CN106049644B - A kind of concrete drain tile contains the quick reparation erecting device of detection drilling and its restorative procedure - Google Patents

A kind of concrete drain tile contains the quick reparation erecting device of detection drilling and its restorative procedure Download PDF

Info

Publication number
CN106049644B
CN106049644B CN201610590198.2A CN201610590198A CN106049644B CN 106049644 B CN106049644 B CN 106049644B CN 201610590198 A CN201610590198 A CN 201610590198A CN 106049644 B CN106049644 B CN 106049644B
Authority
CN
China
Prior art keywords
baffle
connecting rod
fixation
detection drilling
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610590198.2A
Other languages
Chinese (zh)
Other versions
CN106049644A (en
Inventor
周骅
余凯华
沈建彪
鲍月全
辛伟
张琦
王秋光
张彦晶
李宁
季斌
盛忠明
严晔明
韩晓嫣
谢永健
唐坚
邓旭
江晓华
李震宇
徐禅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI CITY MUNICIPAL DRAINAGE CO Ltd
Shanghai Geotechnical Investigations and Design Institute Co Ltd
Original Assignee
SHANGHAI CITY MUNICIPAL DRAINAGE CO Ltd
Shanghai Geotechnical Investigations and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI CITY MUNICIPAL DRAINAGE CO Ltd, Shanghai Geotechnical Investigations and Design Institute Co Ltd filed Critical SHANGHAI CITY MUNICIPAL DRAINAGE CO Ltd
Priority to CN201610590198.2A priority Critical patent/CN106049644B/en
Publication of CN106049644A publication Critical patent/CN106049644A/en
Application granted granted Critical
Publication of CN106049644B publication Critical patent/CN106049644B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes
    • E03F2003/065Refurbishing of sewer pipes, e.g. by coating, lining

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a kind of concrete drain tile to contain the quick reparation erecting device of detection drilling and its restorative procedure, connecting rod, the second fixation connecting rod, the 3rd fixation connecting rod, the 4th fixation connecting rod and connecting rod positioning component are fixed including first baffle, second baffle, third baffle, first, concrete drain tile disclosed by the invention contain detection drilling it is quick repair erecting device and enter in implementation process without staff inside draining pipe culvert carry out formwork, reduce cost and construction risk;Its bottom hole baffle can completely cover whole foot of hole, under the sealing process of hermetic seal material, avoid spillage;For short-term, in the case where bore inner grouting material or high-early (strength) cement mortar be not dry, if pipe culvert inside water pressure is recovered, bottom hole baffle can bear hydraulic pressure, and prevent sewage from leaking outside;For long-term, repair and be all in the milk in hole, the same neighbouring pipe thickness of the concrete thickness formed in hole after slip casting, can hold inner pipe water pressure, favourable to structure stress.

Description

A kind of concrete drain tile contains the quick reparation erecting device of detection drilling and its reparation Method
Technical field
The present invention relates to the recovery technique field of draining pipe culvert in municipal works, and in particular to a kind of concrete drain tile is contained Detection drilling is quick to repair erecting device and its restorative procedure.
Background technology
Concrete drain tile is contained in the long-term use, under internal hydrogen sulfide gas and sewage long-term corrosion, pipe culvert Progressively there is concrete roof corrosion spalling in inside, and major structural defect, the bearing capacities such as reinforcing bar rust breaks, comes off are cut significantly It is weak, pipe culvert safe operation is influenced, structure detection need to be carried out.During being detected to pipe culvert structure, generally require to mixed Solidifying soil pipe culvert top plate core boring sampling.After the completion of drill core, drilling should quickly be repaired before pipe culvert recovers operation hydraulic pressure.Repair Key be to after formwork at aperture on the inside of pipe culvert, pouring into a mould grouting material or high-early (strength) cement mortar to aperture from outside aperture and marking It is high.
Comparatively ideal erecting device need to meet two point requirements:
(1) prevent the grouting material in injection hole or high-early (strength) cement mortar from leaking outside at bottom hole and form joint;
(2) the repairing short-term and long term time interior energy after the completion of making of returning to work bears the effect of pipe culvert inside water pressure power.
In the technical literature of existing announcement, the report for containing detection drilling quick-restoring device to concrete drain tile is not yet found Road.In Practical Project, the formwork in drilling repair process is mainly carried out using two kinds of devices:
One kind is to carry out bottom hole formwork using stopper, can be implemented outside pipe culvert.During implementation, from pipe culvert outside, according to hole Depth, diameter is squeezed into hole at certain depth slightly larger than the round log plug in aperture, between stopper and hole wall under frictional force effect, Stopper can be placed in designated position without falling, then hole inner region injection grouting material or early strong water between stopper and aperture Cement mortar is to aperture absolute altitude.The device shortcoming is stopper with rotten, after-pouring in hole easily occurs after sewage Long Term Contact in pipe culvert Concrete directly bears hydraulic pressure, and its thickness is less than other positions concrete wall thickness, and bearing capacity weakens, and easily causes local hidden Suffer from;
Another kind is the branch carried out with the tube of a base diameter expansion and closing in pipe culvert drilling repair process Mould, need to implement inside pipe culvert.During implementation, the professional that need to be equipped with diving and oxygen supply equipment enters draining pipe culvert, this is filled Diameter small end to be put to be fixed with switch through after drilling inside pipe culvert, device end diameter expansion segment can block bottom hole portion, Prevent grouting material or high-early (strength) cement mortar from leaking outside from bottom hole, so as to reach reparation purpose.The device shortcoming is need to be inside pipe culvert Implement, cost is larger.
Technical scheme is that the quick erecting device of repairing of pipe culvert detection drilling is carried out regarding to the issue above Improve.
The content of the invention
In order to overcome deficiency of the prior art, the present invention provides a kind of concrete drain tile culvert and detects quick repair that drill Erecting device and its restorative procedure, employ combination erecting device, and the bottom hole template that required area is more than to hole area is split as Three baffles, and angle of flap is adjustable, can be easily put into through drilling inside pipe culvert, expansion can be combined to a bottom hole template, Realize and formwork quickly carried out to tube wall drilling on the outside of the concrete pipe culvert, it is ensured that after the grouting material that pours into or high-early (strength) cement mortar not It can leak outside, and the short-term and long term time interior energy that device repairing is returned to work after the completion of making bears the effect of pipe culvert inside water pressure power Target.
In order to reach foregoing invention purpose, technical solution is as follows used by solving its technical problem:
The invention discloses a kind of concrete drain tile to contain the quick reparation erecting device of detection drilling, for repairing pipe culvert top Detection drilling on plate, including first baffle, second baffle, third baffle, the first fixation connecting rod, the second fixation connecting rod, the 3rd Fixed connecting rod, the 4th fix connecting rod and connecting rod positioning component, wherein:
The lower end of the second fixation connecting rod and the 3rd fixation connecting rod passes through corresponding hinge member and described second respectively Baffle and third baffle, which correspond to, to be hinged, and the first fixation connecting rod and the 4th fixation connecting rod are located on the first baffle, and Set along the length direction of the first baffle, described first, which fixes connecting rod and the 4th, fixes the lower end of connecting rod respectively by corresponding Hinge member it is corresponding with the first baffle hinged, form the independent connection structure in left, center, right three altogether;
Three independent connection structures pass sequentially through the detection drilling and are deep into the inside of the draining pipe culvert, and then make Obtain after the first baffle, second baffle and third baffle are unfolded inside pipe culvert and be mutually twisted connection, be combined into a bottom hole mould Plate, the bottom hole template are connected to the draining pipe culvert inner wall and cover the lower face of the detection drilling;
It is described first fix connecting rod, second fix connecting rod, the 3rd fix connecting rod and the 4th fix connecting rod upper end with it is described Connecting rod positioning component is fixedly connected, and the sectional area of the connecting rod positioning component is more than the hole area of the detection drilling, with covering The upper surface of the detection drilling.
Further, some integrated positioning columns, the second baffle are symmetrically arranged with left and right sides of the first baffle Quantity phase is correspondingly provided with position of the third baffle with respect to several integrated positioning columns on the side of the first baffle With several integrated positioning holes, the integrated positioning column on the first baffle is each passed through the second baffle and third baffle On integrated positioning hole so that the first baffle, second baffle and third baffle are connected, and are combined into bottom hole template.
Further, the cross section of the first baffle is in convex shape, its left and right ends forms step-like structure, and described the Two baffles and third baffle are located above the left and right sides of the first baffle, and pass through the step-like structure and described first Baffle is engaged.
Preferably, hermetic seal material is further included, the hermetic seal material is respectively coated in the platform of the first baffle On stepped structure and its upper surface, and the opposite medial surface in upper surface and both of the second baffle and third baffle On.
Further, the cross section of the first baffle is rectangular, and the second baffle and third baffle are positioned at described the Above the left and right sides of one baffle, the second baffle and opposite two medial surfaces of third baffle are pressed on institute after mutually abutting State above first baffle.
Preferably, hermetic seal material is further included, the hermetic seal material is respectively coated in the upper surface of first baffle On, and on the opposite medial surface in upper surface and both of the second baffle and third baffle.
Further, the connecting rod positioning component includes a connecting rod positioning plate, and the connecting rod positioning plate is equipped with a slip casting Hole and four connecting rod location holes, wherein:
Four connecting rod location holes are uniformly distributed around the injected hole square or rectangular, and are respectively positioned on the inspection Drilling is surveyed in the drop shadow spread on the connecting rod positioning plate.
Further, described first the upper of connecting rod, the second fixation connecting rod, the 3rd fixation connecting rod and the 4th fixation connecting rod is fixed End is equipped with screw thread, and is threadedly coupled after being each passed through four connecting rod location holes with nut, so that described first is solid Determine connecting rod, the second fixation connecting rod, the 3rd fixation connecting rod and the 4th fixation connecting rod to be fixedly connected with the connecting rod positioning plate.
Further, several hole for the expansion bolt are also evenly arranged with the connecting rod positioning plate, with some expansions The connecting rod positioning plate is fixed on the drainpipe by the corresponding expansion bolt of number of bolt hole through the hole for the expansion bolt Contain on top plate outer surface, to prevent the connecting rod positioning plate occurred level from moving.
The invention discloses a kind of concrete drain tile to contain detection drilling fast repairing method, comprises the following steps:
Step 1:The lower end of second fixation connecting rod and the 3rd fixation connecting rod is passed through into corresponding hinge member and second respectively Baffle and third baffle correspond to hinged, and will be located on first baffle and along first the consolidating of setting of length direction of first baffle Determine connecting rod and the 4th lower end for fixing connecting rod is hinged by the way that corresponding hinge member is corresponding with first baffle respectively, form left, center, right Three independent connection structures;
Step 2:Connecting rod is fixed by first and the 4th the first connection structure for fixing connecting rod and first baffle formation passes through inspection Survey is drilled into inside pipe culvert, then fixes the second connection structure that connecting rod and second baffle are formed by second, and the 3rd consolidates The 3rd connection structure for determining connecting rod and third baffle formation is drilled into inside pipe culvert through detection, and positioned at the described first connection The left and right sides of structure;
Step 3:First baffle, second baffle and third baffle are mutually twisted connection after being unfolded inside pipe culvert, are combined into One bottom hole template, bottom hole template are connected to draining pipe culvert inner wall and cover the lower face of detection drilling;
Step 4:Sectional area is more than the connecting rod positioning component of detection drilling hole area and first and fixes connecting rod, second company of fixation The upper end of bar, the 3rd fixation connecting rod and the 4th fixation connecting rod is fixedly connected, with the upper surface of covering detection drilling;
Step 5:By being in the milk to the injected hole on connecting rod positioning component, to repair detection drilling.
Further, in step 3, the first baffle, second baffle and third baffle are combined into the tool of bottom hole template Body step includes:
Several integrated positioning columns being symmetrically disposed at left and right sides of the first baffle are each passed through positioned at described The quantity that two baffles and third baffle are accordingly set on the side of the first baffle with respect to several integrated positioning columns Several identical integrated positioning holes, realize that the first baffle, second baffle and third baffle are connected with this, are combined into Bottom hole template.
Further, in step 3, it is further comprising the steps of:
The first baffle for selecting cross section to be in convex shape, makes its left and right ends form step-like structure, so that described Second baffle and third baffle are engaged by the step-like structure with the first baffle.
Further, in step 3, it is further comprising the steps of:
Hermetic seal material is respectively coated on the step-like structure of the first baffle and its upper surface, and it is described On the opposite medial surface in the upper surface and both of second baffle and third baffle, to prevent spillage.
Further, in step 3, it is further comprising the steps of:
Select the rectangular first baffle in cross section so that described the above the left and right sides of the first baffle Two baffles and opposite two medial surfaces of third baffle are pressed on above the first baffle after mutually abutting.
Further, in step 3, it is further comprising the steps of:
Hermetic seal material is respectively coated on the upper surface of the first baffle, and the second baffle and the 3rd On the upper surface of baffle and the opposite medial surface of both, to prevent spillage.
Further, in step 4, it is further comprising the steps of:
Four are opened up on connecting rod positioning plate in connecting rod positioning component around injected hole square or rectangular uniformly to divide The connecting rod location hole of cloth so that four connecting rod location holes are respectively positioned on projection model of the detection drilling on the connecting rod positioning plate In enclosing.
Further, in step 4, it is further comprising the steps of:
The upper end for described first being fixed connecting rod, the second fixation connecting rod, the 3rd fixation connecting rod and the 4th fixation connecting rod is all provided with Into helicitic texture, and it is threadedly coupled after being each passed through four connecting rod location holes with nut, so that described first fixes Connecting rod, the second fixation connecting rod, the 3rd fixation connecting rod and the 4th fixation connecting rod are fixedly connected with the connecting rod positioning plate.
Further, in step 4, it is further comprising the steps of:
Several expansion bolts are passed through corresponding with some expansion bolt quantity and are uniformly arranged on the company Several hole for the expansion bolt on bar positioning plate, with this so that the connecting rod positioning plate is fixed on the draining pipe culvert top plate appearance On face, to prevent the connecting rod positioning plate occurred level from moving.
Further, step 6 is further included:A layer concrete is poured outside the connecting rod positioning component, is realized pair with this Repair the protection of erecting device.
The present invention is due to using above technical scheme, being allowed to compared with prior art, have the following advantages that and actively imitate Fruit:
1st, the quick reparation erecting device of concrete drain tile culvert detection drilling disclosed by the invention need not in implementation process Staff, which enters, carries out formwork inside draining pipe culvert, reduce cost and construction risk;
2nd, the bottom hole baffle that concrete drain tile disclosed by the invention is contained in the quick reparation erecting device of detection drilling can be complete The whole whole foot of hole of covering, under the sealing process of hermetic seal material, avoids spillage;
3rd, concrete drain tile disclosed by the invention contains the quick implementation result for repairing erecting device of detection drilling, from short-term For, in the case where bore inner grouting material or high-early (strength) cement mortar be not dry, if pipe culvert inside water pressure is recovered, bottom hole baffle can Hydraulic pressure is born, and prevents sewage from leaking outside;For long-term, repair and be all in the milk in hole, the Concrete Thick formed in hole after slip casting The same neighbouring pipe wall position thickness of degree, can hold inner pipe water pressure, favourable to structure stress.
Brief description of the drawings
In order to illustrate the technical solution of the embodiments of the present invention more clearly, required use in being described below to embodiment Attached drawing be briefly described.It is clear that drawings in the following description are only some embodiments of the present invention, for ability For field technique personnel, without creative efforts, other attached drawings can also be obtained according to these attached drawings.It is attached In figure:
Fig. 1 is that a kind of concrete drain tile of the present invention contains the quick overall structure signal for repairing erecting device of detection drilling Figure;
Fig. 2 is that a kind of concrete drain tile of the present invention contains the quick usage state diagram for repairing erecting device of detection drilling;
Fig. 3, which is that a kind of concrete drain tile culvert detection drilling of the present invention is quick, repairs each baffle and the company of fixation in erecting device The sectional drawing of bar;
Fig. 4, which is that a kind of concrete drain tile culvert detection drilling of the present invention is quick, repairs each baffle and the company of fixation in erecting device The top view of bar;
Fig. 5 is that a kind of concrete drain tile of the present invention contains the quick each baffle combination peace repaired in erecting device of detection drilling Fill floor map;
Fig. 6 is that a kind of concrete drain tile of the present invention contains the quick knot for repairing connecting rod positioning plate in erecting device of detection drilling Structure schematic diagram;
Fig. 7 is the partial process view that a kind of concrete drain tile of the present invention contains detection drilling fast repairing method;
Fig. 8 is the entire flow figure that a kind of concrete drain tile of the present invention contains detection drilling fast repairing method.
【Primary symbols explanation】
1- pipe culvert top plates;
2- first baffles;
3- second baffles;
4- third baffles;
5- first fixes connecting rod;
6- second fixes connecting rod;
7- the 3rd fixes connecting rod;
8- pipe culvert inner walls;
9- integrated positioning columns;
10- integrated positioning holes;
11- hermetic seal materials;
12- the 4th fixes connecting rod;
13- connecting rod positioning plates;
14- injected holes;
15- connecting rod location holes;
16- nuts;
17- hole for the expansion bolt;
18- expansion bolts;
19- hinge members.
Embodiment
Below with reference to the attached drawing of the present invention, clear, complete description is carried out to the technical solution in the embodiment of the present invention And discussion, it is clear that as described herein is only a part of example of the present invention, is not whole examples, based on the present invention In embodiment, the every other implementation that those of ordinary skill in the art are obtained on the premise of creative work is not made Example, belongs to protection scope of the present invention.
A kind of concrete drain tile of present invention offer contains the quick reparation erecting device of detection drilling and its restorative procedure, uses Combination erecting device, the bottom hole template that required area is more than to hole area is split as three baffles, and angle of flap is adjustable, can Easily it is put into through drilling inside pipe culvert, expansion can be combined to a bottom hole template, and it is quick right on the outside of concrete pipe culvert to realize Tube wall drilling carries out formwork, it is ensured that after the grouting material that pours into or high-early (strength) cement mortar will not leak outside, and device repairing is returned to work Short-term and long term time interior energy after the completion of work bears the target of pipe culvert inside water pressure power effect.
Embodiment one
As shown in Fig. 1,2,4 and 5, the invention discloses a kind of concrete drain tile to contain the quick reparation formwork dress of detection drilling Put, for repairing the drilling of the detection on pipe culvert top plate 1, including first baffle 2, second baffle 3, third baffle 4, first are fixed and connected Bar 5, second fixes connecting rod the 6, the 3rd and fixes the fixation connecting rod 12 of connecting rod the 7, the 4th and connecting rod positioning component, wherein:
Described second, which fixes connecting rod 6 and the 3rd, fixes the lower end of connecting rod 7 respectively by corresponding hinge member and described the Two baffles 3 and third baffle 4, which correspond to, to be hinged, and the first fixation connecting rod 5 and the 4th fixes connecting rod 12 and is located on the first gear On plate 2, and set along the length direction of the first baffle 2, described first fixes the lower end that connecting rod 5 and the 4th fixes connecting rod 12 It is corresponding with the first baffle 2 hinged by corresponding hinge member respectively, the independent connection knot in left, center, right three is formed altogether Structure, in the present embodiment, the angle of baffle and fixed connecting rod is adjustable, its angular range is between 0-90 °;It is in addition, described Hinge member 19 can be that hinge, articulated joint etc. can be achieved the hinged component of two devices;
Three independent connection structures pass sequentially through the detection drilling and are deep into the inside of the draining pipe culvert, and then make Obtain after the first baffle 2, second baffle 3 and third baffle 4 are unfolded inside pipe culvert and be mutually twisted connection, be combined into a bottom hole Template, the bottom hole template are connected to the draining pipe culvert inner wall 8 and cover the lower face of the detection drilling;
It is described first fix connecting rod 5, second fix connecting rod the 6, the 3rd fix connecting rod 7 and the 4th fix connecting rod 12 upper end with The connecting rod positioning component is fixedly connected, and the sectional area of the connecting rod positioning component is more than the hole area of the detection drilling, with Cover the upper surface of the detection drilling.
With reference to figure 3-5, further, the left and right sides of the first baffle 2 is symmetrically arranged with some integrated positioning columns 9, The second baffle 3 and third baffle 4 are on the side of the first baffle 2 with respect to the position of several integrated positioning columns 9 It is correspondingly provided with several identical integrated positioning holes 10 of quantity, the integrated positioning column 9 on the first baffle 2 is each passed through institute State the integrated positioning hole 10 on second baffle 3 and third baffle 4 so that the first baffle 2, second baffle 3 and third baffle 4 It is connected, is combined into bottom hole template.In the present embodiment, the quantity of the integrated positioning column 9 is 4, is distributed in two-by-two described The left and right sides of first baffle 2, while the quantity of integrated positioning hole 10 is similarly 4, is distributed in 3 He of second baffle two-by-two Third baffle 4 is on the side of the first baffle 2.Preferably, it is distributed in the second baffle 3 and third baffle 4 Two integrated positioning holes 10 are symmetrically disposed on described second and fix the both sides up and down that connecting rod 6 and the 3rd fixes connecting rod 7 so that each gear Plate is easy to be engaged after deployment.Certainly, we can set greater number of integrated positioning column 9 and integrated positioning hole 10 herein, Better technique effect is engaged between bringing each baffle with this, but equally brings each baffle and implements not during occlusion Just unfavorable effect.The present embodiment is based on occlusion effect and occlusion difficulty comprehensive consideration, by integrated positioning column 9 and integrated positioning The quantity in hole 10 is arranged to 4, is with the effect optimized.Certainly, in relation to integrated positioning column 9 and combination in the present embodiment Different set of the quantity of location hole 10 belongs to protection scope of the present invention.
As shown in Figs. 1-3, further, the cross section of the first baffle 2 is in convex shape, its left and right ends forms step Shape structure, the second baffle 3 and third baffle 4 are located above the left and right sides of the first baffle 2, and pass through the step Shape structure is engaged with the first baffle 2.Cross section may be such that second baffle 3, first baffle 2 in the first baffle 2 of convex shape A horizontal plane is formed with the upper surface of third baffle 4 and is directly connected to pipe culvert inner wall 8 and detection drilling lower end, is subsequently being in the milk During so that the thickness for part of being in the milk and the consistency of thickness of pipe culvert top plate, repairing effect are good.
With continued reference to Fig. 2,3 and 5, it is preferred that further include hermetic seal material 11, the hermetic seal material 11 applies respectively It is overlying on step-like structure and its upper surface of the first baffle 2, and the upper table of the second baffle 3 and third baffle 4 On face and the opposite medial surface of both.Under the sealing function of the hermetic seal material 11, occlusion seam, each gear between baffle Gap between plate and pipe culvert inner wall 8 can be filled even closer by hermetic seal material 11, prevent the grouting material subsequently poured into Or spillage occurs for high-early (strength) cement mortar.In the present embodiment, the hermetic seal material 11 can use hydro-expansive rubber.
In addition, in an other embodiment, the cross section of the first baffle 2 is rectangular, the second baffle 3 and third gear Plate 4 is located above the left and right sides of the first baffle 2, the second baffle 3 and the opposite two medial surface phases of third baffle 4 The top of first baffle 2 is pressed on after mutually abutting.Preferably, hermetic seal material 11, the hermetic seal material are further included 11 are respectively coated on the upper surface of first baffle 2, and the upper surface and both of the second baffle 3 and third baffle 4 On opposite medial surface.Equally in the present embodiment, the hermetic seal material 11 can use hydro-expansive rubber.
With further reference to Fig. 6, the connecting rod positioning component includes a connecting rod positioning plate 13, is set on the connecting rod positioning plate 13 There are an injected hole 14 and four connecting rod location holes 15, wherein:
Four connecting rod location holes 15 are uniformly distributed around 14 square or rectangular of injected hole, and are respectively positioned on institute Detection drilling is stated in the drop shadow spread on the connecting rod positioning plate 13.That is, the corresponding connection of four connecting rod location holes 15 Four fixed connecting rods be respectively positioned on detection drilling in.In the present embodiment, the injected hole 14 is preferably disposed on the connecting rod positioning 13 center of plate.
With reference to Fig. 3 and 5, further, described first, which fixes connecting rod 5, second, fixes connecting rod 6, the 3rd fixes connecting rod 7 and the The upper end of four fixation connecting rods 12 is equipped with screw thread, and connects after being each passed through four connecting rod location holes 15 with 16 screw thread of nut Connect, so that described first fixes fixation connecting rod the 6, the 3rd fixation connecting rod 7 and the 4th fixation connecting rod 12 of connecting rod 5, second and institute Connecting rod positioning plate 13 is stated to be fixedly connected.In this step, it may be such that fixed connecting rod produces a upward drawing using the design of nut Power so that between each baffle, it is snugly more close between baffle and pipe culvert inner wall 8, sealing effect is more preferably.In addition, nut to Under reaction force under, connecting rod positioning plate 13 can be fitted tightly over the outer surface of pipe culvert top plate 1.
As shown in fig. 6, it is further, several hole for the expansion bolt 17 are also evenly arranged with the connecting rod positioning plate 13, The connecting rod is determined through the hole for the expansion bolt 17 with some corresponding expansion bolts 18 of 17 quantity of hole for the expansion bolt Position plate 13 is fixed on 1 outer surface of draining pipe culvert top plate, to prevent 13 occurred level of connecting rod positioning plate from moving.This In embodiment, the quantity of the hole for the expansion bolt 17 and expansion bolt 18 is 4, and is uniformly distributed in connecting rod positioning plate 13 On four direction, by connecting rod positioning plate 13 and 1 fixation procedure of pipe culvert top plate so that connecting rod positioning plate 13 is on four direction Uniform force, fixed effect is more preferably.Certainly, more, the fixed effect of the quantity of the hole for the expansion bolt 17 and expansion bolt 18 It is better, but for cost and fixed effect comprehensive consideration, only need to being set up and down on four direction in connecting rod positioning plate 13 Hole for the expansion bolt 17, and coordinate expansion bolt 18 to be fixed can to reach desired effects.
Embodiment two
As shown in fig. 7, the invention discloses a kind of concrete drain tile to contain detection drilling fast repairing method, including it is following Step:
Step 1:By second fix connecting rod 6 and the 3rd fix connecting rod 7 lower end respectively by corresponding hinge member 19 with Second baffle 3 and third baffle 4, which correspond to, to be hinged, and will be located on first baffle 2 and be set along the length direction of first baffle 2 First fix connecting rod 5 and the 4th fix connecting rod 12 lower end it is corresponding with first baffle 2 by corresponding hinge member 19 respectively It is hinged, form the independent connection structure in left, center, right three;
Step 2:The first connection structure that first fixation connecting rod 5 and the 4th fixation connecting rod 12 and first baffle 2 are formed is worn Cross detection to drill into inside pipe culvert, the second connection structure for then forming the second fixation connecting rod 6 and second baffle 3, and The 3rd connection structure that 3rd fixation connecting rod 7 and third baffle 4 are formed is drilled into inside pipe culvert through detection, and positioned at described The left and right sides of first connection structure;
Step 3:First baffle 2, second baffle 3 and third baffle 4 are mutually twisted connection after being unfolded inside pipe culvert, combine Into a bottom hole template, bottom hole template is connected to draining pipe culvert inner wall 8 and covers the lower face of detection drilling;
Step 4:Sectional area is more than the connecting rod positioning component of detection drilling hole area and first and fixes the fixation of connecting rod 5, second Connecting rod the 6, the 3rd is fixed connecting rod 7 and is fixedly connected with the upper end of the 4th fixation connecting rod 12, with the upper surface of covering detection drilling;
Step 5:By being in the milk to the injected hole 14 on connecting rod positioning component, to repair detection drilling.
In the present embodiment, before implementation steps 2, the angle between each baffle and each fixed connecting rod is adjusted to first 0 °, each connection structure is facilitated to be put into detection drilling.
For in step 2, the second connection structure and the 3rd connection structure pass through detection to drill into the priority inside pipe culvert Order is not construed as limiting, and only need to ensure that the first connection structure first passes through detection and drills into pipe culvert inside.
Further, before implementation steps 3, by pulling each fixed connecting rod, while by the reaction of pipe culvert inner wall 8 Power so that the angle between each baffle and each fixed connecting rod is sequentially adjusted in as 90 °.
In step 3, the first baffle 2, second baffle 3 and third baffle 4 are combined into the specific steps of bottom hole template Including:
Each baffle relative position is adjusted by fixed connecting rod, can will be symmetrically disposed on the left and right sides of first baffle 2 Several integrated positioning columns 9 are each passed through positioned at the second baffle 3 and third baffle 4 close to the side of the first baffle 2 Several identical integrated positioning holes 10 of the quantity that several integrated positioning columns 9 are accordingly set upper relatively, are realized described with this First baffle 2, second baffle 3 and third baffle 4 are connected, and are combined into bottom hole template.
Further, in step 3, it is further comprising the steps of:
The first baffle 2 for selecting cross section to be in convex shape, makes its left and right ends form step-like structure, so that described Second baffle 3 and third baffle 4 are engaged by the step-like structure with the first baffle 2.
Further, in step 3, it is further comprising the steps of:
Hermetic seal material 11 is respectively coated on the step-like structure of the first baffle 2 and its upper surface, and On the second baffle 3 medial surface opposite with the upper surface of third baffle 4 and both, to prevent spillage.
Further, in step 3, it is further comprising the steps of:
Select the rectangular first baffle 2 in cross section so that described in above the left and right sides of the first baffle 2 Second baffle 3 and opposite two medial surfaces of third baffle 4 are pressed on the top of first baffle 2 after mutually abutting.
Further, in step 3, it is further comprising the steps of:
Hermetic seal material 11 is respectively coated on the upper surface of the first baffle 2, and 3 He of the second baffle On the upper surface of third baffle 4 and the opposite medial surface of both, to prevent spillage.
Further, in step 4, it is further comprising the steps of:
Opened up on connecting rod positioning plate 13 in connecting rod positioning component four around 14 square or rectangular of injected hole it is equal The connecting rod location hole 15 of even distribution so that four connecting rod location holes 15 are respectively positioned on detection drilling in the connecting rod positioning plate 13 On drop shadow spread in.
Further, in step 4, it is further comprising the steps of:
The upper end for fixing the fixation fixation fixation connecting rod 12 of connecting rod 7 and the 4th of connecting rod the 6, the 3rd of connecting rod 5, second by described first Helicitic texture is set as, and is threadedly coupled after being each passed through four connecting rod location holes 15 with nut 16, so that described First fixation connecting rod 5, second is fixed fixation connecting rod 7 and the 4th fixation connecting rod 12 of connecting rod the 6, the 3rd and is consolidated with the connecting rod positioning plate 13 Fixed connection.In this step, the method being fixed using nut may be such that fixed connecting rod produces a upward pulling force, so that respectively Between baffle, it is snugly more close between baffle and pipe culvert inner wall 8, sealing effect is more preferably.In addition, in the downward reaction of nut Under power, connecting rod positioning plate 13 can be fitted tightly over the outer surface of pipe culvert top plate 1.
Further, in step 4, it is further comprising the steps of:
Several expansion bolts 18 are passed through corresponding with some 18 quantity of expansion bolt and are uniformly arranged on institute Several hole for the expansion bolt 17 on connecting rod positioning plate 13 are stated, with this so that the connecting rod positioning plate 13 is fixed on the drainpipe Contain on 1 outer surface of top plate, to prevent 13 occurred level of connecting rod positioning plate from moving.
As shown in figure 8, it is further, further include step 6:A layer concrete is poured outside the connecting rod positioning component, The protection to repairing erecting device is realized with this.
Concrete drain tile disclosed by the invention contains the quick reparation erecting device of detection drilling in implementation process without work Make personnel into progress formwork inside draining pipe culvert, reduce cost and construction risk.Bottom hole baffle in its device can completely cover Whole foot of hole is covered, under the sealing process of hydro-expansive rubber, avoids spillage.With regard to its implementation result aspect, from short term Say, in the case where bore inner grouting material or high-early (strength) cement mortar be not dry, if pipe culvert inside water pressure is recovered, bottom hole baffle can be held By hydraulic pressure, and prevent sewage from leaking outside;For long-term, repair and be all in the milk in hole, the concrete thickness formed in hole after slip casting With neighbouring pipe wall position thickness, inner pipe water pressure can be held, it is favourable to structure stress.
The foregoing is only a preferred embodiment of the present invention, but protection scope of the present invention be not limited thereto, Any one skilled in the art the invention discloses technical scope in, the change or replacement that can readily occur in, It should be covered by the protection scope of the present invention.Therefore, protection scope of the present invention should be with scope of the claims Subject to.

Claims (19)

1. a kind of concrete drain tile is contained, detection drilling is quick to repair erecting device, is bored for repairing the detection on pipe culvert top plate Hole, it is characterised in that consolidate including first baffle, second baffle, third baffle, the first fixation connecting rod, the second fixation connecting rod, the 3rd Determine connecting rod, the 4th fixation connecting rod and connecting rod positioning component, wherein:
The lower end of the second fixation connecting rod and the 3rd fixation connecting rod passes through corresponding hinge member and the second baffle respectively Corresponding with third baffle hinged, the first fixation connecting rod and the 4th fixation connecting rod are located on the first baffle, and along institute The length direction for stating first baffle is set, and described first, which fixes connecting rod and the 4th, fixes the lower end of connecting rod respectively by cutting with scissors accordingly Relay part is corresponding with the first baffle hinged, forms the independent connection structure in left, center, right three altogether;
Three independent connection structures pass sequentially through the inside that the detection drilling is deep into the draining pipe culvert, so that institute State after first baffle, second baffle and third baffle are unfolded inside pipe culvert and be mutually twisted connection, be combined into a bottom hole template, institute Bottom hole template is stated to be connected to the draining pipe culvert inner wall and cover the lower face of the detection drilling;
Described first, which fixes connecting rod, the second fixation connecting rod, the 3rd fixation connecting rod and the 4th, fixes the upper end of connecting rod and the connecting rod Positioning component is fixedly connected, and the sectional area of the connecting rod positioning component is more than the hole area of the detection drilling, with described in covering Detect the upper surface of drilling.
2. a kind of concrete drain tile according to claim 1 is contained, detection drilling is quick to repair erecting device, its feature exists In being symmetrically arranged with some integrated positioning columns at left and right sides of the first baffle, the second baffle and third baffle are close Position on the side of the first baffle with respect to several integrated positioning columns is correspondingly provided with several identical combinations of quantity Location hole, the integrated positioning column on the first baffle are each passed through the integrated positioning in the second baffle and third baffle Hole so that the first baffle, second baffle and third baffle are connected, and are combined into bottom hole template.
3. a kind of concrete drain tile according to claim 1 is contained, detection drilling is quick to repair erecting device, its feature exists In the cross section of the first baffle is in convex shape, its left and right ends forms step-like structure, the second baffle and third gear Plate is located above the left and right sides of the first baffle, and is engaged by the step-like structure with the first baffle.
4. a kind of concrete drain tile according to claim 3 is contained, detection drilling is quick to repair erecting device, its feature exists In, further include hermetic seal material, the hermetic seal material be respectively coated in the first baffle step-like structure and its On upper surface, and on the opposite medial surface in upper surface and both of the second baffle and third baffle.
5. a kind of concrete drain tile according to claim 1 is contained, detection drilling is quick to repair erecting device, its feature exists In the cross section of the first baffle is rectangular, and the second baffle and third baffle are located at the left and right two of the first baffle Above side, the second baffle and opposite two medial surfaces of third baffle are pressed on the first baffle after mutually abutting Side.
6. a kind of concrete drain tile according to claim 5 is contained, detection drilling is quick to repair erecting device, its feature exists In, further including hermetic seal material, the hermetic seal material is respectively coated on the upper surface of first baffle, and described On the opposite medial surface in the upper surface and both of two baffles and third baffle.
7. a kind of concrete drain tile according to claim 1 is contained, detection drilling is quick to repair erecting device, its feature exists In the connecting rod positioning component includes a connecting rod positioning plate, and the connecting rod positioning plate is equipped with an injected hole and four connecting rods are determined Position hole, wherein:
Four connecting rod location holes are uniformly distributed around the injected hole is rectangular, and are respectively positioned on the detection drilling described In drop shadow spread on connecting rod positioning plate.
8. a kind of concrete drain tile according to claim 7 is contained, detection drilling is quick to repair erecting device, its feature exists In, the first fixation connecting rod, the second fixation connecting rod, the 3rd fixation connecting rod and the 4th upper end for fixing connecting rod are equipped with screw thread, And be threadedly coupled after being each passed through four connecting rod location holes with nut, so that described first fixes connecting rod, second solid Determine connecting rod, the 3rd fixation connecting rod and the 4th fixation connecting rod to be fixedly connected with the connecting rod positioning plate.
9. a kind of concrete drain tile according to claim 7 is contained, detection drilling is quick to repair erecting device, its feature exists In, several hole for the expansion bolt are also evenly arranged with the connecting rod positioning plate, it is opposite with some expansion bolt hole numbers The connecting rod positioning plate is fixed on the draining pipe culvert top plate outer surface by the expansion bolt answered through the hole for the expansion bolt, To prevent the connecting rod positioning plate occurred level from moving.
10. a kind of concrete drain tile contains detection drilling fast repairing method, it is characterised in that comprises the following steps:
Step 1:The lower end of second fixation connecting rod and the 3rd fixation connecting rod is passed through into corresponding hinge member and second baffle respectively It is corresponding with third baffle hinged, and will be located on first baffle and along first company of fixation that sets of length direction of first baffle Bar and the 4th lower end for fixing connecting rod are hinged by the way that corresponding hinge member is corresponding with first baffle respectively, form left, center, right three Independent connection structure;
Step 2:Connecting rod is fixed by first and the 4th the first connection structure for fixing connecting rod and first baffle formation is bored through detection Hole enters inside pipe culvert, then fixes the second connection structure that connecting rod and second baffle are formed, and the 3rd company of fixation by second The 3rd connection structure that bar and third baffle are formed is drilled into inside pipe culvert through detection, and is located at first connection structure The left and right sides;
Step 3:First baffle, second baffle and third baffle are mutually twisted connection after being unfolded inside pipe culvert, are combined into a hole End template, bottom hole template are connected to draining pipe culvert inner wall and cover the lower face of detection drilling;
Step 4:Sectional area be more than detection drilling hole area connecting rod positioning component with first fix connecting rod, second fixation connecting rod, The upper end of 3rd fixation connecting rod and the 4th fixation connecting rod is fixedly connected, with the upper surface of covering detection drilling;
Step 5:By being in the milk to the injected hole on connecting rod positioning component, to repair detection drilling.
11. a kind of concrete drain tile according to claim 10 contains detection drilling fast repairing method, it is characterised in that In step 3, the first baffle, second baffle and third baffle are combined into the specific steps of bottom hole template and include:
Several integrated positioning columns being symmetrically disposed at left and right sides of the first baffle are each passed through positioned at the second gear Plate and third baffle are identical with respect to the quantity that several integrated positioning columns are accordingly set on the side of the first baffle Several integrated positioning holes, realize that the first baffle, second baffle and third baffle are connected with this, be combined into bottom hole Template.
12. a kind of concrete drain tile according to claim 10 contains detection drilling fast repairing method, it is characterised in that In step 3, it is further comprising the steps of:
The first baffle for selecting cross section to be in convex shape, makes its left and right ends form step-like structure, so that described second Baffle and third baffle are engaged by the step-like structure with the first baffle.
13. a kind of concrete drain tile according to claim 12 contains detection drilling fast repairing method, it is characterised in that In step 3, it is further comprising the steps of:
Hermetic seal material is respectively coated on the step-like structure of the first baffle and its upper surface, and described second On the opposite medial surface in the upper surface and both of baffle and third baffle, to prevent spillage.
14. a kind of concrete drain tile according to claim 10 contains detection drilling fast repairing method, it is characterised in that In step 3, it is further comprising the steps of:
Select the rectangular first baffle in cross section so that the second gear above the left and right sides of the first baffle Plate and opposite two medial surfaces of third baffle are pressed on above the first baffle after mutually abutting.
15. a kind of concrete drain tile according to claim 14 contains detection drilling fast repairing method, it is characterised in that In step 3, it is further comprising the steps of:
Hermetic seal material is respectively coated on the upper surface of the first baffle, and the second baffle and third baffle Upper surface and the opposite medial surface of both on, to prevent spillage.
16. a kind of concrete drain tile according to claim 10 contains detection drilling fast repairing method, it is characterised in that In step 4, it is further comprising the steps of:
Four are opened up on connecting rod positioning plate in connecting rod positioning component around the rectangular equally distributed connecting rod positioning of injected hole Hole so that four connecting rod location holes are respectively positioned on detection drilling in the drop shadow spread on the connecting rod positioning plate.
17. a kind of concrete drain tile according to claim 16 contains detection drilling fast repairing method, it is characterised in that In step 4, it is further comprising the steps of:
The upper end for described first being fixed connecting rod, the second fixation connecting rod, the 3rd fixation connecting rod and the 4th fixation connecting rod is set as spiral shell Line structure, and be threadedly coupled after being each passed through four connecting rod location holes with nut, so that the first fixation connecting rod, Second fixation connecting rod, the 3rd fixation connecting rod and the 4th fixation connecting rod are fixedly connected with the connecting rod positioning plate.
18. a kind of concrete drain tile according to claim 16 contains detection drilling fast repairing method, it is characterised in that In step 4, it is further comprising the steps of:
Several expansion bolts are passed through corresponding with some expansion bolt quantity and is uniformly arranged on the connecting rod and determines Several hole for the expansion bolt on the plate of position, with this so that the connecting rod positioning plate is fixed on the draining pipe culvert top plate outer surface On, to prevent the connecting rod positioning plate occurred level from moving.
19. a kind of concrete drain tile according to claim 10 contains detection drilling fast repairing method, it is characterised in that Further include step 6:A layer concrete is poured outside the connecting rod positioning component, the guarantor to repairing erecting device is realized with this Shield.
CN201610590198.2A 2016-07-25 2016-07-25 A kind of concrete drain tile contains the quick reparation erecting device of detection drilling and its restorative procedure Active CN106049644B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610590198.2A CN106049644B (en) 2016-07-25 2016-07-25 A kind of concrete drain tile contains the quick reparation erecting device of detection drilling and its restorative procedure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610590198.2A CN106049644B (en) 2016-07-25 2016-07-25 A kind of concrete drain tile contains the quick reparation erecting device of detection drilling and its restorative procedure

Publications (2)

Publication Number Publication Date
CN106049644A CN106049644A (en) 2016-10-26
CN106049644B true CN106049644B (en) 2018-04-17

Family

ID=57417045

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610590198.2A Active CN106049644B (en) 2016-07-25 2016-07-25 A kind of concrete drain tile contains the quick reparation erecting device of detection drilling and its restorative procedure

Country Status (1)

Country Link
CN (1) CN106049644B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107832491B (en) * 2017-09-27 2021-02-02 上海勘察设计研究院(集团)有限公司 Effective water holding rate calculation method for underground water restoration by extraction method
CN109252457B (en) * 2018-10-22 2021-04-02 中国一冶集团有限公司 Quick plugging and repairing device for concrete drainage pipe culvert
CN109540247A (en) * 2018-12-13 2019-03-29 南昌大学 A kind of drilling level of ground water real-time monitoring device
CN109877945B (en) * 2019-01-23 2021-03-26 南昌大学 Hole-forming positioning construction method for reserved hole channel of concrete beam

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006057545A1 (en) * 2004-11-29 2006-06-01 Dong-Hyun Seo Tunnelling method using pre-support concept and an adjustable apparatus thereof
CN102242850A (en) * 2011-05-27 2011-11-16 天津市银龙预应力钢材集团有限公司 Emergency-repair tool for pipe line of prestress steel cylinder concrete pipe
CN103291072A (en) * 2013-05-31 2013-09-11 上海宝冶集团有限公司 Method for reserving holes in floors by aid of PVC (polyvinyl chloride) sleeves
CN204875521U (en) * 2015-03-23 2015-12-16 王豪 Hang blue jib preformed hole plugging device
CN205804559U (en) * 2016-07-25 2016-12-14 上海市城市排水有限公司 Erecting device is quickly repaired in a kind of concrete drain tile culvert detection boring

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7367362B2 (en) * 2004-12-03 2008-05-06 Illinois Tool Works Inc. System and method for pipe repair

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006057545A1 (en) * 2004-11-29 2006-06-01 Dong-Hyun Seo Tunnelling method using pre-support concept and an adjustable apparatus thereof
CN102242850A (en) * 2011-05-27 2011-11-16 天津市银龙预应力钢材集团有限公司 Emergency-repair tool for pipe line of prestress steel cylinder concrete pipe
CN103291072A (en) * 2013-05-31 2013-09-11 上海宝冶集团有限公司 Method for reserving holes in floors by aid of PVC (polyvinyl chloride) sleeves
CN204875521U (en) * 2015-03-23 2015-12-16 王豪 Hang blue jib preformed hole plugging device
CN205804559U (en) * 2016-07-25 2016-12-14 上海市城市排水有限公司 Erecting device is quickly repaired in a kind of concrete drain tile culvert detection boring

Also Published As

Publication number Publication date
CN106049644A (en) 2016-10-26

Similar Documents

Publication Publication Date Title
CN106049644B (en) A kind of concrete drain tile contains the quick reparation erecting device of detection drilling and its restorative procedure
CN104458532B (en) Device and method for testing water permeability resistance of concrete joint under action of controllable lateral restriction
CN110004991B (en) Underground structure anti-floating system based on convex wing foot plate and construction method
CN104988915B (en) A kind of prefabricated installation method of detachable steel casing and under water connection beam
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN111560941A (en) Karst landform cavity treatment method
CN108333109A (en) A kind of concrete structure internal fissure monitoring device and method
CN110284901A (en) Water proof type single shell lining structure and its construction technology
WO2021139063A1 (en) Grouting pipe and method of reinforcing tunnel by surface grouting
CN106245654B (en) Deposited reinforced concrete pile exempts from inter-pile soil excavation construction method
CN108426779B (en) The structural cracks experiment simulator and method of underground engineering under high hydraulic condition
CN114215090B (en) Construction method of raft and pile pressing in closed space
CN104060590B (en) The reinforcement leakage preventing structure of a kind of pressure diversion tunnel and construction method thereof
CN109025899B (en) Well sealing device
CN113153379B (en) Tunnel waterproof and drainage system and construction process
CN206513380U (en) A kind of tunnel double-lining vault with rubber seal reserves Grouting Pipe
CN107288141B (en) A kind of seamless flexible water construction technology of contrary sequence method
CN106193644A (en) Basement reconstruction structure with raft foundation building
CN103205986A (en) Concrete raft foundation construction-joint grouting device and construction method
CN205804559U (en) Erecting device is quickly repaired in a kind of concrete drain tile culvert detection boring
CN116771386A (en) Dynamic sequential grouting method for ultra-temperature hot water tunnel
CN107576574B (en) Testing method for equal-size limit water pressure resistance of deformation joint embedded water stop
CN110144918A (en) Hypogee dewatering well antiseepage plugging construction method
CN113028139B (en) Combined type connector of rain and sewage pipe and construction method
CN114197508B (en) Easy-to-seal water draining device, manufacturing method and using method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant