CN104818738A - 小型钢制储罐环墙基础罐底板锥度修复方法 - Google Patents

小型钢制储罐环墙基础罐底板锥度修复方法 Download PDF

Info

Publication number
CN104818738A
CN104818738A CN201510117248.0A CN201510117248A CN104818738A CN 104818738 A CN104818738 A CN 104818738A CN 201510117248 A CN201510117248 A CN 201510117248A CN 104818738 A CN104818738 A CN 104818738A
Authority
CN
China
Prior art keywords
tank
grouting
injected hole
ringwall
center
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510117248.0A
Other languages
English (en)
Inventor
赵兴品
高印军
郭磊
谢文鹏
吴磊
黄延军
关志伟
王众
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Water Resources Research Institute of Shandong Province
Original Assignee
Water Resources Research Institute of Shandong Province
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Water Resources Research Institute of Shandong Province filed Critical Water Resources Research Institute of Shandong Province
Priority to CN201510117248.0A priority Critical patent/CN104818738A/zh
Publication of CN104818738A publication Critical patent/CN104818738A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本发明公开了一种小型钢制储罐环墙基础罐底板锥度修复方法,包括:1)在环墙上每5m开设与水平夹角15°注浆孔,孔深至环墙中心;2)注浆管上每30cm设一出浆阀,将注浆管插入注浆孔内,其端部至罐底中心;3)注浆输入管连接注浆内管插入注浆外管内,开启位于罐中心的出浆阀,由中心向边沿顺序注浆,整个罐底土体抬升逐步完成;4)开设排水孔或利用废弃注浆孔排水,罐中心土体逐步抬升,罐底板锥度增大,达到0.8%-2.0%的要求;5)对注浆孔清理后用水泥砂浆封堵。本发明不改变原有罐体结构,利用袖阀管注浆法,加固地基的同时逐步抬升土体将罐底托起,无需设备和人员进入罐内,简单可靠,具有费用低、时间短、效果好的优点。

Description

小型钢制储罐环墙基础罐底板锥度修复方法
技术领域
本发明涉及一种小于2000立方立式钢制储罐环墙基础罐底板锥度修复方法,属于化工、石油、水利、建筑技术领域。
背景技术
小型钢制储罐直径小于15m,罐体座在环墙基础上,正常罐底锥度0.8%-2.0%。储罐在长期运行过程中,地基受湿陷、载荷、地下水位变化等作用,地基土会出现沉降,罐底锥度小于0.8%时,罐底钢板就会有空鼓现象,严重时有皱褶、凹陷出现,此时罐底板荷载运行会产生拉应力和剪应力,焊缝会撕裂破坏危及安全。当前储罐底板锥度修复没有较好的方法,一般是拆除罐底板,重新回填,然后再铺设焊接钢板。这种方法的缺点是显而易见的,费用比建一个新罐底板还要高。
发明内容
本发明所要解决的技术问题是针对现有技术存在的缺陷,提供一种小型钢制储罐环墙基础罐底板锥度修复方法。
为解决这一技术问题,本发明提供了一种小型钢制储罐环墙基础罐底板锥度修复方法,具体包括如下步骤:
1)环墙周围布注浆孔:在安置罐体的环墙上开设注浆孔,按环墙外围弧长,每5m开设一个注浆孔,注浆孔的孔径为5cm,与水平夹角15°钻孔,孔深长度至环墙的中心位置;
2)安装注浆管:在注浆管上每30cm设置一个出浆阀;将注浆管斜向插入沿与水平夹角15°的注浆孔内,其端部达至罐底中心的注浆孔底;
3)注浆:将搅浆设备和水泥材料放置在搅拌区,只有一个注浆输入管连接注浆管的注浆内管插入注浆外管内;首先开启位于罐中心部位的出浆阀,由中心向边沿顺序注浆,浆液为水泥浆或水泥与粉煤灰配合比,浆液比重为1.55;浆脉运动方向在土体中沿土体弱应力走向自动调整,随土体加固强度的提高,整个罐底土体抬升逐步完成;
4)修复罐底锥度:随着灌浆量的增加,加固土体孔隙水压力升高,开设排水孔或利用废弃注浆孔进行排水,排水的过程就是土体加固强度提高的过程;罐中心土体逐步抬升,罐底板的锥度增大,最后达到0.8%-2.0%的要求;
5)封堵注浆孔:整个罐底锥度符合要求以后,对罐基础环墙的注浆孔封堵,先清理注浆孔里面的注浆管,清理深度30cm,然后用水泥砂浆封堵抹平。
所述步骤1)中的注浆孔沿环墙周边离地面高30cm处。
所述步骤2)中插入的注浆管是带有单向阀的袖阀注浆管。
有益效果:本发明利用成熟的袖阀管注浆法,加固地基的同时,逐步抬升土体将罐底托起,不需要设备和人员进入罐内,方法简单可靠,不改变原有罐体结构。本发明的环墙外插注浆管的灌浆修复方法与其他方法比较,具有费用低、时间短、效果好的优点。
附图说明
图1为本发明的注浆剖面示意图;
图2为本发明的罐底注浆示意图。
图中:1罐体、2注浆管、3环墙、4罐底板、5浆脉运动方向、6出浆阀。
具体实施方式
下面结合附图及实施案例对本发明做具体描述。
图1所示为本发明的注浆剖面示意图。
图2所示为本发明的罐底注浆示意图。
本发明的创新点在于:在储罐空间极小、设备人员无法进入罐内作业前提下,在储罐基础环墙周围开设多个与水平夹角15°的直径为5cm的小孔作为水平方向的灌浆孔,向储罐底板下土体注浆加固抬升,托起罐底板修复其锥度。
本发明的修复方法,具体包括如下步骤:
1)环墙周围布注浆孔:在安置罐体1的环墙3上开设注浆孔,按环墙3外围弧长,每5m开设一个注浆孔,注浆孔的孔径为5cm,与水平夹角15°钻孔,孔深长度至环墙3的中心位置;
2)安装注浆管:在注浆管2上每30cm设置一个出浆阀6;将注浆管2斜向插入沿与水平夹角15°的注浆孔内,其端部达至罐底中心的注浆孔底(如图1所示);
3)注浆:将搅浆设备和水泥材料放置在搅拌区,只有一个注浆输入管连接注浆管2的注浆内管插入注浆外管内;注浆时,首先开启位于罐中心部位的出浆阀6,由中心向边沿顺序注浆,浆脉运动方向5在土体中沿土体弱应力走向自动调整,随土体加固强度的提高,整个罐底土体抬升逐步完成;浆液为水泥浆或水泥与粉煤灰配合比,浆液比重为1.55;
4)修复罐底锥度:随着灌浆量的增加,加固土体孔隙水压力升高,开设排水孔或利用废弃注浆孔进行排水,排水的过程就是土体加固强度提高的过程;罐中心土体逐步抬升,罐底板4的锥度增大,最后达到0.8%-2.0%的要求(如图2所示);
5)封堵注浆孔:整个罐底锥度符合要求以后,对罐基础环墙3的注浆孔封堵,先清理注浆孔里面的注浆管,清理深度30cm,然后用水泥砂浆封堵抹平。
所述步骤1)中的注浆孔沿环墙周边离地面高30cm处。
所述步骤2)中插入的注浆管2是带有单向阀的袖阀注浆管,灌浆时,由灌浆内管随意拉动,可以选择需要灌浆的部位。
本发明利用成熟的袖阀管注浆法,加固地基的同时,逐步抬升土体将罐底托起,不需要设备和人员进入罐内,方法简单可靠,不改变原有罐体结构。本发明的环墙外插注浆管的灌浆修复方法与其他方法比较,具有费用低、时间短、效果好的优点。
本发明上述实施方案,只是举例说明,不是仅有的,所有在本发明范围内或等同本发明的范围内的改变均被本发明包围。

Claims (3)

1.一种小型钢制储罐环墙基础罐底板锥度修复方法,其特征在于,具体包括如下步骤:
1)环墙周围布注浆孔:在安置罐体(1)的环墙(3)上开设注浆孔,按环墙(3)外围弧长,每5m开设一个注浆孔,注浆孔的孔径为5cm,与水平夹角15°钻孔,孔深长度至环墙(3)的中心位置;
2)安装注浆管:在注浆管(2)上每30cm设置一个出浆阀(6);将注浆管(2)斜向插入沿与水平夹角15°的注浆孔内,其端部达至罐底中心的注浆孔底;
3)注浆:将搅浆设备和水泥材料放置在搅拌区,只有一个注浆输入管连接注浆管(2)的注浆内管插入注浆外管内;注浆时,首先开启位于罐中心部位的出浆阀(6),由中心向边沿顺序注浆,浆液为水泥浆或水泥和粉煤灰的配合比,浆液比重为1.55;浆脉运动方向(5)在土体中沿土体弱应力走向自动调整,随土体加固强度的提高,整个罐底土体抬升逐步完成;
4)修复罐底锥度:随着灌浆量的增加,加固土体孔隙水压力升高,开设排水孔或利用废弃注浆孔进行排水,排水的过程就是土体加固强度提高的过程;罐中心土体逐步抬升,罐底板(4)的锥度增大,最后达到0.8%-2.0%的要求;
5)封堵注浆孔:整个罐底锥度符合要求以后,对罐基础环墙(3)的注浆孔封堵,先清理注浆孔里面的注浆管,清理深度30cm,然后用水泥砂浆封堵抹平。
2.根据权利要求1所述的小型钢制储罐环墙基础罐底板锥度修复方法,其特征在于:所述步骤1)中的注浆孔沿环墙周边离地面高30cm处。
3.根据权利要求1或2所述的小型钢制储罐环墙基础罐底板锥度修复方法,其特征在于:所述步骤2)中插入的注浆管(2)是带有单向阀的袖阀注浆管。
CN201510117248.0A 2015-03-18 2015-03-18 小型钢制储罐环墙基础罐底板锥度修复方法 Pending CN104818738A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510117248.0A CN104818738A (zh) 2015-03-18 2015-03-18 小型钢制储罐环墙基础罐底板锥度修复方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510117248.0A CN104818738A (zh) 2015-03-18 2015-03-18 小型钢制储罐环墙基础罐底板锥度修复方法

Publications (1)

Publication Number Publication Date
CN104818738A true CN104818738A (zh) 2015-08-05

Family

ID=53729203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510117248.0A Pending CN104818738A (zh) 2015-03-18 2015-03-18 小型钢制储罐环墙基础罐底板锥度修复方法

Country Status (1)

Country Link
CN (1) CN104818738A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108396731A (zh) * 2018-02-12 2018-08-14 新疆五家渠现代石油化工有限公司 储油罐基础注浆加固处理方法
CN109826226A (zh) * 2019-01-17 2019-05-31 重庆建筑工程职业学院 历史建筑木桩基础加固方法
CN110258675A (zh) * 2018-05-25 2019-09-20 北京恒祥宏业基础加固技术有限公司 建筑物条形基础箱型复合地基加固纠偏方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08218410A (ja) * 1995-02-17 1996-08-27 Niigata Koji Kk 流体貯蔵タンクの基礎補修工法
KR20020004353A (ko) * 2000-07-05 2002-01-16 이도형 교량 우물통 기초부의 보강공법 및 그 보강구조
CN103643705A (zh) * 2013-12-12 2014-03-19 中石化上海工程有限公司 钢储罐环墙基础地基局部沉陷补强方法
CN104032766A (zh) * 2014-05-16 2014-09-10 同济大学 Lng储液罐隔震层

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08218410A (ja) * 1995-02-17 1996-08-27 Niigata Koji Kk 流体貯蔵タンクの基礎補修工法
KR20020004353A (ko) * 2000-07-05 2002-01-16 이도형 교량 우물통 기초부의 보강공법 및 그 보강구조
CN103643705A (zh) * 2013-12-12 2014-03-19 中石化上海工程有限公司 钢储罐环墙基础地基局部沉陷补强方法
CN104032766A (zh) * 2014-05-16 2014-09-10 同济大学 Lng储液罐隔震层

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
丁涛、赵兴品等: "立式储罐基础下陷的处理措施", 《山东水利》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108396731A (zh) * 2018-02-12 2018-08-14 新疆五家渠现代石油化工有限公司 储油罐基础注浆加固处理方法
CN110258675A (zh) * 2018-05-25 2019-09-20 北京恒祥宏业基础加固技术有限公司 建筑物条形基础箱型复合地基加固纠偏方法
CN109826226A (zh) * 2019-01-17 2019-05-31 重庆建筑工程职业学院 历史建筑木桩基础加固方法
CN109826226B (zh) * 2019-01-17 2021-03-02 重庆建筑工程职业学院 历史建筑木桩基础加固方法

Similar Documents

Publication Publication Date Title
CN103967036B (zh) 用于海上风电的桩与套筒灌浆连接结构及其施工方法
CN106836214B (zh) 旋挖灌注桩桩身塌孔或桩底沉渣质量缺陷处理的施工方法
CN104328786B (zh) 超深预应力管桩桩芯清土施工方法
CN104818738A (zh) 小型钢制储罐环墙基础罐底板锥度修复方法
CN204298821U (zh) 双套筒拔桩设备
CN204551461U (zh) 一种压力分散型葫芦式扩大头锚索
CN104196489B (zh) 一种柱梁式注浆装置及其封孔注浆工艺
CN204753628U (zh) 一种可周转的逆作法钢管柱调垂导向装置
CN204385727U (zh) 螺旋注浆预制桩
CN106894414B (zh) 双液深孔孔底定点精准混合施工工艺及注浆结构
CN103643690A (zh) 一种深基坑勘探孔涌水处理方法
CN103147707B (zh) 桩底沉渣成套处理方法
CN104818737A (zh) 大型钢制立式储罐环墙基础罐底板锥度修复方法
CN103790160A (zh) 一种smw工法型钢拔除注浆方法
CN103334590B (zh) 大型钢管柱混凝土施工装置及施工方法
JP5840891B2 (ja) 土留部材の撤去方法
CN208816080U (zh) 一种钻孔注浆用同径套管止水装置
CN109137919A (zh) 一种适用深井接地极钢套管的底部注浆系统及注浆方法
CN204831716U (zh) 一种顶管施工中管节密封性测试试验装置
CN205999941U (zh) 一种地下连续墙墙段连接装置
CN210086236U (zh) 一种灌注桩的承载力提升装置和灌注桩
CN110485510B (zh) 一种分次压入式回灌井结构及其应用方法
CN101532296A (zh) 一种桩基础的加固处理方法
CN204370413U (zh) 一种钢护筒
CN209163810U (zh) 一种新管幕法施工管支护装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150805