CN106385847A CN201610771836.0A CN201610771836A CN106385847A CN 106385847 A CN106385847 A CN 106385847A CN 201610771836 A CN201610771836 A CN 201610771836A CN 106385847 A CN106385847 A CN 106385847A
Authority
CN
China
Prior art keywords
side slope
slope
fiber blanket
slope face
vegetable fiber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610771836.0A
Other languages
Chinese (zh)
Inventor
陈嘉霖
邱文
余韬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Take Yunnan Ecological Environment Technology Co Ltd
Original Assignee
Take Yunnan Ecological Environment Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Take Yunnan Ecological Environment Technology Co Ltd filed Critical Take Yunnan Ecological Environment Technology Co Ltd
Priority to CN201610771836.0A priority Critical patent/CN106385847A/en
Publication of CN106385847A publication Critical patent/CN106385847A/en
Pending legal-status Critical Current

Links

Classifications

    • AHUMAN NECESSITIES
    • A01AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
    • A01BSOIL WORKING IN AGRICULTURE OR FORESTRY; PARTS, DETAILS, OR ACCESSORIES OF AGRICULTURAL MACHINES OR IMPLEMENTS, IN GENERAL
    • A01B79/00Methods for working soil
    • A01B79/02Methods for working soil combined with other agricultural processing, e.g. fertilising, planting

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Soil Sciences (AREA)
  • Environmental Sciences (AREA)
  • Cultivation Of Plants (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a method for ecological restoration of a high-altitude slope. The method comprises the steps that sundries on the surface of the high-altitude slope are cleared away, wherein the sundries comprise pumice stones and capping mass, and leveling is conducted to the slope surface; an anchor rod position is marked, drilling is conducted, the top of the anchor rod is bent, and an anchoring agent is poured for fixation; a reinforcement net is paved on the slope surface and fixed on the anchor rod reserved on the slope surface; and a plant fiber blanket is paved, a geo-grid is then paved, and watering and conservation are conducted after fixation. According to the invention, rubble falling and collapse on the slope surface can be prevented; the steadiness of the slope surface structure is ensured; the plant fiber blanket is paved on the slope surface; stability of the slope is enhanced; moisture evaporation on the slope surface can be effectively reduced; the plant growth density can be rationally controlled; and vegetation coverage can be ensured, and demands for nutrients can be reduced. The method disclosed by the invention is used for the ecological restoration of the high-altitude slope; construction technologies are simple; the level of management and maintenance is reduced; consumption of manpower and materials can be greatly reduced; construction cost is reduced; and restoration effects of an ecological system are good.

Description

A kind of High aititude slope ecological recovery method
Technical field
The present invention relates to side slope recovery technique field, specifically a kind of High aititude slope ecological recovery method.
Background technology
High aititude side slope is all distributed in China various places.The Common Diseases type of side slope has:Weathering off, flowstone stream mud, Fall block falling rocks, avalanche, topple over, cave in, burst bend, slip collapse, the sliding, landslide of collapsing, straggly etc..Because the gradient is larger, slope is high, side slope Itself water conservation, fertilizer conservation and solid soil ability are very low, and recovering vegetation on slope difficulty is larger, and not only the cycle is long, and effect is not also good.Mesh Front High aititude slope treatment measure mainly has the methods such as thick photoresist greening method, alien earth sparging, plant cover concrete bank protection, thick-layer base Although material greening method can side slope effectively be afforested, it is because the high deadweight with soil of side slope, making spray plant layer cannot support Uprising rain washes away and is exposed to the sun with burning sun, finally causes rill erosion, sheetflood, or even domatic entirety collapses, and not only can not solve solid soil basic Problem, causes secondary domatic damage on the contrary;And the plant cover concrete mode of sowing grass seeds by duster has completely cut off the connection of vegetation and natural soil and rock System, and is restricted by domatic angle and domatic height, causes that seed germination rate is not high, vegetation cover degree is less, root system of plant is unstable A series of problems, such as easily lodge.
Content of the invention
It is an object of the invention to provide a kind of construction technology is relatively simple, reduce pipe and supporting level, reduces construction cost, extensive Multiple respond well High aititude slope ecological recovery method, to solve the problems, such as to propose in above-mentioned background technology.
For achieving the above object, the present invention provides following technical scheme:
A kind of High aititude slope ecological recovery method, comprises the following steps:
1) side slope face cleaning:Remove High aititude side slope face debris, debris include Pumex, surface dust, opposite side is domatic carry out smooth Process;
2) anchor bolt construction:Labelling anchor pole position, carries out bore operation, and rock-bolt length 5-10cm, anchor pole top are reserved in side slope face Portion bends, and irrigates Anchor Agent and be fixed;
3) linked network:In step 2) side slope face laying reinforced bar net, and be fixed on the reserved anchor pole in side slope face;
4) lay vegetable fiber blanket:In step 3) surface laying vegetable fiber blanket, and side slope face is fixed on by mounting ring On reserved anchor pole;Vegetable fiber blanket is provided with soil, straw, fertilizer, slag, water-retaining agent;On vegetable fiber blanket, also mixing is broadcast Plant drought-enduring, impoverishment tolerant type shrub, herbaceous plant seeds, grass blade;
5) secondary linked network:In step 4) surface laying GSZ, make step 4) vegetable fiber blanket is close to side slope face, and consolidate On anchor pole;
6) fixing:In step 5) GSZ and vegetable fiber blanket are fixed on side slope face surface holdfast, wherein side Holdfast need to be encrypted by domatic corner, concavo-convex place and net lap-joint;
7) water seasoning:High-pressure atomization is taken to sow grass seeds by duster mode, to step 6) surface carries out water seasoning, waters many on a small quantity Secondary, till being repeatedly sprayed to saturation.
As the further scheme of the present invention:Step 2) in, anchor hole diameter 30-35mm, hole depth 400-600mm, anchor Pitch of holes 0.8-1.2m*0.8-1.2m, installs bolt diameter 10-14mm, rock-bolt length 400-600mm.
As the further scheme of the present invention:Step 3) in, described reinforced bar net is the plastic steel wire of PVC, size of mesh: 60*80mm, tensile strength >=300MPa.
As the further scheme of the present invention:Step 4) in, on vegetable fiber blanket, soil, straw, fertilizer, slag, guarantor Water preparation is that mass ratio is:80-120:0.5-30:1-15:0.5-20:0.1-10.
As the further scheme of the present invention:Step 4) in, described straw is that crop material is pulverized frustillatum, powdery Or its mixture.
As the further scheme of the present invention:Step 4) in, described fertilizer is to pulverize fertilizer, crosses 3-7mm sieve.
As the further scheme of the present invention:Step 4) in, described slag is boiler room garbage, crosses 3-7mm after pulverizing Sieve.
As the further scheme of the present invention:Step 4) in, described water-retaining agent is commercially available water-retaining agent granule.
Compared with prior art, the invention has the beneficial effects as follows:
The present invention utilizes reinforced bar net fixation domatic, prevents domatic rubble from dropping, collapsing it is ensured that slope structure consolidates, domatic Laying vegetable fiber blanket, strengthens the stability of side slope, effectively reduces domatic moisture evaporation, can rationally control plant growing density, Reduce the demand to nutrient while ensureing vegetation cover degree;GSZ plays suppression to vegetable fiber blanket, prevents from planting Fibres blanket imbibition is excessively separated it is ensured that root system of plant can be colonized on domatic with domatic, plays reinforcement effect.This Bright carry out High aititude slope ecological recovery, construction technology is relatively simple, reduce pipe support level, a large amount of manpowers, thing can be saved Power, reduces construction cost, ecosystem restoration is respond well simultaneously.
Specific embodiment
Below in conjunction with the embodiment of the present invention, the technical scheme in the embodiment of the present invention is clearly and completely described, Obviously, described embodiment is only a part of embodiment of the present invention, rather than whole embodiments.Based in the present invention Embodiment, the every other embodiment that those of ordinary skill in the art are obtained under the premise of not making creative work, all Belong to the scope of protection of the invention.
Embodiment 1
In the embodiment of the present invention, a kind of High aititude slope ecological recovery method, comprise the following steps:
1) side slope face cleaning:Remove High aititude side slope face debris, debris include Pumex, surface dust, opposite side is domatic carry out smooth Process.
2) anchor bolt construction:Labelling anchor pole position, carries out bore operation, anchor hole diameter 30mm, hole depth 400mm, anchor hole Spacing 0.8m*0.8m, installs bolt diameter 10mm, rock-bolt length 400mm, rock-bolt length 5cm is reserved in side slope face, and anchor pole top is curved Roll over, and irrigate Anchor Agent and be fixed.
3) linked network:In step 2) side slope face laying reinforced bar net, and be fixed on the reserved anchor pole in side slope face.Described reinforced bar net is The plastic steel wire of PVC, size of mesh:60*80mm, tensile strength >=300MPa.
4) lay vegetable fiber blanket:In step 3) surface laying vegetable fiber blanket, and side slope face is fixed on by mounting ring On reserved anchor pole;Vegetable fiber blanket is provided with soil, straw, fertilizer, slag, water-retaining agent;On vegetable fiber blanket, soil, straw Stalk, fertilizer, slag, water-retaining agent are that mass ratio is:80:0.5:1:0.5:0.1.Straw is that crop material is ground into fritter Shape, powdery or its mixture.Fertilizer is to pulverize fertilizer, crosses 3mm sieve.Slag is boiler room garbage, crosses 3mm after pulverizing Sieve.Water-retaining agent is commercially available water-retaining agent granule.On vegetable fiber blanket, also drought-enduring, the impoverishment tolerant type shrub of plant, herbaceous plant kind are broadcast in mixing Son, grass blade.
5) secondary linked network:In step 4) surface laying GSZ, make step 4) vegetable fiber blanket is close to side slope face, and consolidate On anchor pole.
6) fixing:In step 5) GSZ and vegetable fiber blanket are fixed on side slope face surface holdfast, wherein side Holdfast need to be encrypted by domatic corner, concavo-convex place and net lap-joint.
7) water seasoning:High-pressure atomization is taken to sow grass seeds by duster mode, to step 6) surface carries out water seasoning, waters many on a small quantity Secondary, till being repeatedly sprayed to saturation.
Embodiment 2
In the embodiment of the present invention, a kind of High aititude slope ecological recovery method, comprise the following steps:
1) side slope face cleaning:Remove High aititude side slope face debris, debris include Pumex, surface dust, opposite side is domatic carry out smooth Process.
2) anchor bolt construction:Labelling anchor pole position, carries out bore operation, anchor hole diameter 35mm, hole depth 600mm, anchor hole Spacing 1.2m*1.2m, installs bolt diameter 14mm, rock-bolt length 600mm, rock-bolt length 10cm, anchor pole top are reserved in side slope face Bend, and irrigate Anchor Agent and be fixed.
3) linked network:In step 2) side slope face laying reinforced bar net, and be fixed on the reserved anchor pole in side slope face.Described reinforced bar net is The plastic steel wire of PVC, size of mesh:60*80mm, tensile strength >=300MPa.
4) lay vegetable fiber blanket:In step 3) surface laying vegetable fiber blanket, and side slope face is fixed on by mounting ring On reserved anchor pole;Vegetable fiber blanket is provided with soil, straw, fertilizer, slag, water-retaining agent;On vegetable fiber blanket, soil, straw Stalk, fertilizer, slag, water-retaining agent are that mass ratio is:120:30:15:20:10.Straw be by crop material pulverize frustillatum, Powdery or its mixture.Fertilizer is to pulverize fertilizer, crosses 7mm sieve.Slag is boiler room garbage, crosses 7mm sieve after pulverizing. Water-retaining agent is commercially available water-retaining agent granule.On vegetable fiber blanket also mixing broadcast drought-enduring, the impoverishment tolerant type shrub of plant, herbaceous plant seeds, Grass blade.
5) secondary linked network:In step 4) surface laying GSZ, make step 4) vegetable fiber blanket is close to side slope face, and consolidate On anchor pole.
6) fixing:In step 5) GSZ and vegetable fiber blanket are fixed on side slope face surface holdfast, wherein side Holdfast need to be encrypted by domatic corner, concavo-convex place and net lap-joint.
7) water seasoning:High-pressure atomization is taken to sow grass seeds by duster mode, to step 6) surface carries out water seasoning, waters many on a small quantity Secondary, till being repeatedly sprayed to saturation.
Embodiment 3
In the embodiment of the present invention, a kind of High aititude slope ecological recovery method, comprise the following steps:
1) side slope face cleaning:Remove High aititude side slope face debris, debris include Pumex, surface dust, opposite side is domatic carry out smooth Process.
2) anchor bolt construction:Labelling anchor pole position, carries out bore operation, anchor hole diameter 32mm, hole depth 500mm, anchor hole Spacing 1m*1m, installs bolt diameter 12mm, rock-bolt length 500mm, rock-bolt length 8cm is reserved in side slope face, anchor pole top bends, And irrigate Anchor Agent and be fixed.
3) linked network:In step 2) side slope face laying reinforced bar net, and be fixed on the reserved anchor pole in side slope face.Described reinforced bar net is The plastic steel wire of PVC, size of mesh:60*80mm, tensile strength >=300MPa.
4) lay vegetable fiber blanket:In step 3) surface laying vegetable fiber blanket, and side slope face is fixed on by mounting ring On reserved anchor pole;Vegetable fiber blanket is provided with soil, straw, fertilizer, slag, water-retaining agent;On vegetable fiber blanket, soil, straw Stalk, fertilizer, slag, water-retaining agent are that mass ratio is:100:10:10:10:5.Straw be by crop material pulverize frustillatum, Powdery or its mixture.Fertilizer is to pulverize fertilizer, crosses 5mm sieve.Slag is boiler room garbage, crosses 5mm sieve after pulverizing. Water-retaining agent is commercially available water-retaining agent granule.On vegetable fiber blanket also mixing broadcast drought-enduring, the impoverishment tolerant type shrub of plant, herbaceous plant seeds, Grass blade.
5) secondary linked network:In step 4) surface laying GSZ, make step 4) vegetable fiber blanket is close to side slope face, and consolidate On anchor pole.
6) fixing:In step 5) GSZ and vegetable fiber blanket are fixed on side slope face surface holdfast, wherein side Holdfast need to be encrypted by domatic corner, concavo-convex place and net lap-joint.
7) water seasoning:High-pressure atomization is taken to sow grass seeds by duster mode, to step 6) surface carries out water seasoning, waters many on a small quantity Secondary, till being repeatedly sprayed to saturation.
It is obvious to a person skilled in the art that the invention is not restricted to the details of above-mentioned one exemplary embodiment, Er Qie In the case of the spirit or essential attributes of the present invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, embodiment all should be regarded as exemplary, and be nonrestrictive, the scope of the present invention is by appended power Profit requires rather than described above limits, it is intended that all in the implication and scope of the equivalency of claim by falling Change is included in the present invention.
Moreover, it will be appreciated that although this specification is been described by according to embodiment, not each embodiment only wraps Containing an independent technical scheme, only for clarity, those skilled in the art should for this narrating mode of description Using description as an entirety, the technical scheme in each embodiment can also form those skilled in the art through appropriately combined Understandable other embodiment.

Claims (8)

1. a kind of High aititude slope ecological recovery method is it is characterised in that comprise the following steps:
1) side slope face cleaning:Remove High aititude side slope face debris, debris include Pumex, surface dust, and opposite side is domatic to carry out smooth process;
2) anchor bolt construction:Labelling anchor pole position, carries out bore operation, and rock-bolt length 5-10cm is reserved in side slope face, and anchor pole top is curved Roll over, and irrigate Anchor Agent and be fixed;
3) linked network:In step 2) side slope face laying reinforced bar net, and be fixed on the reserved anchor pole in side slope face;
4) lay vegetable fiber blanket:In step 3) surface laying vegetable fiber blanket, and it is reserved to be fixed on side slope face by mounting ring On anchor pole;Vegetable fiber blanket is provided with soil, straw, fertilizer, slag, water-retaining agent;On vegetable fiber blanket also mixing broadcast plant resistance to Drought, impoverishment tolerant type shrub, herbaceous plant seeds, grass blade;
5) secondary linked network:In step 4) surface laying GSZ, make step 4) vegetable fiber blanket is close to side slope face, and be fixed on On anchor pole;
6) fixing:In step 5) GSZ and vegetable fiber blanket are fixed on side slope face surface holdfast, wherein side slope face Holdfast need to be encrypted by corner, concavo-convex place and net lap-joint;
7) water seasoning:High-pressure atomization is taken to sow grass seeds by duster mode, to step 6) surface carries out water seasoning, waters multiple, instead on a small quantity Till being sprayed to saturation again.
2. High aititude slope ecological recovery method according to claim 1 is it is characterised in that step 2) in, anchor hole diameter 30-35mm, hole depth 400-600mm, hole interval 0.8-1.2m*0.8-1.2m, install bolt diameter 10-14mm, anchor pole Length 400-600mm.
3. High aititude slope ecological recovery method according to claim 1 is it is characterised in that step 3) in, described reinforcement Net is the plastic steel wire of PVC, size of mesh:60*80mm, tensile strength >=300MPa.
4. High aititude slope ecological recovery method according to claim 1 is it is characterised in that step 4) in, Plant fiber On blanket, soil, straw, fertilizer, slag, water-retaining agent are that mass ratio is:80-120:0.5-30:1-15:0.5-20:0.1-10.
5. High aititude slope ecological recovery method according to claim 1 is it is characterised in that step 4) in, described straw It is that crop material is pulverized frustillatum, powdery or its mixture.
6. High aititude slope ecological recovery method according to claim 1 is it is characterised in that step 4) in, described organic Fertilizer is to pulverize fertilizer, crosses 3-7mm sieve.
7. High aititude slope ecological recovery method according to claim 1 is it is characterised in that step 4) in, described slag For boiler room garbage, after pulverizing, cross 3-7mm sieve.
8. High aititude slope ecological recovery method according to claim 1 is it is characterised in that step 4) in, described water conservation Agent is commercially available water-retaining agent granule.
CN201610771836.0A 2016-08-31 2016-08-31 Method for ecological restoration of high-altitude slope Pending CN106385847A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610771836.0A CN106385847A (en) 2016-08-31 2016-08-31 Method for ecological restoration of high-altitude slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610771836.0A CN106385847A (en) 2016-08-31 2016-08-31 Method for ecological restoration of high-altitude slope

Publications (1)

Publication Number Publication Date
CN106385847A true CN106385847A (en) 2017-02-15

Family

ID=58003823

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610771836.0A Pending CN106385847A (en) 2016-08-31 2016-08-31 Method for ecological restoration of high-altitude slope

Country Status (1)

Country Link
CN (1) CN106385847A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108243932A (en) * 2018-03-21 2018-07-06 合肥雪立歆农业科技有限公司 A kind of Chinese herbaceous peony and the slope planting technique method of black eye flower
CN108243897A (en) * 2017-12-28 2018-07-06 青岛冠中生态股份有限公司 For the high heat insulating ability matrix of high altitude localities breakage mountain body revegetation
CN108990713A (en) * 2018-06-05 2018-12-14 山西大学 A kind of ecological restoring method administered for high altitudes and cold area engineering slope
CN113133380A (en) * 2021-05-17 2021-07-20 兰州大学 Ecological restoration method for cold and arid region side slope and abandoned mine
CN114793770A (en) * 2022-06-02 2022-07-29 国网福建省电力有限公司电力科学研究院 Method for promoting slope ecological restoration through manual intervention
CN115288165A (en) * 2022-08-17 2022-11-04 国网福建省电力有限公司电力科学研究院 Grading slope protection method for slope protection

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6378923A (en) * 1986-09-19 1988-04-09 Masanori Yoshikawa Vegetating work for concrete or mortar retaining wall
KR100917790B1 (en) * 2009-03-09 2009-09-21 주식회사동인건설 Grid type hollow block for ecological restoration of bank and construction method of bank using thereof
CN101748719A (en) * 2009-12-23 2010-06-23 南京大学 Method of vegetation restoration and reconstruction of bare rock slope in East China
CN201957412U (en) * 2010-12-13 2011-09-07 北京市蓝德环能科技开发有限责任公司 Vegetable fiber blanket with grass seeds
CN102425181A (en) * 2011-12-26 2012-04-25 杭州市园林绿化工程有限公司 Side slope greening restoration method
JP4979789B2 (en) * 2010-04-14 2012-07-18 株式会社国土再生研究所 Construction method of stair-permeable permeable retaining fence
CN104303749A (en) * 2014-09-28 2015-01-28 武汉橄石代环境资源科技有限公司 Abrupt slope spray-seeding greening method
CN104947693A (en) * 2015-05-07 2015-09-30 四川大学 Method for restoring vegetation on high and steep slopes by aid of coiled plant materials

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6378923A (en) * 1986-09-19 1988-04-09 Masanori Yoshikawa Vegetating work for concrete or mortar retaining wall
KR100917790B1 (en) * 2009-03-09 2009-09-21 주식회사동인건설 Grid type hollow block for ecological restoration of bank and construction method of bank using thereof
CN101748719A (en) * 2009-12-23 2010-06-23 南京大学 Method of vegetation restoration and reconstruction of bare rock slope in East China
JP4979789B2 (en) * 2010-04-14 2012-07-18 株式会社国土再生研究所 Construction method of stair-permeable permeable retaining fence
CN201957412U (en) * 2010-12-13 2011-09-07 北京市蓝德环能科技开发有限责任公司 Vegetable fiber blanket with grass seeds
CN102425181A (en) * 2011-12-26 2012-04-25 杭州市园林绿化工程有限公司 Side slope greening restoration method
CN104303749A (en) * 2014-09-28 2015-01-28 武汉橄石代环境资源科技有限公司 Abrupt slope spray-seeding greening method
CN104947693A (en) * 2015-05-07 2015-09-30 四川大学 Method for restoring vegetation on high and steep slopes by aid of coiled plant materials

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108243897A (en) * 2017-12-28 2018-07-06 青岛冠中生态股份有限公司 For the high heat insulating ability matrix of high altitude localities breakage mountain body revegetation
CN108243932A (en) * 2018-03-21 2018-07-06 合肥雪立歆农业科技有限公司 A kind of Chinese herbaceous peony and the slope planting technique method of black eye flower
CN108990713A (en) * 2018-06-05 2018-12-14 山西大学 A kind of ecological restoring method administered for high altitudes and cold area engineering slope
CN113133380A (en) * 2021-05-17 2021-07-20 兰州大学 Ecological restoration method for cold and arid region side slope and abandoned mine
CN113133380B (en) * 2021-05-17 2023-11-28 兰州大学 Ecological restoration method for side slopes and abandoned mines in cold and dry areas
CN114793770A (en) * 2022-06-02 2022-07-29 国网福建省电力有限公司电力科学研究院 Method for promoting slope ecological restoration through manual intervention
CN115288165A (en) * 2022-08-17 2022-11-04 国网福建省电力有限公司电力科学研究院 Grading slope protection method for slope protection

Similar Documents

Publication Publication Date Title
CN106385847A (en) Method for ecological restoration of high-altitude slope
CN101761086B (en) Three-dimensional net greening technique for roadbed side slope
CN101818499B (en) Revegetation system on steep rocky slopes and implementing method thereof
CN102677684B (en) Spraying and sowing greening method for concrete anchoring and shotcreting slope
CN108589743B (en) Ecological geogrid for slope protection
CN100397972C (en) Method for recovering vegetation on rock dome in north region
CN105297745A (en) Protection method for high and steep side slope ecological restoration technology
CN105165325B (en) A kind of cohesive soil with low liquid protecting slope ecology method
CN105926533B (en) A kind of embedded type ecology consolidates beach method
CN108605460A (en) Grassland region opencast coal mine dump method for recovering vegetation and ecological recovery method
CN109832074B (en) Method for recovering vegetation in karst region lead-zinc ore polluted rocky desertification area
CN103250536A (en) Method for spraying to green side slope of hard rock with joints being not developed
CN102379201B (en) Method of quick restoration of vegetation in reservoir hydro-fluctuation belt
CN110612793A (en) Spray-seeding greening method for waste rock hill
CN104186137A (en) Technology for cultivating and greening tall fescue grass on inshore mud flat saline-alkali soil
CN108547307A (en) Protecting slope ecology method based on artificial loam
CN110541423A (en) High-steep bare rock slope ecological restoration system and method
CN104947693B (en) A kind of method that utilization plant coiled material carries out high gradient slope revegetation
CN108476649A (en) A kind of gardens abrupt slope plant landscape method
CN112211203A (en) High-strength structure organic fiber composite repair method for high and steep slope
CN210946834U (en) Immersed net type ecological slope protection structure for mine restoration
CN104541641A (en) Method of thinning, eliminating soil salt and increasing yield by arranging crushed ridge bind drain system
CN110622643A (en) Ecological restoration method for rock slope in high-latitude severe cold region
CN105191733A (en) Slope hole planting greening method
CN1257664C (en) Method for planting mixed watering glass for protecting side slope of highroad

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170215