CN205907857U - Double-sided hard partition wall structure - Google Patents

Double-sided hard partition wall structure Download PDF

Info

Publication number
CN205907857U
CN205907857U CN201620808470.5U CN201620808470U CN205907857U CN 205907857 U CN205907857 U CN 205907857U CN 201620808470 U CN201620808470 U CN 201620808470U CN 205907857 U CN205907857 U CN 205907857U
Authority
CN
China
Prior art keywords
cement
ceramic tile
wall structure
steel wire
partition wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620808470.5U
Other languages
Chinese (zh)
Inventor
庄斌
单宝龙
李伟
王康宁
孔德重
王建凯
王永强
徐龙宝
何洪强
郭晓娟
孙浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
China Construction First Bureau Group Decoration Engineering Co Ltd
Original Assignee
China Construction First Group Corp Ltd
China Construction First Bureau Group Decoration Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd, China Construction First Bureau Group Decoration Engineering Co Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201620808470.5U priority Critical patent/CN205907857U/en
Application granted granted Critical
Publication of CN205907857U publication Critical patent/CN205907857U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

A double-sided hard-mounted partition wall structure comprises a keel, a cement fiberboard, a steel wire mesh, a cement mortar layer, a pure cement layer, a cement glue layer and a ceramic tile from inside to outside in sequence; the steel wire mesh and the cement fiberboard are fixedly connected with the keel through the shooting nail. During construction, a cement glue layer is laid on the back of the ceramic tile, a pure cement layer is laid after the cement glue layer is finished, and finally the ceramic tile is attached to a cement fiberboard with a steel wire mesh and a cement mortar layer. The utility model provides an unable direct problem of carrying out the ceramic tile and pasting of ordinary light partition wall, be the technological improvement who goes on to the light partition wall, make the light partition wall can also carry out the ceramic tile veneer and decorate when possessing advantages such as light, easy construction, practice thrift the time limit for a project simultaneously, and paste the quality and promote to some extent than ordinary ceramic tile, be applicable to the area little, the many rooms of molding and the engineering project of the stage of robbing workers.

Description

A kind of two-sided hard dress curtain wall structure
Technical field
This utility model be related to light partition wall technical field and in particular to a kind of room being applied to more than the little moulding of area with And rob the two-sided hard dress curtain wall structure of the engineering project in work stage.
Background technology
With the fast development of China's industry, decoration high-tech trend becomes clear day by day, and it is mainly reflected in new technique, green wood Material, the application of new theory.With the development of decoration industry, high quality, casual labourer are an industrial trend phases, therefore will constantly dash forward Broken technical bottleneck, constantly promotes industry development by measures such as new material, new technique, modified techniques.At present, conventional lightweight Partition wall cannot directly carry out tile paste due to reasons such as its low intensity, poor adhesive force, has a strong impact on the suitability of light partition wall Promote, this project management department passes through to organize scientific and technical innovation, after repeatedly inquiring into, carry out multiple model construction, proposes and sums up The new technique of tile paste is carried out on Os Draconis partition wall, conventional art is improved, and large area is applied in putting into practice project Work, reaches reduction of erection time, the effect of lifting construction quality.
Utility model content
The purpose of this utility model is to provide a kind of two-sided hard dress curtain wall structure, solves on current conventional lightweight partition wall no Method directly carries out the technical barrier of tile paste, light partition wall function in prior art is carried out perfect, so that light partition wall is being gathered around Tile decorative surface decoration, reduction of erection time simultaneously can also be carried out while having the advantages such as light easy construction, lift tile paste quality.
For realizing above-mentioned technical purpose, this utility model adopts the following technical scheme that
A kind of two-sided hard dress curtain wall structure it is characterised in that: its from-inner-to-outer is followed successively by Os Draconis, cement fibrolite plate, steel wire Net, cement sand bed, pure water mud layer, cement glue-line and ceramic tile;Described steel wire and cement fibrolite plate pass through nailing with Os Draconis admittedly Fixed connection.
As optimal technical scheme of the present utility model, the sizing grid of described steel wire is 1 cm × 1cm, steel wire diameter Not less than 1mm.
It is further preferred that described ceramic tile is less than 0.5% vitrified tile for moisture content.
Preferably, the thickness of described pure water mud layer is 1cm, and the ratio of mud meets cement painting and stream pendant does not occur on the wall.
Preferably, the weight of described cement sand bed material therefor cement, sand and water is 1:3:0.6.
Described Os Draconis are lightgage steel joist.
It is furthermore preferred that the gap between described ceramic tile is 2mm, in secondary gap, use white cement wiping seam.
Compared with prior art, of the present utility model it is a technical advantage that:
This utility model solves the problems, such as that conventional lightweight partition wall directly cannot carry out tile paste, is for light partition wall The technological improvement carrying out, makes light partition wall can also carry out tile decorative surface decoration while having the advantages such as light, easy construction, Save the duration simultaneously, and sticking Quality has been lifted than common ceramic tile, can reduce the operation of wet trade, will build work by laying bricks or stones during construction Sequence is changed to Os Draconis operation, and that is, wet trade is changed to dry operation, and integral thickness reduces, and can reach more preferable decorative effect, construction letter Single operating time is short, the room for area is little, more than moulding and rob the work stage, and this product is especially suitable.
Brief description
By the detailed description made in conjunction with the following drawings, of the present utility model above-mentioned and/or other aspects and advantage will Become more apparent upon and be easier to understand, these accompanying drawings simply schematically, are not intended to limit this utility model, wherein:
Fig. 1 is the overall structure diagram of the two-sided hard dress curtain wall structure that this utility model is related to.
Reference: 1- Os Draconis, 2- cement fibrolite plate, 3- steel wire, 4- nailing, 5- cement sand bed, 6- pure water mud layer, 7- cement gel, 8- ceramic tile.
Specific embodiment
Hereinafter, the reality of fireproof thermal insulation decoration integrated board of the present utility model and its manufacture method is described with reference to the accompanying drawings Apply example.
The embodiment that here is recorded is specific specific embodiment of the present utility model, of the present utility model for illustrating Design, is all explanatory and exemplary, should not be construed as the limit to this utility model embodiment and this utility model scope System.The enforcement exception recorded except here, those skilled in the art can also be public based on the application claims and description institute The content opened includes doing using the embodiment that here is recorded using obviously other technical schemes, these technical schemes Go out the technical scheme of any obvious substitutions and modifications.
The accompanying drawing of this specification is schematic diagram, aids in illustrating design of the present utility model, it is schematically indicated each several part Shape and its mutual relation.Note that the structure of each part for the ease of clearly showing this utility model embodiment, respectively Do not draw according to identical ratio between accompanying drawing.Identical reference marker is used for representing identical part.
As shown in figure 1, be related to a kind of two-sided hard dress curtain wall structure it is characterised in that: its from-inner-to-outer be followed successively by Os Draconis 1, Cement fibrolite plate 2, steel wire 3, cement sand bed 5, pure water mud layer 6, cement glue-line 7 and ceramic tile 8;Described steel wire 3 and cement Fibre board 2 is fixedly connected with Os Draconis 1 by nailing 4.Described Os Draconis 1 can be lightgage steel joist or other Os Draconis.Described The sizing grid of steel wire 3 is 1 cm × 1cm, and steel wire diameter is not less than 1mm.Described ceramic tile 8 is less than 0.5% glass for moisture content Change brick.The thickness of described pure water mud layer 6 is 1cm, and the ratio of mud meets cement painting and stream pendant does not occur on the wall.Described cement sand bed The weight of 5 material therefor cement, sand and water is 1:3:0.6.Gap between described ceramic tile 8 is 2mm, uses in secondary gap White cement wiping seam.
The construction technology process of above-mentioned two-sided hard dress curtain wall structure includes: base treatment → metal lathing → get rid of hair → hang is vertical Directly, set side, look for rule, patch ash cake → smear cement sand bed → cellular snap line → row's brick of bottom and smear cement gel at the brick back side → sticking brick → tile pointing and wiping seam → cleaning, are specifically described as follows:
1st, base treatment
Cement fibrolite plate 2 metope is cleared up, cleans the dust dirt etc. on surface it is ensured that its clean smooth no greasy dirt.
2nd, metal lathing
Completely spread steel wire 3 in Cement fibre plate surface, fixing with nailing 4, paving steel wire be favorably improved cement mortar with Tight connection between two kinds of different mediums of cement fibrolite plate, prevents wall brick from integrally coming off from metope.
3rd, get rid of hair
Plaster basic unit should be carried out before bottoming getting rid of hair and process, starch spray with 1:1 cement fine sand or be thrown on wall, it gets rid of a little wants Uniformly, burr length is not preferably greater than 8mm, uses watering can wet curing after final set, until cement mortar burr has higher intensity (to use Handss are broken motionless) till.
4th, hang vertical, set side, look for rule
By the datum line of bullet on wall, respectively doorway angle, metope etc. hang vertically, set side, patch ash cake, ash cake thickness 1cm.
5th, smear cement sand bed
Sweep net surface and float ash, start to smear cement sand bed 5, the proportioning of cement mortar is 1:3, finally uses wooden float brooming, Surface is made to have certain roughness, with ceiling plate inspection it is desirable to vertically smooth, inner corner trim is upright, and furred ceiling is straight with the metope angle of cut, flat Whole, clean.
6th, lattice, snap the line
When bottom ash 6 seventy percent is dry, by drawing, vitrified tile specification and live physical condition carry out arranging brick, snap the line.
7th, arrange brick and smear cement gel at the brick back side
Metope carried out anyhow to row's brick according to design drawing or row's brick design, Men Bian, window are in, mirror, external corner side is preferably arranged Full sized brick, simultaneously horizontally-arranged perpendicular row all cannot be less than the non-full sized brick of 1/2 brick.
Before stickup, cement gel 7 is smeared at the back side in every block of ceramic tile in advance, first cleans the vitrified tile back of the body with half-dried tide cloth before brushing The dirts such as edema over the face ash.Then dip cement gel using roller, the proportioning of cement gel is admixed two barrels of glue for one bag of cement, is painted on The vitrified tile back side, the back side will carry out full brush, apply and brush one times, and be placed in ground and dry 6-8 hour and can carry out wall tile.
The form of construction work smearing cement gel at the vitrified tile back side is different from traditional construction mode, will carry out plucking in metope and change For directly carrying out wharf's pavement quality at the ceramic tile back side, while convenient and swift, increased the cohesive force of ceramic tile and basic unit.And because of glass Change brick water absorption rate low, be directly adhered on wall be susceptible to obscission, using this kind of mode, be no longer that the vitrified tile back side is direct Contact basic unit, is originally the stickup that the stickup of two kinds of materials is converted between similar material, substantially increases cohesive force, reduces de- Fall.
8th, sticking brick
With crackle ware brick labeling on schedule, the mixed mortar being used as ash cake is attached on metope, and the surface in order to control tiling is put down Whole degree.Rebasing chi calculates accurately mouth absolute altitude under next skin brick, puts bottom chi on this basis well, level, stable.Under pasting certainly And on carry out, first pasting two row about wall controls bricks, post-tensioning control line paste big face, dried vitrified tile in cement gel 1cm thickness pure water mud layer 6 is smeared at the back side, and cement is that cement plastering does not occur stream pendant to be advisable on the wall with the proportioning of water, strike off, with Smear with patch it is desirable to cement is full, and check flatness with guiding ruler at any time, ensure that gap width is consistent simultaneously.Seam width is maintained at 2mm.
9th, the jointing of ceramic tile and wiping seam
After having pasted ceramic tile 8 through self-inspection no hollowing, vertically smooth meet the requirements after, wiped clean with cotton yarn, to be pasted firmly after Use white cement wiping seam, be finally cleaned, with cloth, the element stitching slurry is wiped even, brick face is cleaned.
Product and work progress are analyzed, and plaster stickup with masonry panel or the stickup of plastering of Os Draconis cement plate is carried out Cost compares.
(1) quality analysiss
After the construction of this utility model product completes 7 days, pull-out test is carried out to ceramic tile.After testing, adhesive strength is equal In more than 0.3mpa, average is 0.7mpa, and compliant requires, and relatively general exterior wall tile adhesive strength will height.To porcelain Brick seam, flatness are detected, all meet the requirements.Because basic unit is Os Draconis, therefore external corner, perpendicularity is easy to control.Using stainless Steel hammer touches ceramic tile, checks and pastes hollowing rate.Spot-check 102 blocks of ceramic tiles altogether, do not find hollowing, it is very good that overall hollowing rate controls. And from the point of view of by daily construction experience, using the masonry wall body of wall always presence sky to a certain extent of traditional approach patch block Drum.
(2) artificial every square meter Cost comparisons
Daily 131 yuan of carpenter, daily 135 yuan of bricklayer, daily 111 yuan of other works.
Then for cement plate light partition wall every square meter cost of labor: 131 × 0.35+135 × 0.425+111 × 0.775= 189.25 it is first;
For masonry wall every square meter cost of labor: 135 × 1.56+111 × 1.56=383.76 unit;
I.e. two kinds of bodies of wall finish every square meter cost of labor masonry wall (Aerated Concrete) more than cement plate from wall to wall tile Wall 383.76-189.25=194.51 unit.
(3) masonry panel and cement plate material every square meter Cost comparisons
In masonry panel with cement plate body of wall all using the form of construction work of linked network patch block, during analysis of material cost, only contrast Masonry panel and the price variance of the every square meter of cement plate light partition wall.
For cement plate light partition wall, seal monolayer cement plates using 75 Os Draconis systems, 5 yuan of every meter of sky ground joist, every meter is erected To 6 yuan of Os Draconis, 2.67 yuan of every meter of punching Os Draconis, 12.5 yuan of the every square meter of cement plate, that is, for ceiling height 3m, wall area 20m2 Body of wall, employ the long vertical keel of 18 3m, 2 with 6.67m vast of heaven ground joist, the long punching Os Draconis of 2 6.67m.
I.e. the unit price of every square meter cement plate light partition wall is:
(6 × 3 × 18+5 × 2 × 6.67+2.67 × 2 × 6.67) ÷ 20+12.5=33.8 unit;
And 8 yuan of every piece of the aerated blocks for 600 × 300 × 200mm, that is, only aerated blocks when every square meter unit price be:
1 ÷ (0.3 × 0.6) × 8=44.4 unit;
Analyzed by above, masonry wall every square meter unit price when not considering the cement mortar built by laying bricks or stones has been higher than that cement plate is light Matter partition wall 44.4-33.8=10.6 unit.
Therefore, we can draw following comparative result: for from quality, progress and cost, this utility model product It is superior to that masonry panel plasters stickup or Os Draconis cement plate is plastered stickup.
Each technical characteristic of above-mentioned disclosure is not limited to disclosed combining with further feature, and those skilled in the art are also The other that can be carried out according to the purpose of utility model between each technical characteristic combines, and is defined by the purpose realizing this utility model.

Claims (7)

1. a kind of two-sided hard dress curtain wall structure it is characterised in that: its from-inner-to-outer be followed successively by Os Draconis (1), cement fibrolite plate (2), Steel wire (3), cement sand bed (5), pure water mud layer (6), cement glue-line (7) and ceramic tile (8);Described steel wire (3) and cement Fibre board (2) is fixedly connected with Os Draconis (1) by nailing (4).
2. the two-sided hard dress curtain wall structure of one kind according to claim 1 it is characterised in that: the grid of described steel wire (3) Size is 1 cm × 1cm, and steel wire diameter is not less than 1mm.
3. the two-sided hard dress curtain wall structure of one kind according to claim 1 it is characterised in that: described ceramic tile (8) is moisture content Vitrified tile less than 0.5%.
4. the two-sided hard dress curtain wall structure of one kind according to claim 1 it is characterised in that: the thickness of described pure water mud layer (6) Spend for 1cm, the ratio of mud meets cement and applies stream pendant does not occur on the wall.
5. the two-sided hard dress curtain wall structure of one kind according to claim 1 it is characterised in that: described cement sand bed (5) institute Weight with material cement, sand and water is 1:3:0.6.
6. the two-sided hard dress curtain wall structure of one kind according to claim 1 it is characterised in that: described Os Draconis (1) are light steel dragon Bone.
7. the one kind according to claim 1-6 any one two-sided hard dress curtain wall structure it is characterised in that: described ceramic tile (8) gap between is 2mm, uses white cement wiping seam in secondary gap.
CN201620808470.5U 2016-07-29 2016-07-29 Double-sided hard partition wall structure Expired - Fee Related CN205907857U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620808470.5U CN205907857U (en) 2016-07-29 2016-07-29 Double-sided hard partition wall structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620808470.5U CN205907857U (en) 2016-07-29 2016-07-29 Double-sided hard partition wall structure

Publications (1)

Publication Number Publication Date
CN205907857U true CN205907857U (en) 2017-01-25

Family

ID=57803941

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620808470.5U Expired - Fee Related CN205907857U (en) 2016-07-29 2016-07-29 Double-sided hard partition wall structure

Country Status (1)

Country Link
CN (1) CN205907857U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107489210A (en) * 2017-09-26 2017-12-19 珠海兴业绿色建筑科技有限公司 A kind of composite wall body material

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107489210A (en) * 2017-09-26 2017-12-19 珠海兴业绿色建筑科技有限公司 A kind of composite wall body material

Similar Documents

Publication Publication Date Title
CN201198640Y (en) External heat insulation decorative machining structure body
CN103643754B (en) The waterproof treatment structure of building wall body interface seam crossing and processing method
CN104018598A (en) Outer wall structure and construction and installation method
CN101886460B (en) Press polishing method of plastered mesh cloth of inner wall
CN102704635B (en) Paint brushing construction method
CN101314978A (en) Construction method for thermal insulation wall of exterior wall
CN104088416A (en) Gypsum heat preservation painting mortar construction process
CN105525726A (en) Aerated brick wall plastering construction method
CN103291024B (en) A kind of construction method of novel cement-based motar
CN205907857U (en) Double-sided hard partition wall structure
CN207194343U (en) The tapestry brick paving structure of autoclave aerated concrete building block exterior wall
CN102383507A (en) Light steel keel and plasterboard vitrified tile decoration wall and method for constructing same
CN203834826U (en) Novel staircase water drip tank
CN104746832A (en) Wet-fastening method for vitrified tiles
CN103572932A (en) Flexible wall pasting wood veneer
CN2934449Y (en) Combined type natural sandstone board wall surface
CN202248387U (en) Lightgage steel joist gypsum plate vetrified tile decorative wall body
CN212405863U (en) Building facade decoration structure
CN211949245U (en) Roof stone flashing structure
CN103711208A (en) Heat reflection heat-insulation energy-saving system for outer wall and manufacturing method thereof
CN205025042U (en) Big unit pottery sheet metal back of body kiss -coating bonds and constructs
CN202990304U (en) Flexible wall pasting decorative panel
CN207647092U (en) A kind of metope tapestry brick mounting structure
CZ26470U1 (en) Building surface with mockery and aid for making building surface with mockery
CN204040341U (en) A kind of exterior wall old ceramic tile face putty refurbishment system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170125

Termination date: 20210729