CN107489250A - Wall basic unit plastering construction engineering method - Google Patents

Wall basic unit plastering construction engineering method Download PDF

Info

Publication number
CN107489250A
CN107489250A CN201710781980.7A CN201710781980A CN107489250A CN 107489250 A CN107489250 A CN 107489250A CN 201710781980 A CN201710781980 A CN 201710781980A CN 107489250 A CN107489250 A CN 107489250A
Authority
CN
China
Prior art keywords
wall
plaster
coat
water
glue
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710781980.7A
Other languages
Chinese (zh)
Inventor
李志敏
马旭
黄楚周
郭纯
曾伟青
吴锋
赵斯阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong No2 Construction Engineering Co
Original Assignee
Guangdong No2 Construction Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong No2 Construction Engineering Co filed Critical Guangdong No2 Construction Engineering Co
Priority to CN201710781980.7A priority Critical patent/CN107489250A/en
Publication of CN107489250A publication Critical patent/CN107489250A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • E04F13/04Bases for plaster

Abstract

A kind of wall basic unit plastering construction engineering method, comprises the steps successively:(1)Surface of wall is cleaned out;(2)To surface of wall spray water, moisten surface of wall;(3)Cement mortar is patted on surface of wall with sizing device is clapped, forms texturing layer, texturing layer is made up of the multiple projections being covered with surface of wall;(4)Floating screed is carried out on texturing layer, then applies and spreads motar, form coat of plaster;(5)Plaster after completing 34 hours, water spray moistening is carried out to coat of plaster;(6)After coat of plaster initial set, the brushing glue on the surface of coat of plaster, by the plastic sheeting cut paving from top to bottom, make covered rearing with plastic film on coat of plaster, carry out coat of plaster maintenance;(7)After completing overlay film maintenance, plastic sheeting is thrown off.Using the wall basic unit plastering construction engineering method of the present invention, coat of plaster can be made to be securely bonded together with wall, and effectively avoid the shrinkage cracking of coat of plaster, and construction cost can be substantially reduced.

Description

Wall basic unit plastering construction engineering method
Technical field
The present invention relates to construction techniques, and in particular to a kind of wall basic unit plastering construction engineering method.
Background technology
In traditional wall basic unit plastering construction engineering method, because the base treatment of metope, texturing quality are bad, so that wall Face(Particularly concrete shear force wall)Excessively smooth, coat of plaster tends to separate with wall, cause coat of plaster not completely with Wall is bonded together;Moreover, coat of plaster often due to conserve not in time or curing time deficiency, cause the contraction of coat of plaster Cracking, air enters wall basic unit from the gap of shrinkage cracking, and then causes the hollowing of metope, or even the phenomenon to come off.Plaster The shrinkage cracking of layer can not only cause the decortication of wall face decorating layer, ftracture, come off, and influence the overall perception effect of wall, moreover, If there is shrinkage cracking, hollowing in the coat of plaster of exterior wall, it will causes the infiltration of metope, influences the use function of building.
The content of the invention
The technical problems to be solved by the invention are to provide a kind of wall basic unit plastering construction engineering method, using this wall base Layer plastering construction engineering method, can be such that coat of plaster is securely bonded together with wall, and effectively avoid the shrinkage cracking of coat of plaster, And construction cost can be substantially reduced.The technical scheme of use is as follows:
A kind of wall basic unit plastering construction engineering method, it is characterised in that comprise the steps successively:
(1)Surface of wall is cleaned out;
(2)To surface of wall spray water, moisten surface of wall;
(3)Surface of wall frosting treatment
Cement mortar is patted on surface of wall with sizing device is clapped, forms texturing layer after cement mortar solidification, texturing layer is by cloth Full multiple raised compositions on surface of wall;
(4)Plaster
Floating screed is carried out on texturing layer, is then applied on texturing layer and spreads motar, form coat of plaster;
(5)Plaster after completing 3-4 hours, water spray moistening is carried out to coat of plaster using water pistol;
(6)Overlay film conserves
After coat of plaster initial set, the brushing glue on the surface of coat of plaster;After brushing glue, by the plastic sheeting cut by up to Lower paving, makes covered rearing with plastic film on coat of plaster, carries out coat of plaster maintenance;
(7)After completing overlay film maintenance, plastic sheeting is thrown off.
Step(1)In, it is often necessary to will be attached to the dust of surface of wall, greasy dirt, oil stain, residual mortar and other Impurity is all removed totally.During concrete operations, the mortar of can the clean with a brush debris for being attached to surface of wall, dust and residual, Detergent treatment greasy dirt, oil stain can be used if necessary.
Step(2)In, after surface of wall is cleaned out, before carrying out surface of wall frosting treatment, propose the previous day spray Watering, moistens surface of wall.
Preferred steps(3)In used cement mortar formed by water, glue emulsion, middle sand and cement, water, glue breast The weight proportion of liquid, middle sand and cement is water:Glue emulsion:Middle sand:Cement=1:1.8-2.2:1.8-2.2:2.4-2.6.More It is preferred that water, glue emulsion, the weight proportion of middle sand and cement are water:Glue emulsion:Middle sand:Cement=1:2:2:2.5.By than Example water intaking, glue emulsion, middle sand and cement, then by water, glue emulsion, middle sand and cement mixing and stir, you can must To cement mortar.Above-mentioned glue emulsion is used for the cohesive force for increasing cement mortar, Zhongshan city's Ahmedabad richness chemical science and technology can be used to have The model ZS-991A of limit company production glue product emulsion.
Preferred steps(3)In used bat sizing device include that net is clapped and handle, net clap the composite steel for including stacking together Silk screen, multiple mesh are evenly equipped with steel wire, and connection is clapped in handle one end with net;When carrying out surface of wall frosting treatment, hand is held Handle, net bat is immersed in cement mortar, cement mortar is entered in the gap inside net bat, then lifted net and clap simultaneously direction Surface of wall is patted, and will be netted the cement mortar inside clapping and is patted on surface of wall(Now net claps the cement bonded sand in internal clearance Starch and come out from each mesh of the steel wire near surface of wall, and be transferred on surface of wall).By the mode of patting, make water Cement mortar is easier to penetrate into surface of wall, so that texturing layer is more firmly bonded on surface of wall, it is difficult for drop-off, it is ensured that hair Change layer and surface of wall strong bonded;Simultaneously because mesh is uniform on steel wire, and the steel wire between mesh has compartmentation, Cement mortar is divided into cement mortar agglomerate simultaneously after being come out close to the layer of steel wire net mesh of surface of wall when therefore patting It is adhered on surface of wall, is advantageous to form equally distributed projection on surface of wall.When patting cement mortar, should try one's best will Cement mortar is uniformly patted on surface of wall, each projection in texturing layer is evenly distributed on surface of wall.
Generally, above-mentioned each steel wire mesh-shaped is consistent, and size is basically identical.In a kind of concrete scheme, above-mentioned steel wire is square Shape mesh sheet(Long about 320mm, wide about 240mm), multiple squared mesh are evenly equipped with the way of multiple lines and multiple rows on steel wire, The length of side of squared mesh is 8-12mm;There is 1-2mm gap between adjacent two layers steel wire.
In preferred scheme, above-mentioned net is clapped to be formed by a steel wire net-belt through folding, and outermost two layers of steel wire passes through iron wire It is strapped.For example, using long 1200mm, wide 320mm steel wire net-belt, after four times fold, the net with five layers of steel wire is formed Clap, every layer of steel wire length is about 320mm, wide about 240mm;It is by iron wire that outermost two layers of steel wire is strapped again, make each The position of layer steel wire is fixed, will not scattered, and obtains the stronger net of structure and claps.
Above-mentioned handle can use pvc pipe, iron pipe or steel pipe to form.
Step(4)In, the purpose of floating screed controls the thickness and flatness of coat of plaster when being convenient follow-up smearing motar. The method of floating screed is:Ash cake is made at a certain distance on surface of wall with cement mortar(That is cement bonded sand lumps);Then along ash Cake vertically and/or horizontally continues to make one or several gray bars with cement mortar(General spacing is not more than 1.5m).
Preferred steps(4)In used motar be formulated by cement, sand, lime paste and water, cement, sand, lime The weight proportion of cream and water is cement:Lime paste:Sand:Water=1:0.22-0.25:4.3-5:0.6-0.93.Take in proportion cement, Sand, lime paste and water, then cement, sand, lime paste and water are mixed and stirred for uniformly, you can obtain motar.On it is preferred that The strength grade for stating motar is M10.
Step(5)In, water spray should be accomplished not stay dead angle, and the layer surface that makes to plaster seems to form current, makes coat of plaster abundant Absorb moisture.
Preferred steps(6)Glue used is the mixture of water and 108 glue.More preferably step(6)Glue reclaimed water used and 108 The weight ratio of glue is 2:1.108 glue are also known as " formaldehyde polyvinyl acetal ", are to be entered with polyvinyl alcohol and formaldehyde in acid medium Prepared by row condensation reaction, a kind of macromolecule bonded solution, belonged to the translucent or transparent aqueous solution.
In step(6)Before overlay film maintenance, plastic sheeting is cut according to the height of wall and width;Step(6)In, paving When pasting plastic sheeting, the lap of splice >=10cm between adjacent two width plastic sheeting.
Preferred steps(6)In, during brushing glue, glue is from top to bottom completely brushed with roller, with brush with pasting plastic sheeting; In the plastic sheeting paving from top to bottom that will be cut, plastic sheeting is flattened with roller with patch, plastic sheeting with smearing Air extrusion between grieshoch(It should make between plastic sheeting and coat of plaster without obvious bubble);After the completion of paving, then will with roller Plastic sheeting edge compresses.The edge of plastic sheeting is compressed, it is ensured that layer surface of plastering is tightly airtight, so, a side Face can prevent air from entering between plastic sheeting and coat of plaster, in order to avoid maintenance effect and membrane curing time are influenceed, it is another Aspect, the moisture contained in coat of plaster can not be evaporated as water vapor, can only plastic sheeting inner surface to the cold Small water droplet is condensed into, then water droplet is penetrated into coat of plaster again, by repeatedly circulation, is gone round and begun again, coat of plaster is located always In moisturizing, the state of moistening, conserved.In addition, coat of plaster maintenance is carried out using film mulching method, moreover it is possible to which layer surface is entered to plastering Row protection, the layer surface that avoids plastering are contaminated.
Using the wall basic unit plastering construction engineering method of the present invention, conserved by appropriate surface of wall frosting treatment and overlay film Technique, coat of plaster can be made to be securely bonded together with wall, and effectively avoid the shrinkage cracking of coat of plaster, and can be significantly Construction cost is reduced, generates good economic benefit and social benefit.Specially:
(1)Present invention efficiently solves coat of plaster shrinkage cracking common in traditional wall basic unit plastering construction, hollowing, take off The quality problems such as fall, seep water;Avoid simultaneously and hand over complaining for the owner being subject to behind room by the defects of metope ftractures, improve and apply The social image of work enterprise, obtain good social benefit;
(2)Coat of plaster is conserved using film mulching method, water consumption is few, will not cause excess surface water, is created for civilized construction Condition advantageously, and a large amount of construction waters have been saved, energy-saving and emission-reduction are realized, are advantageously implemented green construction;Metope is smeared Grieshoch once survives, and without carrying out secondary repairing to metope, metope perception effect is good, reduces because of building caused by secondary repairing Rubbish, waste of material, save construction period while safety and environmental protection, civilized construction, it is ensured that engineering is timely completed by matter;
(3)Using the construction of the present invention, construction cost is significantly reduced;
By taking the ㎡ of area 3500 that plasters as an example, the cost of construction of the present invention is about 1410 yuan, wherein 810 yuan of material cost(Bag Include:50 liters of dress glue emulsions, 10 barrels, 45 yuan/barrel, totally 450 yuan;One meter wide plastic sheeting volume 15,24 yuan/volume, altogether 360 yuan), 600 yuan of labour cost(Labour cost is 150 yuan/people per work day, needs 6 work days, and it is 150 × 4=600 yuan to need labour cost altogether), due to covering After film conserves good water-retaining property, therefore the construction of metope overlay film terminates, water seasoning is no longer carried out.And the cost of conventional method is about 9588.3 yuan, wherein 85.8 yuan of water rate(3500㎡×0.007m3/㎡=24.5m³=24.5t;Construction water unit price is 3.5 Member/t, 3.5 yuan/t × 24.5t=85.8 yuan of water rate used), 1050 yuan of labour cost(Curing time is 7 days, daily every layer of maintenance Number is 4 times, the use of artificial conversion is daily 1 work day, old friend's expenses of labour is 150 yuan/d × 7d=1050 yuan), secondary repairing expense With 8452.5 yuan(Coat of plaster needs secondary repairing area to consider by the 7% of index bed area, it is necessary to which it is 3500 ㎡ × 7% to repair area The ㎡ of ㎡=254, repairs the Yuan/㎡ of comprehensive unit price 36.5, and secondary renewal expense amounts to Yuan/㎡=8452.5 yuan of 254 ㎡ × 34.5).Adopt It is about 85.3% to save rate with construction of the present invention.
The construction of the present invention is applied to the plastering engineering of the wall basic units such as industry, civil buildings filling wall, shear wall.
Brief description of the drawings
Fig. 1 is the structural representation that sizing device is clapped in the preferred embodiment of the present invention;
Fig. 2 is Fig. 1 top view.
Embodiment
The wall basic unit plastering construction engineering method of the present embodiment comprises the steps successively:
(1)Surface of wall is cleaned out;
This step(1)In, it is necessary to it will be attached to dust, greasy dirt, oil stain, the mortar of residual and the other impurities of surface of wall all Remove clean;During concrete operations, the mortar of can the clean with a brush debris for being attached to surface of wall, dust and residual, if necessary Detergent treatment greasy dirt, oil stain can be used;
(2)To surface of wall spray water(After surface of wall is cleaned out, before carrying out surface of wall frosting treatment, in advance One day spray water), moisten surface of wall;
(3)Surface of wall frosting treatment
Cement mortar is patted on surface of wall with sizing device is clapped, forms texturing layer after cement mortar solidification, texturing layer is by cloth Full multiple raised compositions on surface of wall;
This step(3)In used cement mortar by water, glue emulsion(Glue emulsion is had using Zhongshan city's Ahmedabad richness chemical science and technology The model ZS-991A of limit company production glue product emulsion), middle sand and cement form, water, glue emulsion, middle sand Weight proportion with cement is water:Glue emulsion:Middle sand:Cement=1:2:2:2.5(Water intaking, glue emulsion, middle sand in proportion And cement, then by water, glue emulsion, middle sand and cement mixing and stir, you can obtain cement mortar);
(4)Plaster
Floating screed is carried out on texturing layer, is then applied on texturing layer and spreads motar, form coat of plaster;
Step(4)In, the method for floating screed is:Ash cake is made at a certain distance on surface of wall with cement mortar(That is cement bonded sand Lumps);Then vertically and/or horizontally continue to make one or several gray bars with cement mortar along ash cake(General spacing is not More than 1.5m);
Motar used is formulated by cement, sand, lime paste and water, and cement, sand, the weight proportion of lime paste and water are Cement:Lime paste:Sand:Water=1:0.24:4.7:0.75(Cement, sand, lime paste and water are taken in proportion, then by cement, sand, stone Emplaster and water are mixed and stirred for uniformly, you can obtain motar);
(5)Plaster after completing 3-4 hours, water spray moistening is carried out to coat of plaster using water pistol;
This step(5)In, water spray should be accomplished not stay dead angle, and the layer surface that makes to plaster seems to form current, allows coat of plaster fully to inhale Receive moisture;
(6)Overlay film conserves
After coat of plaster initial set, the brushing glue on the surface of coat of plaster;After brushing glue, by the plastic sheeting cut by up to Lower paving, makes covered rearing with plastic film on coat of plaster, carries out coat of plaster maintenance;
In this step(6)Before overlay film maintenance, plastic sheeting is cut according to the height of wall and width;
This step(6)Glue used is the mixture of water and 108 glue, and the weight ratio of glue reclaimed water and 108 glue is 2:1;
This step(6)In, during brushing glue, glue is from top to bottom completely brushed with roller, with brush with pasting plastic sheeting;It will cut out During the plastic sheeting sheared paving from top to bottom, with roller plastic sheeting is flattened with patch, plastic sheeting and coat of plaster it Between air extrusion(It should make between plastic sheeting and coat of plaster without obvious bubble);After the completion of paving, then it is with roller that plastics are thin Film edge compresses;
This step(6)In, during paving plastic sheeting, the lap of splice >=10cm between adjacent two width plastic sheeting;
(7)After completing overlay film maintenance, plastic sheeting is thrown off.
With reference to figure 1 and Fig. 2, above-mentioned steps(3)In, bat sizing device used includes net and claps 1 and handle 2(Handle 2 can use Pvc pipe, iron pipe or steel pipe are formed);Net claps the 1 multilayer steel wire 11 for including stacking together, and is evenly equipped with steel wire 11 multiple Mesh 12(Steel wire 11 is rectangle mesh sheet, is evenly equipped with multiple squared mesh 12 on steel wire 11 in the way of multiple lines and multiple rows, just The length of side of square mesh 12 is 10mm), there is between adjacent two layers steel wire 11 1-2mm gap 13;Clapped with net the one end of handle 2 1 connection.Net is clapped 1 and formed by a steel wire net-belt through folding, and outermost two layers of steel wire 11 is strapped by iron wire, is specially:Adopt With long 1200mm, wide 320mm steel wire net-belt, after four times fold, form the net with five layers of steel wire 11 and clap, every layer of steel wire The length of net 11 is about 320mm, wide about 240mm;It is by iron wire that outermost two layers of steel wire 11 is strapped again, obtain net and clap 1.Enter During row surface of wall frosting treatment, hand-held handle 2, net is clapped 1 and is immersed in cement mortar, cement mortar is entered net and clap 1 In internal gap, then lift net and clap 1 and patted towards surface of wall, net is clapped to the cement mortar inside 1 and patted in wall On surface(The cement mortar that now net is clapped in internal clearance comes out from each mesh of the steel wire near surface of wall, and turns Move on on surface of wall).When patting cement mortar, it should try one's best and uniformly pat cement mortar on surface of wall.

Claims (10)

1. a kind of wall basic unit plastering construction engineering method, it is characterised in that comprise the steps successively:
(1)Surface of wall is cleaned out;
(2)To surface of wall spray water, moisten surface of wall;
(3)Surface of wall frosting treatment
Cement mortar is patted on surface of wall with sizing device is clapped, forms texturing layer after cement mortar solidification, texturing layer is by cloth Full multiple raised compositions on surface of wall;
(4)Plaster
Floating screed is carried out on texturing layer, is then applied on texturing layer and spreads motar, form coat of plaster;
(5)Plaster after completing 3-4 hours, water spray moistening is carried out to coat of plaster using water pistol;
(6)Overlay film conserves
After coat of plaster initial set, the brushing glue on the surface of coat of plaster;After brushing glue, by the plastic sheeting cut by up to Lower paving, makes covered rearing with plastic film on coat of plaster, carries out coat of plaster maintenance;
(7)After completing overlay film maintenance, plastic sheeting is thrown off.
2. wall basic unit plastering construction engineering method according to claim 1, it is characterised in that:Step(2)In, by wall table After face is cleaned out, before carrying out surface of wall frosting treatment, the previous day spray water is put forward.
3. wall basic unit plastering construction engineering method according to claim 1, it is characterised in that:Step(3)In used cement Mortar is formed by water, glue emulsion, middle sand and cement, and water, glue emulsion, the weight proportion of middle sand and cement are water:Glue Aqueous emulsion:Middle sand:Cement=1:1.8-2.2:1.8-2.2:2.4-2.6.
4. wall basic unit plastering construction engineering method according to claim 3, it is characterised in that:The cement mortar reclaimed water, glue The weight proportion of aqueous emulsion, middle sand and cement is water:Glue emulsion:Middle sand:Cement=1:2:2:2.5.
5. wall basic unit plastering construction engineering method according to claim 1, it is characterised in that:Step(3)In used bat slurry Device includes net bat and handle, and net claps the multilayer steel wire for including stacking together, multiple mesh, handle are evenly equipped with steel wire Connection is clapped with net in one end;When carrying out surface of wall frosting treatment, hand-held handle, net bat is immersed in cement mortar, makes cement Mortar is entered in the gap inside net bat, is then lifted net and is clapped and patted towards surface of wall, will net the cement bonded sand inside bat Slurry is patted on surface of wall.
6. wall basic unit plastering construction engineering method according to claim 5, it is characterised in that:The steel wire is rectangle net Piece, multiple squared mesh are evenly equipped with the way of multiple lines and multiple rows on steel wire, the length of side of squared mesh is 8-12mm;It is adjacent There is 1-2mm gap between two layers of steel wire.
7. wall basic unit plastering construction engineering method according to claim 5, it is characterised in that:The net is clapped by a steel wire net-belt Formed through folding, outermost two layers of steel wire is strapped by iron wire.
8. wall basic unit plastering construction engineering method according to claim 1, it is characterised in that:Step(4)In used plaster Mortar is formulated by cement, sand, lime paste and water, and cement, sand, the weight proportion of lime paste and water are cement:Lime paste: Sand:Water=1:0.22-0.25:4.3-5:0.6-0.93.
9. wall basic unit plastering construction engineering method according to claim 1, it is characterised in that:Step(6)Glue used is water With the mixture of 108 glue;The weight ratio of glue reclaimed water and 108 glue is 2:1.
10. wall basic unit plastering construction engineering method according to claim 1, it is characterised in that:Step(6)In, brushing glue When, glue is from top to bottom completely brushed with roller, with brush with stickup plastic sheeting;From top to bottom spread by the plastic sheeting cut During patch, plastic sheeting is flattened with roller with patch, the air between plastic sheeting and coat of plaster is extruded;After the completion of paving, Plastic sheeting edge is compressed with roller again.
CN201710781980.7A 2017-09-02 2017-09-02 Wall basic unit plastering construction engineering method Pending CN107489250A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710781980.7A CN107489250A (en) 2017-09-02 2017-09-02 Wall basic unit plastering construction engineering method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710781980.7A CN107489250A (en) 2017-09-02 2017-09-02 Wall basic unit plastering construction engineering method

Publications (1)

Publication Number Publication Date
CN107489250A true CN107489250A (en) 2017-12-19

Family

ID=60651275

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710781980.7A Pending CN107489250A (en) 2017-09-02 2017-09-02 Wall basic unit plastering construction engineering method

Country Status (1)

Country Link
CN (1) CN107489250A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108505763A (en) * 2018-04-18 2018-09-07 中建五局土木工程有限公司 Concrete structural surface faulting of slab ends mend the treatment method
CN108999357A (en) * 2018-07-17 2018-12-14 芜湖芬特勘测服务有限公司 A kind of thin limed construction technique
CN109695346A (en) * 2017-10-20 2019-04-30 五冶集团上海有限公司 A kind of inner-outer wall plastering bat slurry construction method
CN113802788A (en) * 2021-09-29 2021-12-17 刘庆祝 Construction method
CN115231874A (en) * 2022-08-03 2022-10-25 武汉三源特种建材有限责任公司 Interface agent for plastering mortar and wall surface treatment process before and after plastering mortar construction

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1598184A (en) * 2003-09-19 2005-03-23 杨小平 Composite silicate hard heat preservating thermal insulating wall and its construction method
CN202202552U (en) * 2011-08-18 2012-04-25 中建四局第六建筑工程有限公司 Telescopic slurry flinging bat for wall plastering construction
CN103821296A (en) * 2014-02-28 2014-05-28 浙江海天建设集团有限公司 Wall plastering technique for aerated concrete block filler wall
US20150071978A1 (en) * 2013-09-06 2015-03-12 Alice Chang Clothing and covering system with various functions
CN104975689A (en) * 2015-06-30 2015-10-14 贵州建工集团有限公司 Thin cast-in-place concrete thin plastering component and construction process thereof
US20160040428A1 (en) * 2013-06-03 2016-02-11 Philip Glen Miller Self-aligning, double wire corner bead for fireproofing structural steel member and method of using same
CN105525726A (en) * 2015-05-26 2016-04-27 中建四局第一建筑工程有限公司 Aerated brick wall plastering construction method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1598184A (en) * 2003-09-19 2005-03-23 杨小平 Composite silicate hard heat preservating thermal insulating wall and its construction method
CN202202552U (en) * 2011-08-18 2012-04-25 中建四局第六建筑工程有限公司 Telescopic slurry flinging bat for wall plastering construction
US20160040428A1 (en) * 2013-06-03 2016-02-11 Philip Glen Miller Self-aligning, double wire corner bead for fireproofing structural steel member and method of using same
US20150071978A1 (en) * 2013-09-06 2015-03-12 Alice Chang Clothing and covering system with various functions
CN103821296A (en) * 2014-02-28 2014-05-28 浙江海天建设集团有限公司 Wall plastering technique for aerated concrete block filler wall
CN105525726A (en) * 2015-05-26 2016-04-27 中建四局第一建筑工程有限公司 Aerated brick wall plastering construction method
CN104975689A (en) * 2015-06-30 2015-10-14 贵州建工集团有限公司 Thin cast-in-place concrete thin plastering component and construction process thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109695346A (en) * 2017-10-20 2019-04-30 五冶集团上海有限公司 A kind of inner-outer wall plastering bat slurry construction method
CN108505763A (en) * 2018-04-18 2018-09-07 中建五局土木工程有限公司 Concrete structural surface faulting of slab ends mend the treatment method
CN108999357A (en) * 2018-07-17 2018-12-14 芜湖芬特勘测服务有限公司 A kind of thin limed construction technique
CN113802788A (en) * 2021-09-29 2021-12-17 刘庆祝 Construction method
CN115231874A (en) * 2022-08-03 2022-10-25 武汉三源特种建材有限责任公司 Interface agent for plastering mortar and wall surface treatment process before and after plastering mortar construction

Similar Documents

Publication Publication Date Title
CN107489250A (en) Wall basic unit plastering construction engineering method
CN102400525B (en) Thin-layer plastering method for autoclaved aerated concrete block wall bodies
CN100575642C (en) Special fine sand high-strength high-performance concrete ultra-high pumping construction method
CN101429786B (en) Thermal-insulation, heat insulation wall and method for producing the same
CN104018598A (en) Outer wall structure and construction and installation method
CN101565997A (en) Construction method for large-area irregular floor tile
CN108412093B (en) Modern landscape decorative rammed earth wall and construction method thereof
US20130266370A1 (en) Multi-layered cement compositions containing photocatalyst particles and method for creating multi-layered cement compositions containing photocatalyst particles
CN104120855A (en) Construction method for paving ground tile floor
CN201972172U (en) Underground rigid composite waterproof construction structure
CN104047410B (en) Stone material paving construction method
CN106884535A (en) A kind of construction technology of imitative stone material Self-leveling waterproof mortar
CN110528823A (en) Self-leveling and PVC plastic floor construction method
CN108468413A (en) A kind of air-entrained concrete building block exempts from anti-hollowing construction method of plastering
CN106284998A (en) Plastering on inner walls completely spreads fiberglass gridding cloth construction method
CN107881902A (en) Concrete construction method and mirror surface concrete pier stud
CN102852290A (en) Roof parapet flashing place structure and construction method thereof
CN103953181B (en) Cement flooring breakage method for repairing and constructing
CN101886457A (en) Method for constructing wear-resistant and crack-resistant hardened ground
CN108130992A (en) Rubble plate, styrofoam and porous brick compound thermal-insulating decorative external wall construction engineering method
CN108301320A (en) The method for paving of water-protected enclosure layer based on C40 microlith fiber concretes
KR100974424B1 (en) A Panel block
CN103291024A (en) Novel cement-based plastering mortar construction method
CN104612343A (en) Method for constructing extruded polystyrene board molding of building outer wall
CN105888084A (en) Whole outer wall internal thermal insulation system construction method by using enhanced composite thermal insulation material

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Li Zhimin

Inventor after: Wang Jianzhong

Inventor after: Ma Xu

Inventor after: Huang Chuzhou

Inventor after: Guo Chun

Inventor after: Zeng Weiqing

Inventor after: Wu Feng

Inventor after: Zhao Siyang

Inventor before: Li Zhimin

Inventor before: Ma Xu

Inventor before: Huang Chuzhou

Inventor before: Guo Chun

Inventor before: Zeng Weiqing

Inventor before: Wu Feng

Inventor before: Zhao Siyang

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171219