CN105781555A - 圆钢管斜柱钢井架模块化安装方法 - Google Patents

圆钢管斜柱钢井架模块化安装方法 Download PDF

Info

Publication number
CN105781555A
CN105781555A CN201410812846.5A CN201410812846A CN105781555A CN 105781555 A CN105781555 A CN 105781555A CN 201410812846 A CN201410812846 A CN 201410812846A CN 105781555 A CN105781555 A CN 105781555A
Authority
CN
China
Prior art keywords
steel
headframe
module
installation
installation method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410812846.5A
Other languages
English (en)
Other versions
CN105781555B (zh
Inventor
王建群
李大浪
黄恒平
王宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 20th Metallurgical Group Co., Ltd
China Nerin Engineering Co Ltd
Original Assignee
China Nerin Engineering Co Ltd
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Nerin Engineering Co Ltd, China MCC20 Group Corp Ltd filed Critical China Nerin Engineering Co Ltd
Priority to CN201410812846.5A priority Critical patent/CN105781555B/zh
Publication of CN105781555A publication Critical patent/CN105781555A/zh
Application granted granted Critical
Publication of CN105781555B publication Critical patent/CN105781555B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明涉及钢井架,尤其涉及一种圆钢管斜柱钢井架的安装方法。本发明一种圆钢管斜柱钢井架模块化安装方法,它包括:步骤一,将钢井架按照功能,主要分为卸载平台模块、紧急罐笼罐道绳固定平台及紧急罐笼天轮平台模块、主提升罐道绳固定平台模块,下天轮平台模块,上天轮平台模块、天轮安装检修平台模块,共六大模块;步骤二,将相应的设备根据设计安装在对应的模块上;步骤三,将步骤二安装了设备的模块依次吊运到设计位置,并进行组装和连接,从而完成钢井架的安装。本发明能缩短现场安装工期,提高安装精度,降低安装成本。

Description

圆钢管斜柱钢井架模块化安装方法
技术领域
本发明涉及钢井架,尤其涉及一种圆钢管斜柱钢井架的安装方法。
背景技术
目前矿山竖井井架设计一般采用大型箱型钢结构,传统的井架安装方法:将钢井架划分为主、副斜架吊装单元,采用地面分片组对,使用吊装设备将主、副斜架竖立就位并完成对接,拼接部位高空焊接固定完毕后,再将设备吊运到位,进行安装。该方法的大型箱型钢结构加劲板纵横交错,构造复杂、用钢量多、焊接工作量大,加工制作周期长。施工过程中存在对吊装设备要求高,安全性能差,施工措施费用高,现场焊接工作环境差,焊接质量难以保证,安装难度大且精度差等缺点。
发明内容
本发明旨在解决上述问题,提供一种圆钢管斜柱钢井架模块化安装方法。本发明能缩短现场安装工期,提高安装精度,降低安装成本。
本发明一种圆钢管斜柱钢井架模块化安装方法,它包括:
步骤一,将钢井架按照功能,主要分为卸载平台模块、紧急罐笼罐道绳固定平台及紧急罐笼天轮平台模块、主提升罐道绳固定平台模块,下天轮平台模块,上天轮平台模块、天轮安装检修平台模块,共六大模块;
步骤二,将相应的设备根据设计安装在对应的模块上;
步骤三,将步骤二安装了设备的模块依次吊运到设计位置,并进行组装和连接,从而完成钢井架的安装。
所述的圆钢管斜柱钢井架模块化安装方法,所述钢井架的斜柱为圆管,圆管之间采用法兰连接。
所述的圆钢管斜柱钢井架模块化安装方法,所述步骤三还包括,除了六大模块以外,所述钢井架还包括辅助钢平台,这些辅助钢平台和其它六大模块一起由工厂加工,并以散件形式运输至现场进行地面组装后吊装。
本发明采用的圆钢管斜柱截面力学特性好,可以节约钢材。主副斜柱分段采用法兰拼接方式,安装方便,最大限度的减少了现场工作量,保证施工进度,降低施工成本。模块化的钢平台由工厂整体制作安装运输至现场分层吊装,可以提高安装精度,降低施工措施费用。井口施工占用场时间短,降低对附近区域其它地表建筑物施工的影响。
具体实施方式
下面,以具体实施方法对本发明作进一步的说明:
本发明一种圆钢管斜柱钢井架模块化安装方法,它包括:
步骤一,将钢井架按照功能,主要分为卸载平台模块、紧急罐笼罐道绳固定平台及紧急罐笼天轮平台模块、主提升罐道绳固定平台模块,下天轮平台模块,上天轮平台模块、天轮安装检修平台模块,共六大模块;模块化的井架强调设备与钢平台集成,各模块由钢平台结构与钢平台上的工艺设备组成并具有相对独立功能;例如:天轮平台模块是由天轮和支承天轮设备的钢平台组合,卸载平台模块是由卸料设备和支承卸料设备的钢平台组合而成;
步骤二,将相应的设备根据设计安装在对应的模块上;
步骤三,将步骤二安装了设备的模块依次吊运到设计位置,并进行组装和连接,从而完成钢井架的安装。
所述的圆钢管斜柱钢井架模块化安装方法,所述钢井架的斜柱为圆管,圆管之间采用法兰连接。
所述的圆钢管斜柱钢井架模块化安装方法,所述步骤三还包括,除了六大模块以外,所述钢井架还包括辅助钢平台,这些辅助钢平台和其它六大模块一起由工厂加工,并以散件形式运输至现场进行地面组装后吊装。

Claims (3)

1.一种圆钢管斜柱钢井架模块化安装方法,其特征在于,它包括:
步骤一,将钢井架按照功能,主要分为卸载平台模块、紧急罐笼罐道绳固定平台及紧急罐笼天轮平台模块、主提升罐道绳固定平台模块,下天轮平台模块,上天轮平台模块、天轮安装检修平台模块,共六大模块;
步骤二,将相应的设备根据设计安装在对应的模块上;
步骤三,将步骤二安装了设备的模块依次吊运到设计位置,并进行组装和连接,从而完成钢井架的安装。
2.根据权利要求1所述的圆钢管斜柱钢井架模块化安装方法,其特征在于,所述钢井架的斜柱为圆管,圆管之间采用法兰连接。
3.根据权利要求1所述的圆钢管斜柱钢井架模块化安装方法,其特征在于,所述步骤三还包括,除了六大模块以外,所述钢井架还包括辅助钢平台,这些辅助钢平台和其它六大模块一起由工厂加工,并以散件形式运输至现场进行地面组装后吊装。
CN201410812846.5A 2014-12-24 2014-12-24 圆钢管斜柱钢井架模块化安装方法 Active CN105781555B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410812846.5A CN105781555B (zh) 2014-12-24 2014-12-24 圆钢管斜柱钢井架模块化安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410812846.5A CN105781555B (zh) 2014-12-24 2014-12-24 圆钢管斜柱钢井架模块化安装方法

Publications (2)

Publication Number Publication Date
CN105781555A true CN105781555A (zh) 2016-07-20
CN105781555B CN105781555B (zh) 2017-12-29

Family

ID=56377265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410812846.5A Active CN105781555B (zh) 2014-12-24 2014-12-24 圆钢管斜柱钢井架模块化安装方法

Country Status (1)

Country Link
CN (1) CN105781555B (zh)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101451397A (zh) * 2007-12-05 2009-06-10 中冶天工建设有限公司 钢结构模块化施工工艺
CN101759079A (zh) * 2009-12-30 2010-06-30 山西四建集团有限公司 钢结构电梯井架地面整体拼接安装方法
CN102528306A (zh) * 2011-12-13 2012-07-04 上海阳东钢结构有限公司 海洋石油钻井架制造工法
CN202690063U (zh) * 2012-03-06 2013-01-23 安徽大昌矿业集团有限公司 一种矿用竖井无井架凿井施工装置
CN102913137A (zh) * 2012-10-19 2013-02-06 金诚信矿业管理股份有限公司 一种凿井钢管井架及该凿井钢管井架的安装方法
CN103243930A (zh) * 2013-04-23 2013-08-14 重庆大学 超高层钢结构模块化施工系统及其方法
CN203248094U (zh) * 2013-05-23 2013-10-23 中煤第三建设(集团)有限责任公司 大直径超深立井凿井井架

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101451397A (zh) * 2007-12-05 2009-06-10 中冶天工建设有限公司 钢结构模块化施工工艺
CN101759079A (zh) * 2009-12-30 2010-06-30 山西四建集团有限公司 钢结构电梯井架地面整体拼接安装方法
CN102528306A (zh) * 2011-12-13 2012-07-04 上海阳东钢结构有限公司 海洋石油钻井架制造工法
CN202690063U (zh) * 2012-03-06 2013-01-23 安徽大昌矿业集团有限公司 一种矿用竖井无井架凿井施工装置
CN102913137A (zh) * 2012-10-19 2013-02-06 金诚信矿业管理股份有限公司 一种凿井钢管井架及该凿井钢管井架的安装方法
CN103243930A (zh) * 2013-04-23 2013-08-14 重庆大学 超高层钢结构模块化施工系统及其方法
CN203248094U (zh) * 2013-05-23 2013-10-23 中煤第三建设(集团)有限责任公司 大直径超深立井凿井井架

Also Published As

Publication number Publication date
CN105781555B (zh) 2017-12-29

Similar Documents

Publication Publication Date Title
US11629033B2 (en) Integral lifting system and lifting method for assembled members
CN103243930B (zh) 超高层钢结构模块化施工系统及其方法
CN103711301A (zh) 双轨道可移动式电动吊篮及升降葫芦施工工法及装置
CN205772984U (zh) 一种单片钢桁架的吊装装置
CN102102344B (zh) 组装式波纹管涵洞快速拼装方法
CN103979383A (zh) 建筑施工多层升降平台系统
CN102121273A (zh) 一种钢筋混凝土烟囱钢内筒液压提升倒装方法
CN103437563B (zh) 一种用于大型钢结构厂房钢骨架的安装方法
CN104528500A (zh) 双平台无脚手架电梯安装方法
CN106245919A (zh) 一种装配式建筑自动化装配平台
CN106544959B (zh) 含有鞍座的主塔吊装节段及桥梁主塔鞍座的施工方法
CN103173582A (zh) 高炉五通球及其导出管高空整体就位安装方法
CN102496771B (zh) 大型钢结构天线的安装方法及装置
CN105781210B (zh) 一种锥形塔架及其工具节辅助穿心式整体提升施工方法
CN104989111A (zh) 钢结构高层吊装施工方法
CN104670418B (zh) 海洋平台的直升机甲板的总装工艺
CN101818563B (zh) 自升式整体提升移动平台及使用方法
CN106088756A (zh) 一种基于bim技术的筒式钢制储罐液压提升倒装的方法
CN102587676B (zh) 安装核电站核岛内主梁结构的方法
CN203486787U (zh) 一种维金斯式煤气柜柜顶的整体提升装置
CN105781555A (zh) 圆钢管斜柱钢井架模块化安装方法
CN107487724B (zh) 一种非吊机辅助的大型浮吊臂架安装装置及安装方法
CN104652829B (zh) 自提升折叠定位操作系统施工方法
CN204080636U (zh) 钢管拱桥拱肋安装平转支撑定位平台
CN210178020U (zh) 预制舱安装限位结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 330031 No. 888, Qian Hu Road, Hongjiao Island, Nanchang, Jiangxi.

Patentee after: CHINA NERIN ENGINEERING Co.,Ltd.

Patentee after: China 20th Metallurgical Group Co., Ltd

Address before: 330031 No. 888, Qian Hu Road, Hongjiao Island, Nanchang, Jiangxi.

Patentee before: CHINA NERIN ENGINEERING Co.,Ltd.

Patentee before: China 20th Metallurgical Group Co., Ltd

CP01 Change in the name or title of a patent holder