CN104766155A - Engineering project element management method and system based on BIM - Google Patents

Engineering project element management method and system based on BIM Download PDF

Info

Publication number
CN104766155A
CN104766155A CN201510080209.8A CN201510080209A CN104766155A CN 104766155 A CN104766155 A CN 104766155A CN 201510080209 A CN201510080209 A CN 201510080209A CN 104766155 A CN104766155 A CN 104766155A
Authority
CN
China
Prior art keywords
bim model
bim
engineering project
model
component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510080209.8A
Other languages
Chinese (zh)
Other versions
CN104766155B (en
Inventor
尹仕友
严国林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Is With Building Information Technology Co Ltd
Original Assignee
Shanghai Is With Building Information Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Is With Building Information Technology Co Ltd filed Critical Shanghai Is With Building Information Technology Co Ltd
Priority to CN201510080209.8A priority Critical patent/CN104766155B/en
Publication of CN104766155A publication Critical patent/CN104766155A/en
Application granted granted Critical
Publication of CN104766155B publication Critical patent/CN104766155B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides an engineering project element management method and system based on the BIM. The method includes the steps of storing attribute data A of a first BIM model in a server; simplifying the first BIM model to obtain and issue a second BIM model, wherein the association with the attribute data A in the server and the matching with the first BIM model in a PC terminal are achieved through the component ID; loading the second BIM model in a mobile terminal A, establishing the association relation between collected engineering project element information and the component ID, and achieving sharing through the server. By means of the association between the two BIM models and the component ID, data interaction and visual interaction are achieved.

Description

Based on management method and the system of the engineering project key element of BIM
Technical field
The present invention relates to the management method based on BIM, relate to particularly based on management method and the system of the engineering project key element of BIM, particularly relate to quality, safety, environment, the progress control method based on BIM.
Background technology
BIM is the abbreviation of Building Information Modeling, is domesticly usually translated into BIM.Be a kind of building Life cycle information system management technology, there is visual, harmony, simulation, optimization and can go out figure fivelarge feature.BIM is a kind of brand-new architectural design, construction, management method, based on three-dimensional digital information technology, the data information in each stages such as planning, design, construction, operation is all included among 3D model, allowing the staff in any stage in the whole life cycle of buildings when using this model, effective, correct decision-making can be made according to accurately complete data.
Mobile Internet (Mobile Internet is called for short MI) is a kind of by intelligent mobile terminal, adopts mobile radio communication system to obtain the emerging service of business and service, comprises terminal, software and application three aspects.Terminating layer comprises smart mobile phone, panel computer, e-book, MID etc.; Software comprises operating system, middleware, database and fail-safe software etc.Application layer comprises different application and the services such as amusement and recreation class, instrument media class, commercial finance and economic.Along with the development of technology and industry, future, the transport network layer gordian techniquies such as LTE (Long Term Evolution, one of 4G communication technology standard) and NFC (near-field communication, the support technology of mobile payment) also by be included into mobile Internet category within.By the use to mobile Internet, easily can realize the paperless management to building Life cycle, ensure that the staff in any post of engineering can obtain complete, real-time engineering information.
The defect of following several respects is there is in the way to manage of the engineering project key elements such as traditional operating mode and progress:
(1) information transfer connection.The unit related to due to engineering management and department numerous, traditional method as modes such as meeting, dispatches, information transmit efficiency very low, each side grasps multidate information in time and more seems very difficult, thus cause the information asymmetry of each side, cause and link up difficulty, even delay project progress;
(2) Information procession aspect.The data such as the quality that in engineering project, operating mode is relevant, safety, environment, progress, amount greatly and ceaselessly in change, manual operations is difficult to gather in time, makes each side be difficult to hold the situation of engineering.Further, engineering figurethe information document such as paper, file, amount is large and generally preserve with the form of paper, and increases along with the progress of engineering and the continuous accumulation of all kinds of data, easily causes document to lose, and even affects the maintenance work that the later stage builds;
(3) information use.The information of magnanimity is certainly led in construction work construct and manage process, particularly to the management most important thing especially of the operating modes such as quality, safety, environment and project progress, but traditional engineering management mode often because not recording in time, each side factor such as communication causes forgeing operating mode, thus affects the quality of engineering and normal progress.
Summary of the invention
For defect of the prior art, the object of this invention is to provide one based on management method and the system of the engineering project key element of BIM.Feature of the present invention comprises:
(1) use development of Mobile Internet technology to realize real time record, the upload and download of engineering information, site problems can be reacted within the shortest time, and can not lose.
(2) information comprise word, voice, figuresheet, video, describe problem more accurate.
(3) all data are all kept in BIM model database, and through encryption and backup, ensure that the safety and reliability of data.
(4) the open safe interface of data access, shares to other Management System Data.
(5) BIM three-dimensional model solid show is adopted, than two dimension figurepaper is more directly perceived.
According to the management method of a kind of engineering project key element based on BIM provided by the invention, comprise as follows step:
stepa: preserve a BIM model in PC end, held by PC, be saved in server by the attribute data A of a BIM model, described attribute data comprises component ID; Simplification is carried out to a BIM model and obtains the 2nd BIM model, and the 2nd BIM Model publish is used for mobile terminal and/or WEB terminal, wherein, after simplifying, the attribute data B of the 2nd BIM model only remains the component ID in the attribute data A of a BIM model, to realize the data correlation with attribute data A in server by component ID, and the BIM model in holding with PC mates;
stepb: load the 2nd BIM model in the A of mobile terminal, to the engineering project element information collected and the relation that is associated between component ID, and engineering project element information and incidence relation are sent to server to carry out preserving and information sharing;
stepc: server, for the component ID come in the request of user terminal, is transferred according to described incidence relation and returns corresponding engineering project element information to third party's terminal, wherein, described user terminal refer to do not comprise mobile terminal A mobile terminal, PC end.
Preferably, described in stepa comprises as follows step:
-summit of causing model face number to exceed setting threshold value in a BIM model is removed;
-summit of causing moulded dimension to exceed setting threshold value in a BIM model is removed;
-submodel in a BIM model is rebuild;
-the race's example in a BIM model simplified and is replaced by MaxScript script;
-submodel of identical material in a BIM model is merged.
Preferably, also as follows step:
In mobile terminal, utilize the 2nd BIM model response user operation, and by the incidence relation between component ID and engineering project element information, return the component model or engineering project element information transferred from server to user.
Preferably, described engineering project element information comprises any one of quality, safety, environment, progress or appoints multinomial information.
Preferably, the attribute data A in server is the key word that mates as unique information of holding member ID and model name only.
According to the management system of a kind of engineering project key element based on BIM provided by the invention, comprise following PC end, server, mobile terminal;
In PC end, preserve a BIM model, held by PC, be saved in server by the attribute data A of a BIM model, described attribute data comprises component ID; Simplification is carried out to a BIM model and obtains the 2nd BIM model, and the 2nd BIM Model publish is used for mobile terminal and/or WEB terminal, wherein, after simplifying, the attribute data B of the 2nd BIM model only remains the component ID in the attribute data A of a BIM model, to realize the data correlation with attribute data A in server by component ID, and the BIM model in holding with PC mates;
In the A of mobile terminal, load the 2nd BIM model, to the engineering project element information collected and the relation that is associated between component ID, and engineering project element information and incidence relation are sent to server to carry out preserving and information sharing;
Server, for the component ID come in the request of user terminal, is transferred according to described incidence relation and returns corresponding engineering project element information to third party's terminal, wherein, described user terminal refer to do not comprise mobile terminal A mobile terminal, PC end.
Preferably, in described PC end, execution is as follows step:
-summit of causing model face number to exceed setting threshold value in a BIM model is removed;
-summit of causing moulded dimension to exceed setting threshold value in a BIM model is removed;
-submodel in a BIM model is rebuild;
-the race's example in a BIM model simplified and is replaced by MaxScript script;
-submodel of identical material in a BIM model is merged.
Preferably, in mobile terminal, utilize the 2nd BIM model response user operation, and by the incidence relation between component ID and engineering project element information, return the component model or engineering project element information transferred from server to user.
Preferably, described engineering project element information comprises any one of quality, safety, environment, progress or appoints multinomial information.
Preferably, the attribute data A in server is the key word that mates as unique information of holding member ID and model name only.
Compared with prior art, the present invention has following beneficial effect:
1) combine the three-dimensional visualization technique of BIM model, carry out engineering management more intuitively;
2) fast development of Internet technology and Intelligent mobile equipment is utilized, achieve multi-platform, the omnibearing Engineering Management Patterns such as computer terminal platform, mobile-terminal platform, enrich ladder of management and instrument, achieve informationization and the variation of engineering management;
3) use mobile Internet and data cloud technology, realize the multi-platform Real-Time Sharing of information data in engineering management, eliminate each party information asymmetry problem in engineering management;
4) clear and definite each platform terminal purposes, simplify process of engineering management, reduce costs expenditure, make the incident management sharpening in engineering management, responsibility distribute make clear, progress monitoring datumization.
Accompanying drawing explanation
By reading with reference to following accompanying drawingto the detailed description that non-limiting example is done, other features, objects and advantages of the present invention will become more obvious:
fig. 1extremely fig. 4the topology of described management method provided by the present invention is shown jointly figure.
Embodiment
Below in conjunction with specific embodiment, the present invention is described in detail.Following examples will contribute to those skilled in the art and understand the present invention further, but not limit the present invention in any form.It should be pointed out that to those skilled in the art, without departing from the inventive concept of the premise, some distortion and improvement can also be made.These all belong to protection scope of the present invention.
According to the management method of a kind of engineering project key element based on BIM provided by the invention, comprise as follows step:
stepa: preserve a BIM model in PC end, held by PC, be saved in server by the attribute data A of a BIM model, described attribute data comprises component ID; Simplification is carried out to a BIM model and obtains the 2nd BIM model, and the 2nd BIM Model publish is used for mobile terminal and/or WEB terminal, wherein, after simplifying, the attribute data B of the 2nd BIM model only remains the component ID in the attribute data A of a BIM model, to realize the data correlation with attribute data A in server by component ID, and the BIM model in holding with PC mates.Such as, the attribute data A of the detailed BIM model as a BIM model is saved in server database by the C/S end on PC, for follow-up data real-time, interactive, described attribute data A preferably can not be edited after in confirmation typing server database as raw data; Detailed BIM model also simplifies by the C/S end on PC, obtains the simplification BIM model as the 2nd BIM model, simplifies by a holding member ID in the attribute data B of BIM model, in order to realize data correlation with the described attribute data A in server database.
stepb: load the 2nd BIM model in mobile terminal A (such as PAD), to the engineering project element information collected and the relation that is associated between component ID, and server engineering project element information and incidence relation is sent to carry out preserving and information sharing.Such as, PAD loads and simplifies BIM model, carry out the information acquisition of quality, safety, environment, progress, and by component ID and detailed BIM model data mutual.
stepc: server, for the component ID come in the request of user terminal, is transferred according to described incidence relation and returns corresponding engineering project element information to third party's terminal, wherein, described user terminal refer to do not comprise mobile terminal A mobile terminal, PC end.
Wherein, described in stepa comprises as follows step:
-summit of causing model face number to exceed setting threshold value in a BIM model is removed;
-summit of causing moulded dimension to exceed setting threshold value in a BIM model is removed;
-submodel in a BIM model is rebuild;
-the race's example in a BIM model simplified and is replaced by MaxScript script;
-submodel of identical material in a BIM model is merged.
Preferably, described engineering project element information comprises any one of quality, safety, environment, progress or appoints multinomial information.Attribute data A in server is the key word that mates as unique information of holding member ID and model name only.In mobile terminal, utilize the 2nd BIM model response user operation, and by the incidence relation between component ID and engineering project element information, return the component model or engineering project element information transferred from server to user.Such as, multiple users (such as multiple mobile terminal or WEB terminal) to be checked the quality gathered, safety, environment, progress msg according to user role authority and comments on, reply, and by clicking component extraction component ID and positional information in simplification BIM model, these quality, safety, environment, progress, comment, return information are associated by component ID with the data of detailed BIM model, realize the interchange real-time in engineering management of each engineering participant.The 2nd BIM model can be utilized in mobile terminal and WEB terminal according to the construction of component, remove time attribute and simulate the process that in whole construction, buildings completes.
Described stepb comprises as follows step:
Mobile terminal A utilize Unity3D show the 2nd BIM model (namely simplifying BIM model);
According to newly-built operating mode instruction on the A of mobile terminal, be associated to component ID by the newly-built operating mode of the 2nd BIM model interpolation quality, safety, environment, progress, and the following attribute information of newly-built operating mode be set:
-operating mode type, wherein, operating mode type comprises safety, quality, environment etc.;
-operating mode founder, wherein, will send the login user of the mobile terminal of newly-built operating mode instruction as operating mode founder;
-creation-time, wherein, the time that operating mode creates was as the criterion with the time of WEB service end;
-closing time, wherein, closing time, for recording the final date of operating mode process, if when this final date arrives when the operating mode situation of operating mode or new problem, then pushes reminder message and operating mode attribute information by WEB service end forward end intelligent platform;
-alarm interval, wherein, the interval time that alarm interval pushes for the reminder message recording adjacent twice warning;
-operating mode situation, wherein, operating mode situation comprises in new problem, process, has processed, closes this four situations;
-operating mode title, wherein, operating mode title is for recording the brief introduction of operating mode content;
-operating mode content, wherein, operating mode content is for recording the practical illustration of operating mode;
-operating mode annex, wherein, operating mode annexcomprise figuresheet, voice, video;
-association component, wherein, the component ID in association BIM model, for recording the component ID associated by operating mode, adopts bubble and highlighted display;
Newly-built work information is issued on the A of mobile terminal, the back-end data cloud of server realizes information data by component ID as association and shares mutual, and be pushed on other mobile terminal by Web end.
Further, with the management method of the described engineering project key element based on BIM correspondingly, present invention also offers a kind of management system of the engineering project key element based on BIM, comprise following PC end, server, mobile terminal;
In PC end, preserve a BIM model, held by PC, be saved in server by the attribute data A of a BIM model, described attribute data comprises component ID; Simplification is carried out to a BIM model and obtains the 2nd BIM model, and the 2nd BIM Model publish is used for mobile terminal and/or WEB terminal, wherein, after simplifying, the attribute data B of the 2nd BIM model only remains the component ID in the attribute data A of a BIM model, to realize the data correlation with attribute data A in server by component ID, and the BIM model in holding with PC mates;
In the A of mobile terminal, load the 2nd BIM model, to the engineering project element information collected and the relation that is associated between component ID, and engineering project element information and incidence relation are sent to server to carry out preserving and information sharing;
Server, for the component ID come in the request of user terminal, is transferred according to described incidence relation and returns corresponding engineering project element information to third party's terminal, wherein, described user terminal refer to do not comprise mobile terminal A mobile terminal, PC end.
Preferably, in described PC end, execution is as follows step:
-summit of causing model face number to exceed setting threshold value in a BIM model is removed;
-summit of causing moulded dimension to exceed setting threshold value in a BIM model is removed;
-submodel in a BIM model is rebuild;
-the race's example in a BIM model simplified and is replaced by MaxScript script;
-submodel of identical material in a BIM model is merged.
Preferably, in mobile terminal, utilize the 2nd BIM model response user operation, and by the incidence relation between component ID and engineering project element information, return the component model or engineering project element information transferred from server to user.
Preferably, described engineering project element information comprises any one of quality, safety, environment, progress or appoints multinomial information.
Preferably, the attribute data A in server is the key word that mates as unique information of holding member ID and model name only.
Described mobile terminal (comprising mobile terminal A) comprises work information administration module, and wherein, described work information administration module, comprises as lower device:
Newly-built operating mode management devices: for according to newly-built operating mode instruction, by the 2nd BIM model add quality, safety, environment, progress newly-built operating mode be associated to component ID, and the following attribute information of newly-built operating mode is set:
-operating mode type, wherein, operating mode type comprises safety, quality, environment;
-operating mode founder, wherein, will send the login user of the mobile terminal of newly-built operating mode instruction as operating mode founder;
-creation-time, wherein, the time that operating mode creates was as the criterion with the time of WEB service end;
-closing time, wherein, closing time, for recording the final date of operating mode process, if when this final date arrives when the operating mode situation of operating mode or new problem, then pushes reminder message and operating mode attribute information by WEB service end forward end intelligent platform;
-alarm interval, wherein, the interval time that alarm interval pushes for the reminder message recording adjacent twice warning;
-operating mode situation, wherein, operating mode situation comprises in new problem, process, has processed, closes this four situations;
-operating mode title, wherein, operating mode title is for recording the brief introduction of operating mode content;
-operating mode content, wherein, operating mode content is for recording the practical illustration of operating mode;
-operating mode annex, wherein, operating mode annexcomprise figuresheet, voice, video;
-association component, wherein, association component, for recording the component associated by operating mode, adopts bubble and highlighted display;
Operating mode comment management devices: for receiving the review information of foreground intelligent platform to operating mode, and review information is added in operating mode content, then by WEB service end synchronized update operating mode content between foreground intelligent platform, WEB service end, background data base end;
Operating mode replys management devices: for receiving other mobile terminal or WEB terminal to the return information of operating mode review information, and return information is added in operating mode content, then by WEB service end synchronized update operating mode content between the background data base end of mobile terminal, WEB service end, server;
The pusher of work information: for will exceeding the cut-off date and the operating mode attribute information of operating mode in operating mode situation or new problem or process, is pushed to by WEB service end the mobile terminal that user instruction specifies.
Schedule management apparatus: management valid data: the progress msg searching association according to the date range selected, as long as the plan of progress starts, terminates; Actual to start, namely the Close Date relevantly with the date of selection show as valid data; The expression of management progress and the time difference.
More specifically, provided by the invention based on management method and the system of the engineering project key element of BIM: all or part of data can by component ID carry out association use development of Mobile Internet technology be saved in WEB service end and server, without the need to manual intervention, front end and after platform meetinganalyze according to data and judge whether the duration reminds untreated safety, quality, environmental problem in predetermined period, in time; Adopt local buffer technology, can realize without the data transmit-receive under network; Unity3D is used mobile terminal, in detail BIM model, three-dimensional real-time, interactive combined technology to be on the leading domestic level.Wherein, principal feature of the present invention to realize BIM model real-time, interactive, specifically comprises:
A. associate with the database in server by simplifying the component ID preserved in BIM model;
B. simplification BIM model and detailed BIM model are mated by component ID;
C. to the information such as structure attribute, model absolute altitude of detailed BIM model, the C/S Program extraction held, be stored in server database by PC, holding member ID and model name, as the key word of these information of unique match, realize information interaction;
D. rotation is realized to simplification BIM model in mobile terminal, the user operation such as convergent-divergent, component are chosen, the simulation of construction progress, and operated by newly-increased, the amendment etc. of model component ID and engineering project key element and be associated, both engineering project key element can be checked by model, also can by checking that engineering project usually will check model information, the virtual interactive interface of implementation model and data.
Utilize the present invention can realize following application
1 utilizes the schedule in the ready-made planned management of project of real work situation comparison of the personnel of collection in worksite, material, machinery, automatically generates the three-dimensional visualization model of working report and model interaction, thus carries out follow-up scheduling more specifically and optimization.
2 real data utilizing on-the-spot each side staff to gather with countrytechnical manual or relevant sample project contrast, and automatically derive relevant final report.The time that each event occurs and geographic position all associate the BIM model of three-dimensional visualization with volume coordinate, thus carry out rationally control to the quality of building operation, concealed work are carried out to record and the accumulation of data.
3 show the event data be consistent with actual conditions associated in the BIM model of three-dimensional visible, the abundant information utilizing each side field staff to gather manages the safety problem of construction work in work progress and control, carries out keep on file in advance and take precautions against for concealed work.
4 utilize the on-the-spot work progress of Real-time Monitoring Data to construction work to monitor, automatic data collection real-time exhibition in the three-dimensional model.Set the warning value of active forewarning, active forewarning of pinpointing the problems simultaneously, and according to the order of importance and emergency automatic decision monitoring frequency of event.
Above specific embodiments of the invention are described.It is to be appreciated that the present invention is not limited to above-mentioned particular implementation, those skilled in the art can make various distortion or amendment within the scope of the claims, and this does not affect flesh and blood of the present invention.

Claims (10)

1., based on a management method for the engineering project key element of BIM, it is characterized in that, comprise the steps:
Steps A: preserve a BIM model in PC end, held by PC, be saved in server by the attribute data A of a BIM model, described attribute data comprises component ID; Simplification is carried out to a BIM model and obtains the 2nd BIM model, and the 2nd BIM Model publish is used for mobile terminal and/or WEB terminal, wherein, after simplifying, the attribute data B of the 2nd BIM model only remains the component ID in the attribute data A of a BIM model, to realize the data correlation with attribute data A in server by component ID, and the BIM model in holding with PC mates;
Step B: load the 2nd BIM model in the A of mobile terminal, to the engineering project element information collected and the relation that is associated between component ID, and engineering project element information and incidence relation are sent to server to carry out preserving and information sharing;
Step C: server is for the component ID come in the request of user terminal, transfer according to described incidence relation and return corresponding engineering project element information to third party's terminal, wherein, described user terminal refer to do not comprise mobile terminal A mobile terminal, PC end.
2. the management method of the engineering project key element based on BIM according to claim 1, it is characterized in that, described steps A comprises the steps:
-summit of causing model face number to exceed setting threshold value in a BIM model is removed;
-summit of causing moulded dimension to exceed setting threshold value in a BIM model is removed;
-submodel in a BIM model is rebuild;
-the race's example in a BIM model simplified and is replaced by MaxScript script;
-submodel of identical material in a BIM model is merged.
3. the management method of the engineering project key element based on BIM according to claim 1, is characterized in that, also following steps:
In mobile terminal, utilize the 2nd BIM model response user operation, and by the incidence relation between component ID and engineering project element information, return the component model or engineering project element information transferred from server to user.
4. the management method of the engineering project key element based on BIM according to claim 1, is characterized in that, described engineering project element information comprises any one of quality, safety, environment, progress or appoints multinomial information.
5. the management method of the engineering project key element based on BIM according to claim 1, is characterized in that, the attribute data A in server is the key word that mates as unique information of holding member ID and model name only.
6. based on a management system for the engineering project key element of BIM, it is characterized in that, comprise following PC end, server, mobile terminal;
In PC end, preserve a BIM model, held by PC, be saved in server by the attribute data A of a BIM model, described attribute data comprises component ID; Simplification is carried out to a BIM model and obtains the 2nd BIM model, and the 2nd BIM Model publish is used for mobile terminal and/or WEB terminal, wherein, after simplifying, the attribute data B of the 2nd BIM model only remains the component ID in the attribute data A of a BIM model, to realize the data correlation with attribute data A in server by component ID, and the BIM model in holding with PC mates;
In the A of mobile terminal, load the 2nd BIM model, to the engineering project element information collected and the relation that is associated between component ID, and engineering project element information and incidence relation are sent to server to carry out preserving and information sharing;
Server, for the component ID come in the request of user terminal, is transferred according to described incidence relation and returns corresponding engineering project element information to third party's terminal, wherein, described user terminal refer to do not comprise mobile terminal A mobile terminal, PC end.
7. the management system of the engineering project key element based on BIM according to claim 6, is characterized in that, in described PC end, perform following steps:
-summit of causing model face number to exceed setting threshold value in a BIM model is removed;
-summit of causing moulded dimension to exceed setting threshold value in a BIM model is removed;
-submodel in a BIM model is rebuild;
-the race's example in a BIM model simplified and is replaced by MaxScript script;
-submodel of identical material in a BIM model is merged.
8. the management method of the engineering project key element based on BIM according to claim 6, it is characterized in that, in mobile terminal, utilize the 2nd BIM model response user operation, and by the incidence relation between component ID and engineering project element information, return the component model or engineering project element information transferred from server to user.
9. the management method of the engineering project key element based on BIM according to claim 6, is characterized in that, described engineering project element information comprises any one of quality, safety, environment, progress or appoints multinomial information.
10. the management method of the engineering project key element based on BIM according to claim 6, is characterized in that, the attribute data A in server is the key word that mates as unique information of holding member ID and model name only.
CN201510080209.8A 2015-02-13 2015-02-13 The management method and system of engineering project element based on BIM Active CN104766155B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510080209.8A CN104766155B (en) 2015-02-13 2015-02-13 The management method and system of engineering project element based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510080209.8A CN104766155B (en) 2015-02-13 2015-02-13 The management method and system of engineering project element based on BIM

Publications (2)

Publication Number Publication Date
CN104766155A true CN104766155A (en) 2015-07-08
CN104766155B CN104766155B (en) 2018-12-04

Family

ID=53647969

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510080209.8A Active CN104766155B (en) 2015-02-13 2015-02-13 The management method and system of engineering project element based on BIM

Country Status (1)

Country Link
CN (1) CN104766155B (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105335558A (en) * 2015-10-28 2016-02-17 上海同筑信息科技有限公司 Engineering circle establishment method and system on basis of BIM (building information modeling)
CN105844380A (en) * 2016-01-26 2016-08-10 湖北文理学院 BIM-based BIM project element management method and system
CN106204745A (en) * 2016-08-31 2016-12-07 中国电建集团昆明勘测设计研究院有限公司 Monitoring BIM model rapid loading interaction method and system based on standard atlas management
CN107146065A (en) * 2017-03-20 2017-09-08 中国铁道科学研究院电子计算技术研究所 Railway engineering management platform system
CN107423886A (en) * 2017-06-29 2017-12-01 中国建筑局(集团)有限公司 Engineering data synchronous management system and method based on tracking table
CN108256831A (en) * 2018-02-02 2018-07-06 北京筑业志远软件开发有限公司 The method that Engineering documents Management is carried out based on visualization BIM models
CN108376376A (en) * 2018-02-02 2018-08-07 北京筑业志远软件开发有限公司 Construction engineering quality management standardized method based on BIM models
CN109214068A (en) * 2018-08-17 2019-01-15 徐州中煤百甲重钢科技股份有限公司 BIM-based bottom assembled building information extraction method
CN109886643A (en) * 2019-01-29 2019-06-14 杭州凌望建筑科技有限公司 BIM multidimensional mould based on IOS examines platform
CN111680970A (en) * 2020-05-25 2020-09-18 中亿丰建设集团股份有限公司 Foundation pit monitoring intelligent management system based on BIM
CN112215939A (en) * 2019-06-24 2021-01-12 华建数创(上海)科技有限公司 Collaborative management method and system for building data
CN113656402A (en) * 2021-07-13 2021-11-16 广东省国际工程咨询有限公司 Engineering project full life cycle data recording and storing method and device based on BIM

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110252461A1 (en) * 2008-05-13 2011-10-13 Monterey Group One, Llc Methods, apparatus and systems for providing secure information via multiple authorized channels to authenticated users and user devices
CN102884532A (en) * 2010-03-09 2013-01-16 欧特克公司 Systems and methods for construction field management and operations with building information modeling
CN103246951A (en) * 2012-12-11 2013-08-14 中建三局第一建设工程有限责任公司 Intelligent electromechanical equipment management system and method based on BIM (building information modeling)

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110252461A1 (en) * 2008-05-13 2011-10-13 Monterey Group One, Llc Methods, apparatus and systems for providing secure information via multiple authorized channels to authenticated users and user devices
CN102884532A (en) * 2010-03-09 2013-01-16 欧特克公司 Systems and methods for construction field management and operations with building information modeling
CN103246951A (en) * 2012-12-11 2013-08-14 中建三局第一建设工程有限责任公司 Intelligent electromechanical equipment management system and method based on BIM (building information modeling)

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
娄夕美: "云计算在BIM设计中的应用", 《城市建设理论研究(电子版)》 *
张建平,等: "BIM在工程施工中的应用", 《施工技术》 *
张建平,等: "基于BIM的工程项目管理系统及其应用", 《土木建筑工程信息技术》 *
朱香华,陆云强: "浅谈3DVIA Composer的功能与特点", 《软件世界》 *
杨远丰,莫颖媚: "多种BIM 软件在建筑设计中的综合应用", 《建筑数字化技术》 *

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105335558A (en) * 2015-10-28 2016-02-17 上海同筑信息科技有限公司 Engineering circle establishment method and system on basis of BIM (building information modeling)
CN105844380A (en) * 2016-01-26 2016-08-10 湖北文理学院 BIM-based BIM project element management method and system
CN106204745A (en) * 2016-08-31 2016-12-07 中国电建集团昆明勘测设计研究院有限公司 Monitoring BIM model rapid loading interaction method and system based on standard atlas management
CN106204745B (en) * 2016-08-31 2023-01-03 中国电建集团昆明勘测设计研究院有限公司 Monitoring BIM model rapid loading interaction method and system based on standard atlas management
CN107146065A (en) * 2017-03-20 2017-09-08 中国铁道科学研究院电子计算技术研究所 Railway engineering management platform system
CN107423886A (en) * 2017-06-29 2017-12-01 中国建筑局(集团)有限公司 Engineering data synchronous management system and method based on tracking table
CN108376376B (en) * 2018-02-02 2021-11-09 北京筑业志远软件开发有限公司 BIM model-based construction engineering quality management standardization method
CN108256831B (en) * 2018-02-02 2021-07-30 北京筑业志远软件开发有限公司 Method for managing engineering data based on visual BIM model
CN108376376A (en) * 2018-02-02 2018-08-07 北京筑业志远软件开发有限公司 Construction engineering quality management standardized method based on BIM models
CN108256831A (en) * 2018-02-02 2018-07-06 北京筑业志远软件开发有限公司 The method that Engineering documents Management is carried out based on visualization BIM models
CN109214068A (en) * 2018-08-17 2019-01-15 徐州中煤百甲重钢科技股份有限公司 BIM-based bottom assembled building information extraction method
CN109214068B (en) * 2018-08-17 2023-03-10 徐州中煤百甲重钢科技股份有限公司 BIM-based bottom assembled building information extraction method
CN109886643A (en) * 2019-01-29 2019-06-14 杭州凌望建筑科技有限公司 BIM multidimensional mould based on IOS examines platform
CN112215939A (en) * 2019-06-24 2021-01-12 华建数创(上海)科技有限公司 Collaborative management method and system for building data
CN111680970A (en) * 2020-05-25 2020-09-18 中亿丰建设集团股份有限公司 Foundation pit monitoring intelligent management system based on BIM
CN113656402A (en) * 2021-07-13 2021-11-16 广东省国际工程咨询有限公司 Engineering project full life cycle data recording and storing method and device based on BIM

Also Published As

Publication number Publication date
CN104766155B (en) 2018-12-04

Similar Documents

Publication Publication Date Title
CN104766155A (en) Engineering project element management method and system based on BIM
CN104680320A (en) BIM-based project management system and method
CN104504497A (en) BIM engineering information management system and method
CN104573032A (en) Emergency simulation drilling all-in-one machine for nuclear emergency device
CN109214784A (en) A kind of method, client, server and the system of fire-fighting inspection management
CN103118114A (en) BIM (building information modeling) collaborative designing system based on cloud servers
CN111445218A (en) BIM-based project progress management method, device, equipment and storage medium
CN107145673A (en) A kind of combined simulation system and method
CN103971311A (en) Reasoning drill method and system based on man-machine coordination
CN109784789A (en) Mine business cooperation job control method, device, system and storage medium
CN109615700A (en) Three-dimension virtual reality tunnel monitoring system and its operating method
Robinson III et al. Development of a high-fidelity simulation environment for Shadow-Mode Assessments of Air Traffic Concepts
CN115857886A (en) Low code development platform for basic government affair application
CN112116332A (en) Task management system and method for wind tunnel test of aerospace aerodynamic technology
CN105488226A (en) Digital museum visiting and exhibiting system
CN115393560A (en) BIM model drawing marking method, device, equipment and readable storage medium
CN114329669A (en) Online collaborative editing method and device, electronic equipment and storage medium
CN115719147A (en) Power transmission line inspection data processing method, device and platform
CN108564281A (en) The implementation method of outsourcing work task scheduling system based on structuring
CN104065566A (en) Method and system for realizing synchronization between WEB application circle and group messages
CN203301527U (en) Cloud server-based building information modeling (BIM) collaborative design device
CN112507053A (en) Method for establishing visualization system and application method
CN112597184A (en) Office management software system, computer, mobile phone and tablet terminal
Kevany GIS in the World Trade Center response: 10 years after
CN105467859A (en) Test application system supporting platform and method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant