CN112942709A - Construction method for preventing hollowing and cracking of wall plastering - Google Patents

Construction method for preventing hollowing and cracking of wall plastering Download PDF

Info

Publication number
CN112942709A
CN112942709A CN202110273538.XA CN202110273538A CN112942709A CN 112942709 A CN112942709 A CN 112942709A CN 202110273538 A CN202110273538 A CN 202110273538A CN 112942709 A CN112942709 A CN 112942709A
Authority
CN
China
Prior art keywords
wall
plastering
wall surface
cracking
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110273538.XA
Other languages
Chinese (zh)
Inventor
林恒舟
郑志阳
何惠君
王东东
黄梅花
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Zhuzhao Construction Co ltd
Original Assignee
Fujian Zhuzhao Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Zhuzhao Construction Co ltd filed Critical Fujian Zhuzhao Construction Co ltd
Priority to CN202110273538.XA priority Critical patent/CN112942709A/en
Publication of CN112942709A publication Critical patent/CN112942709A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F13/00Coverings or linings, e.g. for walls or ceilings
    • E04F13/02Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
    • E04F13/04Bases for plaster
    • E04F13/047Plaster carrying meshes

Abstract

The invention discloses a construction method for preventing hollowing and cracking of wall plastering, which comprises the following steps: (a) treating the surface layer of the wall surface: firstly, cleaning the surface of a wall surface to be constructed, removing dust falling from the wall surface and residual soil blocks and dirt, and watering a plastering structure surface to uniformly and thoroughly wet the plastering structure surface; (b) carrying out primary gluing on the wall surface: uniformly mixing the building glue, and brushing and smearing the building glue on the wall to be constructed; the invention has the beneficial effects that: firstly, building glue is smeared on the surface layer of the treated wall surface, so that the phenomenon of dust adhesion of the wall surface in the using process is avoided, and the plastering quality is improved; the steel wire mesh is hung on the surface of the wall surface, so that the wall surface is smooth, mortar is attached to the wall surface, the hollowing phenomenon cannot occur in the later period, the anti-cracking effect is good, and the wall surface quality is improved; adopt atomizing moisturizing to handle, the wall watering is even, has improved the wall maintenance effect, can effectively avoid the wall fracture.

Description

Construction method for preventing hollowing and cracking of wall plastering
Technical Field
The invention belongs to the technical field of related structures of building construction, and particularly relates to a construction method for preventing hollowing and cracking of wall plastering.
Background
The building construction refers to production activities in the engineering construction implementation stage, is the construction process of various buildings, and also can be a process of changing various lines on a design drawing into a real object at a specified place. The method comprises foundation engineering construction, main structure construction, roofing engineering construction, decoration engineering construction and the like. The site of the construction work is called a "construction site" or "job site", also called a worksite.
Wall plastering is a common flow in building construction, and refers to surface layer engineering of plastering cement mortar, mixed mortar and lime mortar on a wall. The plastering work of the indoor and outdoor wall is a work after the construction of the building structure is finished, and the scientific plastering work can play the functions of moisture prevention, weathering prevention, heat insulation and the like, thereby preventing the wall body of the building from being eroded by wind, rain, snow and the like. The concrete wall surface constructed by the large formwork is smooth and flat, but the wall surface constructed by the large formwork needs to be plastered and straightened at the positions of the joint of the longitudinal and transverse walls, the joint of the upper layer and the lower layer of the staircase, the opening of the door and the window and the like.
The existing wall plastering construction method is simple, the construction efficiency is low, and the hollowing and cracking phenomena are easy to occur on the constructed wall, so that the construction method for preventing the hollowing and cracking of the wall plastering is provided.
Disclosure of Invention
The invention aims to provide a construction method for preventing hollowing and cracking of wall plastering in order to solve the problems, and the construction method ensures that the wall surface is not adhered with dust in the using process by coating building glue on the surface layer of the treated wall surface, improves the plastering quality, avoids secondary treatment of the wall surface, improves the plastering efficiency and accelerates the construction progress; the steel wire mesh is hung on the surface of the wall surface, so that the wall surface is smooth, mortar is attached to the wall surface, the hollowing phenomenon cannot occur in the later period, the anti-cracking effect is good, the processing quality is improved, the service life of the wall surface is prolonged, and the energy-saving, environment-friendly and green building concept is met; adopt atomizing moisturizing to handle, the wall watering is even, has improved the wall maintenance effect, can effectively avoid the wall fracture.
In order to solve the above problems, the present invention provides a technical solution: the construction method for preventing hollowing and cracking of wall plastering comprises the following steps:
(a) treating the surface layer of the wall surface: firstly, cleaning the surface of a wall surface to be constructed, removing dust falling from the wall surface and residual soil blocks and dirt, and watering a plastering structure surface to uniformly and thoroughly wet the plastering structure surface;
(b) carrying out primary gluing on the wall surface: uniformly mixing the building glue, and brushing and smearing the building glue on the wall to be constructed;
(c) hanging a steel wire mesh: hanging a steel wire mesh on the wall surface after the bottom layer plastering is carried out;
(d) carrying out bottom layer plastering: mixing sand and cement in a ratio of 1:1 to obtain cement mortar, then coating bottom layer mortar on a wall surface to be constructed, and after the bottom layer mortar is initially set, carrying out moisture preservation treatment on the surface of the wall surface;
(e) plastering a cover surface: and (d) after the bottom layer plastering after the moisturizing treatment in the step (d) reaches a certain degree, plastering surface ash is plastered, sand and cement are mixed in a ratio of 1:3 to obtain cement mortar, then plastering surface ash is plastered on the surface of the bottom layer plastering, and the overall quality of the building wall plastering is detected.
Wherein, the cement adopted in the step (d) and the step (e) is Portland cement, and the cement strength adopts products with the same color, the same batch number, the same variety and the same strength grade of more than 32.5 groups of grades.
Wherein, the average grain diameter of the sand adopted in the step (d) and the step (e) is 0.35-0.5mm, and the sand needs to be sieved before use, so as to ensure uniform grains.
Wherein the building glue used in the step (b) is 801 building glue.
Wherein, the watering treatment in the step (a) adopts spray spraying, and the maintenance is needed for 3 to 4 days after watering.
Wherein, the moisture treatment in the step (d) adopts spray spraying, and the maintenance is required for 4 to 6 days after watering.
Wherein, the sand screening machine is adopted for sand screening in the screening treatment.
The invention has the beneficial effects that:
(1) firstly, building glue is smeared on the surface layer of the treated wall surface, so that the phenomenon of dust adhesion of the wall surface in the using process is avoided, the plastering quality is improved, the secondary treatment of the wall surface is avoided, the plastering efficiency is improved, and the construction progress is accelerated;
(2) the steel wire mesh is hung on the surface of the wall surface, so that the wall surface is smooth, mortar is attached to the wall surface, the hollowing phenomenon cannot occur in the later period, the anti-cracking effect is good, the processing quality is improved, the service life of the wall surface is prolonged, and the energy-saving, environment-friendly and green building concept is met;
(3) adopt atomizing moisturizing to handle, the wall watering is even, has improved the wall maintenance effect, can effectively avoid the wall fracture.
Detailed Description
The specific implementation mode adopts the following technical scheme: the construction method for preventing hollowing and cracking of wall plastering comprises the following steps:
(a) treating the surface layer of the wall surface: firstly, cleaning the surface of a wall surface to be constructed, removing dust falling from the wall surface and residual soil blocks and dirt, and watering a plastering structure surface to uniformly and thoroughly wet the plastering structure surface;
(b) carrying out primary gluing on the wall surface: uniformly mixing the building glue, and brushing and smearing the building glue on the wall to be constructed;
(c) hanging a steel wire mesh: hanging a steel wire mesh on the wall surface after the bottom layer plastering is carried out;
(d) carrying out bottom layer plastering: mixing sand and cement in a ratio of 1:1 to obtain cement mortar, then coating bottom layer mortar on a wall surface to be constructed, and after the bottom layer mortar is initially set, carrying out moisture preservation treatment on the surface of the wall surface;
(e) plastering a cover surface: and (d) after the bottom layer plastering after the moisturizing treatment in the step (d) reaches a certain degree, plastering surface ash is plastered, sand and cement are mixed in a ratio of 1:3 to obtain cement mortar, then plastering surface ash is plastered on the surface of the bottom layer plastering, and the overall quality of the building wall plastering is detected.
Further, the cement adopted in the step (d) and the step (e) is portland cement, and the cement strength adopts products with the same color, the same batch number, the same variety and the same strength grade of more than 32.5 groups.
Furthermore, the average grain size of the sand adopted in the step (d) and the step (e) is 0.35-0.5mm, and the sand needs to be sieved before use, so that uniform grains are ensured.
Further, the building glue used in the step (b) is 801 building glue.
Furthermore, the watering treatment in the step (a) adopts spray spraying, and the maintenance is required for 3 to 4 days after watering.
Furthermore, the moisture treatment in the step (d) adopts spray spraying, and the maintenance is required for 4 to 6 days after watering.
Furthermore, the sand screening machine is adopted for sand screening in the screening treatment, the screening speed is high, and the efficiency is high.
While there have been shown and described what are at present considered to be the fundamental principles of the invention and its essential features and advantages, it will be understood by those skilled in the art that the invention is not limited by the embodiments described above, which are merely illustrative of the principles of the invention, but that various changes and modifications may be made therein without departing from the spirit and scope of the invention as defined by the appended claims and their equivalents.

Claims (7)

1. The construction method for preventing hollowing and cracking of wall plastering is characterized by comprising the following steps of:
treating the surface layer of the wall surface: firstly, cleaning the surface of a wall surface to be constructed, removing dust falling from the wall surface and residual soil blocks and dirt, and watering a plastering structure surface to uniformly and thoroughly wet the plastering structure surface;
carrying out primary gluing on the wall surface: uniformly mixing the building glue, and brushing and smearing the building glue on the wall to be constructed;
hanging a steel wire mesh: hanging a steel wire mesh on the wall surface after the bottom layer plastering is carried out;
carrying out bottom layer plastering: mixing sand and cement in a ratio of 1:1 to obtain cement mortar, then coating bottom layer mortar on a wall surface to be constructed, and after the bottom layer mortar is initially set, carrying out moisture preservation treatment on the surface of the wall surface;
plastering a cover surface: and (d) after the bottom layer plastering after the moisturizing treatment in the step (d) reaches a certain degree, plastering surface ash is plastered, sand and cement are mixed in a ratio of 1:3 to obtain cement mortar, then plastering surface ash is plastered on the surface of the bottom layer plastering, and the overall quality of the building wall plastering is detected.
2. The construction method for preventing hollowing and cracking of wall plastering according to claim 1, which is characterized in that: the cement adopted in the step (d) and the step (e) is silicate cement, and the cement strength adopts products with the same color, the same batch number, the same variety and the same strength grade of more than 32.5 groups of grades.
3. The construction method for preventing hollowing and cracking of wall plastering according to claim 1, which is characterized in that: the average grain diameter of the sand adopted in the step (d) and the step (e) is 0.35-0.5mm, and the sand needs to be sieved before use, so that uniform grains are ensured.
4. The construction method for preventing hollowing and cracking of wall plastering according to claim 1, which is characterized in that: the building glue used in the step (b) is 801 building glue.
5. The construction method for preventing hollowing and cracking of wall plastering according to claim 1, which is characterized in that: the watering treatment in the step (a) adopts spray spraying, and the maintenance is required for 3 to 4 days after watering.
6. The construction method for preventing hollowing and cracking of wall plastering according to claim 1, which is characterized in that: and (d) spraying the moisture in the step (d), and curing for 4-6 days after watering.
7. The construction method for preventing hollowing and cracking of wall plastering according to claim 3, wherein: and the screening treatment adopts a sand screening machine to screen sand and stone.
CN202110273538.XA 2021-03-15 2021-03-15 Construction method for preventing hollowing and cracking of wall plastering Pending CN112942709A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110273538.XA CN112942709A (en) 2021-03-15 2021-03-15 Construction method for preventing hollowing and cracking of wall plastering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110273538.XA CN112942709A (en) 2021-03-15 2021-03-15 Construction method for preventing hollowing and cracking of wall plastering

Publications (1)

Publication Number Publication Date
CN112942709A true CN112942709A (en) 2021-06-11

Family

ID=76229727

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110273538.XA Pending CN112942709A (en) 2021-03-15 2021-03-15 Construction method for preventing hollowing and cracking of wall plastering

Country Status (1)

Country Link
CN (1) CN112942709A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114635527A (en) * 2022-03-25 2022-06-17 中国五冶集团有限公司 Archaized building ridge structure and construction method thereof
CN114775961A (en) * 2022-04-28 2022-07-22 重庆渝能建筑安装工程有限公司 Plastering construction method and plastering device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575899A (en) * 2009-06-01 2009-11-11 潍坊昌大建设集团有限公司 Construction process for internal wall surface of building wall body
CN102477797A (en) * 2010-11-24 2012-05-30 五冶集团上海有限公司 Construction method for preventing crack of infilled wall
CN103821296A (en) * 2014-02-28 2014-05-28 浙江海天建设集团有限公司 Wall plastering technique for aerated concrete block filler wall
CN105525726A (en) * 2015-05-26 2016-04-27 中建四局第一建筑工程有限公司 Aerated brick wall plastering construction method
CN108193862A (en) * 2017-12-30 2018-06-22 肖勇 Building wall plastering construction method
CN109025109A (en) * 2018-08-17 2018-12-18 徽都建设有限公司 A kind of construction technology coating inner wall of building face

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101575899A (en) * 2009-06-01 2009-11-11 潍坊昌大建设集团有限公司 Construction process for internal wall surface of building wall body
CN102477797A (en) * 2010-11-24 2012-05-30 五冶集团上海有限公司 Construction method for preventing crack of infilled wall
CN103821296A (en) * 2014-02-28 2014-05-28 浙江海天建设集团有限公司 Wall plastering technique for aerated concrete block filler wall
CN105525726A (en) * 2015-05-26 2016-04-27 中建四局第一建筑工程有限公司 Aerated brick wall plastering construction method
CN108193862A (en) * 2017-12-30 2018-06-22 肖勇 Building wall plastering construction method
CN109025109A (en) * 2018-08-17 2018-12-18 徽都建设有限公司 A kind of construction technology coating inner wall of building face

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114635527A (en) * 2022-03-25 2022-06-17 中国五冶集团有限公司 Archaized building ridge structure and construction method thereof
CN114775961A (en) * 2022-04-28 2022-07-22 重庆渝能建筑安装工程有限公司 Plastering construction method and plastering device

Similar Documents

Publication Publication Date Title
CN109838065B (en) Floor tile ground paving construction method
CN101886460B (en) Press polishing method of plastered mesh cloth of inner wall
CN112942709A (en) Construction method for preventing hollowing and cracking of wall plastering
CN104018598A (en) Outer wall structure and construction and installation method
CN103938656A (en) Building wall surface underground waterproof construction method
CN104088416A (en) Gypsum heat preservation painting mortar construction process
CN111305566A (en) High-rise residential full-professional alternate construction floor water interception method
CN108468413A (en) A kind of air-entrained concrete building block exempts from anti-hollowing construction method of plastering
CN105525726A (en) Aerated brick wall plastering construction method
CN105272113A (en) Dry plastering technology
CN101545269B (en) Method for rigid waterproof construction of beam and slab type basement
CN207194343U (en) The tapestry brick paving structure of autoclave aerated concrete building block exterior wall
CN207194353U (en) A kind of prefabricated thermal insulation water-proof decorative external wall panel structure
CN103291024A (en) Novel cement-based plastering mortar construction method
CN112479668A (en) Special cement for building clean water brick wall and construction method thereof
CN107299731A (en) A kind of anti-hollowing of mountain sand cement mortar plastering and cracking construction method
CN209958651U (en) Ceramic tile outer wall waterproof construction
CN106836683A (en) A kind of construction method of Machine-made Sand aggregate dry-mixed mortar coated building metope
CN109853888A (en) A kind of historical building plucking wall surface construction technology
CN107724546A (en) Gypsum based inorganic thermal insulation mortar system construction method
CN112081334A (en) Building facade decoration structure and construction method thereof
CN207063377U (en) Autoclave aerated concrete building block exterior wall base layer structure
CN219241427U (en) Exterior wall stone hollowing and falling repairing and reforming system
CN110565886A (en) Anti-hollowing and cracking plastering gypsum structure and construction method thereof
CN110700599A (en) Plastering-free construction process for shear wall surface

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination