CN105469196A - 一种矿井建设项目过程后评价的综合评价方法及系统 - Google Patents

一种矿井建设项目过程后评价的综合评价方法及系统 Download PDF

Info

Publication number
CN105469196A
CN105469196A CN201510796280.6A CN201510796280A CN105469196A CN 105469196 A CN105469196 A CN 105469196A CN 201510796280 A CN201510796280 A CN 201510796280A CN 105469196 A CN105469196 A CN 105469196A
Authority
CN
China
Prior art keywords
index
evaluation
module
weight
sub
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510796280.6A
Other languages
English (en)
Inventor
王扬
张传明
任英伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University of Science and Technology
Original Assignee
Shandong University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University of Science and Technology filed Critical Shandong University of Science and Technology
Priority to CN201510796280.6A priority Critical patent/CN105469196A/zh
Publication of CN105469196A publication Critical patent/CN105469196A/zh
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/02Agriculture; Fishing; Mining

Abstract

本发明公开了一种矿井建设项目过程后评价的综合评价方法及系统,其中的综合评价方法包括建立指标体系步骤、确定权重步骤及评判步骤;其中的综合评价系统包括建立指标体系模块、确定权重模块及评判模块。本发明能够结合矿井建设项目的工程特点,设置了能全面反映项目投资建设生产工作全过程情况的详细指标体系;既采用主客观相结合的组合赋权法,即层次分析法和熵权法确定各指标权重,避免了单一赋权方法的不足,可以获得更加科学合理的权重系数;又采用模糊评价模型进行综合评价,很好地解决了指标体系多层次,因素众多,定性指标难以量化的模糊评价问题,又避免了常用成功度法,评价结果可信度低的情况,使得评价结果更具准确性。

Description

一种矿井建设项目过程后评价的综合评价方法及系统
技术领域
本发明属于矿井建设项目后评价领域,特别涉及一种矿井建设项目过程后评价的综合评价方法,以及一种矿井建设项目过程后评价的综合评价系统。
背景技术
虽然近几年我国煤炭行业不太景气,但煤炭仍是我国经济发展和人民生活所依赖的主要能源。为满足我国的煤炭需求,我国未来还将有序开发一些煤炭基地,建设一批现代化矿井。但是,在我国以往大量的矿井建设实践中,不难发现达不到预期期望目标的项目屡见不鲜。如何总结经验,汲取教训,在以后的矿井项目投资中不断提高决策、建设和生产经营水平,取得最佳效益,这是当前我国矿井项目投资中亟待解决的问题,而矿井建设项目过程后评价有助于这些问题的解决。项目后评价起始于20世纪30年代的美国,我国也自20世纪80年代中后期开始开展项目后评价工作,项目过程后评价是后评价的核心内容,它通过回顾和检查项目前期工作、建设实施、运营管理的各个环节执行情况,对项目全过程的管理水平及工作质量进行评价,揭示项目实施过程中,在数量、质量、工程进度、造价、安全等方面是否达到了设计规定的目标,以便总结项目决策、技术和管理等方面成功的经验和失败的教训,并得到启示,进而提出对策建议,改进投资决策和项目管理,以达到提高项目投资效益的目的。
到目前为止,尽管我国有些行业如铁路、港口、公路、水利、路桥和油田开发等建设项目对项目后评价都颁布了相关的政策和统一规定,但煤炭行业还没有项目后评价的专门的文件规定,更没有对项目过程后评价的系统研究,没有统一的评价方法、指标体系和评价标准;不同单位、不同评价人员所采用的方法各异,但往往指标粗略,方法过于简单,造成评价结论与项目真实情况偏差较大。因此,如何对矿井建设项目过程做出客观、科学的真实评价,需要深入研究科学的评价方法,以便能够更好地解决好以下三方面问题。
(1)构建系统全面的指标体系。在以往所做的矿井建设项目过程后评价中,往往泛泛地采用我国规定的关于一般建设项目后评价的指标,过于粗略简单,应结合矿井建设项目的工程特点,设置详细的指标体系。矿井建设项目的工程内容和影响因素很多,在建立过程后评价指标体系时要考虑指标的科学性、全面性、代表性、相对独立性和特色性,能客观、正确地反映煤矿项目投资建设生产工作的全过程情况。
(2)采用科学的方法确定合理的指标权重。目前计算指标权重的常用方法可分为主观赋权法和客观赋权法两类。主观赋权法主要有专家打分法、德尔菲法、层次分析法等,主观赋权的方法往往会因为太过依赖专家的主观判断,而具有很大的随意性和人为因素;客观赋权方法主要有因子分析法、变异系数法、TOPSIS法、熵权法、离差最大化方法、灰色关联度法等。客观赋权能充分挖掘指标客观数据信息,但完全忽略了专家的知识与经验,有可能得到的权重结果与主观愿望不一致,在缺乏指标样本数据的情况下无法使用。矿井建设项目过程后评价指标要涉及项目前期决策、建设准备、建设实施和生产运营的全过程,内容众多,既有定性指标又有定量指标,为了得到更加科学合理的指标权重,最好主客观方法相结合,既能充分挖掘数据信息又避免了完全忽略专家的知识与经验。
(3)选择合适的综合后评价模型。在对项目各阶段、各部分、各层次工作进行定性的问题分析和评价的基础上,为了得到项目投资建设生产全过程的整体效果水平的定量评价结果,需采用合适的综合评价方法。常用的主观评价法是成功度法,以专家打分的形式,分析项目是完全成功、基本成功、部分成功、不成功或失败,一般测定的指标在10项左右,对项目的评价比较粗略,其评价结果的可信度低。还有一些客观评价法,如TOPSIS法(逼近理想解法)、数据包络分析法、主成分分析法、聚类分析法和神经网络方法等,都需要有大量的客观样本数据,对一些难以量化的定性指标或客观数据缺乏的情况下无法使用。矿井建设项目过程后评价指标既有定量指标又有定性指标,且因素众多,需要探求有效的解决此类问题的方法。
发明内容
为解决以上问题和克服现有技术的不足,本发明提出了一种矿井建设项目过程后评价的综合评价方法及系统,能够更好地实现对矿井项目投资建设生产全过程的科学、客观和真实评价,为我国矿井建设项目后评价提供参考依据,以提高我国煤矿项目投资决策和项目管理水平。
其技术解决方案是:
一种矿井建设项目过程后评价的综合评价方法,包括以下步骤:
a建立指标体系步骤,结合矿井建设项目的工程特点和过程后评价的内容,按照目标分层法建立了能客观、正确地反映煤矿项目投资建设生产工作的全过程的指标体系,共划分为四个层次,分别是目标层A、分目标层B、一级指标C和二级指标D;其中,分目标层B包含4个指标,一级指标C包含20个指标,二级指标D包含81个指标;
b确定权重步骤,采用层次分析法和熵权法相结合的主客观组合赋权法确定指标权重,先用层次分析法计算各指标的权重,再采用熵权法对指标权重进行修正,得到组合权重值;
c评判步骤,选择模糊评价模型进行矿井建设项目过程后评价的综合评价分析,通过确定评语集V,根据已建立的指标因素集U,确定隶属度向量和评价矩阵,再根据已确立的指标权重,确定权重集W,从而进行模糊运算并进行归一化,得到模糊评价综合结果,对项目作出评判。
进一步地,在步骤b中,利用层次分析法计算指标权重包括以下具体步骤:
b1按照建立的指标体系层次结构模型,采用专家调查法,按照成对比较法和1——9标度法构造两两比较判断矩阵P;
b2对每一比较矩阵采用几何平均法分别计算:
特征向量其中
最大特征根
然后,计算一致性指标:CR=CI/RI,其中CI=(λmax-n)/(n-1)
式中n为判断矩阵阶数;RI为判断矩阵的平均随机一致性指标;当CR﹤0.10时,认为判断矩阵有满意的一致性,特征向量wi即为各指标权重,否则需要调整判断矩阵,再进行分析。
更进一步地,在步骤b中,采用熵权法对利用层次分析法计算出的指标权重进行修正,进一步利用层次分析法确定的判断矩阵提供的信息,计算出各指标的熵权,对采用层次分析法得出的指标权重进行修正,得到组合权重,包括以下具体步骤:
b3对判断矩阵的各列项进行归一化,得到标准矩阵G=(gij)n×n,其中
b4计算第j个指标的输出熵
当gij=o,令gijlngij=0;
b5求指标的差异度δj=1-Hj
b6计算指标的信息熵权当δj=0,令λj=0;
b7利用信息熵权λj修正由AHP法得到的权重向量wj,修正后的组合权重向量:
进一步地,在步骤c中,利用模糊综合评价模型对矿井建设项目过程进行综合评价分析,包括以下具体步骤:
c1确定各指标隶属度及评价矩阵
c11确定评语集
将相关指标评价的优劣程度作为评语集V的元素,共分四个等级,可表示为:V={V1,V2,V3,V4},式中的V1,V2,V3,V4分别表示项目对应指标评价情况:优秀、良好、中等、差四个等级;
c12确定隶属度及评价矩阵Rij
采用专家调查方法,依据评价的统计情况,计算出各指标的隶属度:
σijk (m)=Tm/t(i=1,2,…,n;j=1,2,…,s;k=1,2,…,f;m=1,2,…,p)
其中,Tm——指标属于等级Vm的频数;t——参加评价的专家总人数;n——分目标层指标个数;s——分目标层指标Bi下的一级指标个数,f——一级指标Cij下的二级指标个数;p——指标等级数。
由σijk (m)构成模糊评判向量:Rijk=(σijk (1)ijk (2),......,σijk (p))
从而建立单因素评判矩阵:Rij=(Rij1,Rij2,…Rijk)T
c2综合评判
c21一级模糊综合评判
c22二级模糊综合评判
c23三级模糊综合评判
通过以上分析计算,按照最大隶属度原则确定矿井建设项目过程后评价综合评价结果。
一种矿井建设项目过程后评价的综合评价系统,包括:
建立指标体系模块,该模块结合矿井建设项目的工程特点和过程后评价的内容,按照目标分层法建立了能客观、正确地反映煤矿项目投资建设生产工作的全过程的指标体系,共划分为四个层次,分别是目标层A、分目标层B、一级指标C和二级指标D;其中,分目标层B包含4个指标,一级指标C包含20个指标,二级指标D包含81个指标;
确定权重模块,该模块采用层次分析法和熵权法相结合的主客观组合赋权法确定指标权重,先用层次分析法计算各指标的权重,再采用熵权法对指标权重进行修正,得到组合权重值;
评判模块,该模块选择模糊评价模型进行矿井建设项目过程后评价的综合评价分析,通过确定评语集V,根据已建立的指标因素集U,确定隶属度向量和评价矩阵,再根据已确立的指标权重,确定权重集W,从而进行模糊运算并进行归一化,得到模糊评价综合结果,对项目作出评判。
进一步地,在确定权重模块中,利用层次分析法计算指标权重,具体包括:
构造比较判断矩阵分模块,该分模块按照建立的指标体系层次结构模型,采用专家调查法,按照成对比较法和1——9标度法构造两两比较判断矩阵P;
计算一致性指标分模块,该分模块对每一比较矩阵采用几何平均法分别计算:
特征向量其中
最大特征根
然后,计算一致性指标:CR=CI/RI,其中CI=(λmax-n)/(n-1)
式中n为判断矩阵阶数;RI为判断矩阵的平均随机一致性指标;当CR﹤0.10时,认为判断矩阵有满意的一致性,特征向量wi即为各指标权重,否则需要调整判断矩阵,再进行分析。
更进一步地,在确定权重模块中,采用熵权法对利用层次分析法计算出的指标权重进行修正,进一步利用层次分析法确定的判断矩阵提供的信息,计算出各指标的熵权,对采用层次分析法得出的指标权重进行修正,得到组合权重,具体包括:
归一化分模块,该分模块对判断矩阵的各列项进行归一化,得到标准矩阵G=(gij)n×n
其中
输出熵计算分模块,该分模块用于计算第j个指标的输出熵
当gij=o,令gijlngij=0;
差异度计算分模块,该分模块用于求指标的差异度δj=1-Hj
信息熵权计算分模块,该分模块用于计算指标的信息熵权当δj=0,令λj=0;
权重向量计算分模块,该分模块利用信息熵权λj修正由AHP法得到的权重向量wj,修正后的组合权重向量:
进一步地,在评判模块中,利用模糊综合评价模型对矿井建设项目过程进行综合评价分析,包括确定各指标隶属度及评价矩阵分模块和综合评判分模块,其中的确定各指标隶属度及评价矩阵分模块,具体包括:
确定评语集子模块,该子模块用于将相关指标评价的优劣程度作为评语集V的元素,共分四个等级,可表示为:V={V1,V2,V3,V4},式中的V1,V2,V3,V4分别表示项目对应指标评价情况:优秀、良好、中等、差四个等级;
确定隶属度及评价矩阵Rij子模块,该子模块采用专家调查方法,依据评价的统计情况,计算出各指标的隶属度:
σijk (m)=Tm/t(i=1,2,…,n;j=1,2,…,s;k=1,2,…,f;m=1,2,…,p)
其中,Tm——指标属于等级Vm的频数;t——参加评价的专家总人数;n——分目标层指标个数;s——分目标层指标Bi下的一级指标个数,f——一级指标Cij下的二级指标个数;p——指标等级数。
由σijk (m)构成模糊评判向量:Rijk=(σijk (1)ijk (2),......,σijk (p))
从而建立单因素评判矩阵:Rij=(Rij1,Rij2,…Rijk)T
以及其中的综合评判分模块具体包括:
一级模糊综合评判子模块,其包括式(1):
二级模糊综合评判子模块,其包括式(2)
三级模糊综合评判子模块,其包括式(3)
由综合评判分模块进行分析计算,并按照最大隶属度原则确定矿井建设项目过程后评价综合评价结果。
本发明可具有以下技术特点及有益效果:
针对我国煤炭行业还没有对项目过程后评价的系统研究,没有统一的评价方法、指标体系和评价标准;不同单位、不同评价人员所采用的方法各异,但往往指标粗略,方法过于简单,容易造成评价结论失真的情况。本发明提出的一种矿井建设项目过程后评价的综合评价方法及系统,能够结合矿井建设项目的工程特点,设置了能全面反映项目投资建设生产工作全过程情况的详细指标体系;既采用主客观相结合的组合赋权法,即层次分析法和熵权法确定各指标权重,避免了单一赋权方法的不足,可以获得更加科学合理的权重系数;又采用模糊评价模型进行综合评价,很好地解决了指标体系多层次,因素众多,定性指标难以量化的模糊评价问题,又避免了常用成功度法,评价结果可信度低的情况,使得评价结果更具准确性。
附图说明
图1是本发明中矿井建设项目过程后评价的综合评价方法的一种实施方式流程图。
具体实施方式
下面结合附图1和实例对本发明作更进一步详细的说明。
本发明的一种矿井建设项目过程后评价的综合评价方法,包括以下步骤:
(1)构建系统全面的矿井建设项目过程后评价指标体系。
矿井建设项目是一项庞大复杂的系统工程,矿井建设项目过程后评价也是一项涉及因素众多的复杂评价。根据我国一般建设项目后评价相关规定,结合矿井建设项目的工程特点和过程后评价的内容,并考虑到科学性、全面性、代表性和相对独立性等原则,通过咨询专家意见,按照目标分层法建立了能客观、正确地反映煤矿项目投资建设生产工作的全过程的指标体系(见表1),共划分为四个层次:目标层A、分目标层B(4个指标)、一级指标C(20个指标)、二级指标D(81个指标)。
表1某矿井建设项目过程后评价指标体系及指标权重和单因素模糊隶属度矩阵
(2)采用主客观相结合的组合赋权法确定指标权重
1)方法的提出
通过对多种赋权方法的深入分析,考虑矿井建设项目过程后评价指标体系具有众多定性、模糊、多层次的指标特点,本发明采用AHP法和熵权法相结合的方法确定指标权重,避免了单一赋权方法的不足,可以获得更加科学合理的权重系数。
层次分析法既不单纯的追求高深数学,又不片面的注重行为、逻辑和推理,而是一种把定性方法和定量方法有机结合起来的简洁实用的多目标决策方法,它能使复杂的问题简单化,模糊的问题清晰化,定性的问题定量化,根据矿井建设项目过程后评价的特性,本发明中首选层析分析法进行评价指标权重的确定。考虑到AHP法在应用过程中可能由于评价专家主观上的不确定性及认识上的模糊性,致使主观判断不一致,产生的循环不满足传递性公理,从而丢失部分信息的问题,可通过熵权法再对利用层次分析法确定的指标权重进行修正。因为熵权法以指标的原始数据波动大小为确定权重的依据,能充分挖掘数据本身蕴含的信息,所以可以进一步利用层次分析法确定的判断矩阵提供的信息,计算出各指标的熵权,对采用层次分析法得出的指标权重进行修正,得到组合权重。两种方法相结合,更能提高权重确定的准确性和评价结果的客观性,是目前多目标决策方法中较为科学的评价方法。
2)利用层次分析法计算指标权重
按照建立的指标体系层次结构模型,采用专家调查法,按照成对比较法和1——9标度法构造两两比较判断矩阵P,对每一比较矩阵采用几何平均法分别计算:
特征向量其中
最大特征根
然后,计算一致性指标:CR=CI/RI,其中CI=(λmax-n)/(n-1)
式中n为判断矩阵阶数;RI为判断矩阵的平均随机一致性指标,其值确定见表2。当CR﹤0.10时,认为判断矩阵有满意的一致性,特征向量wi即为各指标权重,否则需要调整判断矩阵,再进行分析。
以总目标层A为例,得出判断矩阵
根据PW=λmaxW求出最大特征根λmax=4.0192,最大特征根对应的特征向量为:
w=(0.5872,0.2181,0.1227,0.0721)T
以上特征向量若能通过检验,各个数值就代表对应各个指标的权重。因此下面进行一致性检验。
第一步,计算一致性指标CI=(λmax-n)/(n-1)=0.0064。
第二步,根据表2,找出相应的平均随机一致性指标RI=0.9。
第三步,计算一致性比例CR=CI/RI=0.0071﹤0.1,通过一致性检验。
由此得到权重向量w=(0.5872,0.2181,0.1227,0.0721)T
同理,计算其他各级指标权重。
表2不同阶数RI的取值
3)采用熵权法进行指标权重修正
进一步利用层次分析法确定的判断矩阵提供的信息,计算出各指标的熵权,对采用层次分析法得出的指标权重进行修正,得到组合权重,其基本步骤如下:
①对判断矩阵的各列项进行归一化,得到标准矩阵G=(gij)n×n,其中
②计算第j个指标的输出熵
当gij=o,令gijlngij=0。
③求指标的差异度δj=1-Hj
④计算指标的信息熵权当δj=0,令λj=0。
⑤利用信息熵权λj修正由AHP法得到的权重向量wj,修正后的组合权重向量:
还是以总目标A为例,按上述公式计算出B1、B2、B3、B4各指标修正后的组合权重,结果见表3。
表3判断矩阵A权重修正
同理,可计算出其他各级指标组合权重μ,结果见表1。
(3)采用模糊评价模型进行矿井建设项目过程后评价的综合评价分析
模糊综合评价方法(FuzzyComprehensiveEvaluation,FCE)就是以模糊数学为基础,以模糊推理为主的定性与定量相结合、精确与非精确相统一的一种综合评价方法,是模糊数学应用于自然科学领域和社会科学领域中的一个重要体现。模糊数学方法提供了一种有效的方法,使定性指标根据隶属度函数和模糊统计方法定量化,将定性和定量方法进行有效结合。在客观事物发展中,很多问题不是绝对的肯定也不是绝对的否定,涉及到模糊因素,FCE方法可以很好地解决综合评价中的模糊性问题,而且更加适合应用于评价因素较多、结构层次较多的对象系统。矿井建设项目过程后评价指标体系具有多层次,且因素众多,很多指标是模糊的定性的指标,经研究分析模糊评价法是解决此类问题的有效方法。
与上述综合评价方法对应的一种矿井建设项目过程后评价的综合评价系统,包括:
建立指标体系模块,该模块结合矿井建设项目的工程特点和过程后评价的内容,按照目标分层法建立了能客观、正确地反映煤矿项目投资建设生产工作的全过程的指标体系,共划分为四个层次,分别是目标层A、分目标层B、一级指标C和二级指标D;其中,分目标层B包含4个指标,一级指标C包含20个指标,二级指标D包含81个指标;
确定权重模块,该模块采用层次分析法和熵权法相结合的主客观组合赋权法确定指标权重,先用层次分析法计算各指标的权重,再采用熵权法对指标权重进行修正,得到组合权重值;
评判模块,该模块选择模糊评价模型进行矿井建设项目过程后评价的综合评价分析,通过确定评语集V,根据已建立的指标因素集U,确定隶属度向量和评价矩阵,再根据已确立的指标权重,确定权重集W,从而进行模糊运算并进行归一化,得到模糊评价综合结果,对项目作出评判。
进一步地,在确定权重模块中,利用层次分析法计算指标权重,具体包括:
构造比较判断矩阵分模块,该分模块按照建立的指标体系层次结构模型,采用专家调查法,按照成对比较法和1——9标度法构造两两比较判断矩阵P;
计算一致性指标分模块,该分模块对每一比较矩阵采用几何平均法分别计算:
特征向量其中
最大特征根
然后,计算一致性指标:CR=CI/RI,其中CI=(λmax-n)/(n-1)
式中n为判断矩阵阶数;RI为判断矩阵的平均随机一致性指标;当CR﹤0.10时,认为判断矩阵有满意的一致性,特征向量wi即为各指标权重,否则需要调整判断矩阵,再进行分析。
更进一步地,在确定权重模块中,采用熵权法对利用层次分析法计算出的指标权重进行修正,进一步利用层次分析法确定的判断矩阵提供的信息,计算出各指标的熵权,对采用层次分析法得出的指标权重进行修正,得到组合权重,具体包括:
归一化分模块,该分模块对判断矩阵的各列项进行归一化,得到标准矩阵G=(gij)n×n
其中
输出熵计算分模块,该分模块用于计算第j个指标的输出熵
当gij=o,令gijlngij=0;
差异度计算分模块,该分模块用于求指标的差异度δj=1-Hj
信息熵权计算分模块,该分模块用于计算指标的信息熵权当δj=0,令λj=0;
权重向量计算分模块,该分模块利用信息熵权λj修正由AHP法得到的权重向量wj,修正后的组合权重向量:
进一步地,在评判模块中,利用模糊综合评价模型对矿井建设项目过程进行综合评价分析,包括确定各指标隶属度及评价矩阵分模块和综合评判分模块,其中的确定各指标隶属度及评价矩阵分模块,具体包括:
确定评语集子模块,该子模块用于将相关指标评价的优劣程度作为评语集V的元素,共分四个等级,可表示为:V={V1,V2,V3,V4},式中的V1,V2,V3,V4分别表示项目对应指标评价情况:优秀、良好、中等、差四个等级;
确定隶属度及评价矩阵Rij子模块,该子模块采用专家调查方法,依据评价的统计情况,计算出各指标的隶属度:
σijk (m)=Tm/t(i=1,2,…,n;j=1,2,…,s;k=1,2,…,f;m=1,2,…,p)
其中,Tm——指标属于等级Vm的频数;t——参加评价的专家总人数;n——分目标层指标个数;s——分目标层指标Bi下的一级指标个数,f——一级指标Cij下的二级指标个数;p——指标等级数。
由σijk (m)构成模糊评判向量:Rijk=(σijk (1)ijk (2),......,σijk (p))
从而建立单因素评判矩阵:Rij=(Rij1,Rij2,…Rijk)T
以及其中的综合评判分模块具体包括:
一级模糊综合评判子模块,其包括式(1):
二级模糊综合评判子模块,其包括式(2)
三级模糊综合评判子模块,其包括式(3)
由综合评判分模块进行分析计算,并按照最大隶属度原则确定矿井建设项目过程后评价综合评价结果。
下面以某煤矿建设项目为例,按照上面建立的指标体系,运用模糊综合评价法对该项目进行过程后评价的综合评价分析,具体步骤如下:
(1)确定各指标隶属度及评价矩阵
①确定评语集
将相关指标评价的优劣程度作为评语集V的元素,共分四个等级,可表示为:V={V1,V2,V3,V4}式中V1,V2,V3,V4分别表示项目对应指标评价情况:优秀、良好、中等、差四个等级。
②确定隶属度及评价矩阵Rij
本项目采用专家调查方法,依据评价的统计情况,得出各指标的隶属度,结果见表1。计算各指标隶属度时采取以下公式:σijk (m)=Tm/t
其中,Tm——属于等级Vm的频数;t——参加评价的专家总人数。
由σijk (m)构成模糊评判向量:Rijk=(σijk (1)ijk (2),......,σijk (p))
从而建立单因素评判矩阵:Rij=(Rij1,Rij2,…Rijk)T
(2)综合评判
①一级模糊综合评判
把表1中的数据代入上式可知:
同理可得:
B12=(0.56040.27510.16460)B13=(0.78570.16670.04760)
B14=(0.64290.357200)B21=(0.339290.50000.06120)
B22=(0.27140.45710.25720)B23=(0.22860.65720.11430)
B24=(0.29020.49220.26160)B31=(0.21200.42690.36110)
B32=(0.32880.41500.25600)B33=(0.61090.34160.04750)
B34=(0.48110.40630.11270)B35=(0.25000.71430.03570)
B36=(0.27900.46260.25850)B37=(0.42860.571400)
B38=(0.28570.57140.14290)B39=(0.15790.59800.24420)
B41=(0.24670.64930.10390)B42=(0.11910.71430.16670)
B43=(0.34410.655900)
②二级模糊综合评判
同理可得:
③三级模糊综合评判
通过以上分析计算结果,按照最大隶属度原则,该煤矿项目的前期决策评价B1、前期准备工作评价B2、建设实施评价B3和生产运行评价B4评价的结果分别为优、良、良、良,最终综合评价结果为良好,说明了该项目投资建设生产状况较好,但在开发建设和生产过程中还存在不足之处,需要认真分析原因,总结经验,进一步提高项目的生产经营管理水平,为未来项目提供有益的借鉴。
从本项目实际调查情况看,尽管各方面工作还存在不足之处,但该煤矿生产实现了预期目标,且具有较好的可持续发展能力,项目还是比较成功的。通过上面的计算得出的后评价结果与实际情况相符合,应证了该发明提出的一种矿井建设项目过程后评价的综合评价方法的实用性和科学性,适合于对煤矿项目过程后评价的分析。
本发明未述及的有关技术内容采取或借鉴已有技术即可实现。

Claims (8)

1.一种矿井建设项目过程后评价的综合评价方法,其特征在于包括以下步骤:
a建立指标体系步骤,结合矿井建设项目的工程特点和过程后评价的内容,按照目标分层法建立了能客观、正确地反映煤矿项目投资建设生产工作的全过程的指标体系,共划分为四个层次,分别是目标层A、分目标层B、一级指标C和二级指标D;其中,分目标层B包含4个指标,一级指标C包含20个指标,二级指标D包含81个指标;
b确定权重步骤,采用层次分析法和熵权法相结合的主客观组合赋权法确定指标权重,先用层次分析法计算各指标的权重,再采用熵权法对指标权重进行修正,得到组合权重值;
c评判步骤,选择模糊评价模型进行矿井建设项目过程后评价的综合评价分析,通过确定评语集V,根据已建立的指标因素集U,确定隶属度向量和评价矩阵,再根据已确立的指标权重,确定权重集W,从而进行模糊运算并进行归一化,得到模糊评价综合结果,对项目作出评判。
2.根据权利要求1所述的一种矿井建设项目过程后评价的综合评价方法,其特征在于:在步骤b中,利用层次分析法计算指标权重包括以下具体步骤:
b1按照建立的指标体系层次结构模型,采用专家调查法,按照成对比较法和1——9标度法构造两两比较判断矩阵P;
b2对每一比较矩阵采用几何平均法分别计算:
特征向量其中
最大特征根
然后,计算一致性指标:CR=CI/RI,其中CI=(λmax-n)/(n-1)
式中n为判断矩阵阶数;RI为判断矩阵的平均随机一致性指标;当CR﹤0.10时,认为判断矩阵有满意的一致性,特征向量wi即为各指标权重,否则需要调整判断矩阵,再进行分析。
3.根据权利要求1所述的一种矿井建设项目过程后评价的综合评价方法,其特征在于:在步骤b中,采用熵权法对利用层次分析法计算出的指标权重进行修正,进一步利用层次分析法确定的判断矩阵提供的信息,计算出各指标的熵权,对采用层次分析法得出的指标权重进行修正,得到组合权重,包括以下具体步骤:
b3对判断矩阵P的各列项进行归一化,得到标准矩阵G=(gij)n×n,其中
b4计算第j个指标的输出熵
当gij=o,令gijlngij=0;
b5求指标的差异度δj=1-Hj
b6计算指标的信息熵权当δj=0,令λj=0;
b7利用信息熵权λj修正由AHP法得到的权重向量wj,修正后的组合权重向量:
4.根据权利要求1所述的一种矿井建设项目过程后评价的综合评价方法,其特征在于:在步骤c中,利用模糊综合评价模型对矿井建设项目过程进行综合评价分析,包括以下具体步骤:
c1确定各指标隶属度及评价矩阵
c11确定评语集
将相关指标评价的优劣程度作为评语集V的元素,共分四个等级,可表示为:V={V1,V2,V3,V4},式中的V1,V2,V3,V4分别表示项目对应指标评价情况:优秀、良好、中等、差四个等级;
c12确定隶属度及评价矩阵Rij
采用专家调查方法,依据评价的统计情况,计算出各指标的隶属度:
σijk (m)=Tm/t(i=1,2,…,n;j=1,2,…,s;k=1,2,…,f;m=1,2,…,p)
其中,Tm——指标属于等级Vm的频数;t——参加评价的专家总人数;n——分目标层指标个数;s——分目标层指标Bi下的一级指标个数,f——一级指标Cij下的二级指标个数;p——指标等级数。
由σijk (m)构成模糊评判向量:Rijk=(σijk (1)ijk (2),......,σijk (p))
从而建立单因素评判矩阵:Rij=(Rij1,Rij2,…Rijk)T
c2综合评判
c21一级模糊综合评判
c22二级模糊综合评判
c23三级模糊综合评判
通过以上分析计算,按照最大隶属度原则确定矿井建设项目过程后评价综合评价结果。
5.一种矿井建设项目过程后评价的综合评价系统,其特征在于包括:
建立指标体系模块,该模块结合矿井建设项目的工程特点和过程后评价的内容,按照目标分层法建立了能客观、正确地反映煤矿项目投资建设生产工作的全过程的指标体系,共划分为四个层次,分别是目标层A、分目标层B、一级指标C和二级指标D;其中,分目标层B包含4个指标,一级指标C包含20个指标,二级指标D包含81个指标;
确定权重模块,该模块采用层次分析法和熵权法相结合的主客观组合赋权法确定指标权重,先用层次分析法计算各指标的权重,再采用熵权法对指标权重进行修正,得到组合权重值;
评判模块,该模块选择模糊评价模型进行矿井建设项目过程后评价的综合评价分析,通过确定评语集V,根据已建立的指标因素集U,确定隶属度向量和评价矩阵,再根据已确立的指标权重,确定权重集W,从而进行模糊运算并进行归一化,得到模糊评价综合结果,对项目作出评判。
6.根据权利要求5所述的一种矿井建设项目过程后评价的综合评价系统,其特征在于:在确定权重模块中,利用层次分析法计算指标权重,具体包括:
构造比较判断矩阵分模块,该分模块按照建立的指标体系层次结构模型,采用专家调查法,按照成对比较法和1——9标度法构造两两比较判断矩阵P;
计算一致性指标分模块,该分模块对每一比较矩阵采用几何平均法分别计算:
特征向量其中
最大特征根
然后,计算一致性指标:CR=CI/RI,其中CI=(λmax-n)/(n-1)
式中n为判断矩阵阶数;RI为判断矩阵的平均随机一致性指标;当CR﹤0.10时,认为判断矩阵有满意的一致性,特征向量wi即为各指标权重,否则需要调整判断矩阵,再进行分析。
7.根据权利要求5所述的一种矿井建设项目过程后评价的综合评价系统,其特征在于:在确定权重模块中,采用熵权法对利用层次分析法计算出的指标权重进行修正,进一步利用层次分析法确定的判断矩阵提供的信息,计算出各指标的熵权,对采用层次分析法得出的指标权重进行修正,得到组合权重,具体包括:
归一化分模块,该分模块对判断矩阵的各列项进行归一化,得到标准矩阵G=(gij)n×n
其中
输出熵计算分模块,该分模块用于计算第j个指标的输出熵
当gij=o,令gijlngij=0;
差异度计算分模块,该分模块用于求指标的差异度δj=1-Hj
信息熵权计算分模块,该分模块用于计算指标的信息熵权当δj=0,令λj=0;
权重向量计算分模块,该分模块利用信息熵权λj修正由AHP法得到的权重向量wj,修
正后的组合权重向量:
8.根据权利要求5所述的一种矿井建设项目过程后评价的综合评价系统,其特征在于:在评判模块中,利用模糊综合评价模型对矿井建设项目过程进行综合评价分析,包括确定各指标隶属度及评价矩阵分模块和综合评判分模块,其中的确定各指标隶属度及评价矩阵分模块,具体包括:
确定评语集子模块,该子模块用于将相关指标评价的优劣程度作为评语集V的元素,共分四个等级,可表示为:V={V1,V2,V3,V4},式中的V1,V2,V3,V4分别表示项目对应指标评价情况:优秀、良好、中等、差四个等级;
确定隶属度及评价矩阵Rij子模块,该子模块采用专家调查方法,依据评价的统计情况,计算出各指标的隶属度:
σijk (m)=Tm/t(i=1,2,…,n;j=1,2,…,s;k=1,2,…,f;m=1,2,…,p)
其中,Tm——指标属于等级Vm的频数;t——参加评价的专家总人数;n——分目标层指标个数;s——分目标层指标Bi下的一级指标个数,f——一级指标Cij下的二级指标个数;p——指标等级数。
由σijk (m)构成模糊评判向量:Rijk=(σijk (1)ijk (2),......,σijk (p))
从而建立单因素评判矩阵:Rij=(Rij1,Rij2,…Rijk)T
以及其中的综合评判分模块具体包括:
一级模糊综合评判子模块,其包括式(1):
二级模糊综合评判子模块,其包括式(2)
三级模糊综合评判子模块,其包括式(3)
由综合评判分模块进行分析计算,并按照最大隶属度原则确定矿井建设项目过程后评价综合评价结果。
CN201510796280.6A 2015-11-18 2015-11-18 一种矿井建设项目过程后评价的综合评价方法及系统 Pending CN105469196A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510796280.6A CN105469196A (zh) 2015-11-18 2015-11-18 一种矿井建设项目过程后评价的综合评价方法及系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510796280.6A CN105469196A (zh) 2015-11-18 2015-11-18 一种矿井建设项目过程后评价的综合评价方法及系统

Publications (1)

Publication Number Publication Date
CN105469196A true CN105469196A (zh) 2016-04-06

Family

ID=55606864

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510796280.6A Pending CN105469196A (zh) 2015-11-18 2015-11-18 一种矿井建设项目过程后评价的综合评价方法及系统

Country Status (1)

Country Link
CN (1) CN105469196A (zh)

Cited By (76)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106202267A (zh) * 2016-06-30 2016-12-07 四川农业大学 一种黄果柑综合品质评价方法
CN106250353A (zh) * 2016-08-10 2016-12-21 广东电网有限责任公司电力科学研究院 一种熵权计算方法和多目标决策方法
CN106295976A (zh) * 2016-08-03 2017-01-04 重庆大学 基于层次分析法和模糊综合评价的ipt系统电磁机构性能评价方法
CN106339798A (zh) * 2016-08-20 2017-01-18 辽宁工程技术大学 一种基于模糊综合评判法的软岩斜井井筒支护体系稳定性评价方法
CN106651169A (zh) * 2016-12-19 2017-05-10 国家电网公司 基于模糊综合评价的配电自动化终端状态评价方法及系统
CN106841545A (zh) * 2017-02-14 2017-06-13 蚌埠学院 基于改进模糊综合评判法的茶叶感官品质评价方法
CN106845870A (zh) * 2017-03-03 2017-06-13 中国水产科学研究院黄海水产研究所 基于灰色关联的模糊层次电厂温排水渔业损害评估方法
CN107180306A (zh) * 2017-05-24 2017-09-19 西安科技大学 一种煤炭资源有利开采区块加权叠加辨识的技术方法
CN107240033A (zh) * 2017-06-07 2017-10-10 国家电网公司客户服务中心 一种电力识别模型的构建方法及系统
CN107544253A (zh) * 2017-03-17 2018-01-05 中国人民解放军91049部队 基于改进模糊熵权法的大型导弹装备退役安全控制方法
CN107766999A (zh) * 2016-08-18 2018-03-06 中核第四研究设计工程有限公司 一种砂岩型铀矿床开发利用的综合评价方法
CN107909290A (zh) * 2017-12-07 2018-04-13 北京能源集团有限责任公司 一种技改专修项目评价方法及系统
CN108182544A (zh) * 2018-01-24 2018-06-19 李超 一种农产品的品质评估方法
CN108596479A (zh) * 2018-04-24 2018-09-28 东北农业大学 一种评价农业机械化发展水平的指标体系
CN108710984A (zh) * 2018-04-04 2018-10-26 中国地质环境监测院 一种矿山地质环境综合评价方法及系统
CN108959791A (zh) * 2018-07-12 2018-12-07 中国船舶重工集团公司第七二四研究所 一种相控阵雷达资源调度效能层级递阶评估方法
CN109033561A (zh) * 2018-07-05 2018-12-18 平安煤炭开采工程技术研究院有限责任公司 矿井通风系统抗灾能力评价方法及装置
CN109118066A (zh) * 2018-07-20 2019-01-01 广州市标准化研究院 一种指数体系模型构建方法
CN109169139A (zh) * 2018-10-16 2019-01-11 东北林业大学 一种松花江干流堤防防护林配置方案综合评价方法
CN109409724A (zh) * 2018-10-19 2019-03-01 中国海洋石油集团有限公司 深水钻井井喷失控风险评价方法
CN109581866A (zh) * 2017-09-28 2019-04-05 中国石油化工股份有限公司 一种抽油机综合评价方法及系统
CN109684484A (zh) * 2018-12-11 2019-04-26 南京大学 一种swot指标体系构建系统
CN109740925A (zh) * 2018-12-29 2019-05-10 精英数智科技股份有限公司 一种基于组合赋权法的煤矿安全风险预警分析方法
CN109993463A (zh) * 2019-04-23 2019-07-09 河南建达工程咨询有限公司 一种综合管廊的工程质量管理评价方法
CN110135708A (zh) * 2019-04-25 2019-08-16 温州大学 基于ahp和信息熵的球阀质量多级模糊综合评价方法
CN110378574A (zh) * 2019-07-01 2019-10-25 山东大学 水下隧道盾构施工开挖面稳定性评价方法、系统及设备
CN110414825A (zh) * 2019-07-23 2019-11-05 华北水利水电大学 一种水文化遗产评价方法
CN110428151A (zh) * 2019-07-18 2019-11-08 国网山东省电力公司电力科学研究院 一种同步调相机油系统的状态评价方法
CN110458390A (zh) * 2019-07-01 2019-11-15 中国石油化工股份有限公司 油田矿场集输类设备的优选评价方法
CN110738435A (zh) * 2019-04-10 2020-01-31 国网浙江省电力有限公司经济技术研究院 一种配电网项目投资决策评价方法
CN110866694A (zh) * 2019-11-14 2020-03-06 国网河北省电力有限公司沧州供电分公司 一种电网建设项目财务评价系统及其方法
CN110910013A (zh) * 2019-11-20 2020-03-24 南方电网能源发展研究院有限责任公司 电力系统项目评价模型的建立方法及评价方法
CN111126853A (zh) * 2019-12-25 2020-05-08 华北水利水电大学 基于模糊fmea的水利工程风险预警分析方法及系统
CN111127234A (zh) * 2019-10-11 2020-05-08 重庆大学 一种突出煤层群开采首采层确定方法及装置
CN111160673A (zh) * 2018-11-07 2020-05-15 内蒙古电力(集团)有限责任公司内蒙古电力经济技术研究院分公司 一种电力建设项目后评价方法和计算设备
CN111199362A (zh) * 2020-01-18 2020-05-26 中煤科工集团重庆研究院有限公司 基于数据驱动的通风系统态势动态评价方法
CN111260235A (zh) * 2020-01-20 2020-06-09 上海电力大学 一种基于模糊综合评价的能源综合应急供应系统评价方法
CN111260187A (zh) * 2020-01-08 2020-06-09 长春工程学院 一种智能矿山地质环境信息评价系统及评价方法
CN111275230A (zh) * 2018-12-05 2020-06-12 辽宁工程技术大学 一种煤矿易自燃煤层安全评价方法
CN111354456A (zh) * 2018-12-21 2020-06-30 广东美的白色家电技术创新中心有限公司 中医体质类型检测方法及装置
CN111369300A (zh) * 2020-03-13 2020-07-03 浙江师范大学 满意度评价方法、装置、计算机设备和可读存储介质
CN111401687A (zh) * 2020-02-14 2020-07-10 重庆国翰能源发展有限公司 功率模块故障诊断方法、装置、设备及存储介质
CN111460371A (zh) * 2020-03-23 2020-07-28 山东大学 一种农产品产地环境风险的评价方法
CN111504778A (zh) * 2020-03-16 2020-08-07 天地科技股份有限公司 液压支架支护能力的检测方法
CN111598429A (zh) * 2020-05-12 2020-08-28 大钊科技唐山有限公司 一种评价起泡剂施工作业效果的方法
CN111612241A (zh) * 2020-05-15 2020-09-01 智慧航海(青岛)科技有限公司 智能船舶路径规划功能实现性的综合评价方法
CN111652487A (zh) * 2020-05-26 2020-09-11 生态环境部南京环境科学研究所 一种自然保护区道路建设项目生态影响评估系统
CN111784166A (zh) * 2020-07-03 2020-10-16 东莞理工学院 一种中低压配电网综合能效评估方法及系统
CN111798146A (zh) * 2020-07-09 2020-10-20 中国第一汽车股份有限公司 一种燃料电池发动机性能评价的方法
CN111859535A (zh) * 2020-06-20 2020-10-30 武汉理工大学 基于ahp-熵权法的极地邮轮减摇鳍选型方法和装置
CN111882210A (zh) * 2020-07-27 2020-11-03 陕西延长石油(集团)有限责任公司 一种基于多层次模糊综合评判的气田总体布局评价方法
CN111914209A (zh) * 2020-05-12 2020-11-10 华北理工大学 一种基于熵值法的排水采气效果模糊综合评价方法
CN111967721A (zh) * 2020-07-23 2020-11-20 国电南京自动化股份有限公司 一种综合能源系统绿色化水平评价方法及系统
CN111967754A (zh) * 2020-08-11 2020-11-20 成都理工大学 基于可持续发展的铁矿尾矿资源综合利用效益评价的方法
CN112116238A (zh) * 2020-09-16 2020-12-22 深圳市维度统计咨询股份有限公司 一种基于指标权重体系设计的满意度评估方法
CN112396331A (zh) * 2020-11-25 2021-02-23 贵州黔西能源开发有限公司 基于层次分析法的煤矿安全风险评估指标体系构建方法
CN112418644A (zh) * 2020-11-18 2021-02-26 中国电建集团昆明勘测设计研究院有限公司 一种结合可信度评估的引水工程结构安全状态评价方法
CN112766729A (zh) * 2021-01-20 2021-05-07 中国人民解放军火箭军工程大学 装备维修训练人员能力评价方法
CN112819354A (zh) * 2021-02-08 2021-05-18 中国地质调查局沈阳地质调查中心 海外矿业项目竞争力评价的方法及装置
CN112855109A (zh) * 2020-12-31 2021-05-28 西南石油大学 基于灰色关联法和层次分析法的压裂酸化选井选层方法
CN112950067A (zh) * 2021-03-30 2021-06-11 国网吉林省电力有限公司四平供电公司 基于模糊综合评价的电力用户用电能效评估方法
CN113077155A (zh) * 2021-04-07 2021-07-06 国家电网有限公司 基于大数据态势感知的电力生产技改项目评价模型
CN113159585A (zh) * 2021-04-25 2021-07-23 中国矿业大学(北京) 基于层次模型的高海拔矿井通风机效能评估方法
CN113205274A (zh) * 2021-05-21 2021-08-03 华设设计集团股份有限公司 一种施工质量定量化排名方法
CN113393078A (zh) * 2021-05-06 2021-09-14 中国标准化研究院 Nqi需求模型构建方法、系统、设备及介质
CN113408878A (zh) * 2021-06-07 2021-09-17 山东电工电气集团有限公司 基于多源信息的电缆隧道运行状态评价方法及区域控制系统
CN113435686A (zh) * 2021-04-28 2021-09-24 国网冀北电力有限公司计量中心 蓄热式电采暖系统评价方法及装置
CN113537708A (zh) * 2021-06-09 2021-10-22 天津电力工程监理有限公司 基于组合赋权法的输变电工程造价管理成效综合评价方法
CN113610383A (zh) * 2021-08-02 2021-11-05 中山大学 大气复合污染观测数据的质量及共享效果评价方法与系统
CN114037347A (zh) * 2021-11-25 2022-02-11 中国矿业大学 一种关闭煤矿采空区煤层气资源选区多层次评价方法
CN114330979A (zh) * 2021-11-11 2022-04-12 中国大唐集团科学技术研究院有限公司火力发电技术研究院 一种燃煤机组智慧电厂建设后评价指标系统
CN115471077A (zh) * 2022-09-16 2022-12-13 生态环境部南京环境科学研究所 一种尾矿库生态修复区生态环境安全评估方法与系统
CN115494881A (zh) * 2022-11-18 2022-12-20 西北工业大学 一种无人机编队协同航迹规划的无约束优化指标赋权方法
CN116384780A (zh) * 2023-06-07 2023-07-04 洪恩流体科技有限公司 一种消防系统安全程度判断方法
CN117541082A (zh) * 2024-01-05 2024-02-09 中国石油大学(华东) 基于油藏-井筒-设备评价指标集成的综合评价方法
CN113361863B (zh) * 2021-05-12 2024-04-30 东南大学 一种基于模糊评价理论的片区雨污分流工程质效评估方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103400044A (zh) * 2013-08-12 2013-11-20 青岛理工大学 一种改进的水环境安全评价分析方法
CN104123680A (zh) * 2014-07-16 2014-10-29 贵州电力试验研究院 一种综合评价电网科技项目的后评估方法
CN104951588A (zh) * 2015-03-16 2015-09-30 中国矿业大学 一种矿井通风系统辅助设计方法
CN105023067A (zh) * 2015-08-04 2015-11-04 环境保护部南京环境科学研究所 基于层次分析法-模糊综合评价的化工项目环境风险评价体系

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103400044A (zh) * 2013-08-12 2013-11-20 青岛理工大学 一种改进的水环境安全评价分析方法
CN104123680A (zh) * 2014-07-16 2014-10-29 贵州电力试验研究院 一种综合评价电网科技项目的后评估方法
CN104951588A (zh) * 2015-03-16 2015-09-30 中国矿业大学 一种矿井通风系统辅助设计方法
CN105023067A (zh) * 2015-08-04 2015-11-04 环境保护部南京环境科学研究所 基于层次分析法-模糊综合评价的化工项目环境风险评价体系

Cited By (94)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106202267A (zh) * 2016-06-30 2016-12-07 四川农业大学 一种黄果柑综合品质评价方法
CN106295976A (zh) * 2016-08-03 2017-01-04 重庆大学 基于层次分析法和模糊综合评价的ipt系统电磁机构性能评价方法
CN106250353A (zh) * 2016-08-10 2016-12-21 广东电网有限责任公司电力科学研究院 一种熵权计算方法和多目标决策方法
CN107766999A (zh) * 2016-08-18 2018-03-06 中核第四研究设计工程有限公司 一种砂岩型铀矿床开发利用的综合评价方法
CN106339798A (zh) * 2016-08-20 2017-01-18 辽宁工程技术大学 一种基于模糊综合评判法的软岩斜井井筒支护体系稳定性评价方法
CN106651169A (zh) * 2016-12-19 2017-05-10 国家电网公司 基于模糊综合评价的配电自动化终端状态评价方法及系统
CN106841545A (zh) * 2017-02-14 2017-06-13 蚌埠学院 基于改进模糊综合评判法的茶叶感官品质评价方法
CN106845870A (zh) * 2017-03-03 2017-06-13 中国水产科学研究院黄海水产研究所 基于灰色关联的模糊层次电厂温排水渔业损害评估方法
CN106845870B (zh) * 2017-03-03 2020-11-24 中国水产科学研究院黄海水产研究所 基于灰色关联的模糊层次电厂温排水渔业损害评估方法
CN107544253B (zh) * 2017-03-17 2020-03-27 中国人民解放军91049部队 基于改进模糊熵权法的大型导弹装备退役安全控制方法
CN107544253A (zh) * 2017-03-17 2018-01-05 中国人民解放军91049部队 基于改进模糊熵权法的大型导弹装备退役安全控制方法
CN107180306A (zh) * 2017-05-24 2017-09-19 西安科技大学 一种煤炭资源有利开采区块加权叠加辨识的技术方法
CN107240033A (zh) * 2017-06-07 2017-10-10 国家电网公司客户服务中心 一种电力识别模型的构建方法及系统
CN107240033B (zh) * 2017-06-07 2021-02-12 国家电网公司客户服务中心 一种电力识别模型的构建方法及系统
CN109581866A (zh) * 2017-09-28 2019-04-05 中国石油化工股份有限公司 一种抽油机综合评价方法及系统
CN107909290A (zh) * 2017-12-07 2018-04-13 北京能源集团有限责任公司 一种技改专修项目评价方法及系统
CN108182544A (zh) * 2018-01-24 2018-06-19 李超 一种农产品的品质评估方法
CN108710984A (zh) * 2018-04-04 2018-10-26 中国地质环境监测院 一种矿山地质环境综合评价方法及系统
CN108710984B (zh) * 2018-04-04 2021-06-08 中国地质环境监测院 一种矿山地质环境综合评价方法及系统
CN108596479A (zh) * 2018-04-24 2018-09-28 东北农业大学 一种评价农业机械化发展水平的指标体系
CN109033561A (zh) * 2018-07-05 2018-12-18 平安煤炭开采工程技术研究院有限责任公司 矿井通风系统抗灾能力评价方法及装置
CN108959791A (zh) * 2018-07-12 2018-12-07 中国船舶重工集团公司第七二四研究所 一种相控阵雷达资源调度效能层级递阶评估方法
CN109118066A (zh) * 2018-07-20 2019-01-01 广州市标准化研究院 一种指数体系模型构建方法
CN109169139A (zh) * 2018-10-16 2019-01-11 东北林业大学 一种松花江干流堤防防护林配置方案综合评价方法
CN109409724A (zh) * 2018-10-19 2019-03-01 中国海洋石油集团有限公司 深水钻井井喷失控风险评价方法
CN111160673A (zh) * 2018-11-07 2020-05-15 内蒙古电力(集团)有限责任公司内蒙古电力经济技术研究院分公司 一种电力建设项目后评价方法和计算设备
CN111275230A (zh) * 2018-12-05 2020-06-12 辽宁工程技术大学 一种煤矿易自燃煤层安全评价方法
CN109684484B (zh) * 2018-12-11 2023-06-09 南京大学 一种swot指标体系构建系统
CN109684484A (zh) * 2018-12-11 2019-04-26 南京大学 一种swot指标体系构建系统
CN111354456A (zh) * 2018-12-21 2020-06-30 广东美的白色家电技术创新中心有限公司 中医体质类型检测方法及装置
CN109740925A (zh) * 2018-12-29 2019-05-10 精英数智科技股份有限公司 一种基于组合赋权法的煤矿安全风险预警分析方法
CN110738435A (zh) * 2019-04-10 2020-01-31 国网浙江省电力有限公司经济技术研究院 一种配电网项目投资决策评价方法
CN109993463A (zh) * 2019-04-23 2019-07-09 河南建达工程咨询有限公司 一种综合管廊的工程质量管理评价方法
CN110135708A (zh) * 2019-04-25 2019-08-16 温州大学 基于ahp和信息熵的球阀质量多级模糊综合评价方法
CN110458390A (zh) * 2019-07-01 2019-11-15 中国石油化工股份有限公司 油田矿场集输类设备的优选评价方法
CN110378574A (zh) * 2019-07-01 2019-10-25 山东大学 水下隧道盾构施工开挖面稳定性评价方法、系统及设备
CN110428151A (zh) * 2019-07-18 2019-11-08 国网山东省电力公司电力科学研究院 一种同步调相机油系统的状态评价方法
CN110414825A (zh) * 2019-07-23 2019-11-05 华北水利水电大学 一种水文化遗产评价方法
CN111127234A (zh) * 2019-10-11 2020-05-08 重庆大学 一种突出煤层群开采首采层确定方法及装置
CN111127234B (zh) * 2019-10-11 2024-01-19 重庆大学 一种突出煤层群开采首采层确定方法及装置
CN110866694A (zh) * 2019-11-14 2020-03-06 国网河北省电力有限公司沧州供电分公司 一种电网建设项目财务评价系统及其方法
CN110910013A (zh) * 2019-11-20 2020-03-24 南方电网能源发展研究院有限责任公司 电力系统项目评价模型的建立方法及评价方法
CN111126853B (zh) * 2019-12-25 2023-08-29 华北水利水电大学 基于模糊fmea的水利工程风险预警分析方法及系统
CN111126853A (zh) * 2019-12-25 2020-05-08 华北水利水电大学 基于模糊fmea的水利工程风险预警分析方法及系统
CN111260187A (zh) * 2020-01-08 2020-06-09 长春工程学院 一种智能矿山地质环境信息评价系统及评价方法
CN111199362A (zh) * 2020-01-18 2020-05-26 中煤科工集团重庆研究院有限公司 基于数据驱动的通风系统态势动态评价方法
CN111199362B (zh) * 2020-01-18 2023-11-17 中煤科工集团重庆研究院有限公司 基于数据驱动的通风系统态势动态评价方法
CN111260235A (zh) * 2020-01-20 2020-06-09 上海电力大学 一种基于模糊综合评价的能源综合应急供应系统评价方法
CN111401687A (zh) * 2020-02-14 2020-07-10 重庆国翰能源发展有限公司 功率模块故障诊断方法、装置、设备及存储介质
CN111369300A (zh) * 2020-03-13 2020-07-03 浙江师范大学 满意度评价方法、装置、计算机设备和可读存储介质
CN111504778B (zh) * 2020-03-16 2023-09-05 天地科技股份有限公司 液压支架支护能力的检测方法
CN111504778A (zh) * 2020-03-16 2020-08-07 天地科技股份有限公司 液压支架支护能力的检测方法
CN111460371A (zh) * 2020-03-23 2020-07-28 山东大学 一种农产品产地环境风险的评价方法
CN111460371B (zh) * 2020-03-23 2022-04-08 山东大学 一种农产品产地环境风险的评价方法
CN111914209A (zh) * 2020-05-12 2020-11-10 华北理工大学 一种基于熵值法的排水采气效果模糊综合评价方法
CN111598429A (zh) * 2020-05-12 2020-08-28 大钊科技唐山有限公司 一种评价起泡剂施工作业效果的方法
CN111612241A (zh) * 2020-05-15 2020-09-01 智慧航海(青岛)科技有限公司 智能船舶路径规划功能实现性的综合评价方法
CN111652487B (zh) * 2020-05-26 2021-07-13 生态环境部南京环境科学研究所 一种自然保护区道路建设项目生态影响评估系统
CN111652487A (zh) * 2020-05-26 2020-09-11 生态环境部南京环境科学研究所 一种自然保护区道路建设项目生态影响评估系统
CN111859535B (zh) * 2020-06-20 2024-04-30 武汉理工大学 基于ahp-熵权法的极地邮轮减摇鳍选型方法和装置
CN111859535A (zh) * 2020-06-20 2020-10-30 武汉理工大学 基于ahp-熵权法的极地邮轮减摇鳍选型方法和装置
CN111784166B (zh) * 2020-07-03 2024-01-16 东莞理工学院 一种中低压配电网综合能效评估方法及系统
CN111784166A (zh) * 2020-07-03 2020-10-16 东莞理工学院 一种中低压配电网综合能效评估方法及系统
CN111798146A (zh) * 2020-07-09 2020-10-20 中国第一汽车股份有限公司 一种燃料电池发动机性能评价的方法
CN111967721A (zh) * 2020-07-23 2020-11-20 国电南京自动化股份有限公司 一种综合能源系统绿色化水平评价方法及系统
CN111882210A (zh) * 2020-07-27 2020-11-03 陕西延长石油(集团)有限责任公司 一种基于多层次模糊综合评判的气田总体布局评价方法
CN111967754A (zh) * 2020-08-11 2020-11-20 成都理工大学 基于可持续发展的铁矿尾矿资源综合利用效益评价的方法
CN112116238A (zh) * 2020-09-16 2020-12-22 深圳市维度统计咨询股份有限公司 一种基于指标权重体系设计的满意度评估方法
CN112418644A (zh) * 2020-11-18 2021-02-26 中国电建集团昆明勘测设计研究院有限公司 一种结合可信度评估的引水工程结构安全状态评价方法
CN112396331A (zh) * 2020-11-25 2021-02-23 贵州黔西能源开发有限公司 基于层次分析法的煤矿安全风险评估指标体系构建方法
CN112855109B (zh) * 2020-12-31 2022-09-16 西南石油大学 基于灰色关联法和层次分析法的压裂酸化选井选层方法
CN112855109A (zh) * 2020-12-31 2021-05-28 西南石油大学 基于灰色关联法和层次分析法的压裂酸化选井选层方法
CN112766729A (zh) * 2021-01-20 2021-05-07 中国人民解放军火箭军工程大学 装备维修训练人员能力评价方法
CN112819354A (zh) * 2021-02-08 2021-05-18 中国地质调查局沈阳地质调查中心 海外矿业项目竞争力评价的方法及装置
CN112950067A (zh) * 2021-03-30 2021-06-11 国网吉林省电力有限公司四平供电公司 基于模糊综合评价的电力用户用电能效评估方法
CN112950067B (zh) * 2021-03-30 2023-05-12 国网吉林省电力有限公司四平供电公司 基于模糊综合评价的电力用户用电能效评估方法
CN113077155A (zh) * 2021-04-07 2021-07-06 国家电网有限公司 基于大数据态势感知的电力生产技改项目评价模型
CN113159585B (zh) * 2021-04-25 2023-07-25 中国矿业大学(北京) 基于层次模型的高海拔矿井通风机效能评估方法
CN113159585A (zh) * 2021-04-25 2021-07-23 中国矿业大学(北京) 基于层次模型的高海拔矿井通风机效能评估方法
CN113435686A (zh) * 2021-04-28 2021-09-24 国网冀北电力有限公司计量中心 蓄热式电采暖系统评价方法及装置
CN113393078A (zh) * 2021-05-06 2021-09-14 中国标准化研究院 Nqi需求模型构建方法、系统、设备及介质
CN113361863B (zh) * 2021-05-12 2024-04-30 东南大学 一种基于模糊评价理论的片区雨污分流工程质效评估方法
CN113205274A (zh) * 2021-05-21 2021-08-03 华设设计集团股份有限公司 一种施工质量定量化排名方法
CN113408878A (zh) * 2021-06-07 2021-09-17 山东电工电气集团有限公司 基于多源信息的电缆隧道运行状态评价方法及区域控制系统
CN113537708A (zh) * 2021-06-09 2021-10-22 天津电力工程监理有限公司 基于组合赋权法的输变电工程造价管理成效综合评价方法
CN113610383A (zh) * 2021-08-02 2021-11-05 中山大学 大气复合污染观测数据的质量及共享效果评价方法与系统
CN114330979A (zh) * 2021-11-11 2022-04-12 中国大唐集团科学技术研究院有限公司火力发电技术研究院 一种燃煤机组智慧电厂建设后评价指标系统
CN114037347A (zh) * 2021-11-25 2022-02-11 中国矿业大学 一种关闭煤矿采空区煤层气资源选区多层次评价方法
CN115471077A (zh) * 2022-09-16 2022-12-13 生态环境部南京环境科学研究所 一种尾矿库生态修复区生态环境安全评估方法与系统
CN115494881B (zh) * 2022-11-18 2023-03-10 西北工业大学 一种无人机编队协同航迹规划的无约束优化指标赋权方法
CN115494881A (zh) * 2022-11-18 2022-12-20 西北工业大学 一种无人机编队协同航迹规划的无约束优化指标赋权方法
CN116384780A (zh) * 2023-06-07 2023-07-04 洪恩流体科技有限公司 一种消防系统安全程度判断方法
CN117541082A (zh) * 2024-01-05 2024-02-09 中国石油大学(华东) 基于油藏-井筒-设备评价指标集成的综合评价方法
CN117541082B (zh) * 2024-01-05 2024-04-05 中国石油大学(华东) 基于油藏-井筒-设备评价指标集成的综合评价方法

Similar Documents

Publication Publication Date Title
CN105469196A (zh) 一种矿井建设项目过程后评价的综合评价方法及系统
Wu et al. An intuitionistic fuzzy multi-criteria framework for large-scale rooftop PV project portfolio selection: Case study in Zhejiang, China
CN106339536B (zh) 基于水污染指数法和云模型的水质综合评价方法
CN105975735A (zh) 一种用于电力设备健康状态评估的建模方法
CN103632203A (zh) 一种基于综合评价的配电网供电区域划分方法
CN105678481A (zh) 一种基于随机森林模型的管线健康状态评估方法
CN104021300B (zh) 一种基于分布式电源接入对配电网影响的综合评估方法
CN111967721A (zh) 一种综合能源系统绿色化水平评价方法及系统
CN104837184A (zh) 一种基于区间三角模糊数的异构无线网络选择方法
CN106355540A (zh) 一种基于gra‑bp神经网络的中小型水库大坝安全评价方法
CN106127242A (zh) 基于集成学习的年极端降水预测系统及其预测方法
CN106355360A (zh) 一种考虑修正系数的配电网中压项目紧迫性评价方法
CN105701693A (zh) 一种基于深度学习的企业信用评价方法
CN109697566A (zh) 机电产品加工工艺评价系统及其评价方法
CN104834975A (zh) 一种基于智能算法优化组合的电网负荷率预测方法
CN108959791A (zh) 一种相控阵雷达资源调度效能层级递阶评估方法
Dang et al. A novel multivariate grey model for forecasting periodic oscillation time series
Weng et al. Private-sector partner selection for public-private partnership projects based on improved CRITIC-EMW weight and GRA-VIKOR method
CN114021873A (zh) 一种数据指标量化方法和智慧园区企业价值评价系统
CN113850516A (zh) 基于t-s模糊神经网络的水质评价方法
CN116596303A (zh) 一种干旱风险评估与区划方法、系统、介质、设备及终端
CN116307913A (zh) 一种综合多层次的污水处理设施污染物削减效能评估方法及系统
CN116823008A (zh) 一种园区能源利用效率评估方法、系统、设备和存储介质
CN112766726A (zh) 一种电网作业标准成本调整系数的制定方法
CN108694527B (zh) 一种配电网评价方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20160406

RJ01 Rejection of invention patent application after publication