CN105716575B - A kind of Tunnel Engineering hole inner plane controls net method for fast measuring - Google Patents

A kind of Tunnel Engineering hole inner plane controls net method for fast measuring Download PDF

Info

Publication number
CN105716575B
CN105716575B CN201511015034.9A CN201511015034A CN105716575B CN 105716575 B CN105716575 B CN 105716575B CN 201511015034 A CN201511015034 A CN 201511015034A CN 105716575 B CN105716575 B CN 105716575B
Authority
CN
China
Prior art keywords
hole
control point
point
station
control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201511015034.9A
Other languages
Chinese (zh)
Other versions
CN105716575A (en
Inventor
郭志广
苏雅拉图
王波
杜伟
乔长宝
谢铁伟
刘莹
白冰
戚浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Tiansheng Surveying and Mapping Engineering Co., Ltd.
China Railway No 3 Engineering Group Co Ltd
Original Assignee
Shanxi Tiansheng Surveying And Mapping Engineering Co Ltd
China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Tiansheng Surveying And Mapping Engineering Co Ltd, China Railway No 3 Engineering Group Co Ltd filed Critical Shanxi Tiansheng Surveying And Mapping Engineering Co Ltd
Priority to CN201511015034.9A priority Critical patent/CN105716575B/en
Publication of CN105716575A publication Critical patent/CN105716575A/en
Application granted granted Critical
Publication of CN105716575B publication Critical patent/CN105716575B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C7/00Tracing profiles
    • G01C7/06Tracing profiles of cavities, e.g. tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Multimedia (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Radar, Positioning & Navigation (AREA)
  • Remote Sensing (AREA)
  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

The invention belongs to Tunnel Engineering to control field of measuring technique, and in particular to a kind of method for fast measuring that horizontal control network is established in Tunnel Engineering hole solves the problems, such as that Traditional control net work operations amount is big, low efficiency.It is characterized in that total station is set up on control point outside hole when control net translocation inside and outside hole, total station is erected at medium position between 2 control points that bilateral symmetry is laid when measuring in hole, horizontal angle, vertical angle and oblique distance between adjacent control points all around are observed, all survey stations observation data form horizontal control networks.It is minimum by horizontal Effect of Refraction that the invention has the following beneficial effects: angular observations;In the completely identical in structure situation of traverse net, station method traverse net is set using centre and improves 60% or more than traditional approach working efficiency.

Description

A kind of Tunnel Engineering hole inner plane controls net method for fast measuring
Technical field
The invention belongs to Tunnel Engineering to control field of measuring technique, and in particular to a kind of Tunnel Engineering hole inner plane controls net Method for fast measuring.
Background technique
In order to guarantee tunnel midline plane penetrating accuracy, it is necessary to be established on the basis of control net outside hole and control net in hole.One As in Tunnel Engineering hole space interfered than narrow, in work progress big, sighting condition is poor, therefore inner plane control net in hole is often adopted With the flexible traverse net of laying.
Traditional hole inside conductor is frequently with close ring traverse net.Advantage is that have redundancy observation, can organize cyclic closure condition, The disadvantage is that fieldwork observation amount is big, and it is inefficient, it is generally used for controlling measurement in the hole of major long tunnel.
Close ring traverse net measurement method is as follows in traditional hole:
1, total station is set up on the A of hole control point, is used as survey station after centering leveling, is set up base on the B of control point outside hole Seat prism group is used as backsight after centering leveling, pedestal prism group is set up on control point 1,2 in hole, before being used as after centering leveling Depending on.
2, start to read live temperature, air pressure, humidity parameter when measurement, be input in total station and carry out ranging achievement automatically Correction.
3, observation process uses method of direction observation.Upper semiobservation observes control point B outside hole, control point 1, hole in hole clockwise Interior control point 2 and zero direction Ji Dongwai control point B, lower semiobservation are observed counterclockwise.It is required that it is same once to sight prism centers When measurement angle and distance.
4, successively all control points (A, 1,2,3 ..., 9) on set up total station be used as survey station, observation it is ipsilateral with survey station Adjacent 2 control points in front and back, control point, specific translocation in translocation survey station opposite side rear or front hole when needing to form close ring Which point will be no more than 4~6 sides according to close ring number of edges to determine, ultimately form close ring traverse net, as shown in Figure 1, figure Intermediate cam indicates control point outside hole, and dot indicates control point in hole, and two-wire indicates known side, and single line indicates observation side, close ring Number is labeled in circle, and close ring is generally made of 4~6 sides.
With the universal use of servo type total station, automatic Observation is carried out using (ATR) technology is sighted automatically, is not only reduced The working strength of survey crew, while observation time is shortened, accuracy of observation is also improved, therefore hole inside conductor net occurs Cross-wire web form, as shown in Fig. 2, figure intermediate cam indicates control point outside hole, dot indicates that hole inside conductor point, two-wire indicate Know side, side is observed in unilateral expression, and close ring number marks in circle, and close ring is generally made of 4 sides.
Cross-wire net is characterized in that in addition to hole in control point and hole outside the last one control point that survey station is seen simultaneously in hole 2 pairs of adjacent control points of front and back are surveyed, advantage is: every 4 sides can form a close ring, in the measuring point of identical quantity Cross-wire net close ring number of combinations significantly enhances control net discovery rough error and resistance far more than close ring traverse net The ability of rough error improves the reliability of Measurement results.The disadvantage is that: each control point is both needed to set up Setting Station of Total Station Instrument observation, And each station observed quantity is than about 1 times of the increase of close ring traverse net.The factors shadow such as big is interfered in often poor by sighting condition in hole, construction It rings, causes loop closure to transfinite, it is necessary to do over again and resurvey.
Summary of the invention
The present invention proposes one kind to solve Tunnel Engineering hole inner plane control net traverse survey efficiency and precision problem Method for fast measuring.
The present invention is achieved by the following technical scheme:
Tunnel Engineering hole inner plane controls net method for fast measuring, it is characterised in that inside and outside hole when control net translocation outside hole Total station is set up on control point, total station is erected at medium position between 2 control points that bilateral symmetry is laid when measuring in hole, Horizontal angle, vertical angle and oblique distance between adjacent control points all around are observed, all survey stations observation data form horizontal control networks.
Specific step is as follows:
1) point arrangement,
Control point is distributed at left and right sides of tunnel middle line and lays by symmetric mode in hole, the left and right in same section mileage 2 control points referred to as point pair;
2) survey station tissue,
(1) total station is set up on hole control point (A), is used as survey station, control point (B) restocking outside hole after centering leveling If prism as backsight, sets up prism on control point II (2) in control point I (1) and hole in symmetrical hole and is used as forward sight, sight altogether Survey 3 points;
(2) successively in point in hole, medium position sets up total station between, is not necessarily to centering, therefore, control point I in hole (1) and in the hole in hole between control point II (2) the 1st survey station will observe 5 points i.e. hole control point (A), symmetrical hole internal control Control point II (2) in system I (1) of point and hole, control point IV (4), the control point in hole in control point III (3) and hole in symmetrical hole The 2nd survey station will observe control point I (1) and hole in the i.e. symmetrical hole of 6 points in hole in III (3) and hole between control point IV (4) Control point IV (4) in control point III (3) and hole in interior control point II (2), symmetrical hole, in symmetrical hole control point V (5) and Control point VI (6) in hole;..., the hole in most latter two symmetrical hole in control point Ⅸ (9) and hole between control point Ⅹ (10) Interior the last leg will observe in the i.e. symmetrical hole of 4 points control point VIII (8) in control point VII (7) and hole, control in symmetrical hole Control point Ⅹ (10) in Ⅸ (9) of point and hole;
3), data observation,
(1) it is high to measure instrument, instrument height refers to after total station leveling total station horizontal axis to the vertical height between the top surface of control point Degree measures instrument height from the amount of control point top surface on control point outside hole when erection Setting Station of Total Station Instrument, point sets middle frame in hole 0m is uniformly set as without measurement when Setting Station of Total Station Instrument;
(2) mirror height is measured, mirror height refers to prism centers to the vertical height between the top surface of control point, and each station starts to measure The mirror at the preceding whole control points for measuring the observation of this survey station is high;
(3) each survey station start before measurement must measure field temperature, air pressure, humidity, be input in total station automatically into The correction of row ranging achievement;
(4) aim at and trigger one-shot measurement after the prism centers that are erected on control point, at the same recording level angle, vertical angle, Oblique distance three readings;
(5) observation process requires to carry out according to method of direction observation, and position number, accuracy of observation and limit are poor, zero direction, are zeroed Observation etc. is determined according to industry standard, measurement grade;
(6) it after completing all position number observations, checks fieldwork observation precision index, does over again and resurvey when unqualified, after qualified Next survey station is adjourned, until completing all survey station observations.
The method of data processing after completing step " 3) data observation " are as follows:
(1) take the observation statistical average of each survey station each survey time as final observing buoy;
(2) it calculates and is put down between survey station and each measuring point away from horizontal angle between, height difference and measuring point, and be that origin calculates survey using survey station Point coordinate;
(3) orientation between two o'clock is calculated by measuring point coordinate, is flat away from, height difference, mentioned according to different conductor net networking condition Required data are taken to form equivalent observation data.
The present invention has the following beneficial effects: compared with the prior art
(1) control point uses point to be laid in tunnel middle line two sides to form in hole, and total station is erected at a little to middle part tunnel Midline position makes angle measurement minimum by horizontal Effect of Refraction.
(2) in the completely identical in structure situation of traverse net, station method conducting wire is set than traditional approach working efficiency using centre Improve 60% or more.
By taking Fig. 1 as an example, using close ring conducting wire net mode: each survey station observes 2 measuring points, sight when needing to form close ring Survey 3 points, left and right sets station for 2 times and removes after coincidence point 4 measuring points of actual observation, using cross-wire net mode: each survey station Observe 4 measuring points, left and right sets station for 2 times and removes after coincidence point 4 measuring points of actual observation, and sets station method traverse net side using centre Formula: once setting station can be completed the observation of 6 points.
(3) the intermediate station method traverse net observation data that set form cross-wire network data, in close ring angular error of closure, overall length After relatively closed difference is met the requirements, using tight method compensating computation.
Detailed description of the invention
Fig. 1 is existing close ring traverse net,
Fig. 2 is existing cross-wire net,
Fig. 3, which is that the present invention is intermediate, sets station method traverse net observation chart
Fig. 4, which is that the present invention is intermediate, sets station method Traverse Network Adjustment figure,
Fig. 5 is to set station method traverse net observation chart among embodiment,
Fig. 6 is to set station method Traverse Network Adjustment figure among embodiment.
In figure: known point outside the hole △, 1 hole inside conductor point set station location among ◎ ,=known side ,-observation side (angle, Distance) ,+observation side (only distance), 1., 2., 3. ... close ring serial number, the centre C1, C2, C3 ... set station serial number.
Specific embodiment
Tunnel Engineering hole inner plane controls net method for fast measuring, it is characterised in that inside and outside hole when control net translocation outside hole Total station is set up on control point, total station is erected at medium position between 2 control points that bilateral symmetry is laid when measuring in hole, Horizontal angle, vertical angle and oblique distance between adjacent control points all around are observed, all survey stations observation data form horizontal control networks.
Specific step is as follows:
1) point arrangement,
Control point is distributed at left and right sides of tunnel middle line and lays by symmetric mode in hole, the left and right in same section mileage 2 control points referred to as point pair;
2) survey station tissue,
(1) total station is set up on hole control point (A), is used as survey station, control point (B) restocking outside hole after centering leveling If prism as backsight, sets up prism on control point II (2) in control point I (1) and hole in symmetrical hole and is used as forward sight, sight altogether Survey 3 points;
(2) successively in point in hole, medium position sets up total station between, is not necessarily to centering, therefore, control point I in hole (1) and in the hole in hole between control point II (2) the 1st survey station will observe 5 points i.e. hole control point (A), symmetrical hole internal control Control point II (2) in system I (1) of point and hole, control point IV (4), the control point in hole in control point III (3) and hole in symmetrical hole The 2nd survey station will observe control point I (1) and hole in the i.e. symmetrical hole of 6 points in hole in III (3) and hole between control point IV (4) Control point IV (4) in control point III (3) and hole in interior control point II (2), symmetrical hole, in symmetrical hole control point V (5) and Control point VI (6) in hole;..., the hole in most latter two symmetrical hole in control point Ⅸ (9) and hole between control point Ⅹ (10) Interior the last leg will observe in the i.e. symmetrical hole of 4 points control point VIII (8) in control point VII (7) and hole, control in symmetrical hole Control point Ⅹ (10) in Ⅸ (9) of point and hole;
3), data observation,
(1) it is high to measure instrument, instrument height refers to after total station leveling total station horizontal axis to the vertical height between the top surface of control point Degree measures instrument height from the amount of control point top surface on control point outside hole when erection Setting Station of Total Station Instrument, point sets middle frame in hole 0m is uniformly set as without measurement when Setting Station of Total Station Instrument;
(2) mirror height is measured, mirror height refers to prism centers to the vertical height between the top surface of control point, and each station starts to measure The mirror at the preceding whole control points for measuring the observation of this survey station is high;
(3) each survey station start before measurement must measure field temperature, air pressure, humidity, be input in total station automatically into The correction of row ranging achievement;
(4) aim at and trigger one-shot measurement after the prism centers that are erected on control point, at the same recording level angle, vertical angle, Oblique distance three readings;
(5) observation process requires to carry out according to method of direction observation, and position number, accuracy of observation and limit are poor, zero direction, are zeroed Observation etc. is determined according to industry standard, measurement grade;
(6) it after completing all position number observations, checks fieldwork observation precision index, does over again and resurvey when unqualified, after qualified Next survey station is adjourned, until completing all survey station observations.
The method of data processing after completing step " 3) data observation " are as follows:
(1) take the observation statistical average of each survey station each survey time as final observing buoy;
(2) it calculates and is put down between survey station and each measuring point away from horizontal angle between, height difference and measuring point, and be that origin calculates survey using survey station Point coordinate;
(3) orientation between two o'clock is calculated by measuring point coordinate, is flat away from, height difference, mentioned according to different conductor net networking condition Required data are taken to form equivalent observation data.
Embodiment: apply and succeed in applicant's project according to the above inventive method.Certain railway tunnel 2.1 kilometers of overall length, import is located at straightway, and other parts are located at curved section, sets station method conducting wire according to centre after tunnel holing through Net is surveyed and has set horizontal control network.In tunnel entrance, the control point GPS outside the hole of translocation respectively is exported, forms rising for hole inside conductor net It calculates and closure condition, hole inside conductor point bilateral symmetry is laid, consecutive points spacing buries 40 point groups between 100~150 meters altogether At 20 points pair.
According to existing " railroad engineering survey specification " TB10101-2009 relevant regulations, inside conductor control net in hole is third leads Line, main technical requirements are shown in Table 1, the main technical requirements of traverse survey.
Fieldwork observation uses Leica TCRP1201+ total station, angle measurement accuracy 1.0 ", range accuracy 1mm+1ppm, every survey It stands 6 survey time of observation.
Tunnel control net sets station method traverse net according to centre and carries out fieldwork observation (Fig. 4), is calculated according to fieldwork observation achievement Conversion forms adjustment file (Fig. 5) after survey station coordinate, forms 1 between control net inlet and outlet and is led by conforming to of forming of 24 points Line, conducting wire conform to precision and are shown in Table 2, form 39 quadrangle close rings, and ring closure accuracy is shown in Table 3.
2 loop closure of table checks table
Connecting traverse: orientation mis-tie misclosure -3.5 ", it is poor to meet limit=16.9 " it requires;2.406 kilometers of conducting wire overall length, 0.0231 meter of coordinate mis-tie misclosure, conducting wire relative closing error of extreme length is 1/104307, meets the requirement of specification 1/55000.
3 ring closure accuracy of table
Close ring: 39, angular error of closure average value 2.1 ", maximum value 7.1 " and, meet specification 7.2 and " require;Coordinate closure Poor average value 1.4mm, maximum value 4.2mm, overall length relative coordinate mis-tie misclosure are respectively less than 1/1000000, meet specification 1/55000 and want It asks.
Traverse net mean square error of angle observation< specification 1.8 " requires.
Wherein:
N-closing of polygon ring number;
fβ- conductor loop angular error of closure (");
N-calculating fβWhen corresponding survey station number.
Hole inner plane controls net conducting wire and presses variance components estimate mode rigorous adjustment, and mean square error of a point is averaged 1.35mm, most (D38 to D40) meets the requirement of specification 1/150000 apart from the phase error of centralization 1/275000 on weak side.

Claims (2)

1. a kind of Tunnel Engineering hole inner plane controls net method for fast measuring, it is characterised in that in hole when control net translocation inside and outside hole Total station is set up on outer control point, total station is erected at middle position between 2 control points that bilateral symmetry is laid when measuring in hole It sets, observes horizontal angle, vertical angle and oblique distance between adjacent control points all around, all survey stations observation data form plane controls Net,
Steps are as follows:
1) point arrangement,
Control point is distributed at left and right sides of tunnel middle line and lays by symmetric mode in hole, the left and right in same section mileage 2 Control point referred to as point pair, consecutive points spacing is between 100~150 meters;
2) survey station tissue,
(1) total station is set up on hole control point (A), is used as survey station after centering leveling, is set up rib on control point (B) outside hole Mirror sets up prism as forward sight on control point II (2) in control point I (1) and hole in symmetrical hole, observes 3 altogether as backsight A point;
(2) successively in hole point between medium position set up total station, be not necessarily to centering, therefore, in hole control point I (1) and The 1st survey station will observe 5 points i.e. hole control point (A) in hole in hole between control point II (2), in symmetrical hole control point I (1) control point II (2) and in hole, control point IV (4), the control point III (3) in hole in control point III (3) and hole in symmetrical hole And the 2nd survey station will be observed in the i.e. symmetrical hole of 6 points and be controlled in control point I (1) and hole in the hole in hole between control point IV (4) II (2) of point, control point IV (4) in control point III (3) and hole, control point V (5) and hole internal control in symmetrical hole in symmetrical hole VI (6) of system point;..., it is last in the hole in most latter two symmetrical hole in control point Ⅸ (9) and hole between control point Ⅹ (10) One station will observe in the i.e. symmetrical hole of 4 points that control point VIII (8) in control point VII (7) and hole, in symmetrical hole control point Ⅸ (9) With control point Ⅹ (10) in hole;
3), data observation,
(1) it is high to measure instrument, instrument height refers to after total station leveling total station horizontal axis to the vertical height between the top surface of control point, In Instrument height is measured when setting up Setting Station of Total Station Instrument outside hole on control point from the amount of control point top surface, point sets total station to middle frame in hole If being uniformly set as 0m without measurement when standing;
(2) mirror height is measured, mirror height refers to prism centers to the vertical height between the top surface of control point, and each station starts to measure preceding amount The mirror at the whole control points for taking this survey station to observe is high;
(3) each survey station starts necessary measure field temperature, air pressure, humidity before measurement, is input in total station and is surveyed automatically Correction away from achievement;
(4) one-shot measurement, while recording level angle, vertical angle, oblique distance are triggered after aiming at the prism centers being erected on control point Three readings;
(5) observation process requires to carry out according to method of direction observation, and position number, accuracy of observation and limit are poor, direction of being zeroed, zero observation It is determined Deng according to industry standard, measurement grade;
(6) it after completing all position number observations, checks fieldwork observation precision index, does over again and resurvey when unqualified, adjourned after qualified Next survey station, until completing all survey station observations.
2. a kind of Tunnel Engineering hole inner plane according to claim 1 controls net method for fast measuring, it is characterised in that complete At the method for the data processing after step " 3) data observation " are as follows:
(1) take the observation statistical average of each survey station each survey time as final observing buoy;
(2) it calculates and is put down between survey station and each measuring point away from horizontal angle between, height difference and measuring point, and be that origin calculates measuring point seat using survey station Mark;
(3) orientation between two o'clock is calculated by measuring point coordinate, is flat away from, height difference, extracting institute according to different conductor net networking condition Data are needed to form equivalent observation data.
CN201511015034.9A 2015-12-31 2015-12-31 A kind of Tunnel Engineering hole inner plane controls net method for fast measuring Active CN105716575B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201511015034.9A CN105716575B (en) 2015-12-31 2015-12-31 A kind of Tunnel Engineering hole inner plane controls net method for fast measuring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201511015034.9A CN105716575B (en) 2015-12-31 2015-12-31 A kind of Tunnel Engineering hole inner plane controls net method for fast measuring

Publications (2)

Publication Number Publication Date
CN105716575A CN105716575A (en) 2016-06-29
CN105716575B true CN105716575B (en) 2019-10-29

Family

ID=56147672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201511015034.9A Active CN105716575B (en) 2015-12-31 2015-12-31 A kind of Tunnel Engineering hole inner plane controls net method for fast measuring

Country Status (1)

Country Link
CN (1) CN105716575B (en)

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106092068B (en) * 2016-08-10 2019-01-29 中矿金业股份有限公司 Misalign the measuring system and measurement method of traverse survey tested point coordinate
CN106840066A (en) * 2017-01-13 2017-06-13 武汉大学 A kind of long distance tunnel internal precision horizontal control network net type
CN109468899B (en) * 2018-09-21 2020-08-14 湖北省水利水电规划勘测设计院 Method for increasing observed quantity between free observation stations of railway track control network
CN109357667B (en) * 2018-09-30 2020-11-27 陕西省引汉济渭工程建设有限公司 Network-forming tunnel plane contact measurement method
CN109459765B (en) * 2018-12-12 2020-09-01 中铁二局集团有限公司 High-precision tunnel independent control network establishment method based on existing GNSS control network
CN109446497A (en) * 2018-12-28 2019-03-08 中国水利水电第四工程局有限公司 One kind is grown up tunnel traverse survey record and data processing method
CN109916373A (en) * 2019-01-21 2019-06-21 中铁第四勘察设计院集团有限公司 A kind of control net measurement of high-speed railway rail and data mobile process system and method
CN109798880A (en) * 2019-01-26 2019-05-24 中交一航局第四工程有限公司 The control points layout method of one step surveying method is combined in a kind of house acceptance survey
CN110375721B (en) * 2019-06-13 2021-07-06 中交二航局第四工程有限公司 Method for precise three-dimensional positioning of high tower top structure
CN111006639A (en) * 2019-12-16 2020-04-14 江苏苏州地质工程勘察院 Interval tunnel penetration measurement method
CN111693021B (en) * 2020-06-22 2022-08-02 中铁六局集团有限公司 Checking method for wire points in tunnel hole
CN111927557B (en) * 2020-09-16 2021-01-12 北京龙软科技股份有限公司 Automatic measuring method and network system for measuring robot of mine fully mechanized coal mining face
CN113532399B (en) * 2021-07-09 2022-12-02 上海宝冶集团有限公司 Multi-target observation control measurement method in tunnel
CN114111735B (en) * 2021-11-02 2024-03-29 上海市基础工程集团有限公司 High-precision control measurement method for shield tunnel in scientific experiment
CN114543772B (en) * 2022-04-25 2022-07-08 中交第一航务工程局有限公司 In-tunnel and out-tunnel contact measurement method of immersed tunnel and double-tunnel point-throwing contact measurement method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102953304A (en) * 2012-09-20 2013-03-06 中铁三局集团有限公司 Precision measurement control method of metro track structure construction
CN103306172A (en) * 2013-06-07 2013-09-18 西南交通大学 Method for building track control CP III network in simple point form

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001165656A (en) * 1999-12-06 2001-06-22 Kumagai Gumi Co Ltd Automatic measurement system for tunnel convergence

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102953304A (en) * 2012-09-20 2013-03-06 中铁三局集团有限公司 Precision measurement control method of metro track structure construction
CN103306172A (en) * 2013-06-07 2013-09-18 西南交通大学 Method for building track control CP III network in simple point form

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
长大隧道洞内自由测站边角交会网平面控制测量;邹浜等;《测绘科学》;20141031;第39卷(第10期);第42页第2栏第16-28行、第43页第1栏第1-25行、图1 *

Also Published As

Publication number Publication date
CN105716575A (en) 2016-06-29

Similar Documents

Publication Publication Date Title
CN105716575B (en) A kind of Tunnel Engineering hole inner plane controls net method for fast measuring
CN110793508B (en) Method and device for processing observation data of control points in three-dimensional control network
CN109631839A (en) A method of bridge pier settlement observation in water is carried out using total station
CN101614127B (en) Method for surveying river-crossing leveling during shield breakthrough construction
CN104848845B (en) Underground tunnel virtual double-lead control measurement method
CN110704809B (en) Method for calculating angle closing difference of corner intersection network of railway CP II free survey station
CN102174893A (en) Testing method for laying ballastless tracks in early stage before overall completion of super long tunnel
CN110044326A (en) Mountainous area highway application Trigonometric Leveling
CN106814367B (en) A kind of autonomous station measurement method of ultra wide band positioning node
CN105823420B (en) A kind of pyramid sub-assembly light echo center of energy coordinate precise deriving method
CN108882149A (en) NLOS apart from dependent probability compensates localization method
CN103115610A (en) Leveling method suitable for compound level gauge
CN107228650B (en) The wire type measurement method of dual system bilateral observation composite level
CN106840129B (en) Method for rapidly measuring three-dimensional coordinates of center of subway segment
CN105241434B (en) Mobile cell site&#39;s fast orienting method based on wMPS systems
CN104199802A (en) Engineering measurement method based on method for solving triangle through sine theorem
CN102636155A (en) Two-instrument simultaneous measuring method for increasing leveling precision
CN110130168A (en) A kind of railroad track control net triangulated height data correction processing method
CN109357667A (en) The method of network forming form tunnel plane connection survey
CN108731598A (en) Matching girder segment localization method based on distance controlling
CN111721260B (en) High-precision light beam method settlement measurement method based on i-angle error correction of level gauge
CN109282802B (en) A kind of Free Station method based on the measurement of single-deck position
CN105821728B (en) A kind of plane net measuring systems of CP III
CN113551643B (en) River-crossing leveling method and system
CN111693021B (en) Checking method for wire points in tunnel hole

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 030073 Yingze Street 269, Yingze District, Taiyuan City, Shanxi Province

Applicant after: Shanxi Tiansheng Surveying and Mapping Engineering Co., Ltd.

Address before: 030002 No. 38 Taoyuan North Road, Yingze District, Taiyuan City, Shanxi Province

Applicant before: Shanxi Tianli Litres o Surveying and Mapping Engineering Co., Ltd.

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190919

Address after: 030001 Yingze street, Shanxi, No. 269, No.

Applicant after: China Railway Third Engineering Co., Ltd.

Applicant after: Shanxi Tiansheng Surveying and Mapping Engineering Co., Ltd.

Address before: 030073 Yingze Street 269, Yingze District, Taiyuan City, Shanxi Province

Applicant before: Shanxi Tiansheng Surveying and Mapping Engineering Co., Ltd.

GR01 Patent grant
GR01 Patent grant