CN106545192A - A kind of suspension type pipe gallery and maintenance platform system - Google Patents
A kind of suspension type pipe gallery and maintenance platform system Download PDFInfo
- Publication number
- CN106545192A CN106545192A CN201611116797.7A CN201611116797A CN106545192A CN 106545192 A CN106545192 A CN 106545192A CN 201611116797 A CN201611116797 A CN 201611116797A CN 106545192 A CN106545192 A CN 106545192A
- Authority
- CN
- China
- Prior art keywords
- pipe gallery
- type pipe
- suspension type
- maintenance platform
- axial
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H5/00—Buildings or groups of buildings for industrial or agricultural purposes
- E04H5/02—Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories
- E04H5/06—Pits or building structures for inspection or services
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
Abstract
The invention discloses a kind of suspension type pipe gallery and maintenance platform system, including:The axial suspension type pipe gallery for hanging between house crossbeam and being located on the inside of house column, and the axial maintenance platform supporting with the axial suspension type pipe gallery;The lateral suspension formula pipe gallery for being installed at the top of house intermediate transverse girder and arranging along crossbeam length direction, and the horizontal maintenance platform supporting with the lateral suspension formula pipe gallery;And it is connected to the sidepiece the termination suspension type pipe gallery through house termination crossbeam of house wind-resistant column.The suspension type pipe gallery and maintenance platform system, can be easy to house inner tube circuit to install and keep in repair, and wiring is neat.
Description
Technical field
The present invention relates to construction engineering technical field, more particularly to a kind of suspension type pipe gallery and maintenance platform system.
Background technology
With the fast development of China railways modernization construction, each high-speed railway, the construction of Line for Passenger Transportation also launch therewith,
The EMUs runed on these high-speed lines will provide more fast and easily trip mode for passenger.With conventional internal combustion, electricity
Power locomotive is different, and EMUs are reorganized and outfit, check and need to carry out in the exclusive inspection storehouse of motor-car utilization.Motor-car with it is be for
The reorganizing and outfit of EMUs (clean, cleaning, supply water, blowdown), park, the field of the provisional upkeep operation of maintenance repair and catastrophic failure
Institute, is the logistics support base of EMUs.With maintenance, regular maintenance guarantees that to each Railway Bureau EMUs safety, operation on schedule seem
It is particularly important.No matter all gradually sudden and violent in actual application after respectively using institute's motor-car inspection storehouse in process of construction or building up
Some problems are exposed, comprehensive pipeline arrangement is especially prominent in storehouse.There is in its storehouse plurality of devices and substantial amounts of pipeline and cable,
Intricate to link together, these distribution of pipe forms will directly influence overhaul of train-set work efficiency.
Successful Application of the piping lane in industry and civil buildings electromechanical installation is hung, its distinguishing feature is to realize peace
The reasonable distribution in dress space and resource-sharing, meet functional requirement, reserve access path, and perception effect is good, has reached space section
The purpose with material economy, the co-ordination amount between reduction specialty are saved, and improves the work efficiency of construction, for railway engineering
Category underground structure or indoor truss structure, and the characteristics of narrow space, it is inevitable to introduce and hang piping lane.
At present, the layout pattern of pipeline layout is varied, mainly (i.e. common with simple rack (" freely-supported ") and integrated pipe canal
Same ditch) arrange based on two kinds of patterns.Both installation approach standards are relatively low, not yet introduce integrated concept.Freely-supported mode lacks
Planning is installed, layout is in disorder, unbalance stress, and mounting process is coarse, the bearing capacity of crime of injuries by explosive substances to buildings and goods therein, destroys building surface
Corrosion-inhibiting coating.Integrated pipe canal installation approach, pipe trench construction investment are big, and the cycle is long;The equipment operating costs such as supporting draining ventilation
Height, and various pipelines and cable are arranged on the underground space, dark moist, especially southern area is easy to hydrops, is easily subject to ground
Using for the infringement of lower water, impact pipeline and cable is safe.So do not only result in motor-car and check the construction in storehouse, retrofit work task
Amount is big, and the safety to system operation, reliability and economy have serious impact.
Therefore, with reference to existing installation approach feature, research is a kind of have simple structure, easy for installation, combination flexibly, pipeline
Maintenance is convenient, and can effectively solving tradition freely-supported pattern and integrated pipe canal pattern every problem during construction and use pipe
Twine helad syntype, that is, hang piping lane and assistance platform pattern, can instruct the arrangement of comprehensive pipeline in MTU depot institute storehouse, effectively can drop
Low construction investment, shortening completion time of project, MTU depot institute storehouse gut line is instructed to install.So be conducive to practical implementation, and just
In theoretical research, with extensive application value.
The content of the invention
It is an object of the invention to propose a kind of suspension type pipe gallery and maintenance platform system, house inner tube can be easy to
Circuit is installed and is keeped in repair, and wiring is neat.
It is that, up to this purpose, the present invention is employed the following technical solutions:
A kind of suspension type pipe gallery and maintenance platform system, including:
The axial suspension type pipe gallery for hanging between house crossbeam and being located on the inside of house column, and with the axial direction
The supporting axial maintenance platform of suspension type pipe gallery;
The lateral suspension formula pipe gallery for being installed at the top of house intermediate transverse girder and arranging along crossbeam length direction, and with institute
State the supporting horizontal maintenance platform of lateral suspension formula pipe gallery;And
It is connected to the sidepiece the termination suspension type pipe gallery through house termination crossbeam of house wind-resistant column.
Specifically, the axial suspension type pipe gallery includes the suspension upper frame being across on multiple crossbeams, described
Hang upper frame and be connected with multiple font hangers, the inner side of each hanger is provided with least one first with its short transverse
Dividing plate, first dividing plate between the two neighboring hanger are corresponded.
Preferably, the suspension upper frame includes two axial stems, and two axial stem spacing side by side are arranged, the hanger
It is connected to two axial stems.
It is further preferred that the hanger includes the first cross bar being connected between two axial stems, described first
The two ends of cross bar are connected with the first montant down, and the second cross bar, second cross bar are connected between two first montants
For first dividing plate.
It is further preferred that between the two neighboring crossbeam, positioned at first montant of the hanger of end
Bottom is connected to the axial stem by brace.
Specifically, the axial maintenance platform is located at the sidepiece of the axial suspension type pipe gallery, and along the axial direction
The length direction of suspension type pipe gallery is arranged;The axial maintenance platform is connected to house column by I-shaped steel corbel.
Preferably, the sidepiece away from the axial suspension type pipe gallery of the axial maintenance platform is provided with axle upward
To guardrail.
Specifically, the lateral suspension formula pipe gallery includes that the length direction along the crossbeam is connected to the crossbeam
On suspension underframe, horizontal hanger is provided with the suspension underframe, positioned at the horizontal maintenance platform of the horizontal hanger sidepiece,
The suspension underframe both sides are provided with horizontal guardrail upward.
Preferably, the horizontal hanger includes being erected on second montant hung on underframe, the second montant court
At least one second partition is provided with its short transverse to the side of the horizontal maintenance platform, the second partition is the 3rd
Cross bar.
Specifically, the termination suspension type pipe gallery include being connected to house termination wind-resistant column sidepiece the 4th cross bar and
5th cross bar, the 4th cross bar and the 5th cross bar are respectively positioned at the upper and lower part of house crossbeam, the 4th cross bar and institute
The other end for stating the 5th cross bar is connected with the 3rd montant.
The suspension type pipe gallery and maintenance platform system of the present invention, by arranging axial suspension type pipe gallery and axial direction
Maintenance platform, lateral suspension formula pipe gallery and horizontal maintenance platform, and termination termination suspension type pipe gallery, its each portion
It is point independently installed, simple structure, easy for installation, combination flexibly, pipeline maintenance it is convenient, and can effectively solving tradition freely-supported pattern and
Every problem of integrated pipe canal pattern outlet during construction and use, can instruct the cloth of comprehensive pipeline in MTU depot institute storehouse
Put, can effectively reduce construction investment, shorten the completion time of project, instruct MTU depot institute storehouse gut line to install, be so conducive to engineering reality
Border is applied, and is easy to theoretical research again, with extensive application value.
Description of the drawings
Fig. 1 is the distributed architecture schematic diagram of house central post, crossbeam and wind-resistant column;
Fig. 2 be the axial suspension comprehensive piping lane of suspension type pipe gallery described in the embodiment of the present invention and maintenance platform system and
The side structure schematic diagram of maintenance platform;
Fig. 3 be the axial suspension comprehensive piping lane of suspension type pipe gallery described in the embodiment of the present invention and maintenance platform system and
Maintenance platform A-A to left view structural representation;
Fig. 4 be the axial suspension comprehensive piping lane of suspension type pipe gallery described in the embodiment of the present invention and maintenance platform system and
Overlooking the structure diagram of the maintenance platform in B-B direction;
Fig. 5 be the axial suspension comprehensive piping lane of suspension type pipe gallery described in the embodiment of the present invention and maintenance platform system and
Maintenance platform C-C to right side structural representation;
Fig. 6 is the lateral suspension formula pipe gallery of suspension type pipe gallery and maintenance platform system described in the embodiment of the present invention
And a kind of side structure schematic diagram of optimal way of maintenance platform;
Fig. 7 is the lateral suspension formula pipe gallery of suspension type pipe gallery and maintenance platform system described in the embodiment of the present invention
And the side structure schematic diagram of another kind of optimal way of maintenance platform;
Fig. 8 is the lateral suspension formula pipe gallery of suspension type pipe gallery and maintenance platform system described in the embodiment of the present invention
And the side structure schematic diagram of another optimal way of maintenance platform;
Fig. 9 is the termination suspension type pipe gallery of suspension type pipe gallery and maintenance platform system described in the embodiment of the present invention
Side structure schematic diagram.
In figure:1- columns;2- crossbeams;3- wind-resistant columns;
4- axial directions suspension type pipe gallery;41- axial stems;The first cross bars of 42-;The first montants of 43-;The second cross bars of 44-;
45- braces;
5- axial directions maintenance platform;6- I-shaped steel corbels;7- axial directions guardrail;
The horizontal hangers of 8-;The second montants of 81-;The 3rd cross bars of 82-;
The horizontal maintenance platforms of 9-;10- hangs underframe;The horizontal guardrails of 11-;
12- terminations suspension type pipe gallery;The 4th cross bars of 1201-;The 5th cross bars of 1202-;The 3rd montants of 1203-.
Specific embodiment
Below in conjunction with the accompanying drawings 1-9 and by specific embodiment further illustrating technical scheme.
As shown in figure 1, for the distributed architecture schematic diagram of house central post, crossbeam and wind-resistant column;In the present embodiment, which is
Distributed architecture schematic diagram inside Motor Car Institute garage.Which has two row's columns 1, and often row includes multiple columns 1.In two row's columns
Crossbeam 2 is erected between two columns 1 of same a line.Wind-resistant column 3 is set in the termination of two row's columns, wind-resistant column 3 is located at
Between two columns of termination, and in the outside of crossbeam 2.Hereinafter, based on such building construction, further illustrate the present invention outstanding
Hanging pipe gallery and maintenance platform system.
A kind of suspension type pipe gallery and maintenance platform system described in the embodiment of the present invention, including:Hang on house horizontal
It is between beam 2 and the axial suspension type pipe gallery 4 that is located on the inside of house column 1, and supporting with axial suspension type pipe gallery 4
Axial maintenance platform 5;The lateral suspension formula integrated pipe for being installed at the top of house intermediate transverse girder 2 and arranging along 2 length direction of crossbeam
Corridor, and the horizontal maintenance platform 9 supporting with lateral suspension formula pipe gallery;And be connected to the sidepiece of house wind-resistant column 3 and pass through
The termination suspension type pipe gallery 12 of house termination crossbeam 2.
Specifically, axial suspension type pipe gallery 4 is arranged on the inside of string column, and is hung on the horizontal stroke being connected with the row column
Liang Shang, is arranged perpendicular to crossbeam;Lateral suspension formula pipe gallery is then arranged at the top of the crossbeam positioned at middle part, along crossbeam
Length direction arrange, parallel to crossbeam;Crossbeam of the termination suspension type pipe gallery 12 then perpendicular to termination is arranged.
As shown in Fig. 2 to 5, axial suspension type pipe gallery 4 includes the suspension upper frame being across on multiple crossbeams 2, hangs
Upper frame is connected with multiple font hangers, and the inner side of each hanger is provided with least one first dividing plates, phase with its short transverse
The first dividing plate between adjacent two hangers is corresponded.In the present embodiment, can be used for placing power bridge by the first dividing plate
The various routes of pipe line such as frame, combined lighting+emergency lighting, information crane span structure, security monitoring crane span structure, feedwater, fire-fighting, blister, pneumatics, with
The upper route of pipe line when mounted, with the length direction layout of axially hanging pipe gallery.
Preferably, the quantity of the first dividing plate is 6, and on the first dividing plate from top to bottom, layout is successively, first first
Dividing plate arranges dynamic crane span structure 400*200, and second the first dividing plate is provided with combined lighting+emergency lighting 300*200, the 3rd
First dividing plate is provided with two information crane span structure 200*100, and the 4th the first dividing plate is provided with security monitoring crane span structure 200*100, the
Five the first dividing plates are provided with feedwater DN150 and fire-fighting DN150, and the 6th the first dividing plate is provided with blister DN250 and pneumatics
DN80.Each layer of layout is independently arranged, and line clear is neat, and wiring is easy, and maintenance is convenient.
Preferably, hanging upper frame includes two axial stems 41, and two 41 spacing side by side of axial stem are arranged, and hanger is connected to two
Individual axial stem 41.It is further preferred that hanger includes the first cross bar 42 being connected between two axial stems 41, the first cross bar 42
Two ends be connected with the first montant 43 down, be connected with the second cross bar 44 between two the first montants 43, the second cross bar 44 is the
One dividing plate.It is further preferred that between two neighboring crossbeam 2, passing through oblique positioned at the bottom of the first montant 43 of the hanger of end
Bar 45 is connected to axial stem 41.
Preferably, axial maintenance platform 5 is located at the sidepiece of axial suspension type pipe gallery 4, and suspension type synthesis vertically
The length direction of piping lane 4 is arranged;Axial maintenance platform 5 is connected to house column 1 by I-shaped steel corbel 6, wherein, I-steel cattle
Lower limb 6 is located at the bottom of axial suspension type pipe gallery 4.Preferably, axial maintenance platform 5 away from axial suspension type pipe gallery
4 sidepiece is provided with axial guardrail 7 upward.
As shown in Fig. 6 to 8, lateral suspension formula pipe gallery includes that the length direction along crossbeam 2 is connected on crossbeam 2
Underframe 10 is hung, is hung, positioned at the horizontal maintenance platform 9 of 8 sidepiece of horizontal hanger, hung
10 both sides of underframe are provided with horizontal guardrail 11 upward.
Preferably, horizontal hanger 8 includes being erected on the second montant 81 hung on underframe 10, and the second montant 81 is towards horizontal
The side of maintenance platform 9 is provided with least one second partition with its short transverse, and second partition is the 3rd cross bar 82.
In the present embodiment, second partition can be used for placement information crane span structure, electric power crane span structure+various routes of pipe line of illuminating lamp,
When the above route of pipe line is installed, with the length direction layout of horizontal hanging pipe gallery.
As a kind of optimal way, as shown in fig. 6, the quantity of second partition is 3, the top surface of underframe 10 now, is hung
The circuit of circuit crane span structure+illumination 200*100 all the way can be placed, on first second partition thereon, another road circuit is placed again
Place the line of information crane span structure 200*100 all the way on the circuit of crane span structure+illumination 200*100, then second second partition above again
Road, places the circuit of another road information crane span structure 200*100 again on uppermost 3rd second partition.
As another kind of optimal way, as shown in fig. 7, the quantity of second partition is 3, now, can on 3 second partitions
To place the route of pipe line of pneumatics DN80, feedwater DN150, fire-fighting DN150, place on first second partition of bottom and disappear
The circuit of anti-DN150, places the circuit of feedwater DN150, on second middle second partition positioned at the 3rd of the top the
The circuit of pneumatics DN80 is placed on individual second partition.
As another optimal way, as shown in figure 8, the quantity of second partition is 1, the top of underframe 10 now, is hung
The circuit of electric power crane span structure 200*100 all the way can be placed in face, and another road electric power crane span structure 200* can be placed on 1 second partition
100 circuit.
In the present embodiment, the quantity of the second partition of horizontal hanger can be decided according to the actual requirements, and be not limited in
The number of the example above, its arrangement circuit are also not necessarily limited to the arrangement of the example above.
As shown in figure 9, termination suspension type pipe gallery 12 includes being connected to the 4th cross bar of 3 sidepiece of house termination wind-resistant column
1201 and the 5th cross bar 1202, the 4th cross bar 1201 and the 5th cross bar 1202 respectively positioned at house termination crossbeam 2 it is upper and lower
The other end of portion, the 4th cross bar 1201 and the 5th cross bar 1202 is connected with the 3rd montant 1203.Now, the bottom of the 4th cross bar 1201
Portion can arrange the route of pipe line of blister DN200, fire-fighting DN150, pneumatics DN80 and feedwater DN32, and the top of the 5th cross bar 1202 can
To arrange the route of pipe line of lighting main 300*100, safety interlocking 200*100, security monitoring 200*100.Space is able to up and down
Effectively utilizes, rational deployment.
The suspension type pipe gallery and maintenance platform system of the present invention, which can be used in large-span steel, and width can be with
9m is reached, its distinguishing feature is to realize reasonable distribution and the resource-sharing of installing space, meets functional requirement, reserve maintenance logical
Road, perception effect are good, have reached the purpose of space saving and material economy, have reduced the co-ordination amount between specialty, and improve
The work efficiency of construction, belongs to underground structure or indoor truss structure for railway engineering, and the characteristics of narrow space, which has such as
Lower advantage:
1) combination type component, fabricated construction, it is neat, beautiful, generous;Without the need for welding and drilling, using component assembling group
Close, it is convenient to carry out tearing down and reconstructing adjustment, it is reusable, also pole can be wasted to the reserved certain space of the extension of later pipeline
It is little.
2) each profession coordination is good, it is ensured that indoor suspended ceiling space absolute altitude;With good compatibility, each specialty can share one
Suspension bracket;Space is made full use of, the tube bank of each specialty can be made to be able to good coordination, space and resource-sharing is reached, improved limited
Space availability ratio, such that it is able to guarantee the absolute altitude in battery limits corridor.
(3) stress is reliable, stable;Complete design and construction atlas, all of primary structure member can realize assembly
The rigidity cooperation of component, connects non-displacement, and step-less adjustment is accurately positioned, shock resistance and vibrations, strengthens the shearing resistance energy of support node
Power.
4) installation rate is fast, and the construction period is short;Suspension rod and cross-arm are the scale products of producer, according to the comprehensive pipeline of in-depth
Figure carries out blanking, just can be assembled, it is each specialty and work post can cross-operation, improve work efficiency, the reduction of erection time.
5) long service life, convenient later maintenance;According to use environment, the specific demand of different parts, there is provided different works
The material of skill has electrogalvanizing (cold galvanizing), galvanizing and sherardizing coating (plastic-blasting), and material has very strong anti-corrosion, using the longevity
Life length.
6) material budget is accurate, and product is standardization semi-finished product, and model identification is apparent, coordinates the management of specification, material and matches somebody with somebody
Waste and loss on part is few.
7) quality assurance really up to the mark;Component is the qualified approved product of producer, meets ISO9000, ISO9002 standard, is protected
The stability of card whole system integrity and piping lane.
8) good versatility:The change of structure, determines the heterogeneity of suspension bracket physical dimension, and some needs are according to position
The physical dimension for putting to design suspension bracket, due to the standard package species that associativity enriches, is available for multiple choices, it is ensured that different bars
The simplicity of all kinds of supports, the suitability and motility under part.
9) environmental protection:Construction need not be welded and naked light, without the need for the PROCESS FOR TREATMENT of conventional spreader anti-corrosion (mopping is zinc-plated), will not
Environment is impacted.
Therefore, motor-car is easier to realize overhaul of train-set work efficiency using piping lane is hung with checked storehouse gut line
Target is lifted, the development trend of railway modernization has been complied with using suspension piping lane.
The know-why of the present invention is described above in association with specific embodiment.These descriptions are intended merely to explain the present invention's
Principle, and limiting the scope of the invention can not be construed to by any way.Based on explanation herein, the technology of this area
Personnel associate other specific embodiments of the present invention by need not paying performing creative labour, these modes fall within
Within protection scope of the present invention.
Claims (10)
1. a kind of suspension type pipe gallery and maintenance platform system, it is characterised in that include:
The axial suspension type pipe gallery for hanging between house crossbeam and being located on the inside of house column, and axially hang with described
The supporting axial maintenance platform of formula pipe gallery;
The lateral suspension formula pipe gallery for being installed at the top of house intermediate transverse girder and arranging along crossbeam length direction, and with the horizontal stroke
To the horizontal maintenance platform that suspension type pipe gallery is supporting;And
It is connected to the sidepiece the termination suspension type pipe gallery through house termination crossbeam of house wind-resistant column.
2. suspension type pipe gallery according to claim 1 and maintenance platform system, it is characterised in that described axially to hang
Formula pipe gallery includes the suspension upper frame being across on multiple crossbeams, and the suspension upper frame is connected with multiple fonts and hangs
Frame, the inner side of each hanger are provided with least one first dividing plates with its short transverse, between the two neighboring hanger
First dividing plate correspond.
3. suspension type pipe gallery according to claim 2 and maintenance platform system, it is characterised in that the suspension upper frame
Including two axial stems, two axial stem spacing side by side are arranged, and the hanger is connected to two axial stems.
4. suspension type pipe gallery according to claim 3 and maintenance platform system, it is characterised in that the hanger includes
The first cross bar being connected between two axial stems, the two ends of first cross bar are connected with the first montant down, two
The second cross bar is connected between first montant, second cross bar is first dividing plate.
5. suspension type pipe gallery according to claim 4 and maintenance platform system, it is characterised in that two neighboring described
Between crossbeam, the bottom positioned at first montant of the hanger of end is connected to the axial stem by brace.
6. suspension type pipe gallery according to claim 1 and maintenance platform system, it is characterised in that described axially to safeguard
Platform is located at the sidepiece of the axial suspension type pipe gallery, and the length direction along the axial suspension type pipe gallery sets
Put;The axial maintenance platform is connected to house column by I-shaped steel corbel.
7. suspension type pipe gallery according to claim 6 and maintenance platform system, it is characterised in that described axially to safeguard
The sidepiece away from the axial suspension type pipe gallery of platform is provided with axial guardrail upward.
8. suspension type pipe gallery according to claim 1 and maintenance platform system, it is characterised in that the lateral suspension
Formula pipe gallery includes the suspension underframe that the length direction along the crossbeam is connected on the crossbeam, on the suspension underframe
Be provided with horizontal hanger, positioned at the horizontal maintenance platform of the horizontal hanger sidepiece, the suspension underframe both sides are provided with upward
Horizontal guardrail.
9. suspension type pipe gallery according to claim 8 and maintenance platform system, it is characterised in that the horizontal hanger
Including be erected on it is described hang underframe on the second montant, second montant towards the horizontal maintenance platform side with which
Short transverse is provided with least one second partition, and the second partition is the 3rd cross bar.
10. suspension type pipe gallery according to claim 1 and maintenance platform system, it is characterised in that the termination hangs
Hanging pipe gallery includes the 4th cross bar and the 5th cross bar for being connected to house termination wind-resistant column sidepiece, the 4th cross bar and institute
State the other end of the 5th cross bar respectively positioned at the upper and lower part of house crossbeam, the 4th cross bar and the 5th cross bar to be connected with
3rd montant.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611116797.7A CN106545192A (en) | 2016-12-07 | 2016-12-07 | A kind of suspension type pipe gallery and maintenance platform system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611116797.7A CN106545192A (en) | 2016-12-07 | 2016-12-07 | A kind of suspension type pipe gallery and maintenance platform system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106545192A true CN106545192A (en) | 2017-03-29 |
Family
ID=58397671
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611116797.7A Pending CN106545192A (en) | 2016-12-07 | 2016-12-07 | A kind of suspension type pipe gallery and maintenance platform system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106545192A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107727366A (en) * | 2017-09-30 | 2018-02-23 | 北京亚欧震达科技发展有限公司 | Detection method, device, system and the storage medium of motor car inspection and repair depositary management corridor illumination |
CN107769141A (en) * | 2017-12-05 | 2018-03-06 | 福建省电力勘测设计院 | Overhead type comprehensive wiring piping lane |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0579580A (en) * | 1991-05-31 | 1993-03-30 | Sakuma Seisakusho:Kk | Pipe supporting fitting |
CN2521802Y (en) * | 2001-09-18 | 2002-11-20 | 何达齐 | Wire-frame box |
CN201810878U (en) * | 2010-12-03 | 2011-04-27 | 中国华西企业股份有限公司 | Bridge type bracket |
CN203907023U (en) * | 2014-06-24 | 2014-10-29 | 国网山东省电力公司潍坊供电公司 | Over cable rack for optical cable |
CN204358258U (en) * | 2014-11-22 | 2015-05-27 | 苏州耀洲金属制品有限公司 | Airduct water pipe shares suspension bracket |
CN204852641U (en) * | 2015-08-12 | 2015-12-09 | 杭州富阳新锐生物科技有限公司 | Piping erection frame |
CN205479755U (en) * | 2016-02-26 | 2016-08-17 | 中铁第四勘察设计院集团有限公司 | A synthesize integrated suspension system of pipe support that is used for motor car application storehouse of inspecting |
-
2016
- 2016-12-07 CN CN201611116797.7A patent/CN106545192A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0579580A (en) * | 1991-05-31 | 1993-03-30 | Sakuma Seisakusho:Kk | Pipe supporting fitting |
CN2521802Y (en) * | 2001-09-18 | 2002-11-20 | 何达齐 | Wire-frame box |
CN201810878U (en) * | 2010-12-03 | 2011-04-27 | 中国华西企业股份有限公司 | Bridge type bracket |
CN203907023U (en) * | 2014-06-24 | 2014-10-29 | 国网山东省电力公司潍坊供电公司 | Over cable rack for optical cable |
CN204358258U (en) * | 2014-11-22 | 2015-05-27 | 苏州耀洲金属制品有限公司 | Airduct water pipe shares suspension bracket |
CN204852641U (en) * | 2015-08-12 | 2015-12-09 | 杭州富阳新锐生物科技有限公司 | Piping erection frame |
CN205479755U (en) * | 2016-02-26 | 2016-08-17 | 中铁第四勘察设计院集团有限公司 | A synthesize integrated suspension system of pipe support that is used for motor car application storehouse of inspecting |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107727366A (en) * | 2017-09-30 | 2018-02-23 | 北京亚欧震达科技发展有限公司 | Detection method, device, system and the storage medium of motor car inspection and repair depositary management corridor illumination |
CN107769141A (en) * | 2017-12-05 | 2018-03-06 | 福建省电力勘测设计院 | Overhead type comprehensive wiring piping lane |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104912004B (en) | Hold rail-type track transportation bridge evacuation maintenance platform | |
CN202881852U (en) | Suspension bridge cable installation system | |
CN205329721U (en) | Air exit and mouthful combined layout's that flees utility tunnel node structure | |
CN202273179U (en) | High-altitude steel cable suspended working platform for construction and maintenance on outer side of bridge box girder | |
CN106545192A (en) | A kind of suspension type pipe gallery and maintenance platform system | |
CN103147389B (en) | Novel bridge protecting facility | |
CN207143708U (en) | Hoisting type foundation pit-crossing comprehensive steel trestle | |
CN106522102A (en) | Side span construction support, rigid frame bridge side span and rigid frame bridge | |
CN101775896A (en) | Method for installing pipeline scaffold of steel roof equipment and rigid suspended scaffold | |
CN101958519B (en) | Method for transforming tangent tower of double-circuit double-bundle transmission lines by lifting in electrified mode in another place | |
CN206272192U (en) | A kind of new 330kV power distribution equipments in high altitude localities | |
CN209145256U (en) | The dedicated climbing frame of assembled architecture | |
CN102174926A (en) | Tower-type wind power station structure | |
CN104358208B (en) | Without longeron half-through arch bridge safe early warning girder construction and method for early warning thereof | |
CN201635377U (en) | Rigid suspended type scaffold provided with large-span steel roof equipment pipeline | |
CN107905043A (en) | A kind of suspension type bottom plate open steel web truss combined track girder system system | |
CN112086918A (en) | Integrated suspension system of city railway inspection library integrated pipeline | |
CN207277169U (en) | A kind of access path arrangement of stopping train checkup shed | |
CN203205717U (en) | Compact 220kV outdoor GIS power distribution equipment | |
CN110466392A (en) | A kind of structural unit and traffic route with contact cage type roadbed | |
CN106764066B (en) | A kind of aerial piping lane | |
CN205976573U (en) | Large -span stand cable protection canopy | |
CN206052560U (en) | A kind of protection hanging canopy for bridge span construction of the highway | |
CN212804594U (en) | Steel construction piping lane | |
CN210319572U (en) | Internal lighting system of single-layer industrial factory building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170329 |
|
RJ01 | Rejection of invention patent application after publication |