel bar is ≥4Φ12;
④在柱、梁或现浇板上植与墙体连接的拉结筋,芯柱竖向钢筋贯穿墙身与芯梁和上下结构层连接;④ Plant tie bars connected to the wall on the column, beam or cast-in-place slab, and the vertical reinforcement of the core column penetrates the wall to connect with the core beam and the upper and lower structural layers;
步骤2,砌筑安装:
①首先砌筑芯柱底部第一皮砖,将砼空心砌块套入芯柱钢筋中,芯柱底部第一皮砖采用开口砌块或U型砌块,砌出清扫孔,砌体完成后,将孔心内部杂物及落地砂浆清扫干净并冲洗干净,浇注芯柱混凝土前封堵;① First build the first skin brick at the bottom of the core column, insert the concrete hollow block into the steel bar of the core column, use open blocks or U-shaped blocks for the first skin brick at the bottom of the core column, and build a cleaning hole. After the masonry is completed , clean and rinse the sundries and ground mortar inside the hole core, and seal it before pouring the concrete of the core column;
②与此同时墙体基础采用与轻质实心砌块相同厚度的页岩模数砖打底,第一皮页岩模数砖的砌筑与芯柱同步进行;②At the same time, the foundation of the wall is made of shale modular bricks with the same thickness as the lightweight solid blocks, and the first layer of shale modular bricks is built simultaneously with the core column;
③根据不同的部位对芯柱进行第二皮排砖,芯柱的砼空心砌块应对孔错缝搭砌,与页岩模数砖压槎搭接不应小于200,芯柱的砼砌块空心部分随砌随用砌筑砂浆填满捣实;③According to different parts, carry out the second skin row of bricks for the core column. The concrete hollow blocks of the core column should be built with holes and joints, and the overlap with the shale modular brick should not be less than 200. The concrete blocks of the core column The hollow part is filled and compacted with masonry mortar along with the masonry;
④继续砌筑,当页岩模数砖打底高度>30cm时用轻质实心砌块替代,砌筑时先砌芯柱砼块,再砌轻质实心砌块,组砌时按砌块不同控制砌筑砂浆或粘接剂的饱满度,两种材料压槎处,用砌筑砂浆把空洞灌满捣实,芯柱每天砌筑高度不宜超过1.8米,砌到门芯梁底时,暂时停止砌筑;④Continue to build. When the base height of shale modular bricks is > 30cm, replace them with lightweight solid blocks. When building masonry, first build core column concrete blocks, and then build lightweight solid blocks. When assembling, the blocks are different Control the fullness of the masonry mortar or adhesive. The place where the two materials are pressed, fill the cavity with masonry mortar and compact it. The daily height of the core column should not exceed 1.8 meters. stop building
⑤砌体砂浆强度达到1.0Mpa以上时可浇注芯柱混凝土,芯柱混凝土应连续浇注,用插入式振捣棒边浇灌边捣实,严禁灌到顶再振捣;⑤ When the strength of the masonry mortar reaches 1.0Mpa or more, the core column concrete can be poured, and the core column concrete should be continuously poured, and the plug-in vibrating rod is used to tamp while pouring, and it is strictly forbidden to vibrate after pouring to the top;
⑥门洞采用U型砖砌筑芯梁兼过梁,过梁处需用木枋等搭好支撑,与芯柱相交处,需将U型砖底部割掉,侧面留清扫孔,绑扎过梁4Φ14钢筋,所述过梁钢筋与芯柱钢筋焊接,完成后浇筑细石砼,当墙高超过4m时设置圈梁,圈梁按芯梁处置;⑥The door opening adopts U-shaped brick masonry to build the core beam and lintel. Reinforcing bar, the lintel reinforcing bar is welded with the core column reinforcing bar, and fine stone concrete is poured after completion, and ring beams are set when the wall height exceeds 4m, and the ring beams are disposed as core beams;
⑦芯梁砼浇注完可马上进行上部墙体的砌筑,砌筑方法同下部墙体,从芯柱钢筋顶把空心砼砌块套进钢筋内,剩最上两皮砖时,把钢筋搭接头绑好,再用U型砖砌到顶,其中最上一皮开口向侧面,用于浇注砼;⑦After pouring the concrete of the core beam, the upper wall can be built immediately. The masonry method is the same as that of the lower wall. Insert the hollow concrete block into the steel bar from the top of the core column steel bar. When the top two skin bricks are left, the steel bar is lapped. Tie it up, and then use U-shaped bricks to build it to the top, and the uppermost skin opens to the side for pouring concrete;
⑧对砌筑墙体长度超过40m,即设置3mm宽的伸缩缝,走廊等墙体长度较长部位每30m设置一道伸缩缝;⑧ For masonry walls with a length of more than 40m, an expansion joint with a width of 3mm shall be set, and an expansion joint shall be set every 30m at the longer part of the wall such as corridors;
步骤3,同步检验:
①砌体灰缝缝饱满度检查,饱满度>95%;① Check the fullness of masonry mortar joints, fullness > 95%;
②墙面垂直度、平整度偏差均在2mm以内;② The verticality and flatness deviation of the wall are within 2mm;
③芯柱、芯梁施工质量检查;③ Construction quality inspection of core columns and core beams;
④墙线走廊等部位均保证在同一直线上检查;④Wall lines, corridors and other parts are guaranteed to be inspected on the same straight line;
步骤4,依据砌体墙面状况刮腻子,腻子厚度为0.5~1mm,完成施工,验收。
所述步骤1①中砼空心砌块为2孔,规格有:390长X190厚X190高、190长X190厚X190高,强度大于MU10。The concrete hollow block in step 1① has 2 holes, and the specifications are: 390 long x 190 thick x 190 high, 190 long x 190 thick x 190 high, and the strength is greater than MU10.
所述步骤1①中轻质实心砌块为ALC轻质实心砌块。The lightweight solid block in step 1① is an ALC lightweight solid block.
所述步骤1①中U型砼砌块外形尺寸与砼空心砌块尺寸相同,强度大于MU10。In the step 1①, the U-shaped concrete block has the same size as the concrete hollow block, and its strength is greater than MU10.
所述步骤1②中砌块墙身墙边线砌体与结构梁采用墙线偏移法,偏移量10~20mm。In the step 1②, the wall line offset method is adopted for the block wall body, wall side line masonry and structural beam, and the offset amount is 10-20mm.
所述步骤1②中设置芯柱、芯梁位置为在墙体端部、墙体转角处、T字交叉处、十字交叉处、小于等于600宽的洞间墙、门边设芯柱,墙体长度大于5米时中间设芯柱,在门洞处设芯梁兼过梁,并在洞口处根据洞口宽度增加过梁配筋,当墙高超过4m时设置圈梁,圈梁按芯梁处置。In the step 1②, the positions of the core columns and the core beams are set at the end of the wall, at the corner of the wall, at the T-shaped intersection, at the intersection of the cross, at the wall between holes less than or equal to 600 wide, and at the edge of the door. When the length is greater than 5 meters, set a core column in the middle, set a core beam and a lintel at the door opening, and add lintel reinforcement at the opening according to the width of the opening. When the wall height exceeds 4m, set a ring beam, and the ring beam is treated as a core beam.
所述步骤2③中不同的部位对芯柱进行第二皮排砖指墙中设芯柱排砖、墙转角处芯柱排砖、小于等于600宽的洞间墙处芯柱排砖、墙T字交叉处芯柱排砖、墙十字交叉处芯柱排砖。Carrying out the second skin row of bricks on the core column in the different parts of the step 2③ refers to the core column row of bricks in the wall, the core column row of bricks at the corner of the wall, the core column row of bricks at the wall between the holes with a width of less than or equal to 600, and the wall T. Row bricks at the intersection of the word core column, and arrange bricks at the intersection of the wall and the core column.
所述步骤4中依据砌体墙面状况为砌体墙面吸附性强时应在刮涂腻子前对砌体墙面用底涂进行封闭。In the
与现有技术相比,采用本发明提出的框架结构中填充墙芯柱、芯梁、砌块砌筑施工方法,即采用芯柱、芯梁的方式,利用混凝土小型空心砌块的空心,代替构造柱圈、过梁模板,省去了模板施工带来的问题,达到了非常理想的效果。根据工程的实际特点,通过经设计师确认,将国家建筑标准设计图集05J102-1砼小型空心砌块墙体建筑构造,与实际采用的实心砌块,通过技术措施有效结合,按预先设定的位置,将所需规格的空心砖或U型砖与轻质实心砌块一起砌筑,按设计要求的规格数量,把钢筋放入砖的孔洞中,等砌体砂浆达到一定强度后,向孔洞浇注混凝土,与墙体形成牢固的整体,连接到结构面上。本发明与传统方法相比所具有的优点是:(1)提高质量:提高了墙体的平整度、垂直度质量,避免了抹灰层空鼓、开裂等质量问题,保证了装修质量。(2)缩短工期:免圈梁、构造柱支模、拆模等工期,无抹灰工序,直接进入下一道工序,很大程度上缩短装修工期。(3)节约成本:采用芯柱、芯梁、砌块组合砌筑技术,节约圈梁、构造柱支模工序的人工、材料、机械等成本的85%,同时带来砌体无抹灰技术直接节约抹灰工序的人工、材料、机械等成本。本发明对新技术、新材料的应用,不但取得了很好的经济效益而且得到了广泛的社会好评。墙体质量明显改善,无抹灰技术直接节约了大量的水泥、黄沙、粘土等资源,在工期紧张的时刻大大缩短了工期,节省经费支出,提高工程质量,推广使用具有显著的综合效益。Compared with the prior art, the construction method of filling wall core columns, core beams and blocks in the frame structure proposed by the present invention is adopted, that is, the method of core columns and core beams is adopted, and the hollow of small concrete hollow blocks is used to replace Constructing column rings and lintel formwork eliminates the problems caused by formwork construction and achieves very ideal results. According to the actual characteristics of the project, after confirmation by the designer, the national building standard design atlas 05J102-1 concrete small hollow block wall building structure is effectively combined with the actual solid block through technical measures, according to the preset Place hollow bricks or U-shaped bricks of required specifications together with lightweight solid blocks, put steel bars into the holes of the bricks according to the specifications and quantities required by the design, and when the masonry mortar reaches a certain Concrete is poured to form a solid integral body with the wall and attached to the structural face. Compared with the traditional method, the present invention has the following advantages: (1) Improvement of quality: the flatness and verticality quality of the wall are improved, quality problems such as hollowing and cracking of the plastering layer are avoided, and the decoration quality is guaranteed. (2) Shorten the construction period: free from the construction period of ring beams, structural column formwork, formwork removal, etc., no plastering process, directly enter the next process, greatly shortening the decoration period. (3) Saving costs: adopting core column, core beam, and block combined masonry technology can save 85% of the cost of labor, materials, and machinery in the formwork support process of ring beams and structural columns, and at the same time bring masonry without plastering technology Directly save labor, material, machinery and other costs in the plastering process. The application of the present invention to new technologies and new materials not only achieves good economic benefits but also has been widely praised by the society. The quality of the wall is significantly improved, and the no-plastering technology directly saves a lot of resources such as cement, yellow sand, and clay. When the construction period is tight, the construction period is greatly shortened, the cost is saved, the project quality is improved, and the promotion and use have significant comprehensive benefits.
附图说明:Description of drawings:
图1为本发明砌体与原结构柱相对位移示意图。Fig. 1 is a schematic diagram of the relative displacement between the masonry of the present invention and the original structural column.
图2为本发明砌体与原结构梁相对位移示意图。Fig. 2 is a schematic diagram of the relative displacement between the masonry of the present invention and the original structural beam.
图3为本发明卫生间芯柱结构布置示意图。Fig. 3 is a schematic diagram of the structure layout of the bathroom core column according to the present invention.
图4为本发明植墙拉筋与芯柱钢筋、芯梁钢筋连接示意图。Fig. 4 is a schematic diagram of the connection between wall-planting ties and core column steel bars and core beam steel bars according to the present invention.
图5为本发明墙中设芯柱排砖示意图,a为第一皮、b为第二皮。Fig. 5 is a schematic diagram of arranging bricks with core columns in the wall of the present invention, where a is the first skin and b is the second skin.
图6为本发明墙转角处芯柱排砖示意图,a为第一皮、b为第二皮。Fig. 6 is a schematic diagram of arranging bricks of the core column at the corner of the wall of the present invention, a is the first skin, and b is the second skin.
图7为本发明小于等于600宽的洞间墙处芯柱排砖示意图,a为第一皮、b为第二皮。Fig. 7 is a schematic diagram of the arrangement of core columns at the inter-wall of the present invention with a width of less than or equal to 600, where a is the first skin and b is the second skin.
图8为本发明墙T字交叉处芯柱排砖示意图,a为第一皮、b为第二皮。Fig. 8 is a schematic diagram of the arrangement of core columns at the T-shaped intersection of the wall according to the present invention, where a is the first skin and b is the second skin.
图9为本发明墙十字交叉处芯柱排砖示意图,a为第一皮、b为第二皮。Fig. 9 is a schematic diagram of the row of bricks in the core column at the intersection of the wall of the present invention, where a is the first skin and b is the second skin.
图10为本发明墙体页岩模数砖打底示意图。Fig. 10 is a schematic diagram of the base of the wall shale modulus brick of the present invention.
图11为本发明墙体门框砌筑示意图。Fig. 11 is a schematic diagram of wall and door frame masonry of the present invention.
具体实施方式:Detailed ways:
下面结合附图对一种框架结构中填充墙芯柱、芯梁、砌块砌筑施工方法作如下详细说明,其步骤为:Below in conjunction with the accompanying drawings, the construction method of filling wall core columns, core beams, and blocks in a frame structure is described in detail as follows, and the steps are:
步骤1,施工准备工作:
①对砼空心砌块、轻质实心砌块、U型砼砌块验收,砌块尺寸偏差≤3mm,且无缺棱掉角。砌块成品必须有出厂合格证或试验合格报告单,据现场施工顺序,将砌块先后顺序分批、分规格堆放整齐,加强成品保护措施;① For the acceptance of concrete hollow blocks, lightweight solid blocks, and U-shaped concrete blocks, the size deviation of the blocks is ≤ 3mm, and there are no missing edges or corners. The finished blocks must have a factory certificate or a test report. According to the construction sequence on site, the blocks are stacked neatly in batches and specifications, and the protection measures for the finished products are strengthened;
②清理基础表面,弹好砌块墙身墙边线、门窗洞口线,并设置芯柱位置线。砌筑前,基础表面弹好墙身轴线、墙边线,为避免因结构尺寸偏差面而使整面墙抹灰,故砌块墙身墙边线砌体与结构梁采用墙线偏移法,偏移量在10~20mm。图1为本发明砌体与原结构柱相对位移示意图。图中1-砼结构柱、2-砌块墙体、3-相对偏移量。图2为本发明砌体与原结构梁相对位移示意图。图中1-砼结构梁、2-砌块墙体、3-相对偏移量。清理包括与砌体相连的板表面、砌筑部位基础或楼板等的灰渣,杂物清除干净,并浇水湿润。根据设计图纸各部位尺寸及平面、立面图绘制砌块排列图,在现场排砖撂底,使组砌方法合理,便于操作。②Clean the surface of the foundation, play the sidelines of the block walls, the opening lines of doors and windows, and set the position lines of the core columns. Before the masonry, the surface of the foundation is well sprung to the axis of the wall body and the edge of the wall. In order to avoid the plastering of the entire wall due to the deviation of the structural size, the masonry of the body of the block wall and the edge of the wall and the structural beam adopt the wall line offset method. The displacement is 10-20mm. Fig. 1 is a schematic diagram of the relative displacement between the masonry of the present invention and the original structural column. In the figure, 1-concrete structural column, 2-block wall, 3-relative offset. Fig. 2 is a schematic diagram of the relative displacement between the masonry of the present invention and the original structural beam. In the figure, 1-concrete structural beam, 2-block wall, 3-relative offset. Clean up the ash and slag including the surface of the slab connected with the masonry, the foundation of the masonry part or the floor slab, etc., remove the sundries, and water and moisten them. According to the size of each part of the design drawings and the plan and elevation drawings, the block arrangement diagram is drawn, and the bricks are arranged on site to make the assembly method reasonable and easy to operate.
③在芯柱处植芯柱钢筋,芯柱截面大于90mm×120mm,芯柱内植筋为HPB235、HRB335级,钢筋≥2Φ12,芯梁截面大于90mm×150mm,钢筋≥4Φ12;所述设置芯柱、芯梁位置为在墙体端部、墙体转角处、T字交叉处、十字交叉处、小于等于600宽的洞间墙、门边设芯柱,墙体长度大于5米时中间设芯柱,在门洞处设芯梁兼过梁,并在洞口处根据洞口宽度增加芯梁配筋,墙体高度大于4米时设置圈梁,圈梁按芯梁处置。图3为本发明卫生间芯柱结构布置示意图。图中1-卫生间、2-芯柱、3-门。图中涂黑部分均为芯柱位置,芯柱的钢筋应与结构梁、板相连。③Put core column reinforcement at the core column, the section of the core column is greater than 90mm×120mm, the internal reinforcement of the core column is HPB235, HRB335 grade, the steel bar is ≥2Φ12, the core beam section is greater than 90mm×150mm, and the steel bar is ≥4Φ12; set the core column , The position of the core beam is to set the core column at the end of the wall, the corner of the wall, the T-shaped intersection, the cross intersection, the wall between the holes less than or equal to 600 wide, and the door side, and set the core in the middle when the wall length is greater than 5 meters For the column, set the core beam and lintel at the door opening, and increase the core beam reinforcement at the opening according to the width of the opening. When the wall height is greater than 4 meters, set the ring beam, and the ring beam is treated as the core beam. Fig. 3 is a schematic diagram of the structure layout of the bathroom core column according to the present invention. In the figure, 1-toilet, 2-stem, 3-door. The blackened part in the figure is the position of the core column, and the reinforcement of the core column should be connected with the structural beam and plate.
④在柱、梁或现浇板上植与墙体连接的拉结筋,芯柱竖向钢筋贯穿墙身与芯梁和上下结构层连接。图4为本发明植墙拉筋与芯柱钢筋、芯梁钢筋连接示意图。图中1-下部板顶、2-上层板底、3-芯柱钢筋、4-芯柱、5-过梁、6-过梁钢筋、7-砼空心砌块、8-轻质实心砌块。图中芯柱钢筋分上下两段分别植在下部板顶和上层板底,留出搭接长度,搭接放在墙顶,自检合格后报监理检查,做好隐蔽工程验收记录。④ Plant tie bars connected to the wall on the columns, beams or cast-in-place slabs, and the vertical reinforcement of the core column penetrates the wall to connect with the core beam and the upper and lower structural layers. Fig. 4 is a schematic diagram of the connection between wall-planting ties and core column steel bars and core beam steel bars according to the present invention. In the figure, 1-top of the lower slab, 2-bottom of the upper slab, 3-core column reinforcement, 4-core column, 5-lintel, 6-lintel reinforcement, 7-concrete hollow block, 8-lightweight solid block . In the figure, the core column steel bar is divided into upper and lower sections and planted on the top of the lower slab and the bottom of the upper slab respectively, leaving the length of the lap joint, and the lap joint is placed on the top of the wall. After passing the self-inspection, report to the supervisor for inspection, and make a record of the concealed project acceptance.
步骤2,砌筑安装:
①首先砌筑芯柱底部第一皮砖,将砼空心砌块套入芯柱钢筋中,芯柱底部第一皮砖采用开口砌块或U型砌块,砌出清扫孔,砌体完成后,将孔心内部杂物及落地砂浆清扫干净并冲洗干净,浇注芯柱混凝土前封堵。砂浆应采用粘聚性和保水性好的砂浆,强度等级不低于Mb7.5。① First build the first skin brick at the bottom of the core column, insert the concrete hollow block into the steel bar of the core column, use open blocks or U-shaped blocks for the first skin brick at the bottom of the core column, and build a cleaning hole. After the masonry is completed , Clean and rinse the sundries and ground mortar inside the hole core, and seal it before pouring the core column concrete. The mortar should be mortar with good cohesion and water retention, and the strength grade should not be lower than Mb7.5.
②与此同时墙体基础采用与轻质实心砌块相同厚度的页岩模数砖打底,第一皮页岩模数砖的砌筑与芯柱同步进行。②At the same time, the foundation of the wall is made of shale modular bricks with the same thickness as the lightweight solid blocks, and the first layer of shale modular bricks is built simultaneously with the core column.
③根据不同的部位对芯柱进行第二皮排砖,芯柱的砼空心砌块应对孔错缝搭砌,与页岩模数砖压槎搭接不应小于200,芯柱的砼砌块空心部分随砌随用砌筑砂浆填满捣实;所述不同部位为指墙体中部、墙体转角处、小于等于600宽的洞间墙、T字交叉处、十字交叉处,这些部位芯柱排砖遵循错缝搭砌的原则,如图5~图9所示,图中1-砼空心砌块、2-轻质实心砌块、3-芯柱钢筋、4-混凝土Cb20、5-砌筑砂浆。图中4为砼空心砌块含芯柱钢筋的空心部分浇注混凝土。③According to different parts, carry out the second skin row of bricks for the core column. The concrete hollow blocks of the core column should be built with holes and joints, and the overlap with the shale modular brick should not be less than 200. The concrete blocks of the core column The hollow part is filled and compacted with masonry mortar; the different parts refer to the middle part of the wall, the corner of the wall, the wall between holes less than or equal to 600 wide, the T-shaped intersection, and the cross intersection. The column row of bricks follows the principle of staggered joints, as shown in Figures 5 to 9, in which 1-concrete hollow blocks, 2-light solid blocks, 3-core column reinforcement, 4-concrete Cb20, 5- Masonry mortar. 4 among the figure is the pouring of concrete in the hollow part of the concrete hollow block containing the steel bar of the core column.
④继续砌筑打底,如图10本发明墙体页岩模数砖打底示意图。图中1-地面结构、2-芯柱、3-芯柱植筋、4-页岩模数砖、5-调整间隙。墙体砌筑时应根据门洞高度、砌块尺寸调整打底高度,使门洞顶部正好位于整皮砖位置,便于设置过梁。图中5为页岩模数砖与地面结构之间的间隙,该间隙可调整。当页岩模数砖打底高度>30cm时用轻质实心砌块替代,砌筑时先砌芯柱砼块,再砌轻质实心砌块,组砌时按砌块不同控制砌筑砂浆或粘接剂的饱满度,砌体的水平灰缝饱满度是影响砌体强度的一个重要因素,砂浆或粘结剂不饱满会使砖局部受压或受弯,降低砌体的抗压强度。在两种材料压槎处,用砌筑砂浆把空洞灌满捣实,芯柱每天砌筑高度不宜超过1.8米,这样可保证芯柱的强度。砌到门芯梁底时,暂时停止砌筑。④Continue to lay the bottom by masonry, as shown in Figure 10, the schematic diagram of the bottom of the wall shale modulus brick of the present invention. In the figure 1- ground structure, 2- core column, 3- core column planting reinforcement, 4- shale modulus brick, 5- adjustment gap. When building the wall, the base height should be adjusted according to the height of the door opening and the size of the blocks, so that the top of the door opening is just at the position of the whole skin brick, which is convenient for setting the lintel. 5 in the figure is the gap between the shale modulus brick and the ground structure, and the gap can be adjusted. When the base height of shale modular bricks is greater than 30cm, it is replaced by lightweight solid blocks. When building masonry, the core column concrete block is firstly built, and then the light solid blocks are built. The fullness of the adhesive and the fullness of the horizontal mortar joints of the masonry are an important factor affecting the strength of the masonry. If the mortar or adhesive is not full, the bricks will be partially compressed or bent, which will reduce the compressive strength of the masonry. At the place where the two materials are pressed, fill the cavity with masonry mortar and compact it. The daily masonry height of the core column should not exceed 1.8 meters, so as to ensure the strength of the core column. When it reaches the bottom of the door core beam, temporarily stop the masonry.
⑤砌体砂浆强度达到1.0Mpa以上时可浇注芯柱混凝土,混凝土应采用高流态、和易性好的细石混凝土,强度等级不应低于Cb20。芯柱混凝土应连续浇注,用插入式振捣棒边浇灌边捣实,严禁灌到顶再振捣。⑤ When the strength of masonry mortar reaches 1.0Mpa or more, core column concrete can be poured. The concrete should be fine stone concrete with high fluidity and good workability, and the strength grade should not be lower than Cb20. The concrete of the core column shall be poured continuously, and shall be compacted while pouring with a plug-in vibrating rod, and it is strictly forbidden to vibrate after pouring to the top.
⑥门洞采用U型砖砌筑芯梁兼过梁,过梁处需用木枋等搭好支撑,以便把U型砖平铺过去,等砼达到一定强度后方可拆除。与芯柱相交处,需将U型砖底部割掉,以保证钢筋混凝土的连贯,U型砖侧面留清扫孔,绑扎过梁4Φ14钢筋,所述过梁钢筋与芯柱钢筋焊接,完成后浇筑细石砼,当墙高超过4m时设置圈梁,圈梁按芯梁处置。图11为本发明墙体门框砌筑示意图。图中1-芯柱、2-芯柱钢筋、3-芯梁、4-芯梁钢筋、5-木枋。利用芯梁兼过梁替代圈梁,操作方便,减少工序并有效保证质量。⑥U-shaped bricks are used to build the core beam and lintel in the door opening, and wooden joist should be used to support the lintel so that the U-shaped bricks can be laid flat, and the concrete can be removed after reaching a certain strength. At the intersection with the core column, the bottom of the U-shaped brick needs to be cut off to ensure the continuity of the reinforced concrete. Cleaning holes are left on the side of the U-shaped brick, and 4Φ14 steel bars are bound to the lintel. For fine stone concrete, set ring beams when the wall height exceeds 4m, and the ring beams shall be treated as core beams. Fig. 11 is a schematic diagram of wall and door frame masonry of the present invention. In the figure, 1-core column, 2-core column reinforcement, 3-core beam, 4-core beam reinforcement, 5-wood beam. The core beam and lintel are used to replace the ring beam, which is easy to operate, reduces the process and effectively guarantees the quality.
⑦芯梁砼浇注完可马上进行上部墙体的砌筑,砌筑方法同下部墙体,从芯柱钢筋顶把空心砼砌块套进钢筋内,剩最上两皮砖时,把钢筋搭接头绑好,再用U型砖砌到顶,其中最上一皮开口向侧面,用于浇注砼。⑦After pouring the concrete of the core beam, the upper wall can be built immediately. The masonry method is the same as that of the lower wall. Insert the hollow concrete block into the steel bar from the top of the core column steel bar. When the top two skin bricks are left, the steel bar is lapped. Tie it well, and then use U-shaped bricks to build it to the top, and the uppermost skin opens to the side for pouring concrete.
⑧对砌筑墙体长度超过40m,即设置3mm宽的伸缩缝,走廊等墙体长度较长部位每30m设置一道伸缩缝。⑧ For masonry walls with a length of more than 40m, an expansion joint with a width of 3mm shall be set, and an expansion joint shall be set every 30m at the longer part of the wall such as corridors.
步骤3,同步检验:
①砌体灰缝饱满度检查,饱满度>95%。① Check the fullness of the masonry mortar joints, and the fullness is >95%.
②墙面垂直度、平整度偏差均在2mm以内。墙面平整度、垂直度是直接影响墙面是否需要抹灰的关键因素。可采用红外线标线仪、水平垂直度靠尺、角尺、红外线测距仪等,随时对偏差校正,确保在允许偏差范围内。② The verticality and flatness deviation of the wall are within 2mm. The flatness and verticality of the wall are the key factors that directly affect whether the wall needs to be plastered. Infrared line markers, horizontal and vertical rulers, angle rulers, infrared rangefinders, etc. can be used to correct the deviation at any time to ensure that it is within the allowable deviation range.
③芯柱、芯梁施工质量检查。③ Construction quality inspection of core columns and core beams.
④墙线走廊等部位均保证在同一直线上检查。④Wall lines, corridors and other parts are guaranteed to be inspected on the same straight line.
步骤4,依据砌体墙面状况涂刮腻子,腻子厚度为0.5~1mm,完成施工,验收。所述依据砌体墙面状况为吸附性强的砌体墙面时应在刮涂腻子前对砌体墙面用底涂进行封闭。涂刮时:应掌握好刮涂时工具的倾斜度,用力均匀,以保证腻子饱满;不要过多地往返刮涂,以免出现卷皮、脱落或将腻子中的胶料挤出,封住表面不易干燥。
应用例:Application example:
南京市某医院工程总建筑面积为22.5万m2,其中地下建筑面积4.7万m2,地上建筑面积17.8m2,自北向南依次由医技楼、住院楼及门诊楼组成。住院楼地上14层,建筑高度56.8m;医技楼地上六层,建筑高度25.5m;门诊楼地上5层,建筑高度21.0m;均设2层地下室。本工程中ALC轻质实心砌块及陶粒空心砌块墙体总工程量约为25000m3,抹灰面积达到267000m2,施工面积较大,若采用砌体正常砌筑及抹灰,人工、材料消耗量巨大,既增加成本又容易造成抹灰层空鼓、开裂等质量问题。效果分析如下:The total construction area of a hospital project in Nanjing is 225,000 m 2 , of which the underground construction area is 47,000 m 2 and the ground construction area is 17.8 m 2 . From north to south, it consists of medical technology building, inpatient building and outpatient building. The inpatient building has 14 floors above ground and a building height of 56.8m; the medical technology building has 6 floors above ground and a building height of 25.5m; the outpatient building has 5 floors above ground and a building height of 21.0m; both have 2 floors of basement. In this project, the total construction volume of ALC lightweight solid blocks and ceramsite hollow block walls is about 25,000m 3 , and the plastering area reaches 267,000m 2 . The construction area is relatively large. If normal masonry and plastering are used, manual, The material consumption is huge, which not only increases the cost but also easily causes quality problems such as hollowing and cracking of the plastering layer. The effect analysis is as follows:
1、在砌体质量方面:避免了构造柱圈梁易涨模的质量通病,避免了砼剔凿问题,甚至使墙体质量达到不抹灰而直接刮腻子的效果。为今后的创优工作打下了基础。1. In terms of masonry quality: it avoids the common quality problem that the structural column ring beam is easy to expand the mold, avoids the problem of concrete picking and chiseling, and even makes the wall quality achieve the effect of directly scraping putty without plastering. It laid the foundation for future excellence work.
2、在施工工期方面:相当于去掉了模板支设的工序,尤其是芯梁砼浇注完,即可进行上部砌体的施工。提高功效20%,本工程砌体共计2.55万立方米,正常工期150天,实际用了120天,缩短工期30天,为工程提前竣交创造了条件。2. In terms of construction period: it is equivalent to removing the process of formwork support, especially after the core beam concrete is poured, the construction of the upper part of the masonry can be carried out. Improve the efficiency by 20%. The total masonry of this project is 25,500 cubic meters. The normal construction period is 150 days, but the actual construction period is 120 days. The construction period is shortened by 30 days, which creates conditions for the early completion of the project.
3、在施工安全方面:减少了一道工序,减少了交叉作业,减少了模板木枋易燃的隐患。减少了木工用电带来的触电隐患,减少了木工机械造成的机械伤害隐患等,为安全文明工地的创建提供了保障。3. In terms of construction safety: one process is reduced, cross operations are reduced, and the hidden danger of formwork timbers being flammable is reduced. It reduces the hidden danger of electric shock caused by woodworking electricity, reduces the hidden danger of mechanical injury caused by woodworking machinery, etc., and provides a guarantee for the creation of a safe and civilized construction site.
4、在经济效益方面:本工程共2.55万立方砌体,采用了芯柱芯梁2380立方,节省模板支设面积32000平方,每平方人工机械材料费用为48元,计153.6万元。增加空心砖2380立方,每立方人工机械材料费390元,共92.8万,实际节约60.8万元。还不计墙体质量达到不抹灰程度,减少的抹灰费用,减少30天工期带来减少的项目管理费用,该施工技术达到了良好效果,取得了很好的经济效益和社会效益。4. In terms of economic benefits: This project has a total of 25,500 cubic meters of masonry, using 2,380 cubic meters of core columns and core beams, saving 32,000 square meters of formwork support area, and the cost of artificial mechanical materials per square meter is 48 yuan, totaling 1.536 million yuan. Add 2380 cubic meters of hollow bricks, 390 yuan per cubic meter of artificial mechanical materials, a total of 928,000 yuan, and an actual saving of 608,000 yuan. Not counting the quality of the wall without plastering, the reduced plastering costs, and the reduced project management costs brought about by the reduction of the 30-day construction period, the construction technology has achieved good results and achieved good economic and social benefits.
上述实施例并不构成对本发明的限制,凡采用等同替换或等效变换的形式所获得的技术方案,均落在本发明的保护范围之内。The above embodiments do not constitute a limitation to the present invention, and all technical solutions obtained in the form of equivalent replacement or equivalent transformation fall within the protection scope of the present invention.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 200910247657 CN102116061B (en) | 2009-12-30 | 2009-12-30 | Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN 200910247657 CN102116061B (en) | 2009-12-30 | 2009-12-30 | Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102116061A true CN102116061A (en) | 2011-07-06 |
| CN102116061B CN102116061B (en) | 2013-03-06 |
Family
ID=44214973
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN 200910247657 Active CN102116061B (en) | 2009-12-30 | 2009-12-30 | Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102116061B (en) |
Cited By (25)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102520457A (en) * | 2011-11-30 | 2012-06-27 | 中国神华能源股份有限公司 | Coal finding method of satellite remote sensor in deep multilayer coverage area |
| CN102767290A (en) * | 2012-08-07 | 2012-11-07 | 天津住宅集团建设工程总承包有限公司 | Construction method for retention position of constructional column of self-insulation sand aerated concrete block exterior wall |
| CN103015563A (en) * | 2012-12-18 | 2013-04-03 | 北京工业大学 | Outer-block inner-masonry building structure system |
| CN103410332A (en) * | 2013-08-07 | 2013-11-27 | 中国核工业第二二建设有限公司 | Concrete hollow block reinforced wall construction technology |
| CN103437562A (en) * | 2013-08-20 | 2013-12-11 | 钟粤 | A construction method for a hollow wall |
| CN103469939A (en) * | 2013-09-24 | 2013-12-25 | 中国建筑第二工程局有限公司 | Masonry infilled wall and main body flexible connection anti-seismic structure and construction method thereof |
| CN103821253A (en) * | 2014-02-28 | 2014-05-28 | 浙江海天建设集团有限公司 | Constructing technique for aerated concrete block filler wall |
| CN103821252A (en) * | 2014-02-28 | 2014-05-28 | 浙江海天建设集团有限公司 | Process for constructing aerated concrete building block infilled wall through membrane maintenance technology |
| CN103883022A (en) * | 2014-03-20 | 2014-06-25 | 中国建筑第二工程局有限公司 | Earthquake-resistant, sound-insulating and crack-resistant integrated structure for inner wall and outer wall of enclosure structure and construction method thereof |
| CN104141353A (en) * | 2013-11-05 | 2014-11-12 | 中国建筑第四工程局有限公司 | Construction method and structure of non-load-bearing thin wall |
| CN104831831A (en) * | 2015-05-07 | 2015-08-12 | 浙江省建工集团有限责任公司 | Foam concrete-large-porosity shale brick outer wall and self heat insulation system construction method |
| CN105464382A (en) * | 2014-09-03 | 2016-04-06 | 中国建筑第四工程局有限公司 | Building block and constructional column integrated construction method and constructional column formwork building block |
| CN106049866A (en) * | 2016-06-08 | 2016-10-26 | 韦刚 | Method for blocking holes of hollow cement bricks and product |
| CN106592810A (en) * | 2016-12-08 | 2017-04-26 | 陕西建工第三建设集团有限公司 | Construction method of wrapping fair brick masonry for concrete structure of historic building |
| CN106948600A (en) * | 2017-03-03 | 2017-07-14 | 重庆大学 | Core column type is without the slurry accurate block masonry of air entrained concrete and its construction method |
| CN108166679A (en) * | 2018-03-01 | 2018-06-15 | 中建八局第建设有限公司 | A kind of concrete lintel constructing structure and its construction method |
| CN108547450A (en) * | 2018-04-25 | 2018-09-18 | 中建八局第三建设有限公司 | A kind of self-insulating brick wall construction method for exempting from formwork |
| CN108612261A (en) * | 2018-05-11 | 2018-10-02 | 上海宝冶集团有限公司 | The construction method of reinforcement masonry lintel |
| CN110952785A (en) * | 2019-12-16 | 2020-04-03 | 中铁四局集团有限公司 | A kind of wall masonry construction technology |
| CN111561103A (en) * | 2020-04-24 | 2020-08-21 | 中国建筑第五工程局有限公司 | BM interlocking building block constructional column, tie beam structure and construction method thereof |
| CN112482746A (en) * | 2020-11-12 | 2021-03-12 | 重庆中科建设(集团)有限公司 | Construction method of combined formwork |
| CN112523393A (en) * | 2020-11-26 | 2021-03-19 | 浙江世润建创科技发展有限公司 | Circular concrete column and masonry filler wall constructional column connecting section and construction method |
| CN112906100A (en) * | 2021-01-15 | 2021-06-04 | 珠海新势力创建筑设计有限公司 | Method and device for automatically generating constructional column based on Revit platform |
| CN112982735A (en) * | 2021-02-25 | 2021-06-18 | 中建八局第四建设有限公司 | Construction method for assembling integral ring beam, lintel, waist beam and constructional column |
| CN116220244A (en) * | 2023-04-10 | 2023-06-06 | 中国二十二冶集团有限公司 | Construction method of thermal insulation exterior wall structure with window sill opening |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109629667A (en) * | 2019-01-29 | 2019-04-16 | 中国建筑局(集团)有限公司 | Fireproof roller shutter structure and construction method based on BIM and meeting high-grade fireproof requirements |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1277298A (en) * | 2000-05-24 | 2000-12-20 | 宋志成 | Hollow reinforced concrete module and its construction process |
| CN2522488Y (en) * | 2001-06-19 | 2002-11-27 | 程国伟 | Combined wall comprising transitional concrete blocks |
| CN1619074A (en) * | 2004-11-24 | 2005-05-25 | 东南大学 | Small block masonry shear wall structure with frame fly ash |
| CN101429803A (en) * | 2008-12-05 | 2009-05-13 | 重庆大学 | Construction column used for masonry structure and its production method and special precast segment |
| US20090260312A1 (en) * | 2006-05-24 | 2009-10-22 | Yan Sup Lee | Fix Holder, Steel Wire, Bricks, and Bricks Walls Reinforcement Method Thereby |
-
2009
- 2009-12-30 CN CN 200910247657 patent/CN102116061B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1277298A (en) * | 2000-05-24 | 2000-12-20 | 宋志成 | Hollow reinforced concrete module and its construction process |
| CN2522488Y (en) * | 2001-06-19 | 2002-11-27 | 程国伟 | Combined wall comprising transitional concrete blocks |
| CN1619074A (en) * | 2004-11-24 | 2005-05-25 | 东南大学 | Small block masonry shear wall structure with frame fly ash |
| US20090260312A1 (en) * | 2006-05-24 | 2009-10-22 | Yan Sup Lee | Fix Holder, Steel Wire, Bricks, and Bricks Walls Reinforcement Method Thereby |
| CN101429803A (en) * | 2008-12-05 | 2009-05-13 | 重庆大学 | Construction column used for masonry structure and its production method and special precast segment |
Non-Patent Citations (1)
| Title |
|---|
| 钟宏志: "浅论混凝土空心砌块建筑施工技术", 《建材与装饰》 * |
Cited By (35)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN102520457A (en) * | 2011-11-30 | 2012-06-27 | 中国神华能源股份有限公司 | Coal finding method of satellite remote sensor in deep multilayer coverage area |
| CN102767290A (en) * | 2012-08-07 | 2012-11-07 | 天津住宅集团建设工程总承包有限公司 | Construction method for retention position of constructional column of self-insulation sand aerated concrete block exterior wall |
| CN102767290B (en) * | 2012-08-07 | 2014-11-12 | 天津住宅集团建设工程总承包有限公司 | Construction method for retention position of constructional column of self-insulation sand aerated concrete block exterior wall |
| CN103015563B (en) * | 2012-12-18 | 2014-11-05 | 北京工业大学 | Outer-block inner-masonry building structure system |
| CN103015563A (en) * | 2012-12-18 | 2013-04-03 | 北京工业大学 | Outer-block inner-masonry building structure system |
| CN103410332A (en) * | 2013-08-07 | 2013-11-27 | 中国核工业第二二建设有限公司 | Concrete hollow block reinforced wall construction technology |
| CN103410332B (en) * | 2013-08-07 | 2015-09-02 | 中国核工业第二二建设有限公司 | A kind of concrete hollow block reinforcement wall construction technology |
| CN103437562A (en) * | 2013-08-20 | 2013-12-11 | 钟粤 | A construction method for a hollow wall |
| CN103437562B (en) * | 2013-08-20 | 2016-01-20 | 钟粤 | A kind of building method of hollow wall |
| CN103469939A (en) * | 2013-09-24 | 2013-12-25 | 中国建筑第二工程局有限公司 | Masonry infilled wall and main body flexible connection anti-seismic structure and construction method thereof |
| CN104141353B (en) * | 2013-11-05 | 2017-01-04 | 中国建筑第四工程局有限公司 | The construction method of a kind of non-bearing thin-wall and structure |
| CN104141353A (en) * | 2013-11-05 | 2014-11-12 | 中国建筑第四工程局有限公司 | Construction method and structure of non-load-bearing thin wall |
| CN103821253A (en) * | 2014-02-28 | 2014-05-28 | 浙江海天建设集团有限公司 | Constructing technique for aerated concrete block filler wall |
| CN103821252A (en) * | 2014-02-28 | 2014-05-28 | 浙江海天建设集团有限公司 | Process for constructing aerated concrete building block infilled wall through membrane maintenance technology |
| CN103883022A (en) * | 2014-03-20 | 2014-06-25 | 中国建筑第二工程局有限公司 | Earthquake-resistant, sound-insulating and crack-resistant integrated structure for inner wall and outer wall of enclosure structure and construction method thereof |
| CN105464382A (en) * | 2014-09-03 | 2016-04-06 | 中国建筑第四工程局有限公司 | Building block and constructional column integrated construction method and constructional column formwork building block |
| CN104831831A (en) * | 2015-05-07 | 2015-08-12 | 浙江省建工集团有限责任公司 | Foam concrete-large-porosity shale brick outer wall and self heat insulation system construction method |
| CN104831831B (en) * | 2015-05-07 | 2017-02-01 | 浙江省建工集团有限责任公司 | Foam concrete-large-porosity shale brick outer wall and self heat insulation system construction method |
| CN106049866A (en) * | 2016-06-08 | 2016-10-26 | 韦刚 | Method for blocking holes of hollow cement bricks and product |
| CN106592810B (en) * | 2016-12-08 | 2018-09-21 | 陕西建工第三建设集团有限公司 | A kind of ancient building concrete structure outsourcing clear water masonry construction method |
| CN106592810A (en) * | 2016-12-08 | 2017-04-26 | 陕西建工第三建设集团有限公司 | Construction method of wrapping fair brick masonry for concrete structure of historic building |
| CN106948600A (en) * | 2017-03-03 | 2017-07-14 | 重庆大学 | Core column type is without the slurry accurate block masonry of air entrained concrete and its construction method |
| CN108166679A (en) * | 2018-03-01 | 2018-06-15 | 中建八局第建设有限公司 | A kind of concrete lintel constructing structure and its construction method |
| CN108547450A (en) * | 2018-04-25 | 2018-09-18 | 中建八局第三建设有限公司 | A kind of self-insulating brick wall construction method for exempting from formwork |
| CN108612261A (en) * | 2018-05-11 | 2018-10-02 | 上海宝冶集团有限公司 | The construction method of reinforcement masonry lintel |
| CN110952785A (en) * | 2019-12-16 | 2020-04-03 | 中铁四局集团有限公司 | A kind of wall masonry construction technology |
| CN111561103B (en) * | 2020-04-24 | 2024-05-14 | 中国建筑第五工程局有限公司 | BM interlocking building block constructional column, tie beam structure and construction method thereof |
| CN111561103A (en) * | 2020-04-24 | 2020-08-21 | 中国建筑第五工程局有限公司 | BM interlocking building block constructional column, tie beam structure and construction method thereof |
| CN112482746A (en) * | 2020-11-12 | 2021-03-12 | 重庆中科建设(集团)有限公司 | Construction method of combined formwork |
| CN112482746B (en) * | 2020-11-12 | 2022-01-18 | 重庆中科建设(集团)有限公司 | Construction method of combined formwork |
| CN112523393A (en) * | 2020-11-26 | 2021-03-19 | 浙江世润建创科技发展有限公司 | Circular concrete column and masonry filler wall constructional column connecting section and construction method |
| CN112906100A (en) * | 2021-01-15 | 2021-06-04 | 珠海新势力创建筑设计有限公司 | Method and device for automatically generating constructional column based on Revit platform |
| CN112982735A (en) * | 2021-02-25 | 2021-06-18 | 中建八局第四建设有限公司 | Construction method for assembling integral ring beam, lintel, waist beam and constructional column |
| CN116220244A (en) * | 2023-04-10 | 2023-06-06 | 中国二十二冶集团有限公司 | Construction method of thermal insulation exterior wall structure with window sill opening |
| CN116220244B (en) * | 2023-04-10 | 2025-09-26 | 中国二十二冶集团有限公司 | Construction method of thermal insulation exterior wall structure with window sill opening |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102116061B (en) | 2013-03-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102116061A (en) | Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure | |
| CN106013811B (en) | A kind of installation method of assembled architecture | |
| CN103266767B (en) | Construction method for preventing and treating cracks between concrete structure and filler wall | |
| CN104358341B (en) | A kind of building masonry and construction masonry method | |
| CN106801517B (en) | A kind of prefabricated porous plate brick mixed structure of school building exterior reinforcement and strengthening method | |
| CN106436893A (en) | Fully-prefabricated structure and construction method thereof | |
| CN103046665B (en) | Insulating mortar strengthening layer rowlock wall with steel wire mesh for setting hose tooth constructional column and manufacturing method thereof | |
| CN104746772A (en) | Ash concrete hollow partition board anti-cracking construction method | |
| CN103352537B (en) | Overall load bearing heat preserving wallboard and production construction process thereof | |
| CN205296584U (en) | Be applied to assembled constructional column of aerated concrete block infilled wall | |
| CN206220238U (en) | Fully-prefabricated assembled structure | |
| CN203821591U (en) | Steel frame-reinforcement brickwork shear wall combined structure | |
| CN105019597A (en) | Lightweight partition board with net rack and fiber-reinforced hollows and splicing method thereof | |
| CN103821263A (en) | Precast assembly self-heat preservation concrete shear wall system and construction method thereof | |
| CN204001278U (en) | A kind of prefabricated assembled self-insulating concrete shear wall system | |
| CN104675138B (en) | A kind of slab balcony reinforcement means for sound insulation and noise reducing transformation | |
| CN201224941Y (en) | Environment protection type structure thermal insulation concrete building block, masonry and anti-vibration residential building | |
| CN102535847B (en) | Construction method of gypsum self-insulation external wall block masonry | |
| CN104389360A (en) | Externally suspended insulation board type reinforcement brickwork shear wall system and construction method thereof | |
| CN105888282B (en) | A kind of seismic reinforcing structure and method that big hole is opened for transformer station's masonry wall | |
| CN204899005U (en) | Hollow light partition wall board of fiber reinforcement | |
| CN203296209U (en) | Self-insulation mortarless block masonry shear wall system | |
| CN104612315A (en) | Concrete self-temperature-preservation composite block and construction method | |
| CN205134703U (en) | Solid light partition wall board of fiber reinforcement | |
| CN223633985U (en) | A prefabricated structure for underground subway station rooms |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C53 | Correction of patent of invention or patent application | ||
| CB03 | Change of inventor or designer information |
Inventor after: Wang Jianying Inventor after: Tian Qihua Inventor after: Zhou Guang Inventor after: Zhang Li Inventor after: Ji Mingjun Inventor after: Xin Jianzhen Inventor after: Zhang Zhiqiang Inventor after: Qian Shaobo Inventor after: Zhu Minghao Inventor after: Wang Jian Inventor after: Cao Zhigang Inventor after: Gao Song Inventor before: Wang Jianying Inventor before: Zhou Guang Inventor before: Zhang Li Inventor before: Ji Mingjun Inventor before: Zhang Zhiqiang Inventor before: Qian Shaobo Inventor before: Zhu Minghao Inventor before: Wang Jian Inventor before: Cao Zhigang Inventor before: Gao Song Inventor before: Tian Qihua |
|
| COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: WANG JIANYING JI MINGJUN ZHANG ZHIQIANG QIAN SHAOBO ZHU MINGHAO WANG JIAN CAO ZHIGANG GAO SONG TIAN QIHUA ZHOU GUANG ZHANG LI TO: WANG JIANYING JI MINGJUN XIN JIANZHEN ZHANG ZHIQIANG QIAN SHAOBO ZHU MINGHAO WANG JIAN CAO ZHIGANG GAO SONG TIAN QIHUA ZHOU GUANG ZHANG LI |
|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20170720 Address after: 100070, No. 19, building ten, 188, base station, South Fourth Ring Road West, Beijing, Fengtai District Patentee after: CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP DECORATION ENGINEERING CO.,LTD. Address before: 200331 No. 303 West Wuwei Road, Shanghai, Putuo District Patentee before: China Railway Construction Engineering Group |
|
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20191025 Address after: 100070 19, ten district headquarters, 188 South Fourth Ring Road, Fengtai District, Beijing. Co-patentee after: China Railway Construction Engineering Group Patentee after: CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP DECORATION ENGINEERING CO.,LTD. Address before: 100070 19, ten district headquarters, 188 South Fourth Ring Road, Fengtai District, Beijing. Patentee before: CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP DECORATION ENGINEERING CO.,LTD. |
|
| PP01 | Preservation of patent right | ||
| PP01 | Preservation of patent right |
Effective date of registration: 20250919 Granted publication date: 20130306 |