CN105525726A - Aerated brick wall plastering construction method - Google Patents
Aerated brick wall plastering construction method Download PDFInfo
- Publication number
- CN105525726A CN105525726A CN201510272919.0A CN201510272919A CN105525726A CN 105525726 A CN105525726 A CN 105525726A CN 201510272919 A CN201510272919 A CN 201510272919A CN 105525726 A CN105525726 A CN 105525726A
- Authority
- CN
- China
- Prior art keywords
- wall
- metope
- plastering
- construction method
- aerated brick
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Curing Cements, Concrete, And Artificial Stone (AREA)
Abstract
The invention discloses an aerated brick wall plastering construction method. The method comprises the following steps that firstly, a wall is cleaned, crack filling is performed, and then, after the wall is showered and moistened by watering, slurry throwing and galling are performed on the wall; next, a steel wire mesh is hung at a junction part between an aerated brick and a concrete wall; then, fine cement mortar is uniformly sprayed and coated on the wall, and primary scraping and leveling is performed; before the primary solidification of the mortar of the first plastering, gridding cloth is fully hung on the whole wall; after the first plastering mortar is finally solidified, the wall is subjected to second plastering guniting; meanwhile, the wall is subjected to cleaning and polishing treatment; and finally, the wall maintenance is performed. The construction method has the advantages that the aerated brick wall is subjected to plastering construction, so that the perpendicularity and the flatness of the wall can be guaranteed; the gridding cloth is arranged between a plastering surface layer and a bottom layer, so that the tensile strength and the deformation resistance of the wall are greatly improved; the aerated brick wall can be effectively prevented from generating plastering cracks; and the construction quality of the plastering wall is improved.
Description
Technical field
The present invention relates to a kind of aerated bricks wall plastering construction method, belong to technical field of building construction.
Background technology
Aerated bricks is a kind of novel wall material, and the raw material of aerated bricks are mainly cement, lime, sand, flyash etc., belongs to cement concrete product, have water/binder ratio large, cementitious matter is many, easy imbibition, dehydration shrinkage, the features such as intensity is low, water absorption rate is high, shrinkage strain is large.Aerated bricks because of its have energy-conservation, save land, pollute the plurality of advantages such as few, by China's building energy conservation, environmental protection and wall reform are praised highly, and be widely used on civil high-rise buildings with on industrial premises.But due to aerated bricks, to receive water-based strong, and when plastering easy " drinking water ", to plastering, metope easily causes the phenomenon such as hollowing, cracking, has a strong impact on metope quality, to user in follow-up finishing, perception with cause harmful effect psychologically.
Summary of the invention
The object of the invention is to, provide that a kind of operation is simple, easy construction, and can effectively prevent aerated bricks metope from producing the aerated bricks wall plastering construction method of cracks in plaster, to overcome prior art deficiency.
Technical scheme of the present invention: a kind of aerated bricks wall plastering construction method, comprises following construction sequence:
(1) base treatment: first metope loose material, grieshoch and dirt are cleaned out, and adopt dry cement mortar to cram pit on metope, crack, then metope is watered drench profit after get rid of slurry and plucking at metope;
(2) gauze wire cloth is hung: the intersection between aerating brick wall and concrete wall hangs gauze wire cloth;
(3) first is plastered: adopt cement fine sand slurry even application on metope, then utilizes guiding ruler to coordinate trowel metope to be carried out preliminary receipts and scrapes levelling;
(4) second is plastered: grid cloth, also before non-initial set, is overworked whole metope by the mortar of plastering at first, carries out second time and to plaster whitewashing, carry out letter out process simultaneously to metope after the final set of first motar to metope;
(5) maintenance: adopt sprayer to spray water to metope, keeps metope moistening, until the final set of second motar.
In preceding method, when carrying out the base treatment described in step (1), the white glue with vinyl aqueous solution or the formaldehyde polyvinyl acetal aqueous solution is adopted to drench profit metope, for improving the adhesive capacity of motar and aerated bricks metope.
Owing to adopting technique scheme, the invention has the advantages that: construction method of the present invention can not only ensure verticality and the planeness of metope, and grid cloth is set between plaster skin coat and bottom, substantially increase tensile strength and the non-deformability of metope, effectively prevent aerated bricks metope from producing cracks in plaster, improve the construction quality of metope of plastering.
Detailed description of the invention
In order to make the object of the invention, technical scheme and advantage clearly, below in conjunction with embodiment, the present invention is described in further detail.
Embodiment
A kind of aerated bricks wall plastering construction method of the present invention, comprises following construction sequence:
(1) base treatment: first metope loose material, grieshoch and dirt are cleaned out, and adopt dry cement mortar to cram pit on metope, crack, then get rid of slurry and plucking at metope after adopting the white glue with vinyl aqueous solution to be watered by metope to drench profit, be convenient to follow-up
(2) hang gauze wire cloth: the intersection between aerating brick wall and concrete wall hangs gauze wire cloth, and the width of gauze wire cloth is 200 ~ 300mm, gauze wire cloth is hung on the boundary line place between aerating brick wall and concrete wall by employing steel nail symmetrically;
(3) first is plastered: adopt cement fine sand slurry even application on metope, coating thickness is 3 ~ 5mm, then utilizes guiding ruler to coordinate trowel metope to be carried out preliminary receipts and scrapes levelling;
(4) second is plastered: grid cloth, also before non-initial set, is overworked whole metope by the mortar of plastering at first, and after the final set of first motar, carry out second time to metope to plaster whitewashing, coating thickness is 8 ~ 10mm, carries out letter out process to metope simultaneously;
(5) maintenance: adopt sprayer to carry out wet curing to metope, keeps metope moistening, until the final set of second motar, completes wall plastering construction.
By construction method of the present invention, plastering construction is carried out to aerated bricks metope, verticality and the planeness of metope can not only be ensured, and grid cloth is set between plaster skin coat and bottom, substantially increase tensile strength and the non-deformability of metope, effectively prevent aerated bricks metope from producing cracks in plaster, improve the construction quality of metope of plastering.
Claims (2)
1. an aerated bricks wall plastering construction method, is characterized in that comprising following construction sequence:
(1) base treatment: first metope loose material, grieshoch and dirt are cleaned out, and adopt dry cement mortar to cram pit on metope, crack, then metope is watered drench profit after get rid of slurry and plucking at metope;
(2) gauze wire cloth is hung: the intersection between aerating brick wall and concrete wall hangs gauze wire cloth;
(3) first is plastered: adopt cement fine sand slurry even application on metope, then utilizes guiding ruler to coordinate trowel metope to be carried out preliminary receipts and scrapes levelling;
(4) second is plastered: grid cloth, also before non-initial set, is overworked whole metope by the mortar of plastering at first, carries out second time and to plaster whitewashing, carry out letter out process simultaneously to metope after the final set of first motar to metope;
(5) maintenance: adopt sprayer to spray water to metope, keeps metope moistening, until the final set of second motar.
2. aerated bricks wall plastering construction method according to claim 1, is characterized in that: when carrying out the base treatment described in step (1), adopts the white glue with vinyl aqueous solution or the formaldehyde polyvinyl acetal aqueous solution to drench profit metope.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510272919.0A CN105525726A (en) | 2015-05-26 | 2015-05-26 | Aerated brick wall plastering construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510272919.0A CN105525726A (en) | 2015-05-26 | 2015-05-26 | Aerated brick wall plastering construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105525726A true CN105525726A (en) | 2016-04-27 |
Family
ID=55768221
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510272919.0A Pending CN105525726A (en) | 2015-05-26 | 2015-05-26 | Aerated brick wall plastering construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105525726A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107419858A (en) * | 2017-07-04 | 2017-12-01 | 合肥安力电力工程有限公司 | A kind of inner wall render smears construction method |
CN107489250A (en) * | 2017-09-02 | 2017-12-19 | 广东省第二建筑工程有限公司 | Wall basic unit plastering construction engineering method |
CN108468413A (en) * | 2018-04-09 | 2018-08-31 | 中建八局第三建设有限公司 | A kind of air-entrained concrete building block exempts from anti-hollowing construction method of plastering |
CN110805218A (en) * | 2019-09-25 | 2020-02-18 | 巨匠建设集团股份有限公司 | Thin plastering construction method for junction of shear wall and brick wall |
CN112942709A (en) * | 2021-03-15 | 2021-06-11 | 福建筑兆建设有限公司 | Construction method for preventing hollowing and cracking of wall plastering |
CN113216541A (en) * | 2021-05-10 | 2021-08-06 | 长沙三树新材料科技有限公司 | Mechanical spraying plastering construction method |
CN113530124A (en) * | 2021-07-27 | 2021-10-22 | 中建一局华江建设有限公司 | Construction method for preventing water-blocking wet plaster inside and outside volcanic rocks on wall surface |
CN115898022A (en) * | 2022-11-22 | 2023-04-04 | 中筑信云发展有限公司 | Machine spraying construction method suitable for preparing dry-mixed mortar product from tailing sand |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6081054A (en) * | 1983-10-06 | 1985-05-09 | 日本プラスター株式会社 | Wet premixture for plaster material |
JPH08158581A (en) * | 1994-11-30 | 1996-06-18 | Hiromitsu Shintani | Method of spraying construction to wall surface |
CN102400525A (en) * | 2010-09-15 | 2012-04-04 | 五冶集团上海有限公司 | Thin-layer plastering method for autoclaved aerated concrete block wall bodies |
CN103291024A (en) * | 2013-05-28 | 2013-09-11 | 柴焕生 | Novel cement-based plastering mortar construction method |
CN103790386A (en) * | 2014-01-17 | 2014-05-14 | 洛阳广鑫建设集团有限公司 | Method for controlling cracks in process of plastering aerated concrete block wall |
CN103821296A (en) * | 2014-02-28 | 2014-05-28 | 浙江海天建设集团有限公司 | Wall plastering technique for aerated concrete block filler wall |
-
2015
- 2015-05-26 CN CN201510272919.0A patent/CN105525726A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6081054A (en) * | 1983-10-06 | 1985-05-09 | 日本プラスター株式会社 | Wet premixture for plaster material |
JPH08158581A (en) * | 1994-11-30 | 1996-06-18 | Hiromitsu Shintani | Method of spraying construction to wall surface |
CN102400525A (en) * | 2010-09-15 | 2012-04-04 | 五冶集团上海有限公司 | Thin-layer plastering method for autoclaved aerated concrete block wall bodies |
CN103291024A (en) * | 2013-05-28 | 2013-09-11 | 柴焕生 | Novel cement-based plastering mortar construction method |
CN103790386A (en) * | 2014-01-17 | 2014-05-14 | 洛阳广鑫建设集团有限公司 | Method for controlling cracks in process of plastering aerated concrete block wall |
CN103821296A (en) * | 2014-02-28 | 2014-05-28 | 浙江海天建设集团有限公司 | Wall plastering technique for aerated concrete block filler wall |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107419858A (en) * | 2017-07-04 | 2017-12-01 | 合肥安力电力工程有限公司 | A kind of inner wall render smears construction method |
CN107489250A (en) * | 2017-09-02 | 2017-12-19 | 广东省第二建筑工程有限公司 | Wall basic unit plastering construction engineering method |
CN108468413A (en) * | 2018-04-09 | 2018-08-31 | 中建八局第三建设有限公司 | A kind of air-entrained concrete building block exempts from anti-hollowing construction method of plastering |
CN110805218A (en) * | 2019-09-25 | 2020-02-18 | 巨匠建设集团股份有限公司 | Thin plastering construction method for junction of shear wall and brick wall |
CN112942709A (en) * | 2021-03-15 | 2021-06-11 | 福建筑兆建设有限公司 | Construction method for preventing hollowing and cracking of wall plastering |
CN113216541A (en) * | 2021-05-10 | 2021-08-06 | 长沙三树新材料科技有限公司 | Mechanical spraying plastering construction method |
CN113530124A (en) * | 2021-07-27 | 2021-10-22 | 中建一局华江建设有限公司 | Construction method for preventing water-blocking wet plaster inside and outside volcanic rocks on wall surface |
CN113530124B (en) * | 2021-07-27 | 2023-02-21 | 中建一局华江建设有限公司 | Construction method for preventing water-blocking wet plaster inside and outside volcanic rocks on wall surface |
CN115898022A (en) * | 2022-11-22 | 2023-04-04 | 中筑信云发展有限公司 | Machine spraying construction method suitable for preparing dry-mixed mortar product from tailing sand |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105525726A (en) | Aerated brick wall plastering construction method | |
CN102477797B (en) | A kind of construction method preventing infilled wall crack | |
CN103046709B (en) | Building construction method of inner wall surface | |
CN101886460B (en) | Press polishing method of plastered mesh cloth of inner wall | |
CN204826464U (en) | Waterproof construction of parapet | |
CN104088416A (en) | Gypsum heat preservation painting mortar construction process | |
CN102400525B (en) | Thin-layer plastering method for autoclaved aerated concrete block wall bodies | |
CN102505762A (en) | Sand aerated concrete heat-insulation block outer wall outer heat-insulation system and construction method thereof | |
CN101713250A (en) | Process for pasting construction of floor tiles | |
CN106284998A (en) | Plastering on inner walls completely spreads fiberglass gridding cloth construction method | |
CN104120860A (en) | Construction method for cement mortar ground leveling | |
CN103291024A (en) | Novel cement-based plastering mortar construction method | |
CN103774696A (en) | Construction process of cement-based permeable-crystallization type waterproof material | |
CN104612343A (en) | Method for constructing extruded polystyrene board molding of building outer wall | |
CN203834826U (en) | Novel staircase water drip tank | |
CN110005174A (en) | Improve the construction method of Machine-blasting mortar plastering quality | |
CN101666144A (en) | Plastering and trough-pulling construction method of face brick wall surface and pull trough plate | |
CN103790386A (en) | Method for controlling cracks in process of plastering aerated concrete block wall | |
CN204040341U (en) | A kind of exterior wall old ceramic tile face putty refurbishment system | |
CN105507524A (en) | Nature-imitated magnesium oxysulfate decorative plate and manufacturing method thereof | |
CN110805218A (en) | Thin plastering construction method for junction of shear wall and brick wall | |
CN205907857U (en) | Double-sided hard partition wall structure | |
CN208473196U (en) | A kind of brushing gypsum metope structure | |
CN204492036U (en) | The overcoat of roofing poling | |
CN101260721B (en) | Composite wall material and method of manufacture |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160427 |
|