CN104895079A - 钢板桩打设的逆做施工方法 - Google Patents

钢板桩打设的逆做施工方法 Download PDF

Info

Publication number
CN104895079A
CN104895079A CN201510320499.9A CN201510320499A CN104895079A CN 104895079 A CN104895079 A CN 104895079A CN 201510320499 A CN201510320499 A CN 201510320499A CN 104895079 A CN104895079 A CN 104895079A
Authority
CN
China
Prior art keywords
steel sheet
purlin
sheet pile
construction
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510320499.9A
Other languages
English (en)
Inventor
张庆国
岳嫣
田玉刚
王宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lioaning Zizhu Pile Foundation Engineering Co Ltd
Original Assignee
Lioaning Zizhu Pile Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lioaning Zizhu Pile Foundation Engineering Co Ltd filed Critical Lioaning Zizhu Pile Foundation Engineering Co Ltd
Priority to CN201510320499.9A priority Critical patent/CN104895079A/zh
Publication of CN104895079A publication Critical patent/CN104895079A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

本发明涉及一种钢板桩打设的逆做施工方法,(1)先按照设计基坑尺寸,进行基坑内挖土,挖至围檩及内支撑设计标高处;(2)安装围檩及内支撑;(3)回填0.5-0.6米厚度覆土;(4)进行钢板桩施工,围檩兼做导向梁;(5)同时进行围檩与钢板桩预定位置的焊接固定;(6)钢板桩施工完毕合拢之后,局部挖土,安装围檩下托板;7)继续基坑内挖土,直至基坑施工完成。本发明施工方法可普遍应用于地下水位不高的建筑基坑、管道基坑等基坑支护工程中,尤其对于室内施工高度有限的基坑工程,可起到较好的效果,同时对于工期要求紧迫的基坑支护工程,同样可以发挥其优势。

Description

钢板桩打设的逆做施工方法
技术领域
本发明涉及钢板桩施工技术应用领域,特别涉及一种钢板桩打设的逆做施工方法。
背景技术
常规钢板桩基坑支护工程中,施工顺序一般为:先打设钢板桩,钢板桩合拢后,挖土至支撑围檩设计标高下约0.5米,进行围檩及支撑安装,然后继续开挖至坑底设计标高。对某些厂房内基坑支护工程,内部净空高度有限,难以满足钢板桩插打施工高度的要求,同时不宜采用较大放坡施工,常规施工方法难以进行。
发明内容
本发明所要解决的技术问题是提供一种钢板桩打设的逆做施工方法,有效解决了某些厂房内打设钢板桩施工高度不够的问题。
为实现上述目的,本发明采用以下技术方案实现:
一种钢板桩打设的逆做施工方法,具体操作步骤如下:
(1)先按照设计基坑尺寸,进行基坑内挖土,挖至围檩及内支撑设计标高处;
(2)将围檩及内支撑摆放在设计位置地面上,将围檩连接处焊接固定,并将内支撑连接到位;
(3)在摆放连接好的围檩及内支撑上,回填0.5-0.6米厚度覆土,以便于打桩机械的行走施工和保护支撑结构不受损坏;
(4)用机械手打桩机进行钢板桩施工,围檩兼做导向梁,先打设定位钢板桩,之后沿着围檩外缘整齐打设;
(5)同时进行围檩与钢板桩预定位置的焊接固定;
(6)钢板桩施工完毕合拢之后,局部挖土,安装围檩下托板;
(7)继续基坑内挖土,直至基坑施工完成。
与现有的技术相比,本发明的有益效果是:
本发明施工方法先铺设围檩,可兼做打桩时的导向架,省工省料。有效解决了某些厂房内打设钢板桩施工高度不够的问题。可边打设钢板桩,边进行围檩与钢板桩的焊接固定,随后逐渐进行挖土工作,这样可较大加快施工进度。
本发明施工方法可普遍应用于地下水位不高的建筑基坑、管道基坑等基坑支护工程中,尤其对于室内施工高度有限的基坑工程,可起到较好的效果,同时对于工期要求紧迫的基坑支护工程,同样可以发挥其优势。
附图说明
图1为本发明实施例施工流程图。
图2为实施例基坑支护平面示意图。
图3为实施例基坑支护立面示意图。
具体实施方式
下面对本发明的具体实施方式进一步说明:
实施例:
厂房内设备基础基坑,设计基坑平面尺寸:60.8x11.6米,基坑深度:放坡1.5米,后开挖深度5.7米。
如图1所示,一种钢板桩打设的逆做施工方法,具体操作步骤如下:
(1)将钢板桩的摆放场地整理平整,原材料进入场地,对施工设备进行调试,检查钢板桩质量;
(2)按照设计基坑尺寸60.8x11.6米测量基线,进行基坑内挖土,挖至围檩及内支撑设计标高距原地面下2米处;
(3)将围檩及内支撑摆放在设计位置地面上,基坑设置一道围檩及内支撑,将围檩连接处焊接固定,并将内支撑连接到位,围檩:热轧HM390x300x10x16型钢,内支撑:热轧HM390x300x10x16型钢,围檩四角布置两道45°斜支撑,水平支撑间距4米;(见图2)
(4)在摆放连接好的围檩及内支撑上,回填0.5米厚度覆土,以便于打桩机械的行走施工和保护支撑结构不受损坏;
(5)用机械手打桩机进行钢板桩施工,围檩兼做导向梁,先打设定位钢板桩,之后沿着围檩外缘整齐打设;钢板桩:热轧拉森钢板桩SPU-IV 400x170,长度9米,钢板桩插打到位后顶部距围檩0.5米;(见图3)
(6)同时进行围檩与钢板桩预定位置的焊接固定;
(7)钢板桩施工完毕合拢之后,局部挖土,安装围檩下托板,每3米焊接安装一个托板;
(8)继续基坑内挖土至5.2米深;
(9)进行基坑内结构施工;
(10)基坑土方回填;
(11)拆除钢板桩。
上面所述仅是本发明的基本原理,并非对本发明作任何限制,凡是依据本发明对其进行等同变化和修饰,均在本专利技术保护方案的范畴之内。

Claims (1)

1.一种钢板桩打设的逆做施工方法,其特征在于,具体操作步骤如下:
(1)先按照设计基坑尺寸,进行基坑内挖土,挖至围檩及内支撑设计标高处;
(2)将围檩及内支撑摆放在设计位置地面上,将围檩连接处焊接固定,并将内支撑连接到位;
(3)在摆放连接好的围檩及内支撑上,回填0.5-0.6米厚度覆土,以便于打桩机械的行走施工和保护支撑结构不受损坏;
(4)用机械手打桩机进行钢板桩施工,围檩兼做导向梁,先打设定位钢板桩,之后沿着围檩外缘整齐打设;
(5)同时进行围檩与钢板桩预定位置的焊接固定;
(6)钢板桩施工完毕合拢之后,局部挖土,安装围檩下托板;
(7)继续基坑内挖土,直至基坑施工完成。
CN201510320499.9A 2015-06-11 2015-06-11 钢板桩打设的逆做施工方法 Pending CN104895079A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510320499.9A CN104895079A (zh) 2015-06-11 2015-06-11 钢板桩打设的逆做施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510320499.9A CN104895079A (zh) 2015-06-11 2015-06-11 钢板桩打设的逆做施工方法

Publications (1)

Publication Number Publication Date
CN104895079A true CN104895079A (zh) 2015-09-09

Family

ID=54028008

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510320499.9A Pending CN104895079A (zh) 2015-06-11 2015-06-11 钢板桩打设的逆做施工方法

Country Status (1)

Country Link
CN (1) CN104895079A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106320349A (zh) * 2016-10-28 2017-01-11 广东省水利水电第三工程局有限公司 基坑加固支护装置
CN107503354A (zh) * 2016-06-14 2017-12-22 五冶集团上海有限公司 一种塔吊基础围护支撑加固及开挖方法
CN108894128A (zh) * 2018-06-25 2018-11-27 德州市公路工程总公司 现役拱涵原位升级结构及施工方法
CN109555108A (zh) * 2018-12-25 2019-04-02 中铁十七局集团有限公司 一种钢板桩围护施工结构
CN113863410A (zh) * 2021-10-25 2021-12-31 中铁十九局集团广州工程有限公司 一种用于沟槽开挖的装配式支撑组件及施工方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102434717A (zh) * 2011-12-16 2012-05-02 中国建筑第八工程局有限公司 工字钢顶管工作坑的施工方法
CN103343538A (zh) * 2013-07-17 2013-10-09 深圳市兴班建筑工程有限公司 一种高流塑深层软基下的钢板桩支护施工方法
JP2015071873A (ja) * 2013-10-02 2015-04-16 株式会社竹中工務店 地下水揚水設備

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102434717A (zh) * 2011-12-16 2012-05-02 中国建筑第八工程局有限公司 工字钢顶管工作坑的施工方法
CN103343538A (zh) * 2013-07-17 2013-10-09 深圳市兴班建筑工程有限公司 一种高流塑深层软基下的钢板桩支护施工方法
JP2015071873A (ja) * 2013-10-02 2015-04-16 株式会社竹中工務店 地下水揚水設備

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503354A (zh) * 2016-06-14 2017-12-22 五冶集团上海有限公司 一种塔吊基础围护支撑加固及开挖方法
CN106320349A (zh) * 2016-10-28 2017-01-11 广东省水利水电第三工程局有限公司 基坑加固支护装置
CN108894128A (zh) * 2018-06-25 2018-11-27 德州市公路工程总公司 现役拱涵原位升级结构及施工方法
CN108894128B (zh) * 2018-06-25 2020-05-29 德州市公路工程总公司 现役拱涵原位升级结构及施工方法
CN109555108A (zh) * 2018-12-25 2019-04-02 中铁十七局集团有限公司 一种钢板桩围护施工结构
CN109555108B (zh) * 2018-12-25 2023-09-29 中铁十七局集团有限公司 一种钢板桩围护施工结构
CN113863410A (zh) * 2021-10-25 2021-12-31 中铁十九局集团广州工程有限公司 一种用于沟槽开挖的装配式支撑组件及施工方法

Similar Documents

Publication Publication Date Title
KR20210130725A (ko) 보강장치 및 다량 수분 함유 자갈 지층 중 심층 피트 국소 냉동 보강 시공 방법
CN104895079A (zh) 钢板桩打设的逆做施工方法
CN102434717B (zh) 工字钢顶管工作坑的施工方法
CN104060615B (zh) 利用新建基坑支护结构清除地下障碍物的施工方法
CN102828517B (zh) 一种车站出入口基坑开挖分层控制的施工方法
CN100510281C (zh) 超大直径、超埋深度调蓄池的半逆作施工方法
CN205024712U (zh) 一种组合式塔吊基础
CN101793023A (zh) 一种基坑施工方法
CN212294747U (zh) 一种顶管井结构
CN101824825B (zh) 一种深基坑明挖施工方法
CN204780933U (zh) 基坑支撑栈桥体系
CN114033388B (zh) 富水粉砂层地下隧道顶管用竖井施工方法
CN110468873A (zh) 一种小空间下桥台桩基托换结构及使用方法
CN101597897B (zh) 一种湿陷性黄土地区地基的二次处理方法及复合地基结构
JP5698405B1 (ja) 地盤改良ベタ基礎工法
CN209941754U (zh) 一种高压电力管涵原地保护结构
CN106988337A (zh) 一种用于减小条形浅基础房屋不均匀沉降的加固方法
CN111139854A (zh) 采用引流注浆法处理基坑勘探孔管涌施工方法
CN110747861A (zh) 一种高水位深基坑开挖施工方法
CN206625238U (zh) 一种圆形基坑的装配式波形钢衬板支护结构
TWI623669B (zh) 連續壁施工前防止工地下陷的先行鋪面的施工方法
JP5739051B1 (ja) 地盤改良ベタ基礎の液状化対策構造、及び液状化による不同沈下発生の修正方法
CN103510525A (zh) 一种重力式水泥土墙结合单排桩的基坑梯级支护方法
CN210031875U (zh) 顶推用沉井装置
CN109742715B (zh) 一种迁改后电力管沟的布置结构及电力管沟迁改方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20150909

RJ01 Rejection of invention patent application after publication