CN103173582A - 高炉五通球及其导出管高空整体就位安装方法 - Google Patents

高炉五通球及其导出管高空整体就位安装方法 Download PDF

Info

Publication number
CN103173582A
CN103173582A CN2013100830493A CN201310083049A CN103173582A CN 103173582 A CN103173582 A CN 103173582A CN 2013100830493 A CN2013100830493 A CN 2013100830493A CN 201310083049 A CN201310083049 A CN 201310083049A CN 103173582 A CN103173582 A CN 103173582A
Authority
CN
China
Prior art keywords
way ball
platform
interface
interim
centering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013100830493A
Other languages
English (en)
Inventor
房政
施光涛
罗东
唐长生
唐姚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN2013100830493A priority Critical patent/CN103173582A/zh
Publication of CN103173582A publication Critical patent/CN103173582A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

本发明公开了高炉五通球及其导出管高空整体就位安装方法,其特征在于:按以下施工步骤进行:1、搭设临时找正平台,在五通球下部框架平台吊车梁上,搭设临时找正平台;再在四根上升管各吊装单元接口处内外两侧搭设接口临时操作平台。2、复测调整,先利用临时找正平台,测出四根上升管接口的对角线偏差值,对偏差值过大的接口进行调整;再在地面测出五通球上四根导出管的对角线偏差,对偏差值过大的导出管接口在地面进行调整。3、吊装,用吊车将五通球及其导出管高空整体吊装就位,直接与上升管四个对接口进行对接找正。本发明的优点是操作简单,方便快捷,安全可靠,缩短了高空对接找正时间。

Description

高炉五通球及其导出管高空整体就位安装方法
技术领域
本发明涉及高炉粗煤气系统安装技术领域,尤其涉及高炉五通球及其导出管高空整体就位安装方法。
背景技术
现有高炉施工中,上升管顶部的五通球安装就位因高度高,危险性大,若简单使用在上升管接口处内外两侧焊接挂架、搭设跳板,往往因四个上升管的对接口偏差值难以测量调整,导致球体四根导出管的接口对接找正时间长,不仅费工费时,成本高,而且影响了大型机械设备吊装的效率。
发明内容
本发明的目的就是针对现有技术存在的上述缺点,提供高炉五通球及其导出管高空整体就位安装方法,缩短高空对接找正时间,提高大型机械设备吊装工效,降低施工成本。
本发明的目的是这样实现的:高炉五通球及其导出管高空整体就位安装方法,其特征在于:按以下施工步骤进行:
1、搭设临时找正平台
在五通球下部框架平台吊车梁上,搭设临时找正平台,临时找正平台由立柱、十字支撑、临时找正平台栏杆组成;再在四根上升管各吊装单元接口处内外两侧搭设接口临时操作平台,临时操作平台由槽钢、跳板、临时操作平台栏杆组成。
2、复测调整
先利用临时找正平台,测出四根上升管接口的对角线偏差值,对偏差值过大的接口进行调整;再在地面测出五通球上四根导出管的对角线偏差,对偏差值过大的导出管接口在地面进行调整,使其对角线与四根上升管接口对角线的偏差值基本一致,调整后将导出管与五通球点焊牢固。
3、吊装
用吊车将五通球及其导出管高空整体吊装就位,直接与上升管四个对接口进行对接找正。由于吊装前通过搭设的临时找正平台对上、下对接口的对角线进行了调整纠偏,大大缩短了高空对接找正时间。
与现有技术相比,本发明的优点是:操作简单,方便快捷,安全可靠,大大缩短了高空对接找正时间,提高了大型机械设备吊装工效,降低了施工成本。
附图说明
图1:高炉五通球及其导出管高空整体就位安装方法示意图。
图中:1、框架平台吊车梁   2、立柱   3、十字支撑    4、临时找正平台栏杆  5、槽钢  6、跳板  7、临时操作平台栏杆  8、导出管  9、上升管  10、五通球。
具体实施方式
为进一步描述本发明,下面结合实施例和附图对本发明作进一步描述。
如图所示,高炉五通球及其导出管高空整体就位安装方法,其特征在于:按以下施工步骤进行:
1、搭设临时找正平台
在五通球10下部框架平台吊车梁1上,搭设临时找正平台,临时找正平台由立柱2、十字支撑3、临时找正平台栏杆4组成;再在四根上升管9各吊装单元接口处内外两侧搭设接口临时操作平台,临时操作平台由槽钢5、跳板6、临时操作平台栏杆7组成。
2、复测调整
先利用临时找正平台,测出四根上升管9接口的对角线偏差值,对偏差值过大的接口进行调整;再在地面测出五通球10上四根导出管8的对角线偏差,对偏差值过大的导出管8接口在地面进行调整,使其对角线与四根上升管9接口对角线的偏差值基本一致,调整后将导出管8与五通球10点焊牢固。
3、吊装
用吊车将五通球10及其导出管8高空整体吊装就位,直接与上升管9四个对接口进行对接找正。

Claims (1)

1.高炉五通球及其导出管高空整体就位安装方法,其特征在于:按以下施工步骤进行:
(1).搭设临时找正平台
在五通球(10)下部框架平台吊车梁(1)上,搭设临时找正平台,临时找正平台由立柱(2)、十字支撑(3)、临时找正平台栏杆(4)组成;再在四根上升管(9)各吊装单元接口处内外两侧搭设接口临时操作平台,临时操作平台由槽钢(5)、跳板(6)、临时操作平台栏杆(7)组成;
(2).复测调整
先利用临时找正平台,测出四根上升管(9)接口的对角线偏差值,对偏差值过大的接口进行调整;再在地面测出五通球(10)上四根导出管(8)的对角线偏差,对偏差值过大的导出管(8)接口在地面进行调整,使其对角线与四根上升管(9)接口对角线的偏差值基本一致,调整后将导出管(8)与五通球(10)点焊牢固;
(3).吊装
用吊车将五通球(10)及其导出管(8)高空整体吊装就位,直接与上升管(9)四个对接口进行对接找正。
CN2013100830493A 2013-03-15 2013-03-15 高炉五通球及其导出管高空整体就位安装方法 Pending CN103173582A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100830493A CN103173582A (zh) 2013-03-15 2013-03-15 高炉五通球及其导出管高空整体就位安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100830493A CN103173582A (zh) 2013-03-15 2013-03-15 高炉五通球及其导出管高空整体就位安装方法

Publications (1)

Publication Number Publication Date
CN103173582A true CN103173582A (zh) 2013-06-26

Family

ID=48633769

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100830493A Pending CN103173582A (zh) 2013-03-15 2013-03-15 高炉五通球及其导出管高空整体就位安装方法

Country Status (1)

Country Link
CN (1) CN103173582A (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103451338A (zh) * 2013-09-13 2013-12-18 中国十九冶集团有限公司 高炉煤气系统上升管及五通球安装方法
CN104060102A (zh) * 2014-07-08 2014-09-24 七冶建设有限责任公司 一种大型闪速熔炼炉安装方法
CN104694765A (zh) * 2013-12-10 2015-06-10 五冶集团上海有限公司 优化闪速熔炼炉安装方法
CN105441614A (zh) * 2015-12-28 2016-03-30 北京首钢建设集团有限公司 一种高炉五通球组对方法
CN105695650A (zh) * 2016-04-27 2016-06-22 中国十九冶集团有限公司 一种高炉五通球安装方法
CN109913599A (zh) * 2019-02-28 2019-06-21 上海二十冶建设有限公司 高炉五通球现场拼装安装方法
CN113538653A (zh) * 2021-06-04 2021-10-22 上海宝冶冶金工程有限公司 一种基于bim模型的五通球导出管位置调整的方法及系统

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101613774A (zh) * 2009-07-03 2009-12-30 中冶京唐建设有限公司 高炉五通球的加工组装工艺
CN101709344A (zh) * 2009-11-25 2010-05-19 武汉冶建安装工程有限责任公司 用于炉顶粗煤气管道平台吊装方法
CN102851421A (zh) * 2012-04-18 2013-01-02 天津二十冶建设有限公司 一种高炉单管下降管的安装方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101613774A (zh) * 2009-07-03 2009-12-30 中冶京唐建设有限公司 高炉五通球的加工组装工艺
CN101709344A (zh) * 2009-11-25 2010-05-19 武汉冶建安装工程有限责任公司 用于炉顶粗煤气管道平台吊装方法
CN102851421A (zh) * 2012-04-18 2013-01-02 天津二十冶建设有限公司 一种高炉单管下降管的安装方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
崔万平等: "3200m³高炉本体钢结构安装施工技术", 《天津冶金》, 31 December 2007 (2007-12-31), pages 77 - 83 *
王雄: "特大型高炉上升、下降管及球节点施工技术", 《2009全国钢结构学术年会论文集》, 31 October 2009 (2009-10-31), pages 411 - 417 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103451338A (zh) * 2013-09-13 2013-12-18 中国十九冶集团有限公司 高炉煤气系统上升管及五通球安装方法
CN103451338B (zh) * 2013-09-13 2015-05-20 中国十九冶集团有限公司 高炉煤气系统上升管及五通球安装方法
CN104694765A (zh) * 2013-12-10 2015-06-10 五冶集团上海有限公司 优化闪速熔炼炉安装方法
CN104694765B (zh) * 2013-12-10 2017-02-01 五冶集团上海有限公司 闪速熔炼炉安装方法
CN104060102A (zh) * 2014-07-08 2014-09-24 七冶建设有限责任公司 一种大型闪速熔炼炉安装方法
CN104060102B (zh) * 2014-07-08 2016-01-20 七冶建设有限责任公司 一种大型闪速熔炼炉安装方法
CN105441614A (zh) * 2015-12-28 2016-03-30 北京首钢建设集团有限公司 一种高炉五通球组对方法
CN105695650A (zh) * 2016-04-27 2016-06-22 中国十九冶集团有限公司 一种高炉五通球安装方法
CN109913599A (zh) * 2019-02-28 2019-06-21 上海二十冶建设有限公司 高炉五通球现场拼装安装方法
CN113538653A (zh) * 2021-06-04 2021-10-22 上海宝冶冶金工程有限公司 一种基于bim模型的五通球导出管位置调整的方法及系统
CN113538653B (zh) * 2021-06-04 2022-07-08 上海宝冶冶金工程有限公司 一种基于bim模型的五通球导出管位置调整的方法及系统

Similar Documents

Publication Publication Date Title
CN103173582A (zh) 高炉五通球及其导出管高空整体就位安装方法
CN104563528B (zh) 预制装配式建筑预制墙板快速就位装置及方法
CN101967886B (zh) 核电站钢制安全壳的组装和安装方法
CN103982045B (zh) 一种屋面网壳结构无支架悬挑安装施工方法
CN103174302A (zh) 大直径筒仓仓顶的施工方法
CN102704681B (zh) 一种钢筋混凝土直筒高耸构筑物液压滑模施工方法
CN105507652A (zh) 烟囱钢内筒液压提升倒装施工方法
CN103437563B (zh) 一种用于大型钢结构厂房钢骨架的安装方法
CN103967284B (zh) 预留柱头对接的钢柱安装方法
CN104453248A (zh) 分层模块化拼装工艺的复杂异形多层网架施工方法
CN102615492B (zh) 塔类容器的吊装对接方法
CN103451338B (zh) 高炉煤气系统上升管及五通球安装方法
CN104989111A (zh) 钢结构高层吊装施工方法
CN203497150U (zh) 一种船舶舱口围脚手架
CN104627849B (zh) 一种用于内天井管道吊装的吊装设备及吊装方法
CN103484584A (zh) 高炉煤气系统下降管安装方法
CN104264781B (zh) 网格状柱面钢结构网壳及其施工方法
CN105800477A (zh) 一种地下暗挖车间逆作法洞内钢结构吊装系统
CN103982048A (zh) 超高层钢结构箱形钢柱空中校正调整器
CN206220534U (zh) 混凝土泵送设备的泵管支撑装置
CN204080636U (zh) 钢管拱桥拱肋安装平转支撑定位平台
CN204645809U (zh) 烟囱钢内筒分片滑动拼装就位装置
CN205293909U (zh) 一种可移动的组装式搬运辅助装置
CN104818675B (zh) 钢筋节段的组拼方法
CN203247718U (zh) 一种钢柱对接安装装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130626