CN105207119A - Electrified span construction method for high-voltage wires and protective device of construction - Google Patents

Electrified span construction method for high-voltage wires and protective device of construction Download PDF

Info

Publication number
CN105207119A
CN105207119A CN201510579220.9A CN201510579220A CN105207119A CN 105207119 A CN105207119 A CN 105207119A CN 201510579220 A CN201510579220 A CN 201510579220A CN 105207119 A CN105207119 A CN 105207119A
Authority
CN
China
Prior art keywords
assembly pulley
head end
conducting wires
voltage conducting
insulation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510579220.9A
Other languages
Chinese (zh)
Other versions
CN105207119B (en
Inventor
李卫民
张凯
王恩祥
张剑
齐楠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Liaoning Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Liaoning Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510579220.9A priority Critical patent/CN105207119B/en
Publication of CN105207119A publication Critical patent/CN105207119A/en
Application granted granted Critical
Publication of CN105207119B publication Critical patent/CN105207119B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses an electrified span construction method for high-voltage wires. The method includes the following specific steps that 1, an aerial constructor lifts a pulley block I at the head end and a pulley block II at the head end, and then climbs a ladder stand to the two intact high-voltage wires, and all pulley blocks I and pulley blocks II are sequentially hung onto the two intact high-voltage wires through pulleys located on the outer sides of the pulley blocks; 2, the tail end of an insulated hauling rope is tied on a temporary ground anchor by a ground constructor, the head end of the insulated hauling rope and the head end of an insulated digging rope are tied with balance weights respectively to be thrown over a crossed span object, the head end of the insulated hauling rope and the head end of the insulated digging rope are tied to temporary ground anchors, and the insulated hauling rope and the insulated digging rope are tightened and then inserted in the ground to be fixed through the temporary ground anchors; 3, an old high-voltage wire to be replaced is placed on the insulated hauling rope, then one end of the old high-voltage wire to be replaced is integrally connected with one end of a new high-voltage wire, the new high-voltage wire is dragged to the other end from one end of the insulated hauling rope, and then the new high-voltage wire is mounted on a corresponding cross arm by one constructor.

Description

A kind of high-voltage conducting wires live across construction method and protector thereof
Technical field
The present invention relates to a kind of high-voltage conducting wires live across construction method and protector thereof.
Background technology
Along with developing rapidly of electric power system, bring many transmission line improvement projects, topmost when meeting customer charge, change high-voltage conducting wires.And when changing high-voltage conducting wires, relate to the problem of scissors crossing below many high-voltage conducting wires, such as: span transmission line, low-voltage distribution wire, highway, river, building construction etc. below high-voltage conducting wires.Before the construction of leap district restringing, need many manpowers to set up multiple crossing frame, cost is higher, complicated operation, the engineering time and interruption duration long.Particularly need when Midspan sag, highway to ask for instructions to relevant department in advance, need after approval to fulfil assignment at the appointed time, after instruction, the stand-by period is long, and affect the duration, the activity duration is short, and operating personnel's operational pressure is large, labour intensity is high.
Summary of the invention
The present invention is to solve the problems of the technologies described above, and provides a kind of and reduces construction cost, easy construction, a kind of high-voltage conducting wires live across construction method of shortening engineering time and interruption duration and protector thereof.
Technical solution of the present invention is:
A kind of high-voltage conducting wires live across construction method, its step is as follows:
1, two intact high-voltage conducting wires between the pre-replacement high-voltage conducting wires crossing over side, district set up cat ladder respectively, the assembly pulley I of head end and the assembly pulley II of head end is mentioned respectively by two aerial workmens, climb cat ladder respectively to two intact high-voltage conducting wires places, each assembly pulley I and assembly pulley II is hung on two intact high-voltage conducting wires by the pulley outside it respectively successively;
2, temporary ground anchor is built on leap opposite side ground, district, by the tail end tying-up temporary ground anchor of ground construction personnel by insulation pull rope, pull insulation pull rope head end and insulation stay cord that the assembly pulley I of head end and assembly pulley II is pulled upward to scissors crossing thing from high-voltage conducting wires again, by insulation pull rope head end and insulation stay cord head end respectively tying-up counterweight got rid of above scissors crossing thing, temporary ground anchor is built on leap opposite side ground, district, in insulation pull rope head end and insulation stay cord head end tying-up temporary ground anchor, and fix being inserted in ground by temporary ground anchor after insulation pull rope and the tension of insulation stay cord,
3, by the old high-voltage conducting wires of pre-replacement from cross-arm pull down be placed on insulation pull rope on, again old high-voltage conducting wires one end of pre-replacement and new high-voltage conducting wires one end are linked together, the high-voltage conducting wires other end of traction pre-replacement makes new high-voltage conducting wires be dragged to the other end from one end on insulation pull rope, then is arranged on corresponding cross-arm by new high-voltage conducting wires by workmen;
4, to dismantle the temporary ground anchor of insulation pull rope head end and insulation stay cord head end, and the counterweight of insulation pull rope and insulation stay cord head end was got rid of in the other direction above scissors crossing thing, assembly pulley I and assembly pulley II is all moved to aerial workmen position by ground construction personnel, and by aerial workmen assembly pulley I and assembly pulley II pulled down and throw away to ground, aerial workmen removes cat ladder, temporary ground anchor of dismantling at the ground that falls.
A protector for high-voltage conducting wires live across construction, comprises multiple assembly pulley I and assembly pulley II; Described assembly pulley I and assembly pulley II is made up of guide roller frame and two pulleys be arranged in guide roller frame, and be provided with opening between be located thereon on guide roller frame two pulleys, distance-detecting rope is connected between adjacent two assembly pulley I and adjacent two assembly pulley II, the assembly pulley I being positioned at head end is connected with insulation stay cord, this protector is also provided with insulation pull rope, described insulation pull rope is penetrated by the assembly pulley II of head end, the staggered pulley walked around inside assembly pulley I and assembly pulley II successively, and passed by the tail end of assembly pulley I or assembly pulley II.
The invention has the beneficial effects as follows: adopt assembly pulley I and assembly pulley II can the intact high-voltage conducting wires of between pre-replacement high-voltage conducting wires two slide arbitrarily, and protective frame effect is played after the staggered insulation pull rope walked around and the tension of insulation stay cord between each assembly pulley I and assembly pulley II, avoid the many cumbersome process setting up crossing frame in circuit scissors crossing place, it also avoid acrossing highway, high-speed railway, alive circuits etc. are important needs closed channel and circuit power-off, without the need to asking relevant department for instructions in advance, can be undertaken by construction plan, without the need to waiting for, great convenience is provided to power department construction operation, save the construction operation time, save many man power and materials simultaneously.This construction method is easy to workmen and grasps, easy and simple to handle, can construct in physical features circumstance complication location, overcomes because many physical features circumstance complications can not set up the construction difficult problem of crossing frame.
Accompanying drawing explanation
Fig. 1 is construction schematic diagram of the present invention;
Fig. 2 is the schematic diagram of high-voltage conducting wires live across construction protection device of the present invention;
Fig. 3 is the structural representation of Fig. 1 middle pulley group I and assembly pulley II;
In figure: 1-assembly pulley I, 2-assembly pulley II, 3-distance-detecting rope, 4-insulate stay cord, and 5-insulate pull rope, 6-high-voltage conducting wires, 7-cat ladder, 8-temporary ground anchor, 101-guide roller frame, 102-pulley.
Embodiment
As shown in the figure, a kind of high-voltage conducting wires live across construction method, its step is as follows:
1, adopt the protector of high-voltage conducting wires 6 live across construction, the protector of described high-voltage conducting wires 6 live across construction, comprises multiple assembly pulley I1 and assembly pulley II2, described assembly pulley I1 and assembly pulley II2 is made up of guide roller frame 101 and two pulleys 102 be arranged in guide roller frame 101, and be provided with opening between two pulleys 102 be located thereon on guide roller frame 101, distance-detecting rope 3 is connected between adjacent two assembly pulley I1 and adjacent two assembly pulley II2, the assembly pulley I1 being positioned at head end is connected with insulation stay cord 4, this protector is also provided with insulation pull rope 5, described insulation pull rope 5 is penetrated by the assembly pulley II2 of head end, the staggered pulley 102 walked around inside assembly pulley I1 and assembly pulley II2 successively, and passed by the tail end of assembly pulley I1 or assembly pulley II2,
2, two intact high-voltage conducting wires 6 between the pre-replacement high-voltage conducting wires 6 crossing over side, district set up cat ladder 7 respectively, the assembly pulley I1 of head end and the assembly pulley II2 of head end is mentioned respectively by two aerial workmens, climb intact high-voltage conducting wires 6 place of cat ladder 7 to two respectively, each assembly pulley I1 and assembly pulley II2 is hung on two intact high-voltage conducting wires 6 by the pulley 102 outside it respectively successively;
3, temporary ground anchor 8 is built on leap opposite side ground, district, by the tail end tying-up temporary ground anchor 8 of ground construction personnel by insulation pull rope 5, pull insulation pull rope 5 head end and insulation stay cord 4 that the assembly pulley I1 of head end and assembly pulley II2 is pulled upward to scissors crossing thing from high-voltage conducting wires 6 again, by insulation pull rope 5 head end and insulation stay cord 4 head end respectively tying-up counterweight got rid of above scissors crossing thing, temporary ground anchor 8 is built on leap opposite side ground, district, in insulation pull rope 5 head end and insulation stay cord 4 head end tying-up temporary ground anchor 8, and be inserted in ground by temporary ground anchor 8 after insulation pull rope 5 and insulation stay cord 4 being strained and fix,
4, by the old high-voltage conducting wires 6 of pre-replacement from cross-arm pull down be placed on insulation pull rope 5 on, again old high-voltage conducting wires 6 one end of pre-replacement and new high-voltage conducting wires 6 one end are linked together, high-voltage conducting wires 6 other end of traction pre-replacement makes new high-voltage conducting wires 6 be dragged to the other end from one end on insulation pull rope 5, then is arranged on corresponding cross-arm by new high-voltage conducting wires 6 by workmen;
5, to dismantle the temporary ground anchor 8 of insulation pull rope 5 head end and insulation stay cord 4 head end, and the counterweight of insulation pull rope 5 and insulation stay cord 4 head end was got rid of in the other direction above scissors crossing thing, assembly pulley I1 and assembly pulley II2 is all moved to aerial workmen position by ground construction personnel, and by aerial workmen assembly pulley I1 and assembly pulley II2 pulled down and throw away to ground, aerial workmen removes cat ladder 7, temporary ground anchor 8 of dismantling at the ground that falls.

Claims (2)

1. a high-voltage conducting wires live across construction method, is characterized in that, concrete steps are as follows:
1) two intact high-voltage conducting wires, between the pre-replacement high-voltage conducting wires crossing over side, district set up cat ladder respectively, the assembly pulley I of head end and the assembly pulley II of head end is mentioned respectively by two aerial workmens, climb cat ladder respectively to two intact high-voltage conducting wires places, each assembly pulley I and assembly pulley II is hung on two intact high-voltage conducting wires by the pulley outside it respectively successively;
2), temporary ground anchor is built on leap opposite side ground, district, by the tail end tying-up temporary ground anchor of ground construction personnel by insulation pull rope, pull insulation pull rope head end and insulation stay cord that the assembly pulley I of head end and assembly pulley II is pulled upward to scissors crossing thing from high-voltage conducting wires again, by insulation pull rope head end and insulation stay cord head end respectively tying-up counterweight got rid of above scissors crossing thing, temporary ground anchor is built on leap opposite side ground, district, in insulation pull rope head end and insulation stay cord head end tying-up temporary ground anchor, and fix being inserted in ground by temporary ground anchor after insulation pull rope and the tension of insulation stay cord,
3), by the old high-voltage conducting wires of pre-replacement from cross-arm pull down be placed on insulation pull rope on, again old high-voltage conducting wires one end of pre-replacement and new high-voltage conducting wires one end are linked together, the high-voltage conducting wires other end of traction pre-replacement makes new high-voltage conducting wires be dragged to the other end from one end on insulation pull rope, then is arranged on corresponding cross-arm by new high-voltage conducting wires by workmen;
4), to dismantle the temporary ground anchor of insulation pull rope head end and insulation stay cord head end, and the counterweight of insulation pull rope and insulation stay cord head end was got rid of in the other direction above scissors crossing thing, assembly pulley I and assembly pulley II is all moved to aerial workmen position by ground construction personnel, and by aerial workmen assembly pulley I and assembly pulley II pulled down and throw away to ground, aerial workmen removes cat ladder, temporary ground anchor of dismantling at the ground that falls.
2. a protector for high-voltage conducting wires live across construction, comprises multiple assembly pulley I and assembly pulley II; Described assembly pulley I and assembly pulley II is made up of guide roller frame and two pulleys be arranged in guide roller frame, and be provided with opening between be located thereon on guide roller frame two pulleys, distance-detecting rope is connected between adjacent two assembly pulley I and adjacent two assembly pulley II, the assembly pulley I being positioned at head end is connected with insulation stay cord, this protector is also provided with insulation pull rope, described insulation pull rope is penetrated by the assembly pulley II of head end, the staggered pulley walked around inside assembly pulley I and assembly pulley II successively, and passed by the tail end of assembly pulley I or assembly pulley II.
CN201510579220.9A 2015-09-12 2015-09-12 Electrified span construction method for high-voltage wires and protective device of construction Active CN105207119B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510579220.9A CN105207119B (en) 2015-09-12 2015-09-12 Electrified span construction method for high-voltage wires and protective device of construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510579220.9A CN105207119B (en) 2015-09-12 2015-09-12 Electrified span construction method for high-voltage wires and protective device of construction

Publications (2)

Publication Number Publication Date
CN105207119A true CN105207119A (en) 2015-12-30
CN105207119B CN105207119B (en) 2017-04-19

Family

ID=54954632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510579220.9A Active CN105207119B (en) 2015-09-12 2015-09-12 Electrified span construction method for high-voltage wires and protective device of construction

Country Status (1)

Country Link
CN (1) CN105207119B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108512123A (en) * 2018-06-13 2018-09-07 贵州电网有限责任公司 A kind of quick close-up device for ultra-high-tension power transmission line

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201315444Y (en) * 2008-11-20 2009-09-23 四川电力送变电建设公司 Suspended cable basket blocking net charged crossing support
CN201355751Y (en) * 2009-01-23 2009-12-02 湖北省输变电工程公司 Electrified spanning frame of insulated cable net
JP2011172448A (en) * 2010-02-22 2011-09-01 Chugoku Electric Power Co Inc:The Device for preventing guide rope from dropping down, and method for stretching guide rope
CN203377546U (en) * 2013-08-05 2014-01-01 国家电网公司 High speed railway spanning construction apparatus
CN203722136U (en) * 2014-03-01 2014-07-16 安徽送变电工程公司 Insulation rope net apparatus for railway crossing tension stringing construction
CN204424793U (en) * 2014-12-29 2015-06-24 国家电网公司 A kind of block crossing frame of power circuit
CN204577983U (en) * 2015-04-30 2015-08-19 国网山西省电力公司信息通信分公司 A kind of coaster setting up leads span net

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201315444Y (en) * 2008-11-20 2009-09-23 四川电力送变电建设公司 Suspended cable basket blocking net charged crossing support
CN201355751Y (en) * 2009-01-23 2009-12-02 湖北省输变电工程公司 Electrified spanning frame of insulated cable net
JP2011172448A (en) * 2010-02-22 2011-09-01 Chugoku Electric Power Co Inc:The Device for preventing guide rope from dropping down, and method for stretching guide rope
CN203377546U (en) * 2013-08-05 2014-01-01 国家电网公司 High speed railway spanning construction apparatus
CN203722136U (en) * 2014-03-01 2014-07-16 安徽送变电工程公司 Insulation rope net apparatus for railway crossing tension stringing construction
CN204424793U (en) * 2014-12-29 2015-06-24 国家电网公司 A kind of block crossing frame of power circuit
CN204577983U (en) * 2015-04-30 2015-08-19 国网山西省电力公司信息通信分公司 A kind of coaster setting up leads span net

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108512123A (en) * 2018-06-13 2018-09-07 贵州电网有限责任公司 A kind of quick close-up device for ultra-high-tension power transmission line
CN108512123B (en) * 2018-06-13 2024-02-02 贵州电网有限责任公司 Quick net sealing device for high-voltage transmission line

Also Published As

Publication number Publication date
CN105207119B (en) 2017-04-19

Similar Documents

Publication Publication Date Title
CN102290742B (en) Tension stringing construction technology
CN105490213A (en) Equipment and method for installing wires of overhead power transmission line
CN102623926B (en) Distant equipotential tackle and method for realizing charged equipotential access by using same
CN105977863B (en) Power transmission line unmanned machine shooting rope has a power failure and live-line maintenance operation method
CN101442194A (en) Spanning method for ultra, extra high voltage line construction without crossover frame
CN204316007U (en) A kind of transmission line crossing construction device
CN106099757A (en) A kind of transmission line insulator crosses over crane span structure and construction technology thereof
CN101707335A (en) Large cable laying device
CN105207119A (en) Electrified span construction method for high-voltage wires and protective device of construction
CN101966823B (en) Carrier cable crossing frame and erecting method thereof
CN204190260U (en) A kind of high pressure power transmission and distribution cable sets up facility across road
CN102593759B (en) One-pulling-two expansion and construction process of large-section lead
CN104836156A (en) Synthetic insulator simple ladder
CN102611057A (en) Crossing mesh
CN104393524B (en) Avoid setting up using aerial earth wire extension pulley group job and cross over frame construction method
CN204376311U (en) The heavy electric power cable high-altitude of lifting formula is handed over across unfolding device
CN105896382A (en) Overhead line tension device and method
CN203445520U (en) Live spanning device
CN107834425B (en) grounding protection device for overhead conductor replacement construction
CN105006773A (en) Operating method for unanchored ground conductor of power transmission line
CN103532052A (en) Live erection of simple crossing structure on ADSS (all-dielectric self-supporting optic fiber cable) and implementation method
CN205791244U (en) Overhead transmission line take-up device
CN101949117A (en) Safety insulating net structure of highway
CN104682268A (en) Method for constructing compact double-loop overhead line by adoption of flying powered parachute
CN107947029A (en) A kind of distribution line crosses over shelves thread-changing coaster and its thread-changing method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Cui Jisheng

Inventor after: Li Weimin

Inventor after: Zhang Kai

Inventor after: Wang Enxiang

Inventor after: Zhang Jian

Inventor after: Qi Nan

Inventor before: Li Weimin

Inventor before: Zhang Kai

Inventor before: Wang Enxiang

Inventor before: Zhang Jian

Inventor before: Qi Nan

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant