- CN105195530A CN105195530A CN201510674070.XA CN201510674070A CN105195530A CN 105195530 A CN105195530 A CN 105195530A CN 201510674070 A CN201510674070 A CN 201510674070A CN 105195530 A CN105195530 A CN 105195530A
- Authority
- CN
- China
- Prior art keywords
- steel plate
- cooling bed
- steel
- cold bed
- steel plates
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21B—ROLLING OF METAL
- B21B43/00—Cooling beds, whether stationary or moving; Means specially associated with cooling beds, e.g. for braking work or for transferring it to or from the bed
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Metal Rolling (AREA)
Abstract
本发明提供了一种轧钢用冷床的装载方法,其步骤包括:当钢板进入冷床区域时,第一块钢板采用头部定位或者尾部定位的方法摆放,后每一块钢板判断钢板长度是否达到冷床区域宽度的一半再进行摆放,依次摆放至布满冷床区域的长度;其中,当钢板长度大于冷床区域宽度一半时,采用与上一块钢板相同定位的方法摆放钢板;当钢板长度小于冷床区域宽度一半时,采用与上一块钢板头尾交错定位的方法摆放钢板。本发明在保证现有冷床钢板负载量的基础上,对短钢板采用头尾交错定位的方式摆放装载上冷床,从而增加了冷床的钢板负载量。本发明不用改变现有轧钢用冷床的基本结构,仅改变控制装载方法即可实现,成本低,具有很强的实用性。
Description
技术领域
本发明涉及冶金轧钢领域,具体是指一种轧钢用冷床的装载方法。
背景技术
冷床是冶金轧钢行业对轧制后产品进行自然冷却的工作台面,其负载量,即冷床上面可以摆放的钢板数量,直接影响了整条生产线的生产效率。现有的冷床一般由若干根活动梁排列组成,在活动梁上方摆放钢板。冷床钢板的摆放方式有:1、头部定位,即所有钢板以头部为标准到达冷床的最前端对齐摆放;2、尾部定位,即所有钢板以尾部为标准对齐到冷床的最后端对齐摆放。当生产厚板时通常钢板长度很短,导致承载钢板重量的活动梁很少,某几根活动梁长期受力,而且单根活动梁的承重有限,因此很容易造成单根活动梁承重超限,造成设备故障甚至设备损坏。
为了保证活动梁承重不超载的情况下尽可能提高冷床的负载量,现有技术一般是通过改变机械结构或者增加机械装置的承载能力来提高活动梁的承载能力,但是这种方法需要投入较大成本,实用性不强。
发明内容
本发明的目的是根据上述不足提供一种轧钢用冷床的装载方法,该装载方法可以保证活动梁承重不超载的情况下提高冷床的负载量,而且成本低。
本发明的技术方案如下:一种轧钢用冷床的装载方法,其步骤包括:
当钢板进入冷床区域时,第一块钢板采用头部定位或者尾部定位的方法摆放,后每一块钢板判断钢板长度是否达到冷床区域宽度的一半再进行依次摆放;
其中,当钢板长度大于冷床区域宽度一半时,采用与上一块钢板相同定位的方法摆放钢板;
当钢板长度小于冷床区域宽度一半时,采用与上一块钢板头尾交错定位的方法摆放钢板。
本发明在保证现有冷床钢板负载量的基础上,对短钢板(即钢板长度小于冷床区域宽度一半的钢板)采用头尾交错定位的方式摆放装载上冷床,从而在不增加单个活动梁承重的情况下,增加了冷床的钢板负载量。本发明不用改变现有轧钢用冷床的基本结构,仅改变控制装载方法即可实现,成本低,具有很强的实用性。
附图说明
图1为现有轧钢用冷床结构示意图;
图2为现有短钢板的冷床装载示意图;
图3为本发明的短钢板的冷床装载示意图;
1-冷床区域Ⅰ、2-冷床区域Ⅱ、3-活动梁、4-短钢板、5-长钢板、6-冷床区域宽度、7-冷床区域长度。
具体实施方式
以下结合附图通过具体实施例进一步说明本发明:
如图1-3所示,现有的轧钢用冷床一般由冷床区域Ⅰ1和冷床区域Ⅱ2组成,每个冷床区域内沿冷床区域长度7的方向间隔的布置有活动梁3。
每个冷床区域宽度6为26米,每根活动梁3之间的间距为1米,每个冷床区域布置有26根活动梁3。当钢板长度小于24米时,每个冷床区域可以单独动作,即钢板可以分区摆放。当冷床上有长度大于24米时的钢板时,冷床两区则同时动作。每根活动梁3的设计承重为4吨,当单根活动梁上承受的重量大于4吨时,活动梁在动作过程中很容易由于超重而损坏。
当钢板进入冷床区域时,第一块钢板采用头部定位或尾部定位的方法摆放。后每一块钢板判断钢板是否为短钢板4,即长度是否达到13米再进行依次摆放。其中,当钢板为长钢板5时,采用与上一块钢板相同定位的方法摆放钢板;当钢板为短钢板4时,采用与上一块钢板头尾交错定位的方法摆放钢板。
现有技术的钢板装载方法中,不对钢板的长度进行判断,直接顺序进行头部定位或尾部定位的方法摆放,如图2所示。在装载长度为10米(即10根活动梁3共同承重),重量为8吨的短钢板时,最大装载量为10×4÷8=5块。而采用本发明方法装载钢板时,在保证每根活动梁3不超载的情况下,最大装载量可以达到10块钢板。
以上所述仅为本发明的较佳实施例,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。
Claims (1)
1.一种轧钢用冷床的装载方法,其步骤包括:
当钢板进入冷床区域时,第一块钢板采用头部定位或者尾部定位的方法摆放,后每一块钢板判断钢板长度是否达到冷床区域宽度的一半再进行依次摆放;
其中,当钢板长度大于冷床区域宽度一半时,采用与上一块钢板相同定位的方法摆放钢板;
当钢板长度小于冷床区域宽度一半时,采用与上一块钢板头尾交错定位的方法摆放钢板。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510674070.XA CN105195530A (zh) | 2015-10-15 | 2015-10-15 | 一种轧钢用冷床的装载方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510674070.XA CN105195530A (zh) | 2015-10-15 | 2015-10-15 | 一种轧钢用冷床的装载方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105195530A true CN105195530A (zh) | 2015-12-30 |
Family
ID=54943675
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510674070.XA Pending CN105195530A (zh) | 2015-10-15 | 2015-10-15 | 一种轧钢用冷床的装载方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105195530A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114309093A (zh) * | 2021-12-30 | 2022-04-12 | 重庆钢铁股份有限公司 | 板材上下冷床的方法、板材编码方法及板材编码辅助装置 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1172448A2 (de) * | 2000-07-11 | 2002-01-16 | HSP Hoesch Spundwand und Profil GmbH | Verfahren und Vorrichtung zum Abkühlen von durch Warmverformen erzeugten, metallischen Langprodukten |
CN1876264A (zh) * | 2006-07-03 | 2006-12-13 | 唐山钢铁股份有限公司 | 一种棒材生产中定尺钢纵向双排自动移送方法 |
CN203018467U (zh) * | 2012-12-20 | 2013-06-26 | 武钢集团昆明钢铁股份有限公司 | 一种钢筋冷床对齐挡板 |
CN103978050A (zh) * | 2014-05-29 | 2014-08-13 | 北京佰能电气技术有限公司 | 一种冷床布料方法 |
CN104550273A (zh) * | 2014-12-31 | 2015-04-29 | 太原重工股份有限公司 | 步进式冷床的布料方法 |
-
2015
- 2015-10-15 CN CN201510674070.XA patent/CN105195530A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1172448A2 (de) * | 2000-07-11 | 2002-01-16 | HSP Hoesch Spundwand und Profil GmbH | Verfahren und Vorrichtung zum Abkühlen von durch Warmverformen erzeugten, metallischen Langprodukten |
CN1876264A (zh) * | 2006-07-03 | 2006-12-13 | 唐山钢铁股份有限公司 | 一种棒材生产中定尺钢纵向双排自动移送方法 |
CN203018467U (zh) * | 2012-12-20 | 2013-06-26 | 武钢集团昆明钢铁股份有限公司 | 一种钢筋冷床对齐挡板 |
CN103978050A (zh) * | 2014-05-29 | 2014-08-13 | 北京佰能电气技术有限公司 | 一种冷床布料方法 |
CN104550273A (zh) * | 2014-12-31 | 2015-04-29 | 太原重工股份有限公司 | 步进式冷床的布料方法 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114309093A (zh) * | 2021-12-30 | 2022-04-12 | 重庆钢铁股份有限公司 | 板材上下冷床的方法、板材编码方法及板材编码辅助装置 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102785290B (zh) | 一种先张法预应力u形梁用穿心牵引式台座及其施工方法 | |
CN103057973B (zh) | 一种适用于取料机回转轴承更换的多点顶升的方法 | |
CN104062193A (zh) | 钢桥水平节点板处的腹板间隙面外变形疲劳试验加载装置 | |
CN205577444U (zh) | 一种轨道预组-胎架牵引的构件传送工具体系 | |
CN104358215A (zh) | 整体预应力全装配箱型模块式钢栈桥制作装配工艺 | |
CN203981518U (zh) | 钢桥水平节点板处的腹板间隙面外变形疲劳试验加载装置 | |
CN105195530A (zh) | 一种轧钢用冷床的装载方法 | |
CN202220949U (zh) | 一种载荷地轨结构 | |
CN202831000U (zh) | 固定式塔吊整体迁移机构 | |
CN209144659U (zh) | 一种适应于spmt车组的模块化支撑系统 | |
CN102926330B (zh) | 一种适用于桥梁施工用挂蓝的安装方法 | |
CN204913165U (zh) | 一种焊接h型钢的人工组立胎架 | |
CN102530582A (zh) | 用于大型装船机整机上岸的方法 | |
CN204662409U (zh) | 一种静载试验设备 | |
CN103663107A (zh) | 可调节吊梁 | |
CN102514918B (zh) | 移动式斜块缓冲装置 | |
CN206142198U (zh) | 一种低噪音加固料仓 | |
CN205025491U (zh) | 一种用于溜井底部放矿的模拟装置 | |
CN201381028Y (zh) | 一种大型长条状铸、锻件运输专用支架 | |
CN210665325U (zh) | 一种装配式高温加载试验平台 | |
CN103587540B (zh) | 一种可转换载荷分配的大吨位移运台车 | |
CN103056649B (zh) | 特大型多功能压机机架安装方法 | |
CN202994492U (zh) | 一种t型桥梁静载试验架 | |
CN106760565A (zh) | 一种结构自动卸载施工方法 | |
CN210917038U (zh) | 连续刚构挂篮托架预压装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20151230 |