CN105716575A - Method for rapid measurement of horizontal control network in engineering tunnel - Google Patents

Method for rapid measurement of horizontal control network in engineering tunnel Download PDF

Info

Publication number
CN105716575A
CN105716575A CN201511015034.9A CN201511015034A CN105716575A CN 105716575 A CN105716575 A CN 105716575A CN 201511015034 A CN201511015034 A CN 201511015034A CN 105716575 A CN105716575 A CN 105716575A
Authority
CN
China
Prior art keywords
hole
control point
observation
station
point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201511015034.9A
Other languages
Chinese (zh)
Other versions
CN105716575B (en
Inventor
郭志广
苏雅拉图
王波
杜伟
乔长宝
谢铁伟
刘莹
白冰
戚浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Tiansheng Surveying and Mapping Engineering Co., Ltd.
China Railway No 3 Engineering Group Co Ltd
Original Assignee
SHANXI TIANLI LITRES O SURVEYING AND MAPPING ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANXI TIANLI LITRES O SURVEYING AND MAPPING ENGINEERING Co Ltd filed Critical SHANXI TIANLI LITRES O SURVEYING AND MAPPING ENGINEERING Co Ltd
Priority to CN201511015034.9A priority Critical patent/CN105716575B/en
Publication of CN105716575A publication Critical patent/CN105716575A/en
Application granted granted Critical
Publication of CN105716575B publication Critical patent/CN105716575B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C7/00Tracing profiles
    • G01C7/06Tracing profiles of cavities, e.g. tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Multimedia (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

The invention belongs to the technical field of tunnel engineering control survey and particularly relates to a method for rapid measurement of horizontal control network established in an engineering tunnel. The method solves the problems of low efficiency and high workload of traditional control networks and is characterized in that a total station is erected on an out-tunnel control point in in-tunnel and out-tunnel control network combined measurement; in in-tunnel measurement, the total station is erected in the middle of two control points in symmetrical left-right arrangement to observe horizontal angles, vertical angles and slope distances of adjacent control points in all directions; observation data of all observation stations form the horizontal control network. The method has the advantages that angle observation is least affected by horizontal refraction; under the condition of complete sameness of traverse network structures, work efficiency is improved by above 60% when a middle station setting type traverse network is compared with a traditional way.

Description

A kind of Tunnel Engineering hole inner plane Controling network method for fast measuring
Technical field
The invention belongs to Tunnel Engineering and control field of measuring technique, be specifically related to a kind of Tunnel Engineering hole inner plane Controling network method for fast measuring.
Background technology
In order to ensure tunnel midline plane penetrating accuracy, it is necessary to set up Controling network in hole with hole outer control net for benchmark.In general Tunnel Engineering hole, space ratio is narrow, and in work progress, interference is big, and sighting condition is poor, and therefore inner plane Controling network in hole is frequently with laying traverse net flexibly.
Traditional hole inside conductor is frequently with Guan Bi ring traverse net.Advantage is to have redundancy to observe, it is possible to makeup ring closure condition, and shortcoming is that fieldwork observation amount is big, inefficient, is generally used in the hole of major long tunnel and controls to measure.
In tradition hole, Guan Bi ring traverse net measuring method is as follows:
1, on the A of control point, hole, set up total powerstation, as survey station after centering leveling, outer control point B in hole sets up pedestal prism group, as backsight after centering leveling, control point 1,2 is set up pedestal prism group in hole, as forward sight after centering leveling.
Read on-the-spot temperature, air pressure, humidity parameter when 2, starting to measure, be input in total powerstation automatically to carry out the correction of range finding achievement.
3, observation process adopts method of direction observation.Upper semiobservation observes in hole outer control point B, hole in control point 1, hole control point 2 and zero direction and hole outer control point B clockwise, and lower semiobservation is observed counterclockwise.Require that once sight prism centers measures angle and distance simultaneously.
4, successively at all control point (A, 1, 2, 3, ..., 9) upper erection total powerstation is as survey station, observe 2 control point adjacent with the front and back of survey station homonymy, composition is needed to close translocation survey station offside rear or Dong Nei control point, front during ring, which point of concrete translocation to be determined less than 4~6 limits according to Guan Bi ring limit number, ultimately form Guan Bi ring traverse net, as shown in Figure 1, figure intermediate cam represents hole outer control point, round dot represents control point in hole, two-wire represents known limit, single line represents observation limit, Guan Bi ring numbering is labeled in circle, Guan Bi ring is generally made up of 4~6 limits.
Along with the universal use of servo type total powerstation, employing is automatically sighted (ATR) technology and is carried out automatic Observation, not only reduces the working strength of survey crew, shorten observation time simultaneously, also improving accuracy of observation, therefore inside conductor net in hole occurs in that cross-wire web form, as shown in Figure 2, figure intermediate cam represents hole outer control point, round dot represents hole inside conductor point, and two-wire represents known limit, monolateral expression observation limit, in Guan Bi ring numbering mark circle, Guan Bi ring is generally made up of 4 limits.
Cross-wire net is characterised by except last control point in hole outer control point and hole, in hole, 2 pairs of control point that front and back are adjacent observed by survey station simultaneously, advantage is: every 4 limits can form a Guan Bi ring, in the measuring point situation of equal number, cross-wire net Guan Bi ring number of combinations is far more than Guan Bi ring traverse net, significantly enhance Controling network and find rough error and the ability of opposing rough error, improve the reliability of Measurement results.Shortcoming is: each control point is both needed to erection Setting Station of Total Station Instrument observation, and the observed quantity of each station is than Guan Bi ring traverse net increase about 1 times.Often, the construct factors such as interference big poor by sighting condition in hole affects, and causes loop closure to transfinite, it is necessary to do over again and resurvey.
Summary of the invention
The present invention is to solve Tunnel Engineering hole inner plane Controling network traverse survey efficiency and precision problem, it is proposed that a kind of method for fast measuring.
The present invention adopts the following technical scheme that realization:
Tunnel Engineering hole inner plane Controling network method for fast measuring, on hole outer control point, total powerstation is set up when it is characterized in that Controling network translocation inside and outside hole, when measuring in hole, total powerstation is erected at medium position between 2 control point of symmetrical laying, observe all around horizontal angle, vertical angle and oblique distance between adjacent control points, all survey stations observation data composition horizontal control network.
Specifically comprise the following steps that
1) point arrangement,
In hole, control point is distributed in the center line left and right sides, tunnel by symmetric mode laying, and the control point, 2, left and right being in same section mileage is right referred to as point;
2) survey station tissue,
(1) on control point, hole (A), total powerstation is set up, as survey station after centering leveling, at hole outer control point (B) upper erection prism as backsight, in symmetrical hole, in control point I (1) and hole, the upper erection prism in control point II (2), as forward sight, observes 3 points altogether;
(2) put in hole successively between medium position erection total powerstation, without centering, therefore, in hole, in control point I (1) and hole, in hole between control point II (2), the 1st survey station will observe 5 points and control point, hole (A), control point II (2) in control point I (1) and hole in symmetrical hole, control point IV (4) in control point III (3) and hole in symmetrical hole, control point II (2) in control point I (1) and hole in the hole that in control point III (3) and hole, in hole between control point IV (4), the 2nd survey station is namely symmetrical by observing 6 points in hole, control point IV (4) in control point III (3) and hole in symmetrical hole, control point VI (6) in control point V (5) and hole in symmetrical hole;..., in the hole that in the hole of latter two symmetry, in control point Ⅸ (9) and hole, in hole between control point Ⅹ (10), the last leg is namely symmetrical by observing 4 points, in control point VII (7) and hole, in the hole of control point VIII (8), symmetry, in control point Ⅸ (9) and hole control point Ⅹ (10);
3), data observation,
(1) instrument height is measured, instrument height refers to that after total powerstation flattens total powerstation transverse axis is to the vertical height between the end face of control point, measure instrument when outer control point in hole sets up Setting Station of Total Station Instrument high from the end face amount of control point, put in hole and unify to be set to 0m without measuring when middle frame sets Setting Station of Total Station Instrument;
(2) measuring mirror height, mirror height refers to that prism centers is to the vertical height between the end face of control point, and the mirror at whole control point that each station measures the observation of this survey station before starting to measure is high;
(3) each survey station start measure before must measure field temperature, air pressure, humidity, be input in total powerstation automatically carry out range finding achievement correction;
(4) diopter triggers one-shot measurement after being located at the prism centers on control point, simultaneously recording level angle, vertical angle, three readings of oblique distance;
(5) observation process requires to carry out according to method of direction observation, and position number, accuracy of observation and limit are poor, zero direction, zero observation etc. are determined according to industry standard, measurement grade;
(6) after completing the observation of all position number, check fieldwork observation precision index, do over again time defective and resurvey, after qualified, adjourn next survey station, until completing the observation of all survey stations.
Completing the method that the data after step " 3) data observation " process is:
(1) the observation statistical average of each survey station each survey time is taken as final observing buoy;
(2) calculate between survey station and each measuring point flat from, the discrepancy in elevation, and horizontal angle between measuring point, and calculate measuring point coordinate with survey station for initial point;
(3) calculate the orientation between 2 by measuring point coordinate, flat from, the discrepancy in elevation, extract desired data to form the observation data of equivalence according to different conductor net networking condition.
Hinge structure of the present invention has the advantages that
(1) in hole, control point adopts point that form is laid in center line both sides, tunnel, and total powerstation is erected at and a little makes angular surveying be subject to horizontal Effect of Refraction minimum tunnel, middle part midline position.
(2) in the completely identical in structure situation of traverse net, set station method wire in the middle of adopting and improve more than 60% than traditional approach work efficiency.
For Fig. 1, adopt Guan Bi ring traverse net mode: each survey station 2 measuring points of observation, need to be formed 3 points of observation during Guan Bi ring, left and right sets station for 2 times and removes after coincidence point 4 measuring points of actual observation, adopt cross-wire net mode: each survey station 4 measuring points of observation, left and right sets station for 2 times and removes after coincidence point 4 measuring points of actual observation, and adopts centre to set station method traverse net mode: once setting station and can complete the observation of 6 points.
(3) the middle station method traverse net observation data that set form cross-wire network data, after Guan Bi ring angular error of closure, relative closing error of extreme length meet requirement, adopt tight method compensating computation.
Accompanying drawing explanation
Fig. 1 is existing Guan Bi ring traverse net,
Fig. 2 is existing cross-wire net,
Fig. 3 sets station method traverse net observation figure in the middle of the present invention
Fig. 4 sets station method Traverse Network Adjustment figure in the middle of the present invention,
Fig. 5 sets station method traverse net observation figure in the middle of embodiment,
Fig. 6 sets station method Traverse Network Adjustment figure in the middle of embodiment.
In figure: known point outside △ hole, 1 hole inside conductor point, set station location in the middle of ◎ ,=known limit, observation limit (angle, distance) ,+observation limit (only distance), 1., 2., 3. ... Guan Bi ring sequence number, C1, C2, C3 ... centre sets station sequence number.
Detailed description of the invention
Tunnel Engineering hole inner plane Controling network method for fast measuring, on hole outer control point, total powerstation is set up when it is characterized in that Controling network translocation inside and outside hole, when measuring in hole, total powerstation is erected at medium position between 2 control point of symmetrical laying, observe all around horizontal angle, vertical angle and oblique distance between adjacent control points, all survey stations observation data composition horizontal control network.
Specifically comprise the following steps that
1) point arrangement,
In hole, control point is distributed in the center line left and right sides, tunnel by symmetric mode laying, and the control point, 2, left and right being in same section mileage is right referred to as point;
2) survey station tissue,
(1) on control point, hole (A), total powerstation is set up, as survey station after centering leveling, at hole outer control point (B) upper erection prism as backsight, in symmetrical hole, in control point I (1) and hole, the upper erection prism in control point II (2), as forward sight, observes 3 points altogether;
(2) put in hole successively between medium position erection total powerstation, without centering, therefore, in hole, in control point I (1) and hole, in hole between control point II (2), the 1st survey station will observe 5 points and control point, hole (A), control point II (2) in control point I (1) and hole in symmetrical hole, control point IV (4) in control point III (3) and hole in symmetrical hole, control point II (2) in control point I (1) and hole in the hole that in control point III (3) and hole, in hole between control point IV (4), the 2nd survey station is namely symmetrical by observing 6 points in hole, control point IV (4) in control point III (3) and hole in symmetrical hole, control point VI (6) in control point V (5) and hole in symmetrical hole;..., in the hole that in the hole of latter two symmetry, in control point Ⅸ (9) and hole, in hole between control point Ⅹ (10), the last leg is namely symmetrical by observing 4 points, in control point VII (7) and hole, in the hole of control point VIII (8), symmetry, in control point Ⅸ (9) and hole control point Ⅹ (10);
3), data observation,
(1) instrument height is measured, instrument height refers to that after total powerstation flattens total powerstation transverse axis is to the vertical height between the end face of control point, measure instrument when outer control point in hole sets up Setting Station of Total Station Instrument high from the end face amount of control point, put in hole and unify to be set to 0m without measuring when middle frame sets Setting Station of Total Station Instrument;
(2) measuring mirror height, mirror height refers to that prism centers is to the vertical height between the end face of control point, and the mirror at whole control point that each station measures the observation of this survey station before starting to measure is high;
(3) each survey station start measure before must measure field temperature, air pressure, humidity, be input in total powerstation automatically carry out range finding achievement correction;
(4) diopter triggers one-shot measurement after being located at the prism centers on control point, simultaneously recording level angle, vertical angle, three readings of oblique distance;
(5) observation process requires to carry out according to method of direction observation, and position number, accuracy of observation and limit are poor, zero direction, zero observation etc. are determined according to industry standard, measurement grade;
(6) after completing the observation of all position number, check fieldwork observation precision index, do over again time defective and resurvey, after qualified, adjourn next survey station, until completing the observation of all survey stations.
Completing the method that the data after step " 3) data observation " process is:
(1) the observation statistical average of each survey station each survey time is taken as final observing buoy;
(2) calculate between survey station and each measuring point flat from, the discrepancy in elevation, and horizontal angle between measuring point, and calculate measuring point coordinate with survey station for initial point;
(3) calculate the orientation between 2 by measuring point coordinate, flat from, the discrepancy in elevation, extract desired data to form the observation data of equivalence according to different conductor net networking condition.
Embodiment: carried out applying and succeeding in applicant's project according to above inventive method.Certain railway tunnel total length 2.1 kilometers, import is positioned at straightway, and other parts are positioned at curved section, sets station method traverse net survey according to centre and set horizontal control network after tunnel holing through.At tunnel entrance, exporting GPS control point outside the hole of translocation respectively, form starting at and closure condition of hole inside conductor net, the symmetrical laying of hole inside conductor point, consecutive points spacing, between 100~150 meters, buries 40 points 20 points of composition underground right altogether.
According to existing " railroad engineering survey specification " TB10101-2009 relevant regulations, hole inside conductor Controling network is third wire, and main technical requirements is in Table 1, the main technical requirements of traverse survey.
Fieldwork observation adopts LeicaTCRP1201+ total powerstation, angle measurement accuracy 1.0 ", range accuracy 1mm+1ppm, every survey station observed for 6 survey time.
Tunnel control net sets station method traverse net according to centre and carries out fieldwork observation (Fig. 4), after calculating survey station coordinate according to fieldwork observation achievement, conversion forms adjustment file (Fig. 5), 1 connecting traverse being made up of 24 points is formed between Controling network is imported and exported, wire conforms to precision in Table 2, forming 39 tetragon Guan Bi rings, ring closure accuracy is in Table 3.
Table 2 loop closure check table
Connecting traverse: orientation mis-tie misclosure-3.5 ", meet limit poor=16.9 " requirements;Wire total length 2.406 kilometers, coordinate mis-tie misclosure 0.0231 meter, wire relative closing error of extreme length is 1/104307, meets specification 1/55000 requirement.
Table 3 ring closure accuracy
Guan Bi ring: 39, angular error of closure meansigma methods 2.1 ", maximum 7.1 " and, meet specification 7.2 " requirement;Coordinate mis-tie misclosure meansigma methods 1.4mm, maximum 4.2mm, total length relative coordinate mis-tie misclosure is respectively less than 1/1000000, meets specification 1/55000 requirement.
Traverse net mean square error of angle observation< specification 1.8 " requirement.
Wherein:
N closing of polygon ring number;
fβConductor loop angular error of closure (");
N calculates fβTime corresponding survey station number.
Hole inner plane Controling network wire presses variance components estimate pattern rigorous adjustment, the average 1.35mm of mean square error of a point, the most weak limit (D38 to D40) the distance phase error of centralization 1/275000, meets specification 1/150000 requirement.

Claims (3)

1. a Tunnel Engineering hole inner plane Controling network method for fast measuring, on hole outer control point, total powerstation is set up when it is characterized in that Controling network translocation inside and outside hole, when measuring in hole, total powerstation is erected at medium position between 2 control point of symmetrical laying, observe all around horizontal angle, vertical angle and oblique distance between adjacent control points, all survey stations observation data composition horizontal control network.
2. Tunnel Engineering hole according to claim 1 inner plane Controling network method for fast measuring, it is characterised in that step is as follows:
1) point arrangement,
In hole, control point is distributed in the center line left and right sides, tunnel by symmetric mode laying, and the control point, 2, left and right being in same section mileage is right referred to as point;
2) survey station tissue,
(1) on control point, hole (A), total powerstation is set up, as survey station after centering leveling, at hole outer control point (B) upper erection prism as backsight, in symmetrical hole, in control point I (1) and hole, the upper erection prism in control point II (2), as forward sight, observes 3 points altogether;
(2) put in hole successively between medium position erection total powerstation, without centering, therefore, in hole, in control point I (1) and hole, in hole between control point II (2), the 1st survey station will observe 5 points and control point, hole (A), control point II (2) in control point I (1) and hole in symmetrical hole, control point IV (4) in control point III (3) and hole in symmetrical hole, control point II (2) in control point I (1) and hole in the hole that in control point III (3) and hole, in hole between control point IV (4), the 2nd survey station is namely symmetrical by observing 6 points in hole, control point IV (4) in control point III (3) and hole in symmetrical hole, control point VI (6) in control point V (5) and hole in symmetrical hole;..., in the hole that in the hole of latter two symmetry, in control point Ⅸ (9) and hole, in hole between control point Ⅹ (10), the last leg is namely symmetrical by observing 4 points, in control point VII (7) and hole, in the hole of control point VIII (8), symmetry, in control point Ⅸ (9) and hole control point Ⅹ (10);
3), data observation,
(1) instrument height is measured, instrument height refers to that after total powerstation flattens total powerstation transverse axis is to the vertical height between the end face of control point, measure instrument when outer control point in hole sets up Setting Station of Total Station Instrument high from the end face amount of control point, put in hole and unify to be set to 0m without measuring when middle frame sets Setting Station of Total Station Instrument;
(2) measuring mirror height, mirror height refers to that prism centers is to the vertical height between the end face of control point, and the mirror at whole control point that each station measures the observation of this survey station before starting to measure is high;
(3) each survey station start measure before must measure field temperature, air pressure, humidity, be input in total powerstation automatically carry out range finding achievement correction;
(4) diopter triggers one-shot measurement after being located at the prism centers on control point, simultaneously recording level angle, vertical angle, three readings of oblique distance;
(5) observation process requires to carry out according to method of direction observation, and position number, accuracy of observation and limit are poor, zero direction, zero observation etc. are determined according to industry standard, measurement grade;
(6) after completing the observation of all position number, check fieldwork observation precision index, do over again time defective and resurvey, after qualified, adjourn next survey station, until completing the observation of all survey stations.
3. a kind of Tunnel Engineering hole according to claim 1 and 2 inner plane Controling network method for fast measuring, it is characterised in that completing the method that the data after step " 3) data observation " process is:
(1) the observation statistical average of each survey station each survey time is taken as final observing buoy;
(2) calculate between survey station and each measuring point flat from, the discrepancy in elevation, and horizontal angle between measuring point, and calculate measuring point coordinate with survey station for initial point;
(3) calculate the orientation between 2 by measuring point coordinate, flat from, the discrepancy in elevation, extract desired data to form the observation data of equivalence according to different conductor net networking condition.
CN201511015034.9A 2015-12-31 2015-12-31 A kind of Tunnel Engineering hole inner plane controls net method for fast measuring Active CN105716575B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511015034.9A CN105716575B (en) 2015-12-31 2015-12-31 A kind of Tunnel Engineering hole inner plane controls net method for fast measuring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511015034.9A CN105716575B (en) 2015-12-31 2015-12-31 A kind of Tunnel Engineering hole inner plane controls net method for fast measuring

Publications (2)

Publication Number Publication Date
CN105716575A true CN105716575A (en) 2016-06-29
CN105716575B CN105716575B (en) 2019-10-29

Family

ID=56147672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511015034.9A Active CN105716575B (en) 2015-12-31 2015-12-31 A kind of Tunnel Engineering hole inner plane controls net method for fast measuring

Country Status (1)

Country Link
CN (1) CN105716575B (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106092068A (en) * 2016-08-10 2016-11-09 中矿金业股份有限公司 Misalign measurement system and the measuring method of traverse survey tested point coordinate
CN106840066A (en) * 2017-01-13 2017-06-13 武汉大学 A kind of long distance tunnel internal precision horizontal control network net type
CN109357667A (en) * 2018-09-30 2019-02-19 陕西省引汉济渭工程建设有限公司 The method of network forming form tunnel plane connection survey
CN109446497A (en) * 2018-12-28 2019-03-08 中国水利水电第四工程局有限公司 One kind is grown up tunnel traverse survey record and data processing method
CN109468899A (en) * 2018-09-21 2019-03-15 湖北省水利水电规划勘测设计院 A method of increasing observed quantity between railroad track control net voluntary intake
CN109798880A (en) * 2019-01-26 2019-05-24 中交一航局第四工程有限公司 The control points layout method of one step surveying method is combined in a kind of house acceptance survey
CN109916373A (en) * 2019-01-21 2019-06-21 中铁第四勘察设计院集团有限公司 A kind of control net measurement of high-speed railway rail and data mobile process system and method
CN110375721A (en) * 2019-06-13 2019-10-25 中交二航局第四工程有限公司 A method of it is positioned for high column overhead structure precision three-dimensional
CN111006639A (en) * 2019-12-16 2020-04-14 江苏苏州地质工程勘察院 Interval tunnel penetration measurement method
CN109459765B (en) * 2018-12-12 2020-09-01 中铁二局集团有限公司 High-precision tunnel independent control network establishment method based on existing GNSS control network
CN111693021A (en) * 2020-06-22 2020-09-22 中铁六局集团有限公司 Checking method for wire points in tunnel hole
CN111927557A (en) * 2020-09-16 2020-11-13 北京龙软科技股份有限公司 Automatic measuring method and network system for measuring robot of mine fully mechanized coal mining face
CN113532399A (en) * 2021-07-09 2021-10-22 上海宝冶集团有限公司 Multi-target observation control measurement method in tunnel
CN114111735A (en) * 2021-11-02 2022-03-01 上海市基础工程集团有限公司 High-precision control measurement method for shield tunnel in scientific experiment
CN114543772A (en) * 2022-04-25 2022-05-27 中交第一航务工程局有限公司 In-tunnel and out-tunnel contact measurement method of immersed tunnel and double-tunnel point-throwing contact measurement method
CN115014281A (en) * 2022-05-18 2022-09-06 中铁八局集团昆明铁路建设有限公司 Hydraulic tunnel steep slope inclined shaft elevation control network measuring method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001165656A (en) * 1999-12-06 2001-06-22 Kumagai Gumi Co Ltd Automatic measurement system for tunnel convergence
CN102953304A (en) * 2012-09-20 2013-03-06 中铁三局集团有限公司 Precision measurement control method of metro track structure construction
CN103306172A (en) * 2013-06-07 2013-09-18 西南交通大学 Method for building track control CP III network in simple point form

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001165656A (en) * 1999-12-06 2001-06-22 Kumagai Gumi Co Ltd Automatic measurement system for tunnel convergence
CN102953304A (en) * 2012-09-20 2013-03-06 中铁三局集团有限公司 Precision measurement control method of metro track structure construction
CN103306172A (en) * 2013-06-07 2013-09-18 西南交通大学 Method for building track control CP III network in simple point form

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
何保喜: "《全站仪测量技术》", 31 August 2005, 黄河水利出版社 *
邹浜等: "长大隧道洞内自由测站边角交会网平面控制测量", 《测绘科学》 *

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106092068B (en) * 2016-08-10 2019-01-29 中矿金业股份有限公司 Misalign the measuring system and measurement method of traverse survey tested point coordinate
CN106092068A (en) * 2016-08-10 2016-11-09 中矿金业股份有限公司 Misalign measurement system and the measuring method of traverse survey tested point coordinate
CN106840066A (en) * 2017-01-13 2017-06-13 武汉大学 A kind of long distance tunnel internal precision horizontal control network net type
CN109468899A (en) * 2018-09-21 2019-03-15 湖北省水利水电规划勘测设计院 A method of increasing observed quantity between railroad track control net voluntary intake
CN109357667A (en) * 2018-09-30 2019-02-19 陕西省引汉济渭工程建设有限公司 The method of network forming form tunnel plane connection survey
CN109357667B (en) * 2018-09-30 2020-11-27 陕西省引汉济渭工程建设有限公司 Network-forming tunnel plane contact measurement method
CN109459765B (en) * 2018-12-12 2020-09-01 中铁二局集团有限公司 High-precision tunnel independent control network establishment method based on existing GNSS control network
CN109446497A (en) * 2018-12-28 2019-03-08 中国水利水电第四工程局有限公司 One kind is grown up tunnel traverse survey record and data processing method
CN109916373A (en) * 2019-01-21 2019-06-21 中铁第四勘察设计院集团有限公司 A kind of control net measurement of high-speed railway rail and data mobile process system and method
CN109798880A (en) * 2019-01-26 2019-05-24 中交一航局第四工程有限公司 The control points layout method of one step surveying method is combined in a kind of house acceptance survey
CN110375721A (en) * 2019-06-13 2019-10-25 中交二航局第四工程有限公司 A method of it is positioned for high column overhead structure precision three-dimensional
CN110375721B (en) * 2019-06-13 2021-07-06 中交二航局第四工程有限公司 Method for precise three-dimensional positioning of high tower top structure
CN111006639A (en) * 2019-12-16 2020-04-14 江苏苏州地质工程勘察院 Interval tunnel penetration measurement method
CN111693021A (en) * 2020-06-22 2020-09-22 中铁六局集团有限公司 Checking method for wire points in tunnel hole
CN111693021B (en) * 2020-06-22 2022-08-02 中铁六局集团有限公司 Checking method for wire points in tunnel hole
CN111927557A (en) * 2020-09-16 2020-11-13 北京龙软科技股份有限公司 Automatic measuring method and network system for measuring robot of mine fully mechanized coal mining face
CN111927557B (en) * 2020-09-16 2021-01-12 北京龙软科技股份有限公司 Automatic measuring method and network system for measuring robot of mine fully mechanized coal mining face
CN113532399A (en) * 2021-07-09 2021-10-22 上海宝冶集团有限公司 Multi-target observation control measurement method in tunnel
CN113532399B (en) * 2021-07-09 2022-12-02 上海宝冶集团有限公司 Multi-target observation control measurement method in tunnel
CN114111735A (en) * 2021-11-02 2022-03-01 上海市基础工程集团有限公司 High-precision control measurement method for shield tunnel in scientific experiment
CN114111735B (en) * 2021-11-02 2024-03-29 上海市基础工程集团有限公司 High-precision control measurement method for shield tunnel in scientific experiment
CN114543772A (en) * 2022-04-25 2022-05-27 中交第一航务工程局有限公司 In-tunnel and out-tunnel contact measurement method of immersed tunnel and double-tunnel point-throwing contact measurement method
CN115014281A (en) * 2022-05-18 2022-09-06 中铁八局集团昆明铁路建设有限公司 Hydraulic tunnel steep slope inclined shaft elevation control network measuring method
CN115014281B (en) * 2022-05-18 2024-05-10 中铁八局集团昆明铁路建设有限公司 Hydraulic tunnel heavy-gradient inclined shaft elevation control network measurement method

Also Published As

Publication number Publication date
CN105716575B (en) 2019-10-29

Similar Documents

Publication Publication Date Title
CN105716575A (en) Method for rapid measurement of horizontal control network in engineering tunnel
CN102174893B (en) Testing method for laying ballastless tracks in early stage before overall completion of super long tunnel
CN104848845B (en) Underground tunnel virtual double-lead control measurement method
CN109631839A (en) A method of bridge pier settlement observation in water is carried out using total station
CN101614127B (en) Method for surveying river-crossing leveling during shield breakthrough construction
CN110044326A (en) Mountainous area highway application Trigonometric Leveling
CN110704809B (en) Method for calculating angle closing difference of corner intersection network of railway CP II free survey station
CN108457143B (en) Track line coordinate measuring system
CN109059844A (en) A kind of measurement method of long range rail linearity degree and flatness
CN103115610B (en) Be applicable to the leveling measuring method of composite level
CN103196425A (en) Estimation method of extra-long tunnel horizontal through error
CN103499340A (en) Measurement device and measurement method for vertical great-height difference height transmission
CN108882149A (en) NLOS apart from dependent probability compensates localization method
CN108534765B (en) Track line coordinate measuring method
CN108318011B (en) Method for monitoring peripheral displacement of construction site through unmanned aerial vehicle carrying total station
CN107228650A (en) The wire type measuring method of dual system bilateral observation composite level
CN109357667A (en) The method of network forming form tunnel plane connection survey
CN108917706A (en) A kind of GNSS leveling measuring method
CN110130168A (en) A kind of railroad track control net triangulated height data correction processing method
CN102493296A (en) Method for measuring longspan steel truss girder rail control network
CN111721260B (en) High-precision light beam method settlement measurement method based on i-angle error correction of level gauge
CN105821728B (en) A kind of plane net measuring systems of CP III
CN103759705A (en) Three-point closed laying measurement method for composite water level
CN109282802B (en) A kind of Free Station method based on the measurement of single-deck position
CN113551643B (en) River-crossing leveling method and system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 030073 Yingze Street 269, Yingze District, Taiyuan City, Shanxi Province

Applicant after: Shanxi Tiansheng Surveying and Mapping Engineering Co., Ltd.

Address before: 030002 No. 38 Taoyuan North Road, Yingze District, Taiyuan City, Shanxi Province

Applicant before: Shanxi Tianli Litres o Surveying and Mapping Engineering Co., Ltd.

CB02 Change of applicant information
TA01 Transfer of patent application right

Effective date of registration: 20190919

Address after: 030001 Yingze street, Shanxi, No. 269, No.

Applicant after: China Railway Third Engineering Co., Ltd.

Applicant after: Shanxi Tiansheng Surveying and Mapping Engineering Co., Ltd.

Address before: 030073 Yingze Street 269, Yingze District, Taiyuan City, Shanxi Province

Applicant before: Shanxi Tiansheng Surveying and Mapping Engineering Co., Ltd.

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant