CN105507462B - Have both the combined wall and its construction method of load-bearing and heat insulation function - Google Patents
Have both the combined wall and its construction method of load-bearing and heat insulation function Download PDFInfo
- Publication number
- CN105507462B CN105507462B CN201510839763.XA CN201510839763A CN105507462B CN 105507462 B CN105507462 B CN 105507462B CN 201510839763 A CN201510839763 A CN 201510839763A CN 105507462 B CN105507462 B CN 105507462B
- Authority
- CN
- China
- Prior art keywords
- styrofoam
- concrete
- board
- wall
- bearing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/74—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls
- E04B1/76—Heat, sound or noise insulation, absorption, or reflection; Other building methods affording favourable thermal or acoustical conditions, e.g. accumulating of heat within walls specifically with respect to heat only
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Acoustics & Sound (AREA)
- Building Environments (AREA)
Abstract
本发明公开了一种兼具承重和保温功能的复合墙体及其施工方法,该复合墙体包括位于中部的聚苯板、平行设于聚苯板两侧的钢筋网片、穿插在聚苯板上的插丝和浇注在聚苯板两侧的外层混凝土与内层混凝土,所述插丝斜插穿过聚苯板、且其两端分别和位于聚苯板两侧的钢筋网片焊接;该墙体通过将保温板预先固定在设计位置,并在保温板内侧和外侧浇注混凝土,使保温板和混凝土墙体真正形成一体化结构,既能实现保温,还能防止外部安装的保温板掉落影响使用安全,同时能够缩短施工周期;该方法通过在墙体混凝土浇注之前即将保温板预先固定在设计位置,浇注混凝土即可完成墙体施工,无需等待建筑结构完成后再安装保温层,缩短施工周期。
The invention discloses a composite wall with both load-bearing and thermal insulation functions and a construction method thereof. The composite wall comprises a polystyrene board located in the middle, steel mesh sheets arranged parallel to both sides of the polystyrene board, and interspersed with polystyrene boards. The insert wire on the board and the outer layer concrete and inner layer concrete poured on both sides of the polystyrene board. Welding; the wall pre-fixes the insulation board at the designed position, and pours concrete on the inside and outside of the insulation board, so that the insulation board and the concrete wall truly form an integrated structure, which can not only achieve heat preservation, but also prevent external installation of heat preservation The falling of the board affects the safety of use, and at the same time, it can shorten the construction period; this method pre-fixes the insulation board at the design position before the wall concrete is poured, and the wall construction can be completed by pouring the concrete, without waiting for the building structure to be completed before installing the insulation layer , shorten the construction period.
Description
技术领域technical field
本发明涉及一种建筑外墙技术领域,尤其涉及一种兼具承重和保温功能的复合墙体及其施工方法。The invention relates to the technical field of building exterior walls, in particular to a composite wall with load-bearing and thermal insulation functions and a construction method thereof.
背景技术Background technique
外墙保温多种多样,传统外墙保温,是由聚合物砂浆、玻璃纤维网格布、阻燃型模塑聚苯乙烯泡沫板(EPS)或挤塑板(XPS)等材料复合而成,现场粘结施工。新型保温装饰一体化板是通过流水线生产,集保温、防水、饰面等功能于一体,是满足当前房屋建筑节能需求,提高工业与民用建筑外墙保温水平的优选材料,也是对既有建筑节能改造的首选材料,将保温装饰一体化板固定安装在建筑外墙实现保温,虽然现有的保温装置一体化板实现了一体化生产和标准化安装,但是固定安装在墙体外侧的保温装饰一体化板仍然存在脱落的风险,而且与既有墙体并未一体化结构,容易存在气隙,影响保温效果和使用安全。There are many kinds of external wall insulation. The traditional external wall insulation is composed of polymer mortar, glass fiber mesh cloth, flame-retardant molded polystyrene foam board (EPS) or extruded board (XPS) and other materials. On-site bonding construction. The new thermal insulation and decoration integrated board is produced through the assembly line, which integrates the functions of thermal insulation, waterproof, and decorative surface. The preferred material for renovation is to install the thermal insulation and decoration integrated board on the outer wall of the building to achieve thermal insulation. Although the existing thermal insulation device integrated board has realized integrated production and standardized installation, the integrated thermal insulation and decoration board fixed on the outside of the wall The board still has the risk of falling off, and it is not integrated with the existing wall, so there is likely to be an air gap, which affects the thermal insulation effect and safety of use.
另外一方面现有的保温装饰一体化板需要在建筑结构完成后进行安装,延长施工周期。On the other hand, the existing thermal insulation and decoration integrated board needs to be installed after the building structure is completed, so as to prolong the construction period.
发明内容Contents of the invention
本发明所要解决的技术问题是提供一种兼具承重和保温功能的复合墙体,将保温板浇注在外层混凝土和内层混凝土之间,无需固定在墙体外侧,形成一体化结构,与墙体混凝土同时施工,缩短施工周期,不存在脱落的风险,确保使用安全。The technical problem to be solved by the present invention is to provide a composite wall with both load-bearing and thermal insulation functions. The thermal insulation board is poured between the outer concrete and the inner concrete without being fixed on the outside of the wall to form an integrated structure that is integrated with the wall. Concrete construction at the same time, shorten the construction period, there is no risk of falling off, to ensure safe use.
本发明所要解决的技术问题是提供一种兼具承重和保温功能的复合墙体施工方法,在墙体混凝土浇注之前即将保温板预先固定在设计位置,浇注混凝土即可完成墙体施工,无需等待建筑结构完成后再安装保温层,缩短施工周期。The technical problem to be solved by the present invention is to provide a composite wall construction method with both load-bearing and thermal insulation functions. Before the wall concrete is poured, the thermal insulation board is fixed in the design position in advance, and the concrete can be poured to complete the wall construction without waiting. After the building structure is completed, the insulation layer is installed to shorten the construction period.
为解决上述技术问题,本发明所采取的技术方案是:一种兼具承重和保温功能的复合墙体,包括位于中部的聚苯板、平行设于聚苯板两侧的钢筋网片、穿插在聚苯板上的插丝和浇注在聚苯板两侧的外层混凝土与内层混凝土,所述插丝斜插穿过聚苯板、且其两端分别和位于聚苯板两侧的钢筋网片焊接。In order to solve the above technical problems, the technical solution adopted by the present invention is: a composite wall with both load-bearing and thermal insulation functions, including a polystyrene board located in the middle, steel mesh sheets arranged in parallel on both sides of the polystyrene board, interspersed Insert wires on the polystyrene board and pour the outer layer concrete and the inner layer concrete on both sides of the polystyrene board, the insertion wires are obliquely inserted through the polystyrene board, and the two ends of the wire are respectively connected to the two sides of the polystyrene board Steel mesh welded.
所述外层混凝土厚度为50-60毫米,所述内层混凝土厚度不小于100毫米。The thickness of the outer layer of concrete is 50-60 mm, and the thickness of the inner layer of concrete is not less than 100 mm.
所述聚苯板内侧平行设置两片钢筋网片,插丝斜插穿过聚苯板后与三片钢筋网片焊接。Two pieces of steel mesh are arranged in parallel on the inner side of the polystyrene board, and the wires are inserted obliquely through the polystyrene board and welded with three pieces of steel mesh.
所述位于聚苯板内侧的钢筋网片所采用的钢筋直径为4毫米,所述位于聚苯板外侧的钢筋网片所采用的钢筋直径为3毫米。The diameter of the reinforcing bar used in the reinforcing mesh sheet positioned inside the polystyrene board is 4 mm, and the diameter of the reinforcing bar used in the reinforcing mesh sheet positioned outside the polystyrene board is 3 mm.
所述位于聚苯板两侧的钢筋网片端部与柱体或拐角处钢筋焊接或绑扎。The ends of the steel mesh sheets located on both sides of the polystyrene board are welded or bound with the steel bars at the columns or corners.
为解决上述技术问题,本发明还提供了一种兼具承重和保温功能的复合墙体施工方法,包括如下步骤,In order to solve the above-mentioned technical problems, the present invention also provides a composite wall construction method with both load-bearing and thermal insulation functions, which includes the following steps,
第一步:边缘构件钢筋绑扎,同时预制保温板;Step 1: Bound the edge members with steel bars, and prefabricated the insulation board at the same time;
第二步:吊装保温板;The second step: hoisting insulation board;
第三步:连接保温板钢筋网片和边缘构件的钢筋;The third step: connect the reinforcement mesh of the insulation board and the reinforcement of the edge member;
第四步:墙体模板支护;The fourth step: wall formwork support;
第五步:墙体混凝土浇注;The fifth step: wall concrete pouring;
第六步:模板拆除;Step 6: Formwork removal;
第七步:墙体混凝土养护;The seventh step: wall concrete maintenance;
第一步所述的边缘构件包括结构柱和墙体拐角,结构柱和墙体拐角根据设计要求绑扎主筋和箍筋,保温板预制过程包括准备聚苯板,安装插丝,插丝采用三维斜插的方式均匀插装在聚苯板上、且穿透聚苯板,穿透聚苯板的插丝两端分别与位于聚苯板两侧的钢筋网片焊接,聚苯板外侧设置一片钢筋网片,聚苯板内侧设置一片或者两片钢筋网片,并在位于聚苯板两侧的钢筋网片上布设定位块。The edge components described in the first step include structural columns and wall corners. The structural columns and wall corners are bound with main reinforcement and stirrups according to the design requirements. The prefabrication process of the insulation board includes preparing polystyrene boards and installing wire insertion. The insertion method is evenly inserted on the polystyrene board and penetrates the polystyrene board. The two ends of the insertion wire penetrating the polystyrene board are respectively welded to the steel mesh on both sides of the polystyrene board, and a piece of steel bar is set outside the polystyrene board. For the mesh, one or two pieces of steel mesh are arranged inside the polystyrene board, and positioning blocks are arranged on the steel mesh on both sides of the polystyrene board.
第二步包括采用塔吊将预制好的保温板吊装就位,并根据设计位置预先采用钢管支架固定,第三步包括将吊装就位保温板的钢筋网片与边缘构件的钢筋连接,采用焊接或者绑扎的方式连接。The second step includes hoisting the prefabricated insulation board into place with a tower crane, and fixing it with steel pipe supports in advance according to the design position. Connected by tying.
所述第四步包括使用钢管支架在保温板两侧支护内侧模板和外侧模板,内侧模板和外侧模板采用穿插拉筋的方式调整间距。The fourth step includes using steel pipe brackets to support the inner formwork and the outer formwork on both sides of the insulation board, and adjusting the distance between the inner formwork and the outer formwork by interspersing tension bars.
混凝土浇注过程中采用自密实混凝土,模板拆除后在内侧混凝土和外侧混凝土表面涂抹养护液。Self-compacting concrete is used in the concrete pouring process. After the formwork is removed, curing fluid is applied to the surface of the inner concrete and the outer concrete.
采用上述技术方案所产生的有益效果在于:通过将保温板预先固定在设计位置,并在保温板内侧和外侧浇注混凝土,使保温板和混凝土墙体真正形成一体化结构,既能实现保温,还能防止外部安装的保温板掉落影响使用安全,同时能够缩短施工周期。The beneficial effect of adopting the above technical solution is that by pre-fixing the insulation board at the designed position, and pouring concrete on the inside and outside of the insulation board, the insulation board and the concrete wall can truly form an integrated structure, which can not only realize heat preservation, but also It can prevent the externally installed insulation board from falling and affect the safety of use, and can shorten the construction period at the same time.
采用上述技术方案还产生的有益效果在于:通过在墙体混凝土浇注之前即将保温板预先固定在设计位置,浇注混凝土即可完成墙体施工,无需等待建筑结构完成后再安装保温层,缩短施工周期。The beneficial effect of adopting the above-mentioned technical solution is that: by pre-fixing the insulation board at the designed position before the concrete pouring of the wall, the wall construction can be completed by pouring the concrete, and there is no need to wait for the completion of the building structure before installing the insulation layer, shortening the construction period .
附图说明Description of drawings
图1是本发明复合墙体结构示意图;Fig. 1 is the composite wall structure schematic diagram of the present invention;
图2是本发明保温板断面结构示意图;Fig. 2 is a schematic diagram of the section structure of the insulation board of the present invention;
在附图中:1、面层;2、内层混凝土;3、插丝;4、钢筋网片;5、聚苯板;6、外层混凝土。In the accompanying drawings: 1. Surface layer; 2. Inner layer concrete; 3. Inserting wire; 4. Steel mesh; 5. Polystyrene board; 6. Outer layer concrete.
具体实施方式Detailed ways
下面结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明的一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention are clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
在下面的描述中阐述了很多具体细节以便于充分理解本发明,但是本发明还可以采用其他不同于在此描述的其它方式来实施,本领域技术人员可以在不违背本发明内涵的情况下做类似推广,因此本发明不受下面公开的具体实施例的限制。In the following description, a lot of specific details are set forth in order to fully understand the present invention, but the present invention can also be implemented in other ways different from those described here, and those skilled in the art can do it without departing from the meaning of the present invention. By analogy, the present invention is therefore not limited to the specific examples disclosed below.
如图1-2所示,本发明公开了一种兼具承重和保温功能的复合墙体,包括位于中部的聚苯板5、平行设于聚苯板5两侧的钢筋网片4、穿插在聚苯板5上的插丝3和浇注在聚苯板5两侧的外层混凝土6与内层混凝土2,所述插丝3斜插穿过聚苯板5、且其两端分别和位于聚苯板5两侧的钢筋网片4焊接;所述外层混凝土6厚度为50-60毫米,所述内层混凝土2厚度不小于100毫米;所述聚苯板5内侧平行设置两片钢筋网片4,插丝3斜插穿过聚苯板5后与三片钢筋网片4焊接;所述位于聚苯板5内侧的钢筋网片4所采用的钢筋直径为4毫米,所述位于聚苯板5外侧的钢筋网片4所采用的钢筋直径为3毫米;所述位于聚苯板5两侧的钢筋网片4端部与柱体或拐角处钢筋焊接或绑扎。As shown in Figure 1-2, the present invention discloses a composite wall with both load-bearing and thermal insulation functions, including a polystyrene board 5 located in the middle, steel mesh sheets 4 parallel to both sides of the polystyrene board 5, interspersed Inserting wire 3 on the polystyrene board 5 and pouring the outer layer concrete 6 and the inner layer concrete 2 on both sides of the polystyrene board 5, the insertion wire 3 is obliquely inserted through the polystyrene board 5, and its two ends are connected with the polystyrene board 5 respectively. The reinforcement mesh sheets 4 located on both sides of the polystyrene board 5 are welded; the thickness of the outer layer of concrete 6 is 50-60 mm, and the thickness of the inner layer of concrete 2 is not less than 100 mm; the inside of the polystyrene board 5 is provided with two parallel sheets Reinforcing mesh sheet 4, insertion wire 3 obliquely inserts and welds with three reinforcement mesh sheets 4 after passing through polystyrene board 5; The steel bar diameter that the described reinforcement mesh sheet 4 that is positioned at polystyrene board 5 inner side adopts is 4 millimeters, and described The diameter of steel bar used in the reinforcement mesh 4 outside the polystyrene board 5 is 3 millimeters; the ends of the reinforcement mesh 4 positioned on both sides of the polystyrene board 5 are welded or bound with the reinforcement at the column or corner.
在具体应用过程中,本发明通过将保温板预先固定在设计位置,并在保温板内侧和外侧浇注混凝土,使保温板和混凝土墙体真正形成一体化结构,既能实现保温,还能防止外部安装的保温板掉落影响使用安全,同时能够缩短施工周期。In the specific application process, the present invention pre-fixes the insulation board at the designed position, and pours concrete on the inside and outside of the insulation board, so that the insulation board and the concrete wall truly form an integrated structure, which can not only realize heat preservation, but also prevent external The fall of the installed insulation board affects the safety of use, and can shorten the construction period at the same time.
本发明还公开了一种兼具承重和保温功能的复合墙体施工方法,包括如下步骤,The invention also discloses a construction method for a composite wall with load-bearing and thermal insulation functions, which includes the following steps:
第一步:边缘构件钢筋绑扎,同时预制保温板;第一步所述的边缘构件包括结构柱和墙体拐角,结构柱和墙体拐角根据设计要求绑扎主筋和箍筋,保温板预制过程包括准备聚苯板5,安装插丝3,插丝3采用三维斜插的方式均匀插装在聚苯板5上、且穿透聚苯板5,穿透聚苯板5的插丝3两端分别与位于聚苯板5两侧的钢筋网片4焊接,聚苯板5外侧设置一片钢筋网片4,聚苯板5内侧设置一片或者两片钢筋网片4,并在位于聚苯板5两侧的钢筋网片4上布设定位块。Step 1: Bound the edge members with reinforcement, and prefabricated the insulation board; the edge members described in the first step include structural columns and wall corners, and the structural columns and wall corners are bound according to the design requirements. Prepare the polystyrene board 5, install the insertion wire 3, the insertion wire 3 is evenly inserted on the polystyrene board 5 by three-dimensional oblique insertion, and penetrates the polystyrene board 5, and penetrates both ends of the insertion wire 3 of the polystyrene board 5 Weld with the reinforcement mesh 4 on both sides of the polystyrene board 5 respectively, a reinforcement mesh 4 is arranged on the outside of the polystyrene board 5, and one or two reinforcement mesh 4 are arranged on the inside of the polystyrene board 5, and the polystyrene board 5 Positioning blocks are arranged on the reinforcement mesh sheets 4 on both sides.
第二步:吊装保温板;The second step: hoisting insulation board;
第三步:连接保温板钢筋网片4和边缘构件的钢筋;第二步包括采用塔吊将预制好的保温板吊装就位,并根据设计位置预先采用钢管支架固定,第三步包括将吊装就位保温板的钢筋网片4与边缘构件的钢筋连接,采用焊接或者绑扎的方式连接。The third step: connect the reinforcement mesh 4 of the insulation board and the steel bars of the edge members; the second step includes hoisting the prefabricated insulation board into place with a tower crane, and fixing it with steel pipe supports in advance according to the design position; the third step includes hoisting the prefabricated insulation board into place. The reinforcement mesh sheet 4 of the thermal insulation board is connected with the steel bars of the edge components by welding or binding.
第四步:墙体模板支护;所述第四步包括使用钢管支架在保温板两侧支护内侧模板和外侧模板,内侧模板和外侧模板采用穿插拉筋的方式调整间距。The fourth step: wall formwork support; the fourth step includes using steel pipe brackets to support the inner formwork and the outer formwork on both sides of the insulation board, and the inner formwork and the outer formwork are adjusted by interspersed tension bars.
第五步:墙体混凝土浇注;The fifth step: wall concrete pouring;
第六步:模板拆除;Step 6: Formwork removal;
第七步:墙体混凝土养护;The seventh step: wall concrete maintenance;
混凝土浇注过程中采用自密实混凝土,模板拆除后在内侧混凝土和外侧混凝土表面涂抹养护液。Self-compacting concrete is used in the concrete pouring process. After the formwork is removed, curing fluid is applied to the surface of the inner concrete and the outer concrete.
在具体应用过程中,本发明通过在墙体混凝土浇注之前即将保温板预先固定在设计位置,浇注混凝土即可完成墙体施工,无需等待建筑结构完成后再安装保温层,缩短施工周期。In the specific application process, the present invention pre-fixes the insulation board at the designed position before pouring the concrete on the wall, and the wall construction can be completed by pouring the concrete, without waiting for the completion of the building structure before installing the insulation layer, shortening the construction period.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510839763.XA CN105507462B (en) | 2015-11-27 | 2015-11-27 | Have both the combined wall and its construction method of load-bearing and heat insulation function |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510839763.XA CN105507462B (en) | 2015-11-27 | 2015-11-27 | Have both the combined wall and its construction method of load-bearing and heat insulation function |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN105507462A CN105507462A (en) | 2016-04-20 |
| CN105507462B true CN105507462B (en) | 2018-08-14 |
Family
ID=55715736
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510839763.XA Active CN105507462B (en) | 2015-11-27 | 2015-11-27 | Have both the combined wall and its construction method of load-bearing and heat insulation function |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105507462B (en) |
Families Citing this family (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106759994A (en) * | 2017-02-20 | 2017-05-31 | 浙江大学建筑设计研究院有限公司 | A kind of warming plate with arrangement of reinforcement and its thermal insulation structure construction method in exterior wall concrete section position |
| CN107386556B (en) * | 2017-07-04 | 2020-04-21 | 山东大学 | Lightweight composite thermal insulation exterior wall panel |
| CN107288256B (en) * | 2017-07-04 | 2023-08-22 | 山东大学 | Light composite heat-insulating external wall panel, special die and manufacturing method thereof |
| CN108505645B (en) * | 2018-03-27 | 2020-04-17 | 黄河科技学院 | CL composite concrete shear wall cast-in-place construction method |
| CN109505373A (en) * | 2018-09-03 | 2019-03-22 | 安徽安保新型节能建材科技有限公司 | Prefabricated float builds floor heat-preservation sound-insulation board and its laying method |
| CN112096072B (en) * | 2020-08-21 | 2022-06-07 | 上海欧跃建筑安装工程有限公司 | Simultaneous concrete pouring method on the same floor of beam-slab lag wall-column used for building machine |
| CN112324001A (en) * | 2020-10-02 | 2021-02-05 | 河南省建筑设计研究院有限公司 | Exterior wall filled with polystyrene concrete sandwich composite thermal insulation slats |
| CN112832411A (en) * | 2021-02-09 | 2021-05-25 | 张以超 | Low-energy-consumption prefabricated bearing wallboard and method for building bearing wall |
| CN113235768A (en) * | 2021-05-21 | 2021-08-10 | 铜陵有色建安钢构有限责任公司 | Composite heat-insulating wall |
| CN113846768A (en) * | 2021-08-18 | 2021-12-28 | 西北矿冶研究院 | An environment-friendly and energy-saving building wall and its construction method |
Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1944836A (en) * | 2006-10-25 | 2007-04-11 | 张晶廷 | Composite shear wall and construction method |
| CN201241404Y (en) * | 2008-07-21 | 2009-05-20 | 河南锦源建设有限公司 | Reinforced concrete external casting built-in heat preservation heat insulation wall |
| CN101608488A (en) * | 2009-06-11 | 2009-12-23 | 浙江大学 | Structural self-insulating concrete wall panel and manufacturing method thereof |
| GB201104061D0 (en) * | 2011-03-10 | 2011-04-20 | Holt John C | Truss |
| CN102304953A (en) * | 2011-07-07 | 2012-01-04 | 李富厚 | Sandwich heat insulation reinforced concrete shear wall and construction method thereof |
| CN202866044U (en) * | 2012-10-09 | 2013-04-10 | 湖北晶达建筑科技有限公司 | Light reinforced concrete central sandwich thermal insulation wall |
| CN203296190U (en) * | 2013-04-26 | 2013-11-20 | 清华大学建筑设计研究院有限公司 | Multi-layer parallel steel wire net rack sandwich insulation board and load-bearing insulation integrated wall body structure |
| CN203334480U (en) * | 2013-04-24 | 2013-12-11 | 石家庄晶达建筑体系有限公司 | Structure of cast-in-place steel bar welding wire frame composite concrete shear wall |
| CN205314308U (en) * | 2015-11-27 | 2016-06-15 | 中国建筑第七工程局有限公司 | Have composite wall of bearing and heat preservation function concurrently |
Family Cites Families (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101280580B (en) * | 2008-05-06 | 2011-08-17 | 张晶廷 | Load bearing screen plate and load bearing masonry composite building structure as well as construction method thereof |
-
2015
- 2015-11-27 CN CN201510839763.XA patent/CN105507462B/en active Active
Patent Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1944836A (en) * | 2006-10-25 | 2007-04-11 | 张晶廷 | Composite shear wall and construction method |
| CN201241404Y (en) * | 2008-07-21 | 2009-05-20 | 河南锦源建设有限公司 | Reinforced concrete external casting built-in heat preservation heat insulation wall |
| CN101608488A (en) * | 2009-06-11 | 2009-12-23 | 浙江大学 | Structural self-insulating concrete wall panel and manufacturing method thereof |
| GB201104061D0 (en) * | 2011-03-10 | 2011-04-20 | Holt John C | Truss |
| CN102304953A (en) * | 2011-07-07 | 2012-01-04 | 李富厚 | Sandwich heat insulation reinforced concrete shear wall and construction method thereof |
| CN202866044U (en) * | 2012-10-09 | 2013-04-10 | 湖北晶达建筑科技有限公司 | Light reinforced concrete central sandwich thermal insulation wall |
| CN203334480U (en) * | 2013-04-24 | 2013-12-11 | 石家庄晶达建筑体系有限公司 | Structure of cast-in-place steel bar welding wire frame composite concrete shear wall |
| CN203296190U (en) * | 2013-04-26 | 2013-11-20 | 清华大学建筑设计研究院有限公司 | Multi-layer parallel steel wire net rack sandwich insulation board and load-bearing insulation integrated wall body structure |
| CN205314308U (en) * | 2015-11-27 | 2016-06-15 | 中国建筑第七工程局有限公司 | Have composite wall of bearing and heat preservation function concurrently |
Also Published As
| Publication number | Publication date |
|---|---|
| CN105507462A (en) | 2016-04-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105507462B (en) | Have both the combined wall and its construction method of load-bearing and heat insulation function | |
| CN103114717B (en) | A kind of both sides, shrinkage joint shear wall formwork system | |
| CN103243837B (en) | Construction and construction method exclusively used in composite shear wall structure filler wall | |
| CN206428872U (en) | A kind of close splicing seam superimposed sheet | |
| CN110439137A (en) | Prefabricated wall panel, wall and prefabricated wall panel production method, prefabricated wall construction method | |
| CN103276916B (en) | Construction method of solid-sealed lightweight concrete slab wall opening and filling plate | |
| CN111673900A (en) | Production process and production structure of a double-sided prefabricated thermal insulation laminated shear wall panel | |
| CN106639093A (en) | Close splicing seam-type laminated slab | |
| CN104712138B (en) | Construction Method of Combining Plastic Formwork and Multi-layer Wooden Formwork for Concrete Exterior Wall | |
| CN205314308U (en) | Have composite wall of bearing and heat preservation function concurrently | |
| CN106351396A (en) | Connecting structure for built-in heat-insulating plate of sandwich heat-insulating external wallboard and wall concrete layer and construction method thereof | |
| CN209817249U (en) | A compound wallboard of prefabricated foam concrete for building infilled wall | |
| CN208803582U (en) | A fireproof insulation board pre-installed on the outer formwork of concrete pouring | |
| CN203066294U (en) | Assembled multifunctional outer wall body | |
| CN207063267U (en) | For making the connection component of superimposed sheet | |
| CN112324009A (en) | A kind of prefabricated concrete hollow thermal insulation wall structure and construction technology | |
| CN105178503B (en) | A kind of prefabricated strap-on insulation wallboard | |
| CN205224332U (en) | Prefabricated wall body and prefabricated wallboard | |
| CN204919605U (en) | Prefabricated assembled reinforced concrete utility tunnel and production mould thereof | |
| CN114197705B (en) | A decorative structure integrated prefabricated hollow wall without mold removal and construction method thereof | |
| CN215054517U (en) | A prefabricated formwork wall integrating decoration and thermal insulation | |
| CN114482344A (en) | Cast-in-place concrete sandwich outer wall construction method capable of improving construction efficiency | |
| CN212602543U (en) | Production structure of two-sided prefabricated heat preservation coincide shear force wallboard | |
| CN208803581U (en) | A fire-proof insulation board lined on the outer formwork of concrete pouring | |
| CN204983661U (en) | Light steel is framed greatly, integrative -in -place mould support system is decorated in protection that keeps warm |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |