CN101532296A - 一种桩基础的加固处理方法 - Google Patents

一种桩基础的加固处理方法 Download PDF

Info

Publication number
CN101532296A
CN101532296A CN200810300545A CN200810300545A CN101532296A CN 101532296 A CN101532296 A CN 101532296A CN 200810300545 A CN200810300545 A CN 200810300545A CN 200810300545 A CN200810300545 A CN 200810300545A CN 101532296 A CN101532296 A CN 101532296A
Authority
CN
China
Prior art keywords
pile
pile foundation
castinplace
castinplace pile
new
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200810300545A
Other languages
English (en)
Inventor
杨华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Original Assignee
Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guiyang Aluminum Magnesium Design and Research Institute Co Ltd filed Critical Guiyang Aluminum Magnesium Design and Research Institute Co Ltd
Priority to CN200810300545A priority Critical patent/CN101532296A/zh
Publication of CN101532296A publication Critical patent/CN101532296A/zh
Pending legal-status Critical Current

Links

Images

Abstract

本发明提供了一种桩基础的加固处理方法,先在灌注桩(1)的旁边制作新补灌注桩(2),再破掉灌注桩(1)的桩头,使之置于桩基承台(3)垫层底标高以下,并相应截断灌注桩(1)内的钢筋(4),然后将新补灌注桩钢筋(5)按构造要求锚入桩基承台(3)内。本发明采用新补灌注桩替换完全失去承载能力的桩基础,施工时废去问题桩,使之与桩基承台毫无联系;此桩基础的加固简便、施工安全可靠。

Description

一种桩基础的加固处理方法
技术领域
本发明涉及一种桩基础的加固处理方法,属于建筑工程的桩基础领域。
背景技术
建筑工程桩基础的类型很多,但通常采用混凝土灌注桩。由于施工队伍的良莠不齐,混凝土灌注桩的工程事故较多,因此质量检验较其它桩种严格。通过具有相关检测资质的单位对桩基础进行检测,经常会发现桩体断桩、桩身混凝土强度未达到桩的承载力设计要求等等现象。如果因断桩或桩的承载力不够而造成建筑安全隐患甚至拆毁建筑,成本损失严重,则就要采取补救措施来加固桩基础。通常采用的固定方法是:(一)用钻机在基础上成孔至要加固的土层,然后用高压灌浆设备将配制好的水泥化学浆液灌入地层,通过劈裂、挤压作用,使土层与浆液产生物理化学反应而胶结,从而达到改善土体结构和性能的目的,提高土体的强度;(二)利用建筑物的承重柱重力作为反力,通过一套液(油)压设备,把预制桩分节压入土中,上下节桩接驳用预埋角铁焊接。但这两种方法同样都会给工程造成一定的损失,施工复杂。
发明内容
本发明所要解决的技术问题就是桩基础当被检测灌注桩完全失去承载能力的情况下,提供对桩基础进行加固的简便、安全可靠地处理方法。
为了解决上述问题,本发明提供了一种桩基础的加固处理方法,先在灌注桩1的旁边制作新补灌注桩2,灌注桩1位于新补灌注桩2的中间,满足桩的最小中心距要求,再破掉灌注桩1的桩头,使之置于桩基承台3垫层底标高以下,并相应截断灌注桩1内的钢筋4,然后将新补灌注桩钢筋5按构造要求安装在桩基承台3内。
灌注桩1的周围可以制作新补灌注桩2的数目为2~4根。
新补灌注桩钢筋5连接新补灌注桩2与桩基承台3。
与现有技术相比,本发明采用新补灌注桩替换完全失去承载能力的桩基础,施工时废去问题桩,使之与桩基承台毫无联系;此桩基础加固简便、施工安全可靠。
附图说明
图1:本发明的新补两根灌注桩平面图;
图2:本发明的新补四根灌注桩平面图;
图3:本发明的剖视图。
具体实施方式
实施例1:如图1,先在灌注桩1的旁边制作2根新补灌注桩2,灌注桩1位于新补灌注桩2的中间,满足桩的最小中心距要求,再破掉灌注桩1的桩头,使之置于桩基承台3垫层底标高以下,并相应截断灌注桩1内的钢筋4,然后将新补灌注桩钢筋5按构造要求锚入桩基承台3内,新补灌注桩钢筋5连接新补灌注桩2与桩基承台3。
实施例2:如图2,先在灌注桩1的旁边制作4根新补灌注桩2,灌注桩1位于新补灌注桩2的中间,满足桩的最小中心距要求,再破掉灌注桩1的桩头,使之置于桩基承台3垫层底标高以下,并相应截断灌注桩1内的钢筋4,然后将新补灌注桩钢筋5按构造要求锚入桩基承台3内,新补灌注桩钢筋5连接新补灌注桩2与桩基承台3。

Claims (4)

  1. 【权利要求1】一种桩基础的加固处理方法,其特征在于:先在灌注桩(1)的旁边制作新补灌注桩(2),再破掉灌注桩(1)的桩头,使之置于桩基承台(3)垫层底标高以下,并相应截断灌注桩(1)内的钢筋(4),然后将新补灌注桩钢筋(5)按构造要求安装在桩基承台(3)内。
  2. 【权利要求2】根据权利要求1所述的桩基础的加固处理方法,其特征在于:灌注桩(1)位于新补灌注桩(2)的中间。
  3. 【权利要求3】根据权利要求1所述的桩基础的加固处理方法,其特征在于:灌注桩(1)的周围可以制作新补灌注桩(2)的数目为2~4根。
  4. 【权利要求4】根据权利要求1所述的桩基础的加固处理方法,其特征在于:新补灌注桩钢筋(5)连接新补灌注桩(2)与桩基承台(3)。
CN200810300545A 2008-03-12 2008-03-12 一种桩基础的加固处理方法 Pending CN101532296A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810300545A CN101532296A (zh) 2008-03-12 2008-03-12 一种桩基础的加固处理方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810300545A CN101532296A (zh) 2008-03-12 2008-03-12 一种桩基础的加固处理方法

Publications (1)

Publication Number Publication Date
CN101532296A true CN101532296A (zh) 2009-09-16

Family

ID=41103146

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810300545A Pending CN101532296A (zh) 2008-03-12 2008-03-12 一种桩基础的加固处理方法

Country Status (1)

Country Link
CN (1) CN101532296A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102433901A (zh) * 2011-09-28 2012-05-02 孔超 一种预应力管桩的弯裂病害桩修复治理方法
CN102587355A (zh) * 2012-01-13 2012-07-18 佛山市顺德电力设计院有限公司 一种八角桩以及应用该八角桩的地基结构
CN103741963A (zh) * 2014-01-06 2014-04-23 北京筑福国际工程技术有限责任公司 一种工业厂房基础加固方法
CN109537614A (zh) * 2018-12-29 2019-03-29 深圳供电局有限公司 灌注桩及其成型方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102433901A (zh) * 2011-09-28 2012-05-02 孔超 一种预应力管桩的弯裂病害桩修复治理方法
CN102433901B (zh) * 2011-09-28 2015-03-11 孔超 一种预应力管桩的弯裂病害桩修复治理装置及其治理方法
CN102587355A (zh) * 2012-01-13 2012-07-18 佛山市顺德电力设计院有限公司 一种八角桩以及应用该八角桩的地基结构
CN103741963A (zh) * 2014-01-06 2014-04-23 北京筑福国际工程技术有限责任公司 一种工业厂房基础加固方法
CN103741963B (zh) * 2014-01-06 2015-09-09 北京筑福国际工程技术有限责任公司 一种工业厂房基础加固方法
CN109537614A (zh) * 2018-12-29 2019-03-29 深圳供电局有限公司 灌注桩及其成型方法

Similar Documents

Publication Publication Date Title
CN101666081B (zh) 深水库区陡坡裸岩钻孔平台及工艺
KR101410471B1 (ko) 기존건물 흙막이용 h파일을 이용한 상향식 지하옹벽 제거공법
CN203034464U (zh) 一种桁架式基坑支护结构
CN101550705B (zh) 一种桩基础的加固处理方法
CN103882869A (zh) 一种用于基坑围护的斜向支撑桩结构及其施工方法
CN205778903U (zh) 一种软岩巷道底鼓防治装置
CN102650212A (zh) 一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法
CN102162258A (zh) 一种塔吊钢管混凝土高桩塔基结构及构建方法
CN110735436A (zh) 一种路堑岩质边坡加固结构
CN101532296A (zh) 一种桩基础的加固处理方法
CN106948347B (zh) 拔桩方法及拔桩系统
CN201172830Y (zh) 塔式起重机锚杆静压桩基础
CN201502056U (zh) 深水库区陡坡裸岩钻孔平台
CN104452775B (zh) 用于基坑的预应力支撑及施工方法
CN203768914U (zh) 一种用于基坑围护的斜向支撑桩结构
CN103882883B (zh) 塔吊与车库框架柱共用一个基础施工方法
CN101550693A (zh) 高地下水位既有地下结构中用钻孔桩加固基础的施工方法
CN205822206U (zh) 一种垂直边坡加固装置
CN210106749U (zh) 一种软土地基超大断面顶管顶进作业的反力结构
CN102220764A (zh) 深基坑支护体系及其施工方法
CN204199296U (zh) 基于老旧地下室外墙结构的基坑支护结构
CN110512667A (zh) 一种处理因水害导致桩基沉降的新方法
CN103911991B (zh) 预应力混凝土ps桩断裂快速接桩施工方法
CN108221955B (zh) 一种可整体循环使用预制地下连续墙、吊具以及施工方法
CN114541439B (zh) 一种无封底双壁钢围堰结构的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20090916