CN102785290B - 一种先张法预应力u形梁用穿心牵引式台座及其施工方法 - Google Patents

一种先张法预应力u形梁用穿心牵引式台座及其施工方法 Download PDF

Info

Publication number
CN102785290B
CN102785290B CN201110129997.7A CN201110129997A CN102785290B CN 102785290 B CN102785290 B CN 102785290B CN 201110129997 A CN201110129997 A CN 201110129997A CN 102785290 B CN102785290 B CN 102785290B
Authority
CN
China
Prior art keywords
counter
centre
force
core
hole jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201110129997.7A
Other languages
English (en)
Other versions
CN102785290A (zh
Inventor
黄静
张长春
常琨
李良才
胡存坚
杜魏林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rail Transit Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Original Assignee
Rail Transit Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rail Transit Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd filed Critical Rail Transit Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Priority to CN201110129997.7A priority Critical patent/CN102785290B/zh
Publication of CN102785290A publication Critical patent/CN102785290A/zh
Application granted granted Critical
Publication of CN102785290B publication Critical patent/CN102785290B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种先张法预应力U形梁用穿心牵引式台座,将张拉液压装置设置在反力墩台外侧,通过钢棒高强螺母对锚固钢横梁进行位置固定同时在锚固钢横梁上安装传感器并通过控制器控制。在使用时采用单根张拉、整体张拉、再单根张拉、持荷静停的方法。本发明具有的优点为:千斤顶允许工作行程较长,非常适宜长线台座施工尤其针对钢绞线伸长值大的生产线,便于倒顶多次重复行程张拉;持荷阶段时期直接拧紧千斤顶与反力墩台间自锁钢棒高强螺母固定在反力墩台上对锚固钢横梁进行位置固定,以使千斤顶卸载;安全、效率高、应力控制精度高。有效解决了预应力筋伸长值过大利用传统工艺频繁重复张拉的低效、高耗的矛盾问题。

Description

一种先张法预应力U形梁用穿心牵引式台座及其施工方法
技术领域
本发明涉及预应力施工的设备和方法,尤其是一种先张法预应力U形梁用穿心牵引式台座及其施工方法。 
背景技术
长线法预应力先张施工就是在一条先张生产台座上同时对2片或2片以上的梁进行串联式预应力先张施工,然后进行混凝土浇注、养护、脱模及同时放张的生产方式。 
施加应力的方式有顶推式和穿心牵引式两种。 
现有的顶推式方案如图1所示:每条台座配置600吨级台座式千斤顶8台,张拉行程200mm;钢横梁两套,另搭配一定数量的配套油泵。用于锚固钢绞线的钢横梁放在张拉台座两端承力墩台外侧,千斤顶设在承力墩台与钢横梁间,张拉原理由千斤顶推动钢横梁张拉钢绞线。该方案主要用于预应力钢绞线的同步整体预拉,同时也可用于对预应力钢绞线初张拉后的整体绷直。其缺点为千斤顶允许工作行程较短,不适宜长线台座施工钢绞线伸长值大的生产线,不便于倒顶二次行程张拉,持荷阶段时期靠在伸缩油缸外加入垫板承力以使千斤顶卸载。垫板压缩量较大,应力损失明显。必须和单束小千斤顶配合施工;行程不宜过长,安全稳定性差。钢横梁受力跨度较大,刚度要求高。 
发明内容
本发明的目的是提供一种先张法预应力U形梁用穿心牵引式台座及其施工方法,以解决现有技术中存在的技术问题。 
本发明的技术方案为:一种先张法预应力U形梁用穿心牵引式台座,包括张拉液压装置、反力墩台、锚固钢横梁、梁体和反力台基础墙,所述反力墩台设置在反力台基础墙两端,所述梁体设置预留孔,所述张拉液压装置设置在反力墩台外侧,反力墩台内侧与梁体之间设置滑移轨道,滑移轨道上设置锚固钢横梁,所述张拉液压装置通过牵引螺杆穿过反力墩台与其内侧的锚固钢横梁连接。 
作为优选,张拉液压装置为穿心式千斤顶,每台工作行程为300mm,在反力台基础墙两端各分布四台。 
作为优选,所述锚固钢横梁通过张拉液压装置与反力墩台之间的钢棒高强螺母进行位置固定。 
作为优选,还包括一台总控箱及其控制的一台电动泵站和一个同步工作子站,所述同步子工作站控制所述张拉液压装置,在所述锚固钢横梁的两端和中部安装3个与同步子工作站连接的应力传感器。 
一种先张法预应力U形梁穿心牵引式施工方法,包括如下步骤: 
1)将钢绞线穿过梁体钢筋笼骨架,两端固定于锚固钢横梁上;
2)将钢绞线逐根张拉至20%σcon;
3)将钢绞线整体张拉至0.80бcon;配备同步控制系统可实现直接整体张拉至设计应力1.00бcon;
4)将单根钢绞线向两端对称张拉至1.00бcon,持荷静停5min;
5)将千斤顶和反力墩台间的钢棒高强自锁螺母锁紧在反力墩台上,张拉液压装置回油,测量回缩值,进行数据复核,完成预应力张拉工艺,张拉完成浇注混凝土达到一定强度后进行放张卸载;
6)将张拉液压装置送油,预先伸出部分油缸行程;
7)张拉液压装置继续送油持荷牵引牵引螺杆使自锁螺母与反力墩台卸载;
8)拧松自锁螺母离开反力墩台一定的放张回缩位移距离;
9)张拉液压装置回油卸载,锚固钢横梁在钢绞线的回缩牵引下移动慢慢卸除荷载,整体放张完成。
综上所述,由于采用了上述技术方案,本发明的有益效果是: 
1)千斤顶允许工作行程较长,非常适宜长线台座施工尤其针对钢绞线伸长值大的生产线,便于重复多次行程张拉;
2)持荷阶段时期直接拧紧牵引螺杆高强螺母对锚固钢横梁进行位置固定,以使千斤顶卸载;
3)预应力卸载整体放张效率高,质量能得到保障;
3)大吨位作用力下稳定性、安全性高,施工效率大大高;
4)配备传感器和控制器后的应力控制精度高,可减少工艺时间提高效率并真正实现应力、应变“双控”。
附图说明
本发明将通过例子并参照附图的方式说明,其中: 
图1是顶推式张拉设备的结构示意图。
图2是本发明的俯视图。 
图3是本发明的立体工况图。 
图中标记:1-1为反力墩台基础墙,1-2为张拉横梁,1-3为反力墩台,1-4为台座式千斤顶,1为千斤顶,2为反力墩台,3为锚固钢横梁,4为钢绞线,5为梁体,6为反力台基础墙,7为牵引螺杆。 
具体实施方式
本说明书中公开的所有特征,或公开的所有方法或过程中的步骤,除了互相排斥的特征和/或步骤以外,均可以以任何方式组合。 
本说明书(包括任何附加权利要求、摘要和附图)中公开的任一特征,除非特别叙述,均可被其他等效或具有类似目的的替代特征加以替换。即,除非特别叙述,每个特征只是一系列等效或类似特征中的一个例子而已。 
如图2、图3 ,一种先张法预应力U形梁用穿心牵引式台座,包括张拉液压装置1、反力墩台2、锚固钢横梁3、梁体5和反力台基础墙6,所述反力墩台2设置在反力台基础墙6两端,所述反力墩台2设置预留孔,所述张拉液压装置1设置在反力墩台2外侧,反力墩台2内侧与梁体5之间设置滑移轨道,滑移轨道上设置锚固钢横梁3,所述张拉液压装置1通过牵引螺杆7穿过反力墩台2与其内侧的锚固钢横梁3连接。 
张拉液压装置1为穿心式千斤顶,每台工作行程为300mm,在反力台基础墙6两端各分布四台。 
所述锚固钢横梁3通过张拉液压装置1与反力墩台2之间的钢棒高强螺母进行位置固定。 
还包括一台总控箱及其控制的一台电动泵站和一个同步工作子站,所述同步子工作站控制所述张拉液压装置1,在所述锚固钢横梁3的两端和中部安装3个与同步子工作站连接的应力传感器。 
一种先张法预应力U形梁穿心牵引式施工方法,包括如下步骤: 
1)将钢绞线4穿过梁体5上的预留孔,两端固定于锚固钢横梁3上;
2)将钢绞线4逐根张拉至20%σcon;
3)将钢绞线4整体张拉至0.80бcon,配置同步控制系统可直接整体张拉至设计应力1.00бcon,以减少张拉环节;
4)将单根钢绞线4向两端对称张拉至1.00бcon,持荷静停5min;
5)将张拉液压装置1回油,调节钢棒高强螺母进行位置固定,测量回缩值,进行数据复核完成预应力张拉张拉完成浇注混凝土达到一定强度后进行整体放张卸载。
6)将张拉液压装置1送油,预先伸出部分油缸行程; 
7)张拉液压装置1继续送油持荷牵引牵引螺杆7使自锁螺母与反力墩台2卸载;
8)拧松自锁螺母离开反力墩台2一定的放张回缩位移距离;
9)张拉液压装置1回油卸载,锚固钢横梁3在钢绞线4的回缩牵引下移动慢慢卸除荷载,整体放张完成。
本发明并不局限于前述的具体实施方式。本发明扩展到任何在本说明书中披露的新特征或任何新的组合,以及披露的任一新的方法或过程的步骤或任何新的组合。 

Claims (5)

1.一种先张法预应力U形梁用穿心牵引式台座,包括穿心式千斤顶、反力墩台(2)、锚固钢横梁(3)、梁体(5)和反力台基础墙(6),所述反力墩台(2)设置在反力台基础墙(6)两端,其特征在于:所述反力墩台(2)设置预留孔,所述穿心式千斤顶设置在反力墩台(2)外侧,反力墩台(2)内侧与梁体(5)之间设置滑移轨道,滑移轨道上设置锚固钢横梁(3),所述穿心式千斤顶通过牵引螺杆(7)穿过反力墩台(2)与其内侧的锚固钢横梁(3)连接。
2.根据权利要求1所述的一种先张法预应力U形梁用穿心牵引式台座,其特征在于:穿心式千斤顶为穿心式千斤顶,每台工作行程为300mm,在反力台基础墙(6)两端各分布四台。
3.根据权利要求1或2所述的一种先张法预应力U形梁用穿心牵引式台座,其特征在于:所述锚固钢横梁(3)通过穿心式千斤顶(1)与反力墩台(2)之间的钢棒高强螺母进行位置固定。
4.根据权利要求2所述的一种先张法预应力U形梁用穿心牵引式台座,其特征在于:还包括一台总控箱及其控制的一台电动泵站和一个同步工作子站,所述同步子工作站控制所述穿心式千斤顶,在所述工作端的四个穿心式千斤顶上安装4个与同步子工作站连接的应力和位移传感器。
5.一种先张法预应力U形梁穿心牵引式施工方法,其特征在于包括如下步骤:
1)将钢绞线(4)按设计位置穿过梁体(5)的钢筋骨架,两端固定于锚固钢横梁(3)上;
2)将钢绞线(4)逐根张拉至20%σcon,进行初应力初调达到受力一致;
3)将钢绞线(4)整体张拉至0.80бcon,配置同步控制系统可直接整体张拉至设计应力1.00бcon;
4)将单根钢绞线(4)向两端对称张拉至1.00бcon,持荷静停5min;
5)将穿心式千斤顶回油,调节钢棒高强螺母进行位置固定,测量回缩值,进行数据复核完成张拉待梁体浇注混凝土后强度达到设计后卸载,整体同步放张;
6)将穿心式千斤顶送油,预先伸出部分油缸行程;
7)穿心式千斤顶继续送油持荷牵引牵引螺杆(7)使自锁螺母与反力墩台(2)卸载;
8)拧松自锁螺母离开反力墩台(2)一定的放张回缩位移距离;
9)穿心式千斤顶回油卸载,锚固钢横梁(3)在钢绞线的回缩牵引下移动慢慢卸除荷载,整体放张完成。
CN201110129997.7A 2011-05-19 2011-05-19 一种先张法预应力u形梁用穿心牵引式台座及其施工方法 Active CN102785290B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110129997.7A CN102785290B (zh) 2011-05-19 2011-05-19 一种先张法预应力u形梁用穿心牵引式台座及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110129997.7A CN102785290B (zh) 2011-05-19 2011-05-19 一种先张法预应力u形梁用穿心牵引式台座及其施工方法

Publications (2)

Publication Number Publication Date
CN102785290A CN102785290A (zh) 2012-11-21
CN102785290B true CN102785290B (zh) 2014-11-19

Family

ID=47150971

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110129997.7A Active CN102785290B (zh) 2011-05-19 2011-05-19 一种先张法预应力u形梁用穿心牵引式台座及其施工方法

Country Status (1)

Country Link
CN (1) CN102785290B (zh)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103089018B (zh) * 2013-02-07 2014-10-22 中冶建工集团有限公司 一种精确建立张拉力的预应力钢结构张拉施工方法
CN103255718B (zh) * 2013-04-28 2015-04-08 中交第三公路工程局有限公司 一种先张法板梁轨道移动式钢横梁整体张拉装置与张拉工艺
CN103726510A (zh) * 2013-11-29 2014-04-16 中交第四航务工程局有限公司 一种大体积沉管钢筋笼的建造方法
CN104308989B (zh) * 2014-10-11 2017-02-15 常州圣东机械有限公司 轨道板模具张拉装置及其使用方法
CN105114101B (zh) * 2015-09-29 2018-03-27 中铁科工集团轨道交通装备有限公司 一种带持续张力的管片二次衬砌设备
CN105479598B (zh) * 2015-11-20 2018-01-23 长春工业大学 一种轨枕预应力筋自动张拉装置
CN105835226B (zh) * 2016-05-26 2019-02-01 中铁二十三局集团轨道交通工程有限公司 一种先张法预制梁台座
CN106945170A (zh) * 2016-12-27 2017-07-14 山西高行液压股份有限公司 先张法生产高速铁路无砟轨道板的钢筋张拉装置
CN106863585A (zh) * 2017-01-20 2017-06-20 俞晓东 用于制造预应力桩的张拉装置
CN107542272B (zh) * 2017-09-25 2023-09-22 沈阳工业大学 新型便携式预应力拉杆张拉装置
CN107599158A (zh) * 2017-09-26 2018-01-19 汤始建华建材(苏州)有限公司 一种用于预应力构件双向张拉的工艺方法
CN108221718A (zh) * 2018-03-05 2018-06-29 湖南省交通规划勘察设计院有限公司 梁体横向偏位的桥墩受力自平衡纠偏装置及纠偏方法
CN109176866B (zh) * 2018-09-21 2024-05-14 江苏华江祥瑞现代建筑发展有限公司 张拉装置及采用张拉装置生产叠合梁或叠合板的生产方法
CN109500993B (zh) * 2018-12-29 2023-10-27 新元果业(山东)集团有限公司 预应力锚具、预应力张拉装置及预应力张拉方法
CN110154230A (zh) * 2019-07-01 2019-08-23 浙江省交通规划设计研究院有限公司 一种钢板组合梁桥面板的预制方法及施工方法
CN112356262B (zh) * 2020-09-28 2022-04-01 广东博智林机器人有限公司 张拉机和预制件生产线
CN112497479A (zh) * 2020-10-16 2021-03-16 保利长大工程有限公司 一种先张法预制梁板同步张拉及放张系统
CN113510840B (zh) * 2021-03-30 2023-10-10 中铁十四局集团房桥有限公司 用于高速岔枕生产的预应力钢丝整体张拉放张系统及方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4485677A (en) * 1981-06-09 1984-12-04 Freyssinet International (Stup) Device for tensioning pre-stress bars and for determining this tension
US5113630A (en) * 1990-09-05 1992-05-19 Rock Of Ages Corporation Adjustable stone formed work support and method of providing same
CN1840782A (zh) * 2005-12-12 2006-10-04 中铁大桥局股份有限公司 预应力混凝土梁采用低强初张措施控制梁体裂缝施工工艺
CN101659082A (zh) * 2009-09-21 2010-03-03 中铁大桥局集团第四工程有限公司 箱梁钢筋骨架整体绑扎、整体吊装系统及其施工方法
CN202100011U (zh) * 2011-05-19 2012-01-04 中铁二十三局集团轨道交通工程有限公司 一种先张法预应力u形梁用穿心牵引式台座

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4485677A (en) * 1981-06-09 1984-12-04 Freyssinet International (Stup) Device for tensioning pre-stress bars and for determining this tension
US5113630A (en) * 1990-09-05 1992-05-19 Rock Of Ages Corporation Adjustable stone formed work support and method of providing same
CN1840782A (zh) * 2005-12-12 2006-10-04 中铁大桥局股份有限公司 预应力混凝土梁采用低强初张措施控制梁体裂缝施工工艺
CN101659082A (zh) * 2009-09-21 2010-03-03 中铁大桥局集团第四工程有限公司 箱梁钢筋骨架整体绑扎、整体吊装系统及其施工方法
CN202100011U (zh) * 2011-05-19 2012-01-04 中铁二十三局集团轨道交通工程有限公司 一种先张法预应力u形梁用穿心牵引式台座

Also Published As

Publication number Publication date
CN102785290A (zh) 2012-11-21

Similar Documents

Publication Publication Date Title
CN102785290B (zh) 一种先张法预应力u形梁用穿心牵引式台座及其施工方法
CN103255718B (zh) 一种先张法板梁轨道移动式钢横梁整体张拉装置与张拉工艺
CN203546626U (zh) 钢管混凝土拱桥吊杆更换装置
CN205521921U (zh) 整体张拉设备
CN202285309U (zh) 提升式带电跨越架
CN202169644U (zh) 先张法预应力混凝土板桩整体式张拉台座
CN204339983U (zh) 先张法预制板梁拉杆式整体张拉装置
CN102152396A (zh) 移动式预应力钢绞线张拉装置
CN207862749U (zh) 一种新型组合式吊杆
CN102409619B (zh) 一种提高多梁式组合小箱梁桥桥面结构横向整体性的方法
CN110205940A (zh) 0#块施工托架及其反拉预压方法
CN105835226A (zh) 一种先张法预制梁台座
CN203639833U (zh) 用于二次张拉低回缩锚固体系的二次张拉系统
CN205223871U (zh) 一种悬索桥桥塔横梁支架预压装置
KR101206519B1 (ko) 거더지지장치와 이동장치를 이용한 거더 제작방법, 이를 이용하여 제작된 거더 및 교량시공방법
CN204570686U (zh) 压力分散型锚索的分单元张拉系统
CN106012834B (zh) 一种空间扭曲曲线异型反对称钢主塔内支撑及张拉系统
CN201239993Y (zh) 一种先张法预应力张拉工艺用整体张拉、放张系统
CN109773960B (zh) 一种多尺寸装配式t梁齿块钢筋预绑扎装置
CN203284732U (zh) 一种先张法板梁轨道移动式钢横梁整体张拉装置
CN110883937A (zh) 一种可移动式非预张双向预应力生产线
CN214656451U (zh) 前支点复合式挂篮
CN203792513U (zh) 一种批量生产预应力空心板梁的施工设施
CN202100011U (zh) 一种先张法预应力u形梁用穿心牵引式台座
CN105034162A (zh) 单模台非预张整体张拉装置及其工作方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant