CN105696471A - 一种钢箱梁顶推组件及施工方法 - Google Patents

一种钢箱梁顶推组件及施工方法 Download PDF

Info

Publication number
CN105696471A
CN105696471A CN201610048956.8A CN201610048956A CN105696471A CN 105696471 A CN105696471 A CN 105696471A CN 201610048956 A CN201610048956 A CN 201610048956A CN 105696471 A CN105696471 A CN 105696471A
Authority
CN
China
Prior art keywords
girder
steel box
pushing
sliding beam
spelling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610048956.8A
Other languages
English (en)
Other versions
CN105696471B (zh
Inventor
张才伦
黄修生
胡晓金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YINGDU BRIDGE STEEL STRUCTURE ENGINEERING Co Ltd
Original Assignee
YINGDU BRIDGE STEEL STRUCTURE ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YINGDU BRIDGE STEEL STRUCTURE ENGINEERING Co Ltd filed Critical YINGDU BRIDGE STEEL STRUCTURE ENGINEERING Co Ltd
Priority to CN201610048956.8A priority Critical patent/CN105696471B/zh
Publication of CN105696471A publication Critical patent/CN105696471A/zh
Application granted granted Critical
Publication of CN105696471B publication Critical patent/CN105696471B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal

Abstract

本发明属于桥梁施工领域,具体涉及一种钢箱梁顶推组件及施工方法,包括并排分布的若干顶推架和两组拼架,所述顶推架上安放有滑梁,滑梁上分布有若干短柱,短柱抵接钢箱梁,滑梁的两端设置有前后导梁;所述滑梁与若干顶推架接触面为水平面。本发明使用设备简单,有效的减少抄垫工作量的同时能保证钢箱梁质量,并简化了施工流程,缩短施工工期。

Description

一种钢箱梁顶推组件及施工方法
技术领域
本发明属于桥梁施工领域,具体涉及一种钢箱梁顶推组件及施工方法。
背景技术
步履式多点顶推是钢箱梁施工常用的方法之一,在连续钢箱梁采用步履式多点顶推时,一般需要带线形顶推,顶推过程中每个支点的高程不断发生着变化,支点高度要不断的调整,所以抄垫工作量非常大,且顶推过程中对钢箱梁结构的变形无法进行有效控制。有鉴于此,本申请人提供一种钢箱梁顶推组件及施工方法,本案由此产生。
发明内容
本发明的目的在于提供一种钢箱梁顶推组件及施工方法,使钢箱梁的线形质量得到有效控制。使用设备简单,有效的减少抄垫工作量的同时能保证钢箱梁质量,并简化了施工流程,缩短施工工期。
为实现上述目的,本发明具体提供的技术方案为:一种钢箱梁顶推组件,包括并排分布的若干顶推架和两组拼架,所述顶推架上安放有滑梁,滑梁上分布有若干短柱,短柱抵接钢箱梁,滑梁的两端设置有前后导梁;所述滑梁与若干顶推架接触面为水平面。
进一步,所述顶推架包括基础,位于基础上的底座和位于底座上的顶推支点。
一种钢箱梁的施工方法,包括如下步骤:1)、搭设排分布的若干顶推架、两组组拼架;2)、在组拼架上拼第一节段钢箱梁;3)在钢箱梁底部的顶推架上设置滑梁和短柱,并与钢箱梁固定,在钢箱梁两端设置前后导梁;4)钢箱梁向前进行第一轮顶推;5)后导梁拆除,在组拼架上拼第二节段钢箱梁;6)在钢箱梁底部的顶推架上设置滑梁和短柱,并与钢箱梁固定,安装后导梁;8)依次进行其他节段钢箱梁的组拼和顶推作业。
本发明的有益效果:解决了钢箱梁顶推过程中抄垫过多和线形难以控制这一难题,使用设备简单,有效的节约成本的同时能保证钢箱梁线形质量,并简化了施工流程,缩短施工工期,产生了良好的经济效益。
附图说明
图1为本发明结构示意图;
图2-4为本发明施工方法步骤图。
具体实施方式
如图1所示,本发明揭示的是一种钢箱梁顶推组件,包括并排分布的若干顶推架1和两组拼架2,所述顶推架上安放有滑梁3,滑梁3上分布有若干短柱4,短柱4抵接钢箱梁6,滑梁3的两端设置有前后导梁5;所述滑梁3与若干顶推架1接触面为水平面;所述顶推架1包括基础11,位于基础11上的底座12和位于底座12上的顶推支点13。
结合图2-4所示,一种钢箱梁的施工方法,包括如下步骤:1)、搭设排分布的若干顶推架、两组组拼架;2)、在组拼架上拼第一节段钢箱梁;3)在钢箱梁底部的顶推架上设置滑梁和短柱,并与钢箱梁固定,在钢箱梁两端设置前后导梁;4)钢箱梁向前进行第一轮顶推;5)后导梁拆除,在组拼架上拼第二节段钢箱梁;6)在钢箱梁底部的顶推架上设置滑梁和短柱,并与钢箱梁固定,安装后导梁;8)依次进行其他节段钢箱梁的组拼和顶推作业。
滑梁与短柱之间焊接固定,短柱与钢箱梁之间点焊固定。施工过程中,由于滑梁底板水平,所以只需要控制顶升和推拉的千斤顶保证同步,钢箱梁即可顺利向前顶推前进。
通过滑梁的设置,使得钢箱梁顶推线形变为一条水平直线,每个支点的高度h值相同,顶推过程中每个支点油缸的伸缩量相同,大大的减少了现场抄垫的工作量。且通过短柱的布置,使钢箱梁的线形完全可以按照设计线形来顶推平移,钢箱梁的质量得到了有效的保证。

Claims (3)

1.一种钢箱梁顶推组件,其特征在于:包括并排分布的若干顶推架和两组拼架,所述顶推架上安放有滑梁,滑梁上分布有若干短柱,短柱抵接钢箱梁,滑梁的两端设置有前后导梁;所述滑梁与若干顶推架接触面为水平面。
2.根据权利要求1所述的一种钢箱梁顶推组件,其特征在于:所述顶推架包括基础,位于基础上的底座和位于底座上的顶推支点。
3.一种钢箱梁的施工方法,其特征在于,包括如下步骤:1)、搭设排分布的若干顶推架、两组组拼架;2)、在组拼架上拼第一节段钢箱梁;3)在钢箱梁底部的顶推架上设置滑梁和短柱,并与钢箱梁固定,在钢箱梁两端设置前后导梁;4)钢箱梁向前进行第一轮顶推;5)后导梁拆除,在组拼架上拼第二节段钢箱梁;6)在钢箱梁底部的顶推架上设置滑梁和短柱,并与钢箱梁固定,安装后导梁;8)依次进行其他节段钢箱梁的组拼和顶推作业。
CN201610048956.8A 2016-01-26 2016-01-26 一种钢箱梁顶推组件及施工方法 Expired - Fee Related CN105696471B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610048956.8A CN105696471B (zh) 2016-01-26 2016-01-26 一种钢箱梁顶推组件及施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610048956.8A CN105696471B (zh) 2016-01-26 2016-01-26 一种钢箱梁顶推组件及施工方法

Publications (2)

Publication Number Publication Date
CN105696471A true CN105696471A (zh) 2016-06-22
CN105696471B CN105696471B (zh) 2018-03-13

Family

ID=56228445

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610048956.8A Expired - Fee Related CN105696471B (zh) 2016-01-26 2016-01-26 一种钢箱梁顶推组件及施工方法

Country Status (1)

Country Link
CN (1) CN105696471B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442252A (zh) * 2018-03-08 2018-08-24 中交武汉港湾工程设计研究院有限公司 一种长距离曲线段主梁顶推方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006348647A (ja) * 2005-06-17 2006-12-28 Oriental Construction Co Ltd 橋桁の押出し工法
CN101250855A (zh) * 2008-03-28 2008-08-27 山东省路桥集团有限公司 多点整体顶推钢箱梁施工工法
CN102587291A (zh) * 2012-03-27 2012-07-18 中交四航局第一工程有限公司 一种钢箱梁步履式多点顶推施工方法及施工系统
CN102888813A (zh) * 2012-08-20 2013-01-23 中铁二十三局集团有限公司 一种桁架梁的拖拉架设方法
CN103266573A (zh) * 2013-06-17 2013-08-28 中铁山桥集团有限公司 自锚式悬索桥钢箱梁三滑道同步顶推施工方法
CN203498760U (zh) * 2013-09-16 2014-03-26 中铁十七局集团第二工程有限公司 大跨径箱梁顶推用接引装置
CN103924528A (zh) * 2014-04-14 2014-07-16 上海市机械施工集团有限公司 大跨度桥箱梁结构整体长距离顶推滑移施工方法
CN205474868U (zh) * 2016-01-26 2016-08-17 盈都桥梁钢构工程有限公司 一种钢箱梁顶推组件

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006348647A (ja) * 2005-06-17 2006-12-28 Oriental Construction Co Ltd 橋桁の押出し工法
CN101250855A (zh) * 2008-03-28 2008-08-27 山东省路桥集团有限公司 多点整体顶推钢箱梁施工工法
CN102587291A (zh) * 2012-03-27 2012-07-18 中交四航局第一工程有限公司 一种钢箱梁步履式多点顶推施工方法及施工系统
CN102888813A (zh) * 2012-08-20 2013-01-23 中铁二十三局集团有限公司 一种桁架梁的拖拉架设方法
CN103266573A (zh) * 2013-06-17 2013-08-28 中铁山桥集团有限公司 自锚式悬索桥钢箱梁三滑道同步顶推施工方法
CN203498760U (zh) * 2013-09-16 2014-03-26 中铁十七局集团第二工程有限公司 大跨径箱梁顶推用接引装置
CN103924528A (zh) * 2014-04-14 2014-07-16 上海市机械施工集团有限公司 大跨度桥箱梁结构整体长距离顶推滑移施工方法
CN205474868U (zh) * 2016-01-26 2016-08-17 盈都桥梁钢构工程有限公司 一种钢箱梁顶推组件

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
杨庆琪: "跨越多层立交大跨径、款截面钢箱梁整体式顶推施工技术", 《世界桥梁》 *
荣杰: "西安富裕路沣河桥钢箱梁顶推安装施工技术", 《城市建设理论研究(电子版)》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108442252A (zh) * 2018-03-08 2018-08-24 中交武汉港湾工程设计研究院有限公司 一种长距离曲线段主梁顶推方法
CN108442252B (zh) * 2018-03-08 2019-11-12 中交武汉港湾工程设计研究院有限公司 一种长距离曲线段主梁顶推方法

Also Published As

Publication number Publication date
CN105696471B (zh) 2018-03-13

Similar Documents

Publication Publication Date Title
CN105350459A (zh) 一种大型钢梁滑移装置及其施工方法
CN105696471A (zh) 一种钢箱梁顶推组件及施工方法
CN207788119U (zh) 一种钢箱梁拼装定位装置
CN104942506A (zh) 低地板转向架外侧梁组焊工装及其组焊方法
CN204389300U (zh) 一种带有可滑动连接装置的压力试验机
CN205474868U (zh) 一种钢箱梁顶推组件
CN104612064B (zh) 桥梁墩柱纠偏装置
CN205099249U (zh) 一种用于装配起重机活动支腿的装置
CN103712811B (zh) 组合梁预应力式液压支架试验台
CN103968212A (zh) 一种机械设备安装架
CN208917714U (zh) 一种用于装配式t梁桥支座更换的顶升反力装置
CN104668873A (zh) 钢筋笼加工模具
CN203171165U (zh) 钢箱梁焊接结构
CN204156273U (zh) 电缆压接装置
CN204818679U (zh) 一种狭小空间自动对中机构
CN204747870U (zh) 低地板转向架外侧梁组焊工装
CN204817778U (zh) 铝蜂窝芯热压机精密导向系统
CN203541898U (zh) 埋弧自动焊机用厚t型材焊接工装
CN203495856U (zh) 用于液压支架底座结构件整体组装的划线及拼装胎具和液压支架
CN102328184B (zh) 一种管子装卸起重机的超长导轨的制作方法
CN103104101B (zh) 运用递推压顶法的建筑物纠偏方法
CN104859813A (zh) 可调节支撑盒
KR20160006364A (ko) 대형 구조물 이송장치
CN205032530U (zh) H型钢导轨拉伸机
CN105150303A (zh) 一种可对活动底梁限位的热压机

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180313

CF01 Termination of patent right due to non-payment of annual fee