CN105350512A - 一种碳酸盐岩块石填料强夯加冲击碾压的施工方法 - Google Patents
一种碳酸盐岩块石填料强夯加冲击碾压的施工方法 Download PDFInfo
- Publication number
- CN105350512A CN105350512A CN201510634981.XA CN201510634981A CN105350512A CN 105350512 A CN105350512 A CN 105350512A CN 201510634981 A CN201510634981 A CN 201510634981A CN 105350512 A CN105350512 A CN 105350512A
- Authority
- CN
- China
- Prior art keywords
- rock
- impact
- rolling
- construction method
- carbonate rock
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/046—Improving by compacting by tamping or vibrating, e.g. with auxiliary watering of the soil
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Road Paving Structures (AREA)
Abstract
本发明公开了一种碳酸盐岩块石填料强夯加冲击碾压的施工方法:首先,铺摊碳酸盐岩块石填料至6m高度,采用4000kN?m能级强夯机以一定间距进行点夯;完成夯击后,将场地平整,采用冲击式压路机对填筑体进行补强。本发明能使得深层和表层地基都得到有效加固,是处理块石地基的较好方法,也能够显著快加施工进度,降低工程成本。
Description
技术领域
本发明涉及地基夯实处理技术,特别是处理碳酸盐岩块石地基强夯结合冲击碾压的方法。
背景技术
随着建筑用地日趋紧张,开山填沟造地的人工填方地基将成为解决建设用地的重要途径。在山区人工填方地基场地的基础决定着整个工程项目结构的稳定性、耐久性和使用功能。对于高填方地基,特别是填石地基,传统的分层碾压和重夯都有较大的局限性,强夯的有效加固深度达4.0m,有效影响深度在5.0~6.0m,冲击碾压影响深度在1.5m左右,都无法满足部分工程地基更高的密实、均匀、稳定性的需求。因此利用强夯加冲击碾压技术的有效结合,能够解决分层碾压、重夯技术的压实功能低、级配和粒径要求高、工期长、施工质量难以保证等局限。两者结合使得深层和表层地基都得到有效加固,是处理块石高填方地基的较好方法,能显著减小工后沉降,提高地基强度和均匀性,也可以加快施工进度,降低工程成本,达到工程要求。
发明内容
本发明要解决的技术问题是:提供一种强夯加冲击碾压的施工方法,解决部分工程对碳酸盐岩块石填料密实度和稳定性的更高需求,并且能够短缩工期,提高工程质量。
本发明的技术方案为:一种碳酸盐岩块石填料强夯加冲击碾压的施工方法,包括对施工场地进行清表、整平,标记施工界限、边界线以及测量地基初始高程,其特征在于:对碳酸盐岩块石填料分层堆填后,采用强夯机进行点夯,强夯完毕后,整平场地,使用冲击式压路机对填筑体补强。所述强夯机为4000kN•m能级。碳酸盐岩块石填料铺摊厚度为6m。强夯处理时,夯击第一遍间距按5m正方形布点,第二遍夯点位于第一遍夯点中间,单点击数≥10击。对填筑体进行补强时,采用三边双轮25KJ冲击式压路机冲压,冲压遍数≥20遍。
碳酸盐岩填料强夯加冲击碾压的施工方法有以下主要步骤:
步骤一、在强夯前对施工场地进行清表、整平,标记施工界限、边界线以及测量地基初始高程。对碳酸盐岩块石填料分层堆填后,采用强夯机进行点夯,强夯完毕后,整平场地,使用冲击式压路机对填筑体补强。
步骤二、将步骤一中碳酸盐岩填料分层虚铺至6m高度,采用4000kN•m能级强夯法处理。
步骤三、填筑体每层强夯处理完成后,必须整平,然后采用冲击碾压进行补强。
步骤四、完成一遍作业后,用高精度水准仪测量填筑体平均沉降量,当填筑体平均沉降量满足标准时停止碾压。在碾压后填筑体的基础上,不断重复上述步骤二、三,直至填筑到填方体的设计标高。
本发明采用了强夯与冲击碾压联合施工,能够提高地基的强度和均匀性,也可以加快施工进度,降低工程成本,并且满足设计和规范要求,工程质量优良。
附图说明
图1为本发明流程示意图。
具体实施方式
一种碳酸盐岩填料强夯加冲击碾压的施工方法,该方法包括以下具体步骤:
步骤一、在强夯前对施工场地进行清表、整平,标记施工界限、边界线以及测量地基初始高程。
步骤二、将碳酸盐岩填料分层虚铺至6m高度,采用4000kN•m能级强夯法处理。强夯处理时,夯击第一遍间距按5m正方形布点,第二遍夯点位于第一遍夯点中间,单点击数≥10击。以保证填筑体厚度在强夯处理的有效处理深度范围内,同时保证夯击的均匀性。
步骤三、填筑体每层强夯处理完成后,将场地平整,然后进行冲击补强。对填筑体进行补强时,采用三边双轮25KJ冲击式压路机冲压,冲压遍数≥20遍。
步骤四、完成一遍作业后,用高精度水准仪测量填筑体平均沉降量,当填筑体平均沉降量满足标准时停止碾压。在碾压后填筑体的基础上,不断重复上述步骤二、三,直至填筑到填方体的设计标高。
Claims (5)
1.一种碳酸盐岩块石填料强夯加冲击碾压的施工方法,包括对施工场地进行清表、整平,标记施工界限、边界线以及测量地基初始高程,其特征在于:对碳酸盐岩块石填料分层堆填后,采用强夯机进行点夯,强夯完毕后,整平场地,使用冲击式压路机对填筑体补强。
2.根据权利要求1所述的一种碳酸盐岩块石填料强夯加冲击碾压的施工方法,其特征在于:所述强夯机为4000kN•m能级。
3.根据权利要求1所述的一种碳酸盐岩块石填料强夯加冲击碾压的施工方法,其特征在于:碳酸盐岩块石填料铺摊厚度为6m。
4.根据权利要求1所述的一种碳酸盐岩块石填料强夯加冲击碾压的施工方法,其特征在于:强夯处理时,夯击第一遍间距按5m正方形布点,第二遍夯点位于第一遍夯点中间,单点击数≥10击。
5.根据权利要求1所述的一种碳酸盐岩块石填料强夯加冲击碾压的施工方法,其特征在于:对填筑体进行补强时,采用三边双轮25KJ冲击式压路机冲压,冲压遍数≥20遍。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510634981.XA CN105350512A (zh) | 2015-09-30 | 2015-09-30 | 一种碳酸盐岩块石填料强夯加冲击碾压的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510634981.XA CN105350512A (zh) | 2015-09-30 | 2015-09-30 | 一种碳酸盐岩块石填料强夯加冲击碾压的施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105350512A true CN105350512A (zh) | 2016-02-24 |
Family
ID=55326564
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510634981.XA Pending CN105350512A (zh) | 2015-09-30 | 2015-09-30 | 一种碳酸盐岩块石填料强夯加冲击碾压的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105350512A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106087946A (zh) * | 2016-06-13 | 2016-11-09 | 贵州正业工程技术投资有限公司 | 一种碳酸盐岩大块石强夯复合换填置换地基加固方法 |
CN108301393A (zh) * | 2018-02-12 | 2018-07-20 | 中国科学院武汉岩土力学研究所 | 一种浅层吹填珊瑚砂地基洒水冲击碾压施工工法 |
CN113969524A (zh) * | 2021-10-20 | 2022-01-25 | 中交路桥华南工程有限公司 | 填石路堤的施工方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1263188A (zh) * | 1999-02-12 | 2000-08-16 | 蓝派冲击压实技术开发(北京)有限公司 | 利用冲击压来处理道路的方法 |
CN2494837Y (zh) * | 2001-07-30 | 2002-06-12 | 北京欣路特科技发展有限公司 | 自行式强夯机 |
JP2002285539A (ja) * | 2001-03-26 | 2002-10-03 | Fumio Kinoshita | 改良土壌の締固方法及び改良土壌の締固装置及び柱状体 |
CN102251512A (zh) * | 2011-05-05 | 2011-11-23 | 西安建筑科技大学 | 振动碾压与强夯联合压实黄土高填方体的施工方法 |
CN102518117A (zh) * | 2011-11-16 | 2012-06-27 | 辽宁省石油化工规划设计院有限公司 | 一种振冲碎石桩与强夯组合复合地基的施工方法 |
CN102619208A (zh) * | 2012-04-18 | 2012-08-01 | 贵州正业工程技术投资有限公司 | 一种碳酸盐岩大块石填料原位试验方法 |
CN103114569A (zh) * | 2013-02-07 | 2013-05-22 | 山西机械化建设集团公司 | 超高能级直接强夯进行低含水量湿陷性黄土处理工艺 |
-
2015
- 2015-09-30 CN CN201510634981.XA patent/CN105350512A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1263188A (zh) * | 1999-02-12 | 2000-08-16 | 蓝派冲击压实技术开发(北京)有限公司 | 利用冲击压来处理道路的方法 |
JP2002285539A (ja) * | 2001-03-26 | 2002-10-03 | Fumio Kinoshita | 改良土壌の締固方法及び改良土壌の締固装置及び柱状体 |
CN2494837Y (zh) * | 2001-07-30 | 2002-06-12 | 北京欣路特科技发展有限公司 | 自行式强夯机 |
CN102251512A (zh) * | 2011-05-05 | 2011-11-23 | 西安建筑科技大学 | 振动碾压与强夯联合压实黄土高填方体的施工方法 |
CN102518117A (zh) * | 2011-11-16 | 2012-06-27 | 辽宁省石油化工规划设计院有限公司 | 一种振冲碎石桩与强夯组合复合地基的施工方法 |
CN102619208A (zh) * | 2012-04-18 | 2012-08-01 | 贵州正业工程技术投资有限公司 | 一种碳酸盐岩大块石填料原位试验方法 |
CN103114569A (zh) * | 2013-02-07 | 2013-05-22 | 山西机械化建设集团公司 | 超高能级直接强夯进行低含水量湿陷性黄土处理工艺 |
Non-Patent Citations (1)
Title |
---|
王志文: "浅层软土地基的组合加固法-浅谈浦东国际机场第二跑道基础的地基处理施工", 《上海空港》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106087946A (zh) * | 2016-06-13 | 2016-11-09 | 贵州正业工程技术投资有限公司 | 一种碳酸盐岩大块石强夯复合换填置换地基加固方法 |
CN108301393A (zh) * | 2018-02-12 | 2018-07-20 | 中国科学院武汉岩土力学研究所 | 一种浅层吹填珊瑚砂地基洒水冲击碾压施工工法 |
CN113969524A (zh) * | 2021-10-20 | 2022-01-25 | 中交路桥华南工程有限公司 | 填石路堤的施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104131546B (zh) | 一种湿陷性黄土地基的处理方法 | |
CN204356594U (zh) | 无砟轨道膨胀土路堑-基床构造 | |
CN102251512A (zh) | 振动碾压与强夯联合压实黄土高填方体的施工方法 | |
CN101016740A (zh) | 多重增压快速固结密实软土地基处理方法 | |
CN110761264A (zh) | 一种滨海淤泥软土地基二次强夯碎石置换加固方法 | |
CN101575848A (zh) | 组合锤法地基处理方法 | |
CN105350512A (zh) | 一种碳酸盐岩块石填料强夯加冲击碾压的施工方法 | |
CN107869138A (zh) | 高填方石料换填地基处理施工方法 | |
CN105200973A (zh) | 一种软弱地基综合处理方法 | |
CN108570909A (zh) | 一种粉细砂路基的填筑压实方法 | |
CN101787689B (zh) | 昔格达土高边坡填方的强夯施工方法 | |
CN103993533B (zh) | 用于黄土地区高填方路堤的综合压实方法 | |
CN104818658B (zh) | 一种湿陷性黄土地基层上道路拓宽方法 | |
CN104727295A (zh) | 预成孔填料置换平锤强夯法 | |
CN102677681A (zh) | 大型土方快速回填分层处理方法 | |
CN105369797A (zh) | 湿陷性黄土真空辐射固结法 | |
CN104404918B (zh) | 采用复合土工膜和部分换填粘土修补粘土贯穿裂缝的方法 | |
CN103122631A (zh) | 软土地基堆载冲压加固法 | |
CN110029652A (zh) | 一种减少湿陷性黄土工后沉降的施工工艺 | |
CN102635044B (zh) | 一种强夯对路床挖方路基的处理方法 | |
CN207003417U (zh) | 山区弃碴回填体沉降及稳定控制结构 | |
CN206477351U (zh) | 用于大厚度高湿陷性黄土地基的素土挤密桩 | |
CN106906816B (zh) | 一种改善软土地基预制桩沉桩挤土效应的方法 | |
CN112900176B (zh) | 一种高填方的土石路堤的填筑方法 | |
CN205934899U (zh) | 一种提高强夯夯击质量的消能结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |