CN102650212A - 一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法 - Google Patents

一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法 Download PDF

Info

Publication number
CN102650212A
CN102650212A CN2012101348906A CN201210134890A CN102650212A CN 102650212 A CN102650212 A CN 102650212A CN 2012101348906 A CN2012101348906 A CN 2012101348906A CN 201210134890 A CN201210134890 A CN 201210134890A CN 102650212 A CN102650212 A CN 102650212A
Authority
CN
China
Prior art keywords
tunnel
mid
pilot tunnel
board
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012101348906A
Other languages
English (en)
Other versions
CN102650212B (zh
Inventor
谢兰敏
金玲玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201210134890.6A priority Critical patent/CN102650212B/zh
Publication of CN102650212A publication Critical patent/CN102650212A/zh
Application granted granted Critical
Publication of CN102650212B publication Critical patent/CN102650212B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法,利用中导洞后拆除的半边临时支护,使其与隧道先行主洞的初衬支护,以及已浇筑的中墙顶部,形成的一个钢筋混凝土的刚性连接,实现中墙所承受的水平不平衡力转移到中导洞临时支护上承受的目的。本发明可以达到有效抵抗中隔墙在隧道施工过程中所承受的水平不平衡力;在后一半中导洞临时支护拆除前,有效地加以利用,节约了材料,降低了成本。

Description

一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法
技术领域
本发明属于连拱隧道施工技术领域,具体地说涉及连拱隧道施工中保证中隔墙施工质量的措施,适用于所有连拱隧道中隔墙的施工。
背景技术
目前,连拱隧道在我国公路、铁路、市政等基础设施中广泛使用。连拱隧道是一种较为新颖而结构特殊的隧道形式,具有受地形条件限制小、节约土地、结构整体性好以及综合造价低等特点,是目前国内修建隧道的理想选择之一。
在联拱隧道施工时,往往采用三导洞法施工,即首先开挖中导洞,然后施做中隔墙,再分别开挖左右导洞。开挖中导洞主要是为了首先施做中隔墙。
但是,由于连拱隧道施工过程中,中隔墙的受力多变的特点和隧道围岩性质的不确定性,客观上造成了连拱隧道中隔墙的施工质量不易保证。这是因为,中隔墙施工完成后,在左右主洞先后施工过程中,中隔墙需要承受来自先行主洞初期支护施工时带来的不对称作用力,加之隧道拱部的围岩荷载以及隧道左右洞频繁爆破开挖的震动,极易引起中隔墙开裂、滑移及倾斜,甚而导致隧道围岩失稳、拱顶坍塌等严重后果。
当前,在连拱隧道的施工中,为了平衡先行主洞二次衬砌产生的水平推力,防止先行主洞开挖和施做衬砌时中隔墙发生开裂、滑移及倾斜,一般采取在先行主洞相反侧的中隔墙与中导 洞临时支护之间,加设工字钢、方木临时支撑或回填混凝土作为临时支撑。采用工字钢、方木临时支撑,不仅存在操作面小,施工不方便的问题,而且在爆破开挖频繁震动的情况下,容易发生松动,影响支撑效果;采用回填混凝土材料临时支撑,虽然效果较好,但混凝土不能重复使用,而且还需要爆破拆除,浪费严重。另外,上述两种支撑都需要大量材料,成本高,费用大。
发明内容
为了克服上述工字钢、方木临时支撑或回填混凝土存在的不足,消除上述两种措施抵抗中隔墙水平不平衡推力带来的问题,本发明提供一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法。
在连拱隧道中隔墙施工前,需要进行中导洞开挖,并进行中导洞临时支护施工,以进行中隔墙施工,并保证中隔墙施工时的安全。
随着左右主洞的先后施工,中导洞临时支护的左右两半边,将先后逐步拆除。本发明专利就是利用后拆除的半边中导洞临时支护,来抵抗中隔墙在隧道施工中所承受的水平不平衡力,达到节约材料,降低成本的目的。
为实现本发明的上述目的,本发明一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法所采取的技术方案是:
第一步:中导洞开挖和临时支护:按设计要求开挖中导洞、施工中导洞临时支护,中导洞临时支护形式采取锚杆、挂钢筋网、喷射混凝土以及工字钢拱架联合支护形式,具有很强的抵御外力的能力。
所述的锚杆使用Φ25中空注浆锚杆或Φ22砂浆锚杆,按围岩不同,锚杆长2.5~3.5m,径向间距1.5~2.5m;钢筋网使用Φ8钢筋网,网格尺寸(20±2)×(20±2)cm。
第二步:施工连拱隧道钢筋混凝土中隔墙,中隔墙顶部的预留钢筋按设计图纸要求预留。
第三步:连拱隧道先行主洞石方开挖及技术措施:按设计要求分段开挖(每段2~3m)连拱隧道先行主洞石方,围岩稳定后,分段拆除(每段2~3m)先行主洞一侧的中导洞临时支护。分段拆除(每段2~3m)中导洞临时支护拆除时,喷射混凝土和型钢拱架、钢筋网均拆除至临时支护的竖向中线位置,其中型钢拱架和钢筋网钢筋预留35± 5cm锚固长度,其余割除。
第四步:把预留的35± 5cm锚固长度型钢拱架和钢筋网钢筋,与中隔墙顶部预留钢筋,以及主洞初衬的型钢拱架和钢筋网钢筋对接,并绑扎牢固。
第五步:施工主洞初衬喷射混凝土,使主洞的初衬支护与中导洞的临时支护结构,以及中隔墙顶部形成一个钢筋混凝土的整体,实现中隔墙所承受的水平不平衡力转移到中导洞临时支护上承受的目的。
本发明的有益效果是,可以达到有效抵抗中隔墙在隧道施工过程中所承受的水平不平衡力;在后一半中导洞临时支护拆除前,有效地加以利用,节约了材料,降低了成本。
具体实施方式
下面结合实施方案对本发明一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法作进一步说明。
本发明一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法采用的工艺、步骤为:
第一步:开挖中导洞,按设计要求施工中导洞临时支护。支护形式采取锚杆、挂钢筋网、喷射混凝土以及I14工字钢拱架联合支护,设计方案为:锚杆使用Φ25中空注浆锚杆或Φ22砂浆锚杆,按围岩不同,锚杆长2.5~3.5m,径向间距1.5~2.5m;钢筋网使用Φ8钢筋网,网格尺寸20×20cm;喷射混凝土标号C20,厚度20cm;工字钢拱架:IV级围岩采用I14型工字钢,间距为1.00m/榀,V级围岩采用I14型工字钢,间距为0.60m/榀, V+级围岩采用I16型工字钢,间距为0.60m/榀。
第二步:施工连拱隧道钢筋混凝土中隔墙,中隔墙顶部的预留钢筋按设计图纸要求预留。
第三步:连拱隧道先行主洞石方分段开挖(每段2~3m),围岩稳定后,分段拆除(每段2~3m)先行主洞一侧的中导洞临时支护。分段拆除(每段2~3m)中导洞临时支护拆除时,喷射混凝土和型钢拱架、钢筋网均拆除至临时支护的竖向中线位置,其中型钢拱架和钢筋网钢筋预留35± 5cm锚固长度,其余割除。
第四步:把预留的35cm锚固长度型钢拱架和钢筋网钢筋,与中隔墙顶部预留钢筋,以及主洞初衬的型钢拱架和钢筋网钢筋对接,并绑扎牢固。
第五步:施工主洞初衬喷射混凝土,使主洞的初衬支护与中导洞的临时支护结构,以及中隔墙顶部形成一个钢筋混凝土的刚性连接的整体。

Claims (3)

1.一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法,其特征在于采用以下工艺、步骤:
第一步:中导洞开挖和临时支护:按设计要求开挖中导洞、施工中导洞临时支护,中导洞临时支护形式采取锚杆、挂钢筋网、喷射混凝土以及工字钢拱架联合支护形式;
第二步:施工连拱隧道钢筋混凝土中隔墙,中隔墙顶部的预留钢筋按设计图纸要求预留;
第三步:连拱隧道先行主洞石方分段开挖及技术措施:按设计要求分段开挖连拱隧道先行主洞石方,每段2~3m;围岩稳定后,分段拆除先行主洞一侧的中导洞临时支护;分段拆除中导洞临时支护拆除时,喷射混凝土和型钢拱架、钢筋网均拆除至临时支护的竖向中线位置,其中型钢拱架和钢筋网钢筋预留35± 5cm锚固长度,其余割除;
第四步:把预留的35± 5cm锚固长度型钢拱架和钢筋网钢筋,与中隔墙顶部预留钢筋,以及主洞初衬的型钢拱架和钢筋网钢筋对接,并绑扎牢固;
第五步:施工主洞初衬喷射混凝土,使主洞的初衬支护与中导洞的临时支护结构,以及中隔墙顶部形成一个钢筋混凝土的整体。
2.如权利要求1所述的一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法,其特征在于:所述的锚杆使用Φ25中空注浆锚杆或Φ22砂浆锚杆,按围岩不同,锚杆长2.5~3.5m,径向间距1.5~2.5m;钢筋网使用Φ8钢筋网,网格尺寸(20±2)×(20±2)cm。
3.如权利要求1或2所述的一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法,其特征在于:喷射混凝土标号C20,厚度20cm;工字钢拱架:IV级围岩采用I14型工字钢,间距为1.00m/榀, V+级围岩采用I16型工字钢,间距为0.60m/榀。
CN201210134890.6A 2012-05-04 2012-05-04 一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法 Active CN102650212B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210134890.6A CN102650212B (zh) 2012-05-04 2012-05-04 一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210134890.6A CN102650212B (zh) 2012-05-04 2012-05-04 一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法

Publications (2)

Publication Number Publication Date
CN102650212A true CN102650212A (zh) 2012-08-29
CN102650212B CN102650212B (zh) 2014-04-09

Family

ID=46692327

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210134890.6A Active CN102650212B (zh) 2012-05-04 2012-05-04 一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法

Country Status (1)

Country Link
CN (1) CN102650212B (zh)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104405402A (zh) * 2014-10-13 2015-03-11 中铁二院重庆勘察设计研究院有限责任公司 隐式中墙连拱隧道对称中隔壁施工方法
CN104500093A (zh) * 2014-12-16 2015-04-08 湖南科技大学 上软下硬地层大断面隧道支护结构中临时中墙定位方法
CN107387131A (zh) * 2017-08-30 2017-11-24 中国电建集团中南勘测设计研究院有限公司 一种非对称岔洞支护结构及其施工方法
CN108266191A (zh) * 2018-01-17 2018-07-10 中铁隆工程集团有限公司 一种连拱隧道优化施工方法
CN109505609A (zh) * 2018-11-21 2019-03-22 中交第四公路工程局有限公司 浅埋暗挖城市地下综合管廊无支架施工方法及综合管廊
CN109611100A (zh) * 2018-11-20 2019-04-12 中铁十二局集团有限公司 一种隧道中导洞双侧扩挖施工方法
CN109973123A (zh) * 2019-03-28 2019-07-05 西安建筑科技大学 一种连拱隧道中导洞临时支护拱架拆除方法
CN114263467A (zh) * 2021-11-17 2022-04-01 湖南省交通规划勘察设计院有限公司 一种四连拱隧道的开挖设计施工方法
CN115045669A (zh) * 2022-08-11 2022-09-13 湖南省交通规划勘察设计院有限公司 一种软弱地层超大断面双连拱隧道的施工方法
CN117489351A (zh) * 2023-10-07 2024-02-02 保利长大工程有限公司 一种连拱隧道施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101737061A (zh) * 2009-12-24 2010-06-16 中国水电顾问集团华东勘测设计研究院 既有单洞隧道改扩建为连拱隧道的施工方法
CN102121385A (zh) * 2011-03-18 2011-07-13 同济大学 一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法
KR20110133370A (ko) * 2010-06-04 2011-12-12 주식회사 픽슨 비상대피공간을 갖는 지중터널 및 그 시공방법
CN102373930A (zh) * 2011-09-23 2012-03-14 中南大学 一种软弱围岩大断面连拱隧道的快速施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101737061A (zh) * 2009-12-24 2010-06-16 中国水电顾问集团华东勘测设计研究院 既有单洞隧道改扩建为连拱隧道的施工方法
KR20110133370A (ko) * 2010-06-04 2011-12-12 주식회사 픽슨 비상대피공간을 갖는 지중터널 및 그 시공방법
CN102121385A (zh) * 2011-03-18 2011-07-13 同济大学 一种既有单洞隧道扩建为双联拱隧道的隧道开挖方法
CN102373930A (zh) * 2011-09-23 2012-03-14 中南大学 一种软弱围岩大断面连拱隧道的快速施工方法

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104405402A (zh) * 2014-10-13 2015-03-11 中铁二院重庆勘察设计研究院有限责任公司 隐式中墙连拱隧道对称中隔壁施工方法
CN104500093A (zh) * 2014-12-16 2015-04-08 湖南科技大学 上软下硬地层大断面隧道支护结构中临时中墙定位方法
CN107387131A (zh) * 2017-08-30 2017-11-24 中国电建集团中南勘测设计研究院有限公司 一种非对称岔洞支护结构及其施工方法
CN108266191A (zh) * 2018-01-17 2018-07-10 中铁隆工程集团有限公司 一种连拱隧道优化施工方法
CN108266191B (zh) * 2018-01-17 2019-08-27 中铁隆工程集团有限公司 一种连拱隧道优化施工方法
CN109611100A (zh) * 2018-11-20 2019-04-12 中铁十二局集团有限公司 一种隧道中导洞双侧扩挖施工方法
CN109611100B (zh) * 2018-11-20 2020-07-21 中铁十二局集团有限公司 一种隧道中导洞双侧扩挖施工方法
CN109505609B (zh) * 2018-11-21 2023-11-14 中交建筑集团有限公司 浅埋暗挖城市地下综合管廊无支架施工方法及综合管廊
CN109505609A (zh) * 2018-11-21 2019-03-22 中交第四公路工程局有限公司 浅埋暗挖城市地下综合管廊无支架施工方法及综合管廊
CN109973123A (zh) * 2019-03-28 2019-07-05 西安建筑科技大学 一种连拱隧道中导洞临时支护拱架拆除方法
CN114263467A (zh) * 2021-11-17 2022-04-01 湖南省交通规划勘察设计院有限公司 一种四连拱隧道的开挖设计施工方法
CN115045669A (zh) * 2022-08-11 2022-09-13 湖南省交通规划勘察设计院有限公司 一种软弱地层超大断面双连拱隧道的施工方法
CN117489351A (zh) * 2023-10-07 2024-02-02 保利长大工程有限公司 一种连拱隧道施工方法

Also Published As

Publication number Publication date
CN102650212B (zh) 2014-04-09

Similar Documents

Publication Publication Date Title
CN102650212B (zh) 一种利用中导洞临时支护保护连拱隧道中隔墙的施工方法
CN101864963B (zh) 一种大断面黄土隧道施工方法
CN101614125B (zh) V级围岩隧道施工方法
CN102733827B (zh) 隧道换拱施工方法及用于隧道换拱施工中的施工结构
CN101338678B (zh) 一次扣拱暗挖逆作施工方法
CN102042019B (zh) 浅埋大跨软塑粘土隧道两台阶五步开挖的施工方法
CN206205908U (zh) 一种预防隧道沉降变形的槽钢拱架托梁
CN102003187B (zh) 深埋软岩大型隧洞落底开挖支护的施工方法
CN102587922A (zh) 一种软弱破碎岩层斜交斜井上弧导挑顶施工方法
CN101967984A (zh) 深井巷道锚网索刚柔耦合支护及围岩整体加固支护方法
CN107605489A (zh) 三线大跨隧道斜井进正洞施工方法
CN103628885A (zh) 一种超浅埋隧道出洞盖挖施工方法
CN108412519A (zh) 高原地区软岩轻微大变形单线隧道支护装置及施工方法
CN103696784A (zh) 一种浅埋大跨隧道下穿建构筑物的大直径长管幕施工方法
CN203879506U (zh) 一种岩质地层大断面深竖井的支护结构体系
CN103982188A (zh) 岩质地层大断面深竖井的支护结构体系及其施工方法
CN103882869A (zh) 一种用于基坑围护的斜向支撑桩结构及其施工方法
CN110629671A (zh) 一种悬索桥锚碇及其施工方法
CN104295301B (zh) 一种浅埋暗挖碎裂岩体地铁隧道交叉点的施工方法
CN103510540A (zh) 浆砌片石挡土墙加固施工方法及其结构
CN104775830A (zh) 一种膨胀土隧道拱墙初期支护施工方法
CN111335915A (zh) 一种用于隧道仰拱隆起破坏修复的型钢支撑结构及方法
CN104632232A (zh) 一种扩挖大直径盾构隧道建造地铁车站的管片拆除方法
CN100473787C (zh) 一种用于桩锚支护体系中的连接结构及其实施方法
CN203768914U (zh) 一种用于基坑围护的斜向支撑桩结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant